Professional Documents
Culture Documents
TABLE OF CONTENTS
PART 1 GENERAL 1
1.04 REFERENCES..................................................................................................... 2
1.06 SUBMITTALS....................................................................................................... 5
PART 2 PRODUCTS 9
PART 3 EXECUTION 24
PART 1 GENERAL
A. This Section specifies the minimum technical requirements for design engineering,
furnishing, manpower, installing and supervision, of Conductors and Cables as per
the Contract Documents.
B. The Contractor shall, as part of his full responsibility scope, check the conductors
and cables as specified in the Contract Drawings/Documents. When this check
indicates that the specified conductors and cables are not adequate, the Contractor
shall notify the Royal Commission and take the necessary action/changes with
approval by the Royal Commission.
C. The Contractor shall also check and verify every requirements, aspect and detail
necessary for coordinating with new or existing systems of conductors and cables.
D. These Specifications define the minimum requirements for conductors and cables
with either IEC/SASO or North American based standards, as specified in par. 1.04.
1.04 REFERENCES
A. The referred codes and standards are intended to provide an acceptable level of
quality for materials and products. In case of conflict between these standards and
the text of this Specification, the Specification text shall govern.
B. The latest revision of the referred codes and standards shall be used wherever
applicable. In case of conflict, the Contractor shall propose equipment conforming to
one group of codes and standards.
4. ASTM E28 Test Method for Softening Point by Ring and Bell
Apparatus
5. IEC 60840 Tests for Power Cables with Extruded Insulation for
Rated Voltage Above 30 kV (Um = 36 kV) up to
150 kV (Um = 170 kV)
1.05 DEFINITIONS
A. ampacity: The current in amperes that a conductor can carry continuously under the
conditions of use without exceeding its temperature rating.
G. heat shrink: A material used to connect two pieces of conductor together. The
material shrinks to fit when heat is applied.
I. jacket (the outer covering of a cable): A tough plastic material that provides
physical protection for the cable. Jacketed cable protects against physical damage
and corrosion, thus reducing the risk of damage to the primary neutral.
J. manhole: A subsurface enclosure which personnel may enter, manholes are for
installing, operating and maintaining underground cable systems.
K. splice: The joining of two or more cables by connecting the conductors pair to pair.
L. shield (screen): A metallic layer usually in the form of a braid of foil surrounding one
or more electrical conductors to insulate them from electromagnetic interference.
M. overcurrent: Any current in excess of the rated current of equipment or the ampacity
of a conductor. It may result from overload, short circuit, or ground fault.
1.06 SUBMITTALS
A. The Contractor shall submit to the Royal Commission, under the provision of
SECTION 01330, the following items for review and approval before commencing
work:
a) List of manufacturers.
g) Certificate of compliance.
B. The Contractor shall submit field test reports after the completion of Testing and
Commissioning.
A. The Contractor shall be responsible for the quality of work and shall develop and
propose programs and methods of construction and testing such as to achieve the
specific quality to the approval of the Royal Commission in accordance with
SECTION 01450.
3. Contractor
B. In the absence of any of the above, best accepted industry practice shall be
employed throughout.
A. General
1. All conductors and cables and their accessories shall be tested at the factory
in accordance with the latest approved manufacturing codes and standards.
The Contractor shall notify the Royal Commission in writing not less than
30 days prior to the scheduled starting date of the factory tests.
2. The Royal Commission reserves the right of deputing their representative for
witnessing the factory testing.
3. Upon completion of factory tests, and before shipment of the conductors and
cables and their accessories, the Contractor shall submit 5 certified copies of
test reports not later than 10 days after the completion of all factory tests for
review and approval by the Royal Commission.
A. All the cables and accessories installed indoor shall be suitable for continuous
operation under the following service conditions:
a) A maximum of 40°C.
b) A minimum of 0°C.
B. All the cables and accessories installed outdoor shall be suitable for continuous
operation under the following service conditions:
a) A maximum of 50°C.
2. Altitude
C. All the cables and accessories to be installed in classified areas, as indicated on the
Contract Drawings, shall be suitable for such installation as per NEC Article 500.
A. The Contractor shall deliver, handle and store material and product units in
7. The Contractor shall be held responsible for damage of the cables and
accessories during storage or transportation.
PART 2 PRODUCTS
2.01 GENERAL
A. All goods and products covered in these Specifications shall be procured, when
available, from an in-Kingdom manufacturer. However, procurement of all goods and
products manufactured out-of-Kingdom or in-Kingdom must be approved by the
Royal Commission.
B. Where Royal Commission utilities interface with power company (SEC) the cables
and related materials shall be approved by SEC.
A. General
1. The cable shall meet or exceed the requirement of this Specification in all
respects.
2. The cables shall be manufactured in accordance with SASO, AEIC, ICEA, IEC
or equivalent standards.
3. The cable shall be designed for use in all low voltage power circuits and for
installation in conduits, underground ducts, cable trays, raceways or for directly
buried installations.
4. Cables shall be suitable for all service conditions as specified in par. 1.10
that occur in the areas where they are installed.
5. Cables shall be suitable for operation in wet or dry locations with alternately
wet and dry conditions. If exposed cable tray installations are used, cables
shall be suitable for operation in a sandy and salty atmosphere without
affecting its physical and electrical characteristics.
2. Single core cables shall not be larger than 300 mm2. Conductors 4 mm2 and
larger shall be stranded, while conductors below 4 mm2 may be stranded or
solid, as specified on the Contract Drawings.
2. The insulation shall be heat and moisture resistant, flame retardant and ozone
resisting compound suitable for 85/90°C maximum conductor temperature
under normal operating conditions.
Conductor Insulation
Conductor Size
Thickness (mm2)
No. of Strands
mm2 AWG or MCM PVC XLPE
D. Jacket
1. The jacket shall be black, ST 2 type, extruded PVC per IEC 60502-1 or ICEA-
S-66-524 with heat, moisture, oil, sunlight, acid, alkali and flame resistant
properties.
A. General
2. Cable material and construction shall be suitable for storage, installation and
operation in service conditions stated in par. 1.10. The impact of the higher
ambient temperature on ampacity will be factored in cable selection and
application during system design.
3. Conductor
4. Conductor Shield
b) The minimum thickness of the conductor shield shall not be less than
80% of the average thickness.
2. The minimum thickness of the insulation shall not be less than 90% of the
average thickness.
4. Insulation Shield
b) The average thickness of the insulation shield shall not be less than
125% of the minimum point thickness.
5. Metallic Shield
b) When copper tape is used as a metallic shield, the tape shall have a
minimum thickness of 0.178 mm applied at 25% overlap.
a) The moisture impervious layer shall be applied over the metallic shield
to prevent top ingress of moisture.
7. Jacket
8. Overall Diameter
70 40
95 41
120 43
185 47
240 49
400 56
500 59
TABLE 2G: FOR POWER CABLES WITH COPPER WIRE METALLIC SHIELD
9. Fabrication
d) The power cable shall be free of material and manufacturing defects that
would prevent it from meeting the requirement of this Specification.
A. General
1. The XLPE insulated power cable rated 115 kV shall meet or exceed the
requirements of this Specification in all respects.
2. For service conditions and other details, refer to par. 2.03 above.
1. The power cable rated 115 kV shall be manufactured in accordance with AEIC
CS7 and tested in accordance with AEIC CS7 or IEC 60840.
3. Conductor
b) For 115 kV power cable, conductor sizes shall be 400, 630, 800, 1000,
and 1200 mm2.
4. Conductor Shield
c) The outer surface of the conductor shield shall be cylindrical and shall
be firmly bonded to the overlying insulation. The extruded shield shall be
easily removable from the conductor.
3. Insulation Shield
4. Metallic Sheath
c) For power cables to be installed above water table level, the sheath
shall be extruded lead alloy or seamless tube of corrugated aluminum.
6. Jacket
7. Conductive Layer
8. Fabrication
d) The power cable shall be free of material and manufacturing defects that
would prevent it from meeting the requirements of this Specification.
