Professional Documents
Culture Documents
0 MLD
STP BIAL
1. PURPOSE
The purpose of this Method statement is to ensure that Installation of Power Transformer
630 kva 2 nos in accordance with the contract requirements, approved method statement
and manufacturer's recommendations / instructions and that all quality assurance
procedures and control methods are practiced and activated in a systematic manner,
works are inspected and finally conformance is verified and documented.
2. SCOPE
This procedure is applicable to the Installation of Power Transformer 630 kva 2 nos for the
project titled “3.0 MLD sewage treatment plant at Bangalore international Airport”
3. DEFINITIONS/ ABBREVIATIONS
COMPANY/CLIENT : BIAL
CONTRACTOR : Hydrotech Paryavaran (India) PVT.LTD.
PROJECT : 3.0 MLD sewage treatment plant at Bangalore international Airport”
CT : Construction Team
ST : Survey Team
ITP : Inspection Test Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
QA/QC : Quality Assurance / Quality Control
PTW : Permit to Work
QC Inspector : Company / Contractor / Sub-contractor personnel as applicable
Site Engineer : Sub-contractor Engineer Responsible for the activity
GFC : Good For Construction
MS : Method Statement
PPE : Personnel Protective Equipment
4. REFERENCE DRAWING
C00M04-HPL-E_SF-304a-XX-SPC-0001
C00M04-HPL-E_SF-304a-XX-SPC-0004
C00M04-HPL-E_DB-304a-XX-DWG-0001
C00M04-HPL-E_SF-304a-XX-SPC-0006
C00M04-HPL-E_MC-304a-XX-DWG-0006
C00M04-HPL-E_MC-304a-XX-DWG-0005
C00M04-HPL-E_MC-304a-XX-MAR-0005
5. RESPONSIBILITIES
5.6 SUBCONTRACTOR HSE ENGINEER / OFFICER - Shall ensure all work permits are
available prior to commence of any work. Review personnel and their compliance with
safety requirements, such as wearing Personnel Protection Equipment (PPE). Check
work areas for any unsafe conditions. Liaise with Field Supervisors and Foremen that
work is carried out in accordance with Project Safety Plan / Procedure.
5.7 CONSTRUCTION TEAM (CT) - Subcontractor construction team comprises with
Construction manager, Site Engineers, and Foremen each holds their own
responsibility for the execution of this activity shall directed by Construction Manager
who holds the responsibility to perform the activity by all terms accepted & approved.
6. INSTALLATION
6.1 GENERAL
Ensure all relevant shop drawings are available at site for execution of work.
All the materials received at site shall be inspected as per relevant ITP
Obtain the necessary permit required for the mentioned activity.
All installation shall be done as per project specifications and project standard.
Loading of the equipment shall be done with suitable crane and as per the
manufacturer specification, if any.
Transporting; while transportation care shall be taken in order to avoid violently
shaken and damage to the equipment and apparatus mounted inside. Also make
sure that the equipment is not placed upside down while loading and transporting,
manufacturer recommendations shall be followed.
Unloading shall be done with suitable crane and adequate lifting tools.
Unpacking; prior to unpacking the Vendor representative has to be called
wherever applicable. If upon unpacking any visual damage of the equipment is
observed, the same shall be reported to the Management and Vendor.
Care shall be taken to see that the water protective packaging is not damaged.
Wastes - after unpacking the packing materials, has to be collected together and
transported and dumped at the appropriate location.
Equipment shall be protected from the ingress of sand and water after unpacking.
Unpacking; prior to unpacking the Vendor representative has to be called
wherever applicable. If upon unpacking any visual damage of the equipment is
observed, the same shall be reported to the Management and Vendor.
Care shall be taken to see that the water protective packaging is not damaged.
6.3 Unpacking Of Transformers
Employees shall maintain a safe distance from the people during removing
packing.
All protruding nails shall be removed or hammered down.
The dismantled materials to be stacked properly (don’t stack to height) and to be
barricaded.
Keep stripped materials stacked neat and orderly. Properly place feet for support
when prying forms loose.
Firefighting equipment’s must be available with carry out the hot work activities.
Certified Fire Watch must be present during and after hot work.
