Professional Documents
Culture Documents
CGK 063
1.0 PURPOSE.......................................................................................................................................................
2.0 SCOPE OF WORK...........................................................................................................................................
3.0 DEFINATIONS................................................................................................................................................
4.0 REFERENCE....................................................................................................................................................
5.0 RESPONSIBILITIES.........................................................................................................................................
6.0 PROCEDURE..................................................................................................................................................
6.1 General Description...............................................................................................................................
6.2 Material..................................................................................................................................................
6.3 Plants, Machinery & Equipment............................................................................................................
6.4 Manpower..............................................................................................................................................
7.0 PROCEDURES REFRIGERANT & CONDENSATE PIPE INSTALLATION...........................................................
7.1 Introduction...........................................................................................................................................
7.1.1 Pre - Planing Stage.......................................................................................................................
7.2 Receiving Material at Site......................................................................................................................
7.3 Refrigerant Pipe Installation..................................................................................................................
7.3.1 Refrigerant Fabrication................................................................................................................
7.3.2 Flushing Pipe.................................................................................................................................
7.3.3 Pipe Leakage & Pressure Test.......................................................................................................
7.3.4 Vacuum.........................................................................................................................................
7.3.5 Charging........................................................................................................................................
8.0 APPENDICES..................................................................................................................................................
8.1 Drawing..................................................................................................................................................
As Attached Drawing.............................................................................................................................
8.2 RISK ASSESSMENT (RA)..........................................................................................................................
8.3 INSPECTION TEST PLAN (ITP).................................................................................................................
8.3.1 CGK063-ITP-RFSI-Request for Site Inspection.................................................................................
8.3.2 CGK063-ITP-M.03 - Site General Report..........................................................................................
8.3.3 CGK063-ITP-M.04 - Site Defect Inspection Report..........................................................................
8.3.4 CGK063-ITP-M.13 - Piping Installation Checklist.............................................................................
8.3.5 CGK063-ITP-M.14 - Condensate Drain Pipe Water Leakage Test...................................................
8.3.6 CGK063-ITP-M.15(1) - Condensate Flow Test Before Insulation.....................................................
8.3.7 CGK063-ITP-M.15(2) - Condensate Flow Test After Insulation.......................................................
8.3.8 CGK063-ITP-M.16 - Piping Pressure Test & Leakage Function Test................................................
8.3.9 CGK063-ITP-M.17- Pipe Flushing Test.............................................................................................
1.0 PURPOSE
The purpose of this statement is to document the correct procedure and installation of
refrigerant & condensate pipe for CGK 063 project, and to ensure that all concerned
are familiar with the sequence of activities, utilization of resources and execution of the
works in compliance with applicable safety, quality procedures and project documents
and specification.
3.0 DEFINATIONS
Terms Definition
Project CGK 063
JO PT Jaya Obayashi
MOS Method of Statement
MSA Material Submission Approval
Table 1: Definitions
4.0 REFERENCE
The following Standards of Practice shall be applicable to the works:
ASTM C921 : Standard Practice for Determining the Properties of Jacketing
Materials for Thermal Insulation.
NFPA : National Fire Protection Association
5.0 RESPONSIBILITIES
No Designation Qty Responsibility
.
Responsible for overall commercial, contractual
& technical performances associated with
1 Project Manager 1
specific project. Reporting to the Project
Director.
2 M&E Engineer 4 Planning and supervising installation activities.
Inspect, verify, and prepare work statement for a
quality installation works. Material storage, fit
3 QA / QC Engineer 2
for use tools and equipment, and installation
works
To provide toolbox and guidance to work and to
4 Safety Officer 1
ensure that work is carried out in a safe manner.
Obtain permit to work, control the sequence
according to MOS, approved shop drawings, and
MSA, ensure mechanical aspects of the work are
according to the specifications, ensure safe
practices are followed and ensure quality of
workmanships during execution. Ensure material
5 Supervisor 3-5
temporary storage and protection meet vendor
and standards requirement
6.2 Material
Materials are as below.
No Description Brand
1 Refrigerant Piping and Fitting KEMBLA ASTM B280
K-Flex
2 Refrigerant Insulation Pipe
Class "0"/ Density: 48 - 70 Kg/m3
6.4 Manpower
The actual manpower of each type of installation may vary according to the site
condition and requirement.
All workers shall wear appropriate PPE (Hard Hat, Protective Boots, Goggles,
High Visibility Vest and Protective Gloves) and safety harness when working
above 2 meter in height.
7.0 PROCEDURE REFRIGERANT & CONDENSATE PIPE INSTALLATION
7.1 Introduction
Refrigerant and condensate pipe installation is applied for VRF system with
water cooled type system, the implementation of work must follow the Shop
Drawing and specifications.
PINCHING
TAPING
2. Flaring
This point must be check while worker do a flaring works,
Uniform flare size and shiny inside surface.
Flared part has uniform wall thickness.
Flare has appropriate size.
NOTE: Precisely round and uniformly shaped, shiny inside with no
scar/scratch.
Remaining of burrs
Scar/scratch by filings
Undersized
Oversized
Crack
3. Brazing
Procedure for copper tube brazing:
Adjust torch flame; Make sure torch flame gets neutral before starting
brazing.
Pre-heating; Evenly heat tube and socket part. DO NOT keep placing
torch flame in a single spot but continue moving it. Proper pre-heat
temperature ranges 1000°F, brazing alloys containing more than 0.05
percent phosphorus are prohibited. Finish heating on socket side,
rather than tube.
Place torch flame at as right angle as possible with tube surface, and
heat tube and socket part.
Picture 4: The Pre-heated & Brazing Process
Good Bad
Picture 6: Brazing connection results
4. Insulation
All copper tube will insulation with formed nitrite rubber 19mm, but
when installation every joint, and fitting will install insulation after pipe
line finish leakage and pressure test and test was acceptable. Bellow its
detail for insulation copper tube:
Flare connection; Attach and fill insulation material around flare nut
of liquid and gas lines separately. Press insulation onto equipment
surface and secure it with tape, etc.
Brazed joint; Ensure brazed part is cooled off until it can be touched
with bare hands. Attach and fill appropriate size of insulation material
and secure it with tape, etc.
Elbows; Cut slits in insulation material and slide it over piping length
wise. After piping is bent, slide insulation back to bent (elbow) part.
Refrigerant branch piping; Fill insulation material in the gap between
refrigerant pipe insulation and branch connection insulation.
Equipment connection; Prevent condensate from infiltrating
refrigerant piping.
Do not install insulation until system testing has been completed and
all leaks have been eliminated. Pre-insulated pipe is acceptable.
Install piping free of sags or bends and with ample space between
piping to permit proper insulation applications.
Install piping tight to slabs, beams, joists, columns, walls, and other
permanent elements of the building. Provide space to permit
insulation applications, with 1 inch clearance outside the insulation.
Allow sufficient space above removable ceiling panels to allow for
panel removal.
Picture 7: Installation of insulation on the connection
7.3.4 Vacuum
Vacuum purposed for remove moisture from system and dry inside
piping. Moisture remaining inside piping may result in lowering of
system performance, i.e. compressor damage. Caution:
PROJECT : 063
Category:
Material/Equipment:
Manufacturer: Model:
Inspection Report
Date : Date :
No. DESCRIPTION Check Check Re marks
(Sub-contractor) (Main Contractor)
1 No Physical Damage ? OK / NG OK / NG
2 Details given above correct ? OK / NG OK / NG
3 Conform with Approved submission ? OK / NG OK / NG
4 Accessories/ Spare Parts included ? OK / NG OK / NG
OK / NG OK / NG
The above material has been inspected on Site and found at time of inspection to be
Satisfactory / Unsatisfactory
Comments
Signature
ME MANAGER ENGINEER SUB-CONTRACTOR