1. Purpose:
The purpose of this method statement is to describe the Installation of cable trays and Trunking.
2. Scope:
Responsibilities for ensuring that the steps in this procedure shall be carried out arespecified at relevant
steps in the procedure:
2. Reference:
Project Manager
Construction manager
Site Engineer
QA/QC Inspector
HSE officer
Site Foreman
Store Keeper
747543505.docx Page - 1
MEP
Project Manager is overall responsible for the project in terms of work execution, safety,planning &
quality. The Project Manager will maintain the planning progress and coordination of works with the main
contractor.
The work progress shall be carried out as per planned program and all the equipment’s
required to execute the works shall be available and in good condition as per project planned. Specific
attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC
Inspector and in line with PQP.
Construction Manager is responsible to supervise and control the work on site. Coordinating with
QA/QC Inspector and site Team and foremen for all activities on site. Control and sign all WIR’s before
issuing to Consultant approval.
The monitoring of executions of works at site should be as per the approved drawings and project
specification.
Ensure WIRs are being raised for activities in timely manner and inspected by the Consultant.
Check and ensure that all activities / work done I completed prior to offer for consultant
inspection.
He will follow and carried out all the relevant tests as per project specifications.
Obtain the required clearance prior to Consultant’s inspections. Coordinate with site construction
team.
747543505.docx Page - 2
MEP
Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
The site is maintained in a clean and tidy manner.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items as required. Ensure adequate
lighting is provided in the working area at night time.
Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
Ensure safe access to site work at all times.
3. Scope Of Work:
The method statement is written for the purpose of establishing method and procedures for the
installation of cable tray and cable trunking for the building MEP services.
747543505.docx Page - 3
MEP
747543505.docx Page - 4
MEP
Where cable tray crossing building expansion joint, the tray shall be installed suitably to provide
expansion/ contraction with the building expansion.
Cable trays/Ladder system support shall be determined in accordance with the manufacture’s
structural information to ensure the undue stress or bending shall not occur.
All accessories and fittings such as bends, tees, elbow, cross units and angles shall be of the same
specification as that of the cable tray finish and shall be standard products from the same
manufacture as the cable tray. Site fabrication shall not be permitted.
Where cable tray carries 13.8 kv cable, a tray lid shall be installed.
Provide sufficient space around cable tray for access. Cable Support System
Use fish plate to joint & align cable tray where cable tray passes through fire rated wall, approved
fire shop drawing installation method shall be followed.
On completion of cable tray/ ladder installation including fittings, inspect exposed finish. Remove
burrs & construction debris and repair damages finishes including chips, scratches & abrasions.
Surface/ floor cable trunking shall be used with prior approval of the engineer, wherever possible
to replace multiple conduits runs.
Metal surface/ floor cable trunking shall comply with NEC and shall be manufacturer from
galvanized steel sheet.
Surface/floor cable trunking shall be single or multi-compartment as required. Where multi-
compartment is used, vertical dividers shall be provided between the compartments which shall be
welded to the trunking prior to galvanizing’s.
Heavy duty uPVC trunking with clip on lid (all insulated) shall be used if show on the drawings or
specified elsewhere.
7. Acceptance Of Equipment’s And Materials:
As per the scope of work, support material and all consumables will be supplied by SAB. All
material supplied by SAB shall be inspected prior to installation to ensure material complied with project
standards.
1. Before storing these materials on shelves, certificates and period of validity will be checked,
and inventory will be prepared for control. Unqualified material or equipment will be rejected.
2. Material inspection shall be carried from time to time after receiving these materials from
warehouse during the installation period according to company specification.
747543505.docx Page - 5
MEP
8. Resource:
8.1 MATERIAL:
747543505.docx Page - 6
MEP
10. Check adequacy and availability of all tools, before commencement of install ation
activity.
11. The safety officer shall verify that all the necessary and applicable documents, related
to the safe site operation are in possession before commencing the job.
12. Safety procedures shall be followed at all times.
13. Area shall be kept clean at all time.