Professional Documents
Culture Documents
1.0 PURPOSE
The purpose of this procedure is to describe the system of control for all activities and define the
sequence of work for installation of HV, MV & LV Cables. This procedure also includes the
interface activities, and responsibilities relating to HV, MV & LV Cables Installation & Testing
activities, in compliance with project specifications and IFC drawings.
2.0 SCOPE
The scope of this procedure covers the activities during the Installation & Testing of HV, MV &
LV Cables and related inspection activities
3.0 REFERENCES
3.2.1QA/QC Documents:
4.1 Company :
4.2 Contractor :
4.3 Sub Contractor
4.7 ITP : Inspection and Test Plan
4.9 QA : Quality Assurance
4.10 QC : Quality Control
4.11 RFI : Request for Inspection
4.13 NCR : Non Conformance Report
4.14 PQP : Project Quality Plan
4.10 HSE : Health Safety & Environment.
Following are the roles and responsibilities of personnel involved in this scope of procedure.
Cranes, Fork Lifts, lifting belts, slings and other necessary tools and tackles for rigging &
material handling operation shall be calibrated & colour coded as per HSE requirement
Hand tools & calibrated all testing Equipments suitable for HV, MV & LV Cables installation
and testing.
The Supervisor / Foreman shall ensure that the equipment & accessories used are suitable for
the job and are in good working condition to complete the electrical work shall be as per good
engineering practices.
The Engineering Department shall issue to construction department the Issued for Construction
Drawings provided with Material Traceability List complete with information such as identified
profile and description to corresponding material items.
After receiving the Issued for Construction Drawings, the Construction Department shall request
the equipment from the Store. The Store shall issue the Material issue Slip with equipment
stated.
The measuring instruments like Insulation tester, Multimeter, Phase sequence meter,
Hi-pot Tester, surveying instruments, spirit level, measuring tape etc. deployed during
installation & inspection activities shall be calibrated periodically once in six months at certified
laboratory and the certificates may be submitted for review The certificates are to be made
available at site during various stages of inspection.
9.0 QUALITY CONTROL
9.1.1 Check the availability of “IFC” drawings, vendor manuals and instructions etc.
9.1.2 All material received shall be stored according to the installation schedule,
material identification & traceability and manufacturer’s instruction.
9.1.3 All Material Receiving Inspection to be completed before installation in position and if any
discrepancy found, item will be entered in the punch list and maintain a record further inform to
site Engineer immediately.
9.1.4 Verify the quality, year of manufacturing (if any) and country of origin.
9.1.6 Proper protection will be provided against wind, dust, rain corrosion etc as per
material preservation procedure
9.2.1 Check and verify the installation Procedure and make sure the proper method
of installation is being used as per the approved Method Statement
9.2.2 Verify the cable type, size, colour and route of the cables are as per the
approved drawing & cable schedule.
9.2.3 Continuity & Insulation resistance test on drum. Insulation resistance shall not
be less than as per DEP 63.10.08.11-Gen, A12.2 (10 x kV / km) in MΩ
9.2.4 Verify cable trench & sand bedding as per project specification.
ie, 132 kV 100 mm & all other cable 75 mm
9.2.5 Ensure trained, well experienced and skilled persons do the cable pulling.
9.3.1.1 Verify the laying sequence of the cables to avoid crossing and over lapping.
9.3.1.2 Check and verify the installation Procedure and make sure the proper method
of installation is being used as per the approved Method statement for
installation of cables
9.3.1.4 Cable roller shall be placed at the span of every 10 meters and angle roller at all turning
points where there is a change in direction.
9.3.1.4 Follow the direction shown in the cable drum for the rotation of cable drum.
9.3.1.5 Make sure the cable coming from the top of the drum and cable shall not drag
on the floor.
9.3.1.6 Follow and adhere to the manufacturer’s permissible pulling force for cable pulling.
9.3.1.8 Each set of single core cables comprising a three phase circuit shall be run
close together in trefoil formation.
9.3.1.9 Cable crossing under road shall be through reinforced concrete duct bank.
9.3.2.1 Cable shall be laid on trays in accordance with laying pattern indicated on
AFC layout drawings.
9.3.2.2 The cut end of the cable shall be protected from moisture entry.
9.3.2.3 Cable identification shall be for underground and above ground application, engraved
stainless steel cable tags, at each end, at both ends of sleeves, all entry point to JB and along the
route shall not exceed 10 M for under ground cabling. For above ground cabling the spacing
between cable number shall be at every 25 meters. Cable shall also be numbered where they
branch off from main route.
9.3.2.4 Witness & verify continuity & insulation resistance test are carried out as acceptable
critical DEP 63.10.08.11-Gen, A 12.2 before and after installation of every length of cable.
9.3.2.5 Witness & verify the Hi-pot test for HV & MV Cables. The test voltage & timing
of Hi-pot test shall be as per DEP 63.10.08.11 Appendix A 11.1.1
9.4 QUALITY CONTROL CHECK DURING CABLE JOINTING & TERMINATION
9.4.1 All cable joints / termination shall be strictly in accordance with cable manufacturer’s
recommendation
9.4.2 All cable joints / termination kits shall be compatible to the cable and shall be
Confirmed by the cable manufacturer.
9.4.3 At most care shall be taken while preparing the cable for jointing / termination
9.4.4 Qualified and well experienced person shall be engaged for cable jointing /
termination
9.4.5 Check continuity & insulation resistance with calibrated instrument before cable jointing /
termination.
9.4.6 Check and ensure the cable jointing / termination kit is complete with all
materials as per the packing list.
9.4.7 All cable conductor shall be fitted with company approved make & correct size ferrule / leg.
The ferrule / leg shall be crimped compression type as specified by the manufacturer.
9.4.8 Cable glands shall be double sealed compression type with earth clamping features to IP55.
9.4.9 All EE xd, EE xe cable glanding and termination shall be done by trained technician
10.0 TESTING
RFI shall be raised 24 hours before the actual schedule for inspection as per
approved ITP
12.0 HEALTH AND SAFETY REQUIREMENTS
12.1 Hazards:
Accidents during loading & unlading cable drums from storage yard to the point of installation
Personal injury during cable pulling and using torch blower for heating during cable
termination & joining.
Electric shock during megger testing / Hi-pot testing.
Pollution due to excess & waste materials.
Prior to commencement of any activity, all personnel involved on the job shall attend the
project HSE Induction training.
The site management, supervisors and safety officers will closely supervise and monitor all
phases of activities in connection with the compliance of safe working models.
All equipment like Cranes, Fork lifts, Chain pulley blocks, lifting belts, slings and other
necessary tools and tackles for rigging & material handling operation, electrical equipment etc.
shall be inspected by competent personnel prior to use at site. Equipment will be regularly
checked and inspected by the safety officer.
Any accident / Injury / near miss shall be reported immediately to appropriate authorities.
Work shall stop and area secured until approved
The Construction Engineer / Supervisor shall immediately correct any hazards observed or
reported to him. In the case of major hazards, work shall be stopped and appropriate and
satisfactory permanent action to remove the hazards shall be taken.
Good housekeeping shall be maintained at all times
All activities reflected to HSE shall be carried out according to the approved documents
a) Project HSE Plan –
b) Contractor HSE Plan –