Professional Documents
Culture Documents
FOR
TRANSFORMER INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1.SCOPE
This procedure to clear the method of the supply, installations of
Transformer for the project.
This document details Transformer Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Pre-Installation:
All materials and documentation relevant to this particular section of
works shall be checked by the Construction Department prior to the
commencement of works ensuring that these are correct and approved
type.
Before any permanent works will continue, pre-inspection on all
materials, tools and access for installation to be carried out.
Installation:
Before the transformer will be delivered to site, ensure that the
transformer railing is fixed as per approved drawings and comply on
municipality requirement.
Move the transformers from the designated off-loading area or storage
area using fork lift and set them in position near to the transformer
room.
Make sure that the orientation of the transformer with regards to the
position of cable entries is correct.
Push in the transformers inside the transformer room. Set the
transformer on their final positions and make sure that they are
properly secured and protected.
Raise Request for Inspection for Transformer Installation.
Conduct on site test for the transformer.
Test shall include winding insulation resistance test and shall conform
to manufacturer’s recommendation and specification.
All tests must be recorded and conducted in the presence of
Consultant by manufacturer testing engineer.
Dress and terminate the incoming and outgoing cables on the
transformers.
Ensure that the cables were supported properly.
Cable glands, lugs and termination kits shall be approved type.
After termination works has been completed, clean the transformer
cable box and ensure that it is free from foreign materials and excess
openings must be sealed off and ensure that all the connections are
properly tight and torque.
Raise Request for Inspection for the cable terminations and dressing.
Commissioning:
Cover the cable boxes.
Bolts and nuts must be tightened properly.
Make sure that the transformer room is clean and free from foreign
materials.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper