THE PROCEDURE FOR INSTALLATION OF POWER
Florinel Petrilă November ‘17
AND CONTROL CABLES
APPROVED BY DATE
Gheorghe Ţăranu November ‘17
2|8
1. PURPOSE
This procedure establishes and describes the installation activities for electric power and
secondary cables.
2. SCOPE
The herein is applicable to installation of electric power and secondary cables within
electrical, automation and data systems and for the technological systems they serve.
3.1.2 - Secondary 3.1.2 – the cable used within instrumentation, signaling, control, block up, protection
cable and automation systems of voltage inferior to 400V. This category includes cables
for remote protection, tele-management, data transmission, having a service voltage
lower than 60V used in tele-signaling. Tele-measure, remote controls and remote
protection systems.
3.1.3 – Installation 3.1.3 – a document (cable list, IntEC sheet, DICON sheet, drawing, manufacturer
design specifications and instructions etc.) accepted by the client, containing all necessary
data (the equipment to be connected via a cable, cable type, route, terminal points
to connect the electric connection between two equipment.
4. REFERENCE DOCUMENTS
3|8
NOTE: The user’s responsibility is to ensure that it is using the valid editions of the
documents, by reading the reference list of the documents.
5. RESPONSIBILITIES
Position / Competence
5.1. Site Superintendent
5.1.1. Shall make certain that works shall be accomplished with proper calibrated tools, devices and
instruments.
5.1.2. Shall make certain that only well qualified and trained personnel will perform the work.
5.1.3. Shall provide the working team with contractual documents, updated technical documentation as
well with applicable work procedures.
5.2. Work Supervisor
5.2.1. Shall ensure that the necessary preliminary conditions to start the work are in effect.
5.2.2. Ensures that the installation works are performed according to the installation documentation
and observing present procedure provisions.
5.2.3. Ensures the work performing with qualified and authorized personnel, as necessary.
5.2.4. Is responsible to instruct all subordinated personnel with the provisions of present procedure.
5.2.5. He answers for the good evolution of the work from technical viewpoint, organizationally, of
security of the labor, of fire prevention and of the environment protection.
5.2.6. Confirms the quality of the work in the related quality records.
5.2.7. Notify CTC Department before starting the works and the activities marked with H or W in
specific ITP. Cooperates with CTC Department during whole duration of the works.
5.3 CTC responsible of the work
5.3.1. Shall control the installation works as per specific ITP.
5.3.2. .Shall confirm the quality of works by signing, dating and stamping the related quality records.
6. PROCEDURE
6.1 Preliminary conditions
6.1.1. Before laying the cable, preliminary conditions must be ensured.
6.1.2. Cable trenches have been digged and cable trays, conduits / tubes are installed and
the equipment to connect the cables are installed.
6.1.3. Before pulling cables the correspondence between design and site, regarding the
route shall be verified.
6.1.4. Cables reel was stored for at least 12 hours in a room at minimum 20 °C if air
temperature is lower than the one specified by cable manufacturer as minimum temperature when
pulling cables.
6.1.5. Before pulling cable on the drum continuity and insulation resistance have been
checked and the results are corresponding.
6.1.6. Before pulling each cable shall be identified according to design with a waterproof
tag.
6.1.7. When pulling cables in conduits / tubes, the cleanliness of the conduit / tube and lack
of moisture shall be verified. It is not permitted to pull cables in flashed conduits, with zinc spatters
or moisture.
6.1.8. Before pulling cables in conduits, the following verifications shall be performed:
a) interior diameter of conduit / tube is 1.5 greater than cable external diameter;
b) when several cables must be pulled in a conduit, conduit cross-section is 2+2.5
greater than the sum of cables cross-section.
6.1.9. A cable reserve to compensate deformations and to permit terminals and cable
sleeves renewal shall be provided in the following cases:
4|8
a) both sides of the penetrations;
b) for all cable sleeves, regardless of installation place, nominal tension or cable
type;
c) at the ends of cable route for cable with nominal tension of 6 kV or higher,
regardless of cable type;
d) when passing between structures with different vibration behavior.
6.1.10.The following minimum lengths shall be provided for the reserves:
a) for sleeves and penetrations the length necessary to remake twice the respective
sleeve;
b) for terminals the length necessary to remake once the respective terminal.
5|8
6.3.6. In cities and inhabited areas cables shall be installed, usually, in the non-passable
part of the streets (under the sidewalk) or, in certain conditions, in the green areas of the inhabited
areas.
6.3.7. Cables installed in the passable area of the streets shall have appropriate mechanical
protection.
6.3.8. The order of cables installation under the sidewalk, from building to the passable area
are (keeping the distances between the cables):
a) low voltage distribution cables;
b) medium voltage distribution cables;
c) pilot-wire cables for tele-management
d) public lighting cables.
6|8
6.6 Cables installed apparent
6.6.1. Cable supports shall be installed parallel to constructive lines of the buildings when
installing cables apparent.
6.6.2. If not otherwise specified by design, distances between supports shall be as follows:
Horizontal Vertical
(mm) (mm)
Unsheathed cables 500 1000
Sheathed cables 800 1500
.
6.6.3. If the vertical length of cable route is more than 7.5 m and cable weight is greater,
than the pulling tension distances between supports will diminish.
7|8
6.9 Cables connection to equipment
6.9.1. Cable terminal head shall be fastened in the equipment as per design requirements
using plastic straps.
6.9.2. If not otherwise specified by design, the cable shall be fastened at least 0.5 m before
connection.
6.9.3. A reserve sufficient for an eventual reconnection shall be ensured in the equipment.
6.9.4. The conductors will be identified according to point 6.6 and will be connected to
equipment terminals according to design.
6.9.5. The metallic shield of the cables shall be connected to the grounding system
according to design requirements.
6.9.6. It is not allowed to connect more than to conductors into a terminal / connector.
6.9.7. Conductors fastening screw shall be tightened according to connector’s manufacturer
torque moments.
8|8