Don’t operate power tools in damp/wet conditions.
Ensure tools are fitted with dead man’s switch.
Double insulated tools must be used.
All equipment’s, power tools and electrical cords shall be inspected by a
competent personal, colour coded and validated prior to start the job.
All power cords, including extension cords must be maintained in a serviceable
condition to comply safety policy.
Avoid loose connection and multiple connections in one socket.
Ensure competent personnel are provided to operating the Equipment’s.
Auxiliary handle and safe guards must be with respective Power tools.
Sharp edges shall be shaped by file in a safe manner.
Good cable management must be ensured while using on ruff surface.
Electrical cords must be protected from damage while crossing access.
Hand placement shall be in safe positioning to avoid pinch points/ crushing injuries
Appropriate hand protection to be provided to those who involved in the activity
Suitable ear protection to be worn in noisy areas.
Dust mask must be worn during drilling and chipping.
6.5 INSTALLATION
1. WORK PROCEDURE
On receipt of the transformer and accessories at site, necessary precautions shall be taken for
unloading, moving & storage as follows:
Material shall be stored in a covered / dry space at all time.
All materials received at site shall be inspected and ensure that the materials are as per
approved material submittal.
Any discrepancies, damage etc. found will be noticed and reported for further action.
The site engineer has to ensure that all equipment used at site is free from any damage
or deformity of any kind. Any minor damage observed shall be repaired suitably and in
case if the repairs could not be done correctly, the equipment are to be removed from
site.
All material deliveries shall have certificates documents such as certificate of origin, etc.
TESTING EQUIPMENTS
MATERIAL REQUIREMENTS
Wood planks
Fasteners
Sealants
Rivets
Brush
Approved Paint
QUALITY
Quality system shall be in accordance with the quality manual and inspection test plan (ITP)
together with all related / referenced procedures.
QC Engineer shall establish a proper coordination with the representative of the
CONTRACTOR/COMPANY regarding Quality and keep records of all inspections related to
the works.
Quality system shall be in accordance with the approved Project Quality Plan, ITP’s, Quality
Control Procedures together with approved drawings and specifications.
Construction team shall always ensure compliance with the quality requirements.
QC Engineer shall establish a proper coordination with the representative of the
CONTRACTOR/COMPANY regarding Quality and keep records of all inspections related to
the works.
HSE TEAM
Subcontractor HSE team comprises Site HSE manager, HSE engineers, safety officers and
safety assistants and are responsible for ensuring compliance with HSE standards and
procedures during execution of the works.
A team of Construction engineer, Field engineer & HSE Engineer shall be responsible for
carrying out complete job safety analysis (JSA) and mitigation proposal and HSE Engineer
shall coordinate with COMPANY/CONTRACTOR HSE team and getting their approval for the
same.
Safety is everybody’s responsibility, foremen, construction site engineers, construction
manager shall ensure implementation of safety requirements and Site HSE manager and HSE
team holds the responsibility to ensuring that all safety requirements mentioned in project
standards & HSE policy including those mentioned in this procedure & JSA are followed
entirely and strictly during the execution.
HSE
Health, Safety and Environmental consideration is of foremost importance.
SUBCONTRACTOR is firmly committed to full compliance with all applicable HSE industry
standards and local laws.
SUBCONTRACTOR shall be responsible to implement these policies fully within the project.
SUBCONTRACTOR shall be responsible for monitoring the activities of the site operations and
for coordinating with COMPANY Site HSE Manager for any support or emergency response
that is required. He shall be responsible for ensuring all personnel on the project are suitably
trained and that all safety certifications, documentation for the equipment are available.
All personnel shall obtain necessary safety induction training and required passes prior to
mobilization to island and SUBCONTRACTOR construction & HSE team shall ensure that all
works shall be carried out in accordance with approved HSE plan / risk assessments(RA)
CONTRACTOR / SUB CONTRACTOR shall follow all safety requirements and PTW system
set by COMPANY.
REFERENCE DOCUMENTS
SOP- MOWP process- Version 1.2 2.
QAQC plan
BIAL - Projects Construction EHS Regulations
SITE ACCESS-STP
ATTACHMENTS
Risk Assessment (RA)
STP Project team Emergency Contacts