Professional Documents
Culture Documents
CGK 063
3.0 DEFINATIONS
Terms Definition
Project CGK 063
JO PT Jaya Obayashi
MOS Method of Statement
MSA Material Submission Approval
Table 1: Definitions
4.0 REFERENCE
The following Standards of Practice shall be applicable to the works:
− STULZ India Factory : Eurovent Certified
− ISO 9001: 2015 : Design, Manufacture and Supply of Precision Air-
Conditioning, Air Handling Units, Intelligent Server Rack and
Allied Products.
− ISO 14001: 2015 : Design and Manufacture of Precision Air-Conditioning, Air
Handling Units, Intelligent Server Rack and Allied Products.
− ISO 45001: 2018 : Design and Manufacture of Precision Air-Conditioning, Air
Handling Unit, Intelligent Server Rack and Allied Products.
5.0 RESPONSIBILITIES
No. Designation Qty Responsibility
Responsible for overall commercial, contractual
& technical performances associated with
1 Project Manager 1
specific project. Reporting to the Project
Director.
2 M&E Engineer 4 Planning and supervising installation activities.
Inspect, verify, and prepare work statement for a
quality installation works. Material storage, fit
3 QA / QC Engineer 2
for use tools and equipment, and installation
works
To provide toolbox and guidance to work and to
4 Safety Officer 1
ensure that work is carried out in a safe manner.
Obtain permit to work, control the sequence
according to MOS, approved shop drawings, and
MSA, ensure mechanical aspects of the work are
according to the specifications, ensure safe
practices are followed and ensure quality of
5 Supervisor 3-5
workmanships during execution. Ensure material
temporary storage and protection meet vendor
and standards requirement. Ensure tools being
used for installation are calibrated and meet
vendor and standards requirement
To carry out all the mechanical aspects of the
6 General Workers 10-15
unloading and positioning for DAHU.
6.2 Material
Materials are as below.
− Pull & down the all the palettes and put it in approved space area and
split the area based on quantity of the DAHU delivered (note: STULZ
coordination with GC).
TRUCK ACCESS ROAD
TC 3
DAHU GALERY
CLEAR AREA
33 M ± 7.75 TON
43 M ± 5.65 TON
56 M ± 4.05 TON
A B C D E F
UNLOADING UNIT FROM TOWER CRANE TO HAND PALLET
MOBILISASI & POSITIONING DAHU WITH FORKLIF IN THE DAHU GALLERY
POSITIONING & INSTALLAION UNIT 1
− Ensure all foundation bolt has been drilled based on approved drawing.
Unit 1 – Base Dimension
Note: Marking & providing anchor bolt by STULZ, Drilling & installation anchor
bolt by GC.
− Assembly Lower Module of DAHU.
• Lift the fan module lower and place to approved assembly area.
• Lift the coil module lower and put beside the fan module lower for
assembling.
• Lift the filter module lower and put beside the coil module lower
for assembling.
Note: Lifting by GC& STULZ coordination with GC for lifting & assembly.
− Lift the lower deck from assembly area to DAHU position on the
mechanical gallery. Do positioning and installed the anchor bolt.
− Assembly Upper Module of DAHU.
• Lift the fan module upper and place to approved assembly area.
• Lift the coil module upper and put beside the fan module upper
for assembling.
• Lift the filter module upper and put beside the coil module upper
for assembling.
Note: Lifting by GC & STULZ coordination with GC for lifting & assembly.
− Lift the upper deck from assembly area and join to lower deck which has
been anchored on the mechanical gallery.
• Joint the unit base (upper deck) to lower deck.
• Joint the Chiller Water pipe for upper & lower deck.
• Install internal wiring (power & control cables).
Note: Lifting by GC
2. POSITIONING & INSTALLAION UNIT 2
− Ensure all foundation bolt has been drilled based on approved drawing.
Unit-2 base Installation should be carried out next to Unit-1 base.
− Lift the fan module lower from assembly to DAHU unit-2 position on the
mechanical gallery. Do positioning and installed the anchor bolt.
Picture 9: Lift the fan module lower from assembly to DAHU unit-2 position
Note: Lifting by GC & STULZ coordination with GC for lifting & assembly.
− Lift the coil module lower from assembly to DAHU unit-2 position on the
mechanical gallery. Do positioning and installed the anchor bolt.
Picture 10: Lift the coil module lower from assembly to DAHU unit-2 position
Note: Lifting by GC & STULZ coordination with GC for lifting & assembly.
− Lift the filter module lower from assembly to DAHU unit-2 position on the
mechanical gallery. Do positioning and installed the anchor bolt.
Picture 11: Lift the filter module lower from assembly to DAHU unit-2 position
Note: Lifting by GC & STULZ coordination with GC for lifting & assembly.
− Lift the other module and put on the respective module which has been
anchored on the mechanical gallery.
a. Fan module upper to fan module lower.
b. Coil module upper to coil module lower.
c. Filter module upper to filter module lower
• Joint the unit base (upper deck) to lower deck.
• Joint the Chiller Water pipe for upper & lower deck.
• Install internal wiring (power & control cables).
Picture 12: Lift the other module and put on the respective module which has been anchored
Note: Lifting by GC & STULZ coordination with GC for lifting & assembly.
UNLOADING & POSITIONING WITH TC-2 (PHASE-1)
UNLOADING & POSITIONING WITH TC-3 (PHASE-1)
UNLOADING & POSITIONING WITH TC-2 (PHASE-2)
UNLOADING & POSITIONING WITH TC-2 (PHASE-3 & PHASE-4)
− Install Inner-Module Jointing Plates – for Unit 2 ONLY.