1. PURPOSE
This procedure describes the installation and installation inspection activities of the
mechanical and chemical anchors in the concrete structures.
2. DOMAIN
This procedure applies to installation of the mechanical and chemical anchors in the
concrete structures of the industrial, nuclear installations and other areas, achieved by S.C.
ELCOMEX I.E.A. S.A.
4. REFERENCE DOCUMENTS
NOTE: The user’s responsibility is to ensure that it is using the valid editions of the
documents, by reading the reference list of the documents.
5. RESPONSIBILITIES
Position / Competence
5.1. Site Supervizor
5.1.1. Shall ensure that the works will be performed with corresponding tools and devices as well as
with measurement devices with metrological visa.
5.1.2. Shall ensure that the works will be performed by qualified and licensed personnel.
5.1.3. Ensures distribution of the present procedure at all subordinate operational entity and verifies its
implementation.
5.1.4. Ensure that Health and Safety Plan is implemented.
5.2. Area Supervisor
5.2.1. Ensures that the preliminary conditions to start the work are accomplished.
5.2.2. Ensures that the installation works are performed according to design and observing present
procedure provisions.
5.2.3. Ensures the work performing only with trained, qualified and authorized personnel as necessary
3|7
5.2.4. Is responsible to use only authorized equipment, accredited and tested tools and devices.
5.2.5. Is responsible to use only the materials specified by design.
5.2.6. Is responsible to instruct all subordinated personnel with the provisions of present procedure.
5.2.7. Is responsible for the good evolution of the works from technical viewpoint, organizationally, of
health and safety work, of fire protection and of the environment protection.
5.2.8. Confirms the quality of the work in the related quality records.
5.2.9. Notify CTC Department before starting the works and the activities marked with H or W in
specific ITP. Cooperates with CTC Department during whole duration of the works.
5.3 QC Responsible for work
5.3.1. Controls the installation works according to design, present procedure and specific ITP/Quality
Plan.
5.3.2. Confirms the quality of the work by signing, dating and stamping the related quality records.
5.3.3. Uses only tools and control devices with valid metrological visa to control the works.
6. PROCEDURE
6.1 General Requirements
6.1.1 Prerequisites
All the people who perform installation and control of mechanical and chemical
anchors must be taught and familiarized with this procedures.
All installation anchors operators must be familiarized with the properties of the tools,
machines and devices to be used and understand the operational regulation and methods.
All the necessary tools, anchors and devices are available, inspected, calibrated in order to
perform the installation. Tools and devices are:
a) Drill Press;
b) Drill bit, Diamond Core bit;
c) Compressed air source or blow-out bulb;
d) Torque indicator wrenches;
e) Health and Safety Plan is Implemented.
6.1.2. All concrete mechanic/chemical anchors shall be installed in accordance with
manufactured specifications and recommendations and the requirements specified herein.
6.1.3 The locations where concrete mechanic/chemical anchors will be installed, and the
types and sizes of the anchors, shall be as specified by design and/or design modification
documents.
6.1.4 The minimum effective embedded (anchorage) length, spacing and edge distances
for concrete mechanic/chemical anchors shall be conform to design and manufacturers
specifications.
6.1.5 Welding on concrete mechanical anchors is not allowed, if longer bolts are required,
client approval is required.
6.1.6 After the anchors are installed, the sealing around the anchors and plates shall be
according to design.
6.1.7 For nuclear systems Installation it is not permitted to use plastic anchors.
5|7
6.3.9 When installing support/ equipment base plates on shims, 50% of torque value will be
applied to anchors. The remainder will be applied after grouting or injection material has cured and
only after the grouting injections and the used materials reached the strength as per specifications
or project.
6.3.10 Where the concrete surface is uneven the following criteria/procedures shall be
followed, unless otherwise provided by design:
a) Gaps between the mounting concrete surface and the anchor plates are
acceptable without shimming if width of gap along the length of the anchor plate
does not exceed the tolerances as per project or manufactured technical
specification.
b) For gaps not meeting the requirements as per project or manufactured
specification, the concrete surface shall be improved by grinding or bush
hammering or by grouting.
c) For floor mounting supports, the shims shall be flat or tapered and of the thickness
as required to fill the gap and must be located between anchors. The shims shall
extend into the gap as required but need not exceed dimensions of supporting
plate. All shims shall be made of the same material as the plate.
d) Inject the gap under the plate with client accepted material.
6.3.11 These criteria/procedures need not to be met when:
a) base plate assemblies are supporting rod-type hangers only;
b) two-anchor base plate assemblies are supporting electrical conduits;
c) four anchor base plate assemblies are indicated on the Design Drawing as S.N.R.
(Shimming not required).
6|7
Engineering Department will approved the changes as per specified by anchors
bolts manufactured specifications.
e) For plates, supports or other elements not fabricated, it is strongly recommended
that holes in those plates shall be drilled after the completion of the concrete
drilling to match the anchor location. If the anchor location has been relocated for
some rebar anchor interference reason, the holes in the plates shall be field drilled
to suite the new anchor location.
7.2 Appendix
7.2.1. FORM-ELC-075 rev.4 - Measurement Sheet for Mechanical/Chemical Anchors
Torque Moment.
7|7
Measurement Sheet for Mechanical/Chemical Anchors Torque Moment
Page
of:
No. dwg: Anchors type
Client:
Order / Contract: Support code/equipment/steel structures: