You are on page 1of 8

METHOD STATEMENT

FOR
TRANSFORMER INSTALLATION

 TABLE OF CONTENTS

1. SCOPE

2. DEFINITIONS

3. HEALTH AND SAFETY

4. OPERATION

5. INSTALLATION AND FIXATION

6. RESPONSIBILITIES

7. MANPOWER REQUIRED

8. MATERIALS REQUIREMENTS

9. EQUIPMENTS REQUIREMENTS

10. WASTE MANAGEMENT

11. SPECIAL CONTROL MEASURES.

12. SUPPORTING DOCUMENTATION

13. DISTRIBUTION
1.SCOPE
 This procedure to clear the method of the supply, installations of
Transformer for the project.
 This document details Transformer Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.

2. DEFINITIONS
PQP : Project Quality Plan

PSP : Project Safety Plan

QCP : Quality Control Procedure

HSE : Health, Safety and Environment

MS : Method Statement

ITP : Inspection Test Plan

QA/QC : Quality Assurance / Quality Control Engineer.

WIR : Inspection and Test Request

MIR : Material Verification Record.

3. HEALTH AND SAFETY


 Strictly followed as per the manufacturer's Health and Safety
recommendations for handling and use of the materials.

 Ensure all involved personnel shall be aware of the same.

 Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.

4. OPERATION
 Material:

 Material used will be as approved by the Engineer.


 The sizes and routes routing will be as per the approved Shop
Drawings.

 Storage and Protection:

 Deliver components parts to site, completely identified in accordance


with shop and certified CAD Drawings prepared for this work.

 Store in accordance with the manufacturer’s instructions, above


ground, properly protected from the weather and construction activities.

5. INSTALLATION AND FIXATION


 Off-Loading:
 Use Fork Lifts or Mobile Crane to off-load the transformers.
 Make sure that the capacity of the fork lifts or mobile crane can carry
the weight of the transformers.
 Off load the transformer on the designated off loading area.
 Proper care must be observed during off loading to prevent
unnecessary damage or dents on the transformers.
 Ensure that the transformers are properly protected and covered with
tarpaulin.

 Pre-Installation:
 All materials and documentation relevant to this particular section of
works shall be checked by the Construction Department prior to the
commencement of works ensuring that these are correct and approved
type.
 Before any permanent works will continue, pre-inspection on all
materials, tools and access for installation to be carried out.

 Installation:
 Before the transformer will be delivered to site, ensure that the
transformer railing is fixed as per approved drawings and comply on
municipality requirement.
 Move the transformers from the designated off-loading area or storage
area using fork lift and set them in position near to the transformer
room.
 Make sure that the orientation of the transformer with regards to the
position of cable entries is correct.
 Push in the transformers inside the transformer room. Set the
transformer on their final positions and make sure that they are
properly secured and protected.
 Raise Request for Inspection for Transformer Installation.
 Conduct on site test for the transformer.
 Test shall include winding insulation resistance test and shall conform
to manufacturer’s recommendation and specification.
 All tests must be recorded and conducted in the presence of
Consultant by manufacturer testing engineer.
 Dress and terminate the incoming and outgoing cables on the
transformers.
 Ensure that the cables were supported properly.
 Cable glands, lugs and termination kits shall be approved type.
 After termination works has been completed, clean the transformer
cable box and ensure that it is free from foreign materials and excess
openings must be sealed off and ensure that all the connections are
properly tight and torque.
 Raise Request for Inspection for the cable terminations and dressing.

 Commissioning:
 Cover the cable boxes.
 Bolts and nuts must be tightened properly.
 Make sure that the transformer room is clean and free from foreign
materials.

 Technical Assistance:
 The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
 This instruction shall be scheduled at the convenience of the staff.
 All such instruction shall be properly recorded.
 WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.

6. RESPONSIBILITIES

 PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.

2. To ensure that the progressing of works is carried out according


to the planned program and as per the approved method of
statement.

3. To ensure that all the equipment and material required


executing the work are available according to the planned
construction program.

4. To co-ordinate with the Main contractor, MEP coordinator,


Safety Officer for a safe and proper execution of the works.
 SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.

2. To provide all necessary information and distribute


responsibilities to his construction.

3. To monitor the progress of work in relation with the work


program and to report to the Project Manager.

4. To co-ordinate with the safety officer and to ensure that the


works are carried out in safe practicing method.

 FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.

2. To ensure that his assistant foreman/ charge hand are aware of


the job requirements and they have enough information to carry
out their duties properly.

3. To ensure that the daily work is progressing as planned and


advice the site engineer of any requirement for additional
resources.

4. To ensure in consultation with the site engineer that the


manpower involved in the works are moving as agreed and
planned for the work.

5. To control disposal of waste materials according to the


instructions received from the site engineer.

6. To ensure full coordination with the safety officer to maintain


safe working and proper house keeping of the site, following the
proved safety measures and further ensure that all his working
team are aware of the same to prevent accident and losses.

7. To inform the site engineer regarding areas ready for inspection.

8. Foreman and the storekeeper are responsible for the distribution


and control of materials.
 SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.

2. Ensure all the implemented safety measures are adequate to


maintain safe working on the site.

3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.

4. Ensure that the site is maintained clean and tidy.

 TECHNICIAN FROM SUPPILER


1. The carrying-out of work and the proper distribution of all the
available resources in coordination with the sub-contractor
Site Engineer on a daily basis.
2. Daily reports of the works are achieved and coordinated for
the future planning with the Site Engineer.
3. Complying with the sub-contractor basic design practices,
particularly those related to safety and engineering
4. Meeting with any type of unforeseen incident or requirement
and reporting the same to the Site Engineer immediately.

 STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.

7. MANPOWER REQUIRED

 Charge hand and Experienced Technicians

8. MATERIALS REQUIREMENTS

 Transformer Components and Accessories

9. EQUIPMENTS REQUIREMENTS

 The Equipment that will be engaged for Transformer Installation will be as


follows:
1. Hand Tools

2. Power Tools (if required)

3. Diagonal-Cutting Pliers

4. Wire Stripper/Cutter with Spring

5. Side-Cutting Pliers

6. Shank Screwdriver/Flat screw driver

7. Compression lug crimp tool

8. Necessary conduit for System Cabling

9. Knock out set (for conduit)

10. P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves


& safety vest )

10. WASTE MANAGEMENT


 The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.

11. SPECIAL CONTROL MEASURES


 The following general control measures against Safety, Environment and
Quality shall be required for our scope of work and special control
measures are not applicable for us :

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made
available to site.
 All workers doing the work shall be briefed on this method statement
and risk assessment.
12. SUPPORTING DOCUMENTATION
 This method Statement should be read in conjunction with the below
referenced documentations:

 ITP for Anti – termite Treatment.

 Insulation Resistance and continuity Test Report.

13. DISTRIBUTION
 Copy of this method statement shall be issued to the following for
information / action / comments:

1. Project Manager

2. Site Engineer

3. Foremen

4. Safety Engineer

5. Technician From Supplier

6. Store Keeper

You might also like