Professional Documents
Culture Documents
FOR
INSTALLATION OF POWER AND LIGHTING SYSTEM WIRING
TABLE OF CONTENTS
3. LOCATION OF ACTIVITY
6. OPERATION
7. INSTALLATION
8. RESPONSIBILITIES
9. MANPOWER REQUIRED
15. DISTRIBUTION
1. INTRODUCTION AND SCOPE
This method of statement specifies the detailed requirements and
procedures for the installation of Power and Lighting System Wiring.
Division: Installation
3. LOCATION OF ACTIVITY
Power and lighting system for the whole building.
6. OPERATION
7. INSTALLATION
4. Where Conduits are installed for wiring by others, a draw wire shall be
provided between each draw in position.
8. RESPONSIBILITIES
1. PROJECT MANAGER
1. To ensure that all the preparation and application works are carried
out according to the Contract Specification and with the approved
drawings.
2. SITE ENGINEER
1. To ensure that the works are carried out according to the Contract
Specifications, approved method statement and the shop drawings.
3. FOREMAN
2. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their
duties properly.
4. To ensure that the daily work is progressing as planned and advise the
site engineer of any requirement for additional resources. To control
disposal of waste materials according to the instructions received from
the site engineer.
6. To inform the site engineer and of the areas ready for inspection.
4. SAFETY ENGINEER
3. Inspect all the site activities and train the person to prevent accidents
and it’s proper implementation.
1. Measuring tape
2. Cutting plier
4. Bending spring
5. Pipe Wrench
6. Drilling Machine
7. Crimping tool
8. Screw driver
9. Pulling spring
10. Hammer
15. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer