You are on page 1of 6

METHOD STATEMENT

FOR
INSTALLATION OF POWER AND LIGHTING SYSTEM WIRING

 TABLE OF CONTENTS

1. INTRODUCTION AND SCOPE

2. APPLICABLE PROJECT SPECIFICATION

3. LOCATION OF ACTIVITY

4. HEALTH AND SAFETY

5. HEALTH AND SAFETY HAZARDS

6. OPERATION

7. INSTALLATION

8. RESPONSIBILITIES

9. MANPOWER REQUIRED

10. MATERIALS REQUIRMENTS

11. EQUIPMENTS REQUIREMENTS


12. WASTE MANAGEMENT
13. SPECIAL CONTROL MEASURES

14. SUPPORTING DOCUMENTATION

15. DISTRIBUTION
1. INTRODUCTION AND SCOPE
 This method of statement specifies the detailed requirements and
procedures for the installation of Power and Lighting System Wiring.

2. APPLICABLE PROJECT SPECIFICATION


 Section: Cables and wiring

 Division: Installation

 Sub Division: Subdivision

3. LOCATION OF ACTIVITY
 Power and lighting system for the whole building.

4. HEALTH AND SAFETY


 Strictly followed as per the manufacturer’s Health and Safety
recommendations for handling and use of the materials. Ensure all
involved personnel shall be aware of the same.

5. HEALTH AND SAFETY HAZARDS


 Specific safety measures have to follow as applicable, and all the
safety measures are covered separately in the project safety plan.

6. OPERATION

1. Material: Material used will be as approved by the engineer. The sizes


and routes routing will be as per the approved shop drawing.

2. Storage and Protection: Deliver components parts to site, completely


identified in accordance with shop and certified drawings prepared for
this work. Store in accordance with the manufacturer’s instructions,
above ground, properly protected from the weather and construction
activities.

7. INSTALLATION

1. No wiring be carried out until the appropriate tests required or in the


electrical testing section have been done and the consultant has given
his clearance for wiring to commence.
2. A loop in form of wiring shall be used as far as practicable or unless
otherwise indicated. Joints in conductors shall be made using insulated
terminal blocks complying with requirements of this specification.

3. At expansion joints adequate slack shall be left in the cable.

4. Where Conduits are installed for wiring by others, a draw wire shall be
provided between each draw in position.

5. Where three-phase circuits comprising single-core cables are installed


in trunking, all cables of a shall be tied together at intervals not
exceeding 200mm.

6. Cables forming part of alarm, control, communication or monitoring


circuits shall have identification sleeves at their terminations.
Identification shall be consistent with the relevant wiring diagrams.

8. RESPONSIBILITIES

1. PROJECT MANAGER
1. To ensure that all the preparation and application works are carried
out according to the Contract Specification and with the approved
drawings.

2. To ensure that the progressing of work is carried out according to


the planned program and as per the approved method of statement.

3. To ensure that all the equipment and materials required to execute


the work are available according to the planned construction
program.

4. To co –ordinate with the Main contractor, MEP Coordinator and


Safety Officer, for a safe and proper execution of the works.

2. SITE ENGINEER

1. To ensure that the works are carried out according to the Contract
Specifications, approved method statement and the shop drawings.

2. To provide all necessary information and distribute responsibilities to


his construction team.

3. To monitor the progress of work in relation with the work program


and to report to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are
carried out in safe practising methods.

3. FOREMAN

1. The foreman will carry out his duties by maintaining continuous


coordination with the site engineer on daily basis, and ensure proper
distribution of the workforce in the required and planned locations.

2. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their
duties properly.

3. To ensure in consultation with the site engineer that the manpower


involved in the works are moving as agreed and planned for the work.

4. To ensure that the daily work is progressing as planned and advise the
site engineer of any requirement for additional resources. To control
disposal of waste materials according to the instructions received from
the site engineer.

5. To ensure full coordination with the safety officer to maintain safe


working and proper house keeping of the site, following the approved
safety measures and further ensure that all his working team are aware
of the same to prevent accident and losses.

6. To inform the site engineer and of the areas ready for inspection.

7. Distribution and the control of material shall be monitored by foreman


and store keeper.

4. SAFETY ENGINEER

1. Ensure the implementation of all the safety measures in accordance


with the HSE plan and everybody aware of it for it’s proper
implementation.

2. Ensure all the implemented safety measures are adequate to maintain


safe working on the site.

3. Inspect all the site activities and train the person to prevent accidents
and it’s proper implementation.

4. Ensure that the site is maintained clean and tidy.


9. MANPOWER REQUIRED
 Charge hand and Experienced Technicians

10. MATERIALS REQUIRMENTS


 Power/Lighting System Wiring and accessories

11. EQUIPMENTS REQUIREMENTS


 The requirements that will be engaged for Power and lighting System
Wiring works will be as follows:

1. Measuring tape

2. Cutting plier

3. Box spanner set

4. Bending spring

5. Pipe Wrench

6. Drilling Machine

7. Crimping tool

8. Screw driver

9. Pulling spring

10. Hammer

11. Common tools

12. WASTE MANAGEMENT


 The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.

13. SPECIAL CONTROL MEASURES


 The following general control measures against Safety, Environment and
Quality shall be required for our scope of work and special control
measures are not applicable for us :

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made
available to site. All workers doing the work shall be briefed on this
method statement and risk assessment.

14. SUPPORTING DOCUMENTATION


 This method Statement should be read in conjunction with the below
referenced documentations:

 ITP for Anti – termite Treatment.

 Insulation Resistance and continuity Test Report.

15. DISTRIBUTION
 Copy of this method statement shall be issued to the following for
information/ action/ comments:

1. Project Manager

2. Site Engineer

3. Foremen

4. Safety Engineer

You might also like