Professional Documents
Culture Documents
System INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. HEALTH AND SAFETY
3. OPERATION
4. installation and fixation
5. RESPONSIBILITIES
6. MANPOWER REQUIRED
7. MATERIALS REQUIREMENTS
8. EQUIPMENTs REQUIREMENTs
9. WASTE MANAGEMENT
10. SPECIAL CONTROL MEASURES
1. SCOPE
This procedure to clear the method of the supply, installations of CCTV system for the project.
This document details the CCTV system Installation:
Preparation of work.
Specific safety measures have to follow as applicable, and all the safety measures are covered
3. OPERATION
Material:
Material used will be as approved by the Engineer.
The sizes and routes routing will be as per the approved Shop Drawings.
Deliver components parts to site, completely identified in accordance with shop and certified CAD
Store in accordance with the manufacturer’s instructions, above ground, properly protected from
Installation will be carried out as per manufacturer recommendations, Approved shop drawings
Installation:
Civil Clearance before start the installation of the CCTV system (Cameras & Panels).
Check that all conduits for the Data of the camera installed as per approved shop drawings.
Check that the CCTV system and its Accessories approved as per material submittal.
Check that the location of the camera/ panels and the position set as per approved shop drawings
Check that the Installed Camera is the correct type other (PTZ or Dome type).
Al specific CCTV camera locations shall be selected to provide a view of the maximum amount of
space.
Refer to relevant CCTV drawing layouts and schematic diagrams for all active and passive
components provided in this section for exact location and details of integration with other sub-
systems.
Check that the cameras setting and programmed as per project requirements and manufacturer
recommendations.
Installation of Wires:
Install cables in raceways and cable trays except within consoles, back boxes, desks, and counters.
Using CAT-6A type cable the maximum length of the cable not exceeds more than 90 mtrs. Of
manufacturer recommendation, which will provided from structural cabling system supplier.
Comply with requirements for raceways and boxes specified in Division 26 Section “Raceways,
Conceal conductors and cables in accessible ceilings, walls, and floors where possible.
Wiring within Enclosures:
Connect to terminal points with no excess and without exceeding manufacturer’s limitations on
bending radius.
Grounding
Comply with requirements in Division 26 Section “Grounding and Bonding for Electrical
Bond metallic equipment to the system grounding bus bar, using not smaller than the specified
Identification
Identify system components, wiring, and cabling complying with ADDC Electricity Wiring
Programming
After making sure all the system installed in correct way from Subcontractor and supplier,
programming of the system must take place before final testing and commissioning according to
Testing and commissioning of the system submitted separately for this system mentioned all the
Technical Assistance:
The installation supervising technician for the system trade shall instruct the CONSULTANT
Engineer, and Construction Site Manager on the programming and correct operation of the system
WIR will be issued for Consultant approval upon making sure that the installation of the system
equipment’s done as per approved shop drawings, approved specs and manufacturer
recommendations.
5. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out according to the Contract
1. To ensure that the progressing of works is carried out according to the planned program and as per
2. To ensure that all the equipment and material required executing the work are available according
3. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper
FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination with the site
engineer on daily basis, and ensure proper distribution of the work force on the required and
planned locations.
1. To ensure that his assistant foreman/ charge hand are aware of the job requirements
and they have enough information to carry out their duties properly.
2. To ensure that the daily work is progressing as planned and advice the site engineer of
3. To ensure in consultation with the site engineer that the manpower involved in the
4. To control disposal of waste materials according to the instructions received from the
site engineer.
5. To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the proved safety measures and further ensure that
all his working team are aware of the same to prevent accident and losses.
7. Foreman and the storekeeper are responsible for the distribution and control of
materials.
SAFETY OFFICER
1. Ensure the implementation of all the safety measures in accordance with the HSE plan and
1. Ensure all the implemented safety measures are adequate to maintain safe working on
the site.
2. Inspect all the site activities and train the person to prevent accidents and its proper
implementation.
TECHNICIAN
1. The carrying-out of work and the proper distribution of all the available resources in coordination
2. Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
3. Complying with the sub-contractor basic design practices, particularly those related to safety and
engineering
4. Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
6. MANPOWER REQUIRED
Charge hand and Experienced Technicians
7. MATERIALS REQUIREMENTS
CCTV System Components and Accessories.
8. EQUIPMENTs REQUIREMENTs
The Equipment that will be engaged for CCTV System Installation will be as follows:
Tools for fitting the Remote Units (either Surface or Flush mount).
Pulling Spring
Hammer
Measuring Wheel.
Drilling tools.
Ladders.
fluorescent vest, and safety gloves to ensure maximum ability of safe work and dust
9. WASTE MANAGEMENT
The Rubbish which would be created from our scope of works will be disposed to the designated
dumping ground.
for our scope of work and special control measures are not applicable for us:
Approved work method statement and risk assessment will be made available to site.
All workers doing the work shall be briefed on this method statement and risk assessment.