A. The jacket for all the cables shall be marked by embossing in English at intervals not
exceeding 1 m with the following minimum information:
1. Electric Cable.
7. Year of manufacture.
8. Cumulative length at every 1 m with the highest length mark on the outer end
of the cable.
1. Connectors and splice caps shall be tin-plated copper (compression type only)
and shall meet the requirements specified in par. 1.04.
2. Terminal lugs required for termination on bolt or screw terminals shall be tin-
plated copper (compression type only).
1. General
2. Design Criteria
a) Splices
2) The splice system shall meet all requirements of IEEE 404, and
shall be designed such that no insulating or semi-conducting
tapes are required. Only heat-shrinkable polyolefin material shall
be acceptable.
3. Termination
4. Fabrication
a) Splices
5) In case of tape armored and shielded cable, all items needed for
wire or tapes clamping shall also be included. Ratings shall be
provided for such applications.
b) Termination
c) Marking
1. General
2. Design Criteria
a) The splice design shall also prevent the presence of air especially at
stress points.
c) The jacket tubing, if needed, shall be generally suitable for indoor and
outdoor installation, be ultraviolet and chemical resistant and with or
without adhesive coatings. It shall also be capable of being stored
without damage at temperatures not exceeding 50°C. Shelf life of the
jacket tubing shall be at least 5 years.
d) The details specified in 2.06 B.2.a.3, 2.06 B.4.a.2 and 3 shall also be
applicable.
b) For connections wherein the conductor of the cable and the connector
are of the same material, the effective cross-sectional area of the
connector shall at least equal the size of conductor of the cable.
4. Splice Insulation
b) The recovered wall thickness of splice jacket shall match or exceed the
thickness of the cable jacket.
8. Grounding
9. Fabrication
c) In case of shielded cable, all items needed for wire or tape clamping
shall also be included. Roll springs shall be provided for such
application.
10. Marking
a) Splice Kits
b) Termination Kits
c) Connector Kits
1) For compressor type connectors, the surface shall be marked with
crimp position knurls, die index number and manufacturer’s code
number.
PART 3 EXECUTION
3.01 GENERAL
A. The Contractor shall provide all equipment and labor as deemed necessary to show
proper execution of the work.
C. All SEC direct interface work shall be done with prior SEC approval and in strict
accordance with SEC standards.
A. General
1. The duct for underground cables shall not be located in the main (busy lane) of
the street or road and should be at least 1.5 m from the median bay.
2. The location of all underground ducts shall be selected with consideration for
future structural installations in the area.
3. All the duct banks shall be constructed with the use of concrete forms or by the
use of pre-cast duct banks.
5. Duct bank shall be provided with a minimum of 20% spare conduits of each
size required.
6. The ends of ducts and conduit terminating below grade or in open air shall be
sealed with duct sealing putty or an equivalent compound.
7. All cables shall be routed as required by the Drawings. If at any time during the
progress of the work the Contractor finds raceways which appear inadequate
to accommodate the assigned cable, he shall notify the Royal Commission at
once and shall discontinue any further work on the questionable raceway until
advised by the Royal Commission on how to proceed.
8. Immediately prior to the placement of each cable or cable group, the raceway
route shall be inspected and ascertained to be complete in installation and free
of all materials detrimental to the cables or their placement.
9. All cables assigned to a particular duct or conduit shall be grouped and pulled
in simultaneously, using cable grips or pulling eyes and acceptable lubricants.
10. Maximum percent of cross section of conduit or duct fill for all types of
conductor shall be as specified in Chapter 9 of NEC.
11. All cables shall be carefully checked, both, with regards to size and length,
before being pulled into conduits or ducts. Cables pulled into the wrong conduit
or duct or cut too short to rack, train, and splice as specified herein, shall be
removed and replaced. Cable removed from one conduit or duct shall not be
pulled into another conduit or duct.
12. Figures 3A, 3B, 3C, 3D, and 3E, indicate standard Duct Bank Design
Parameters for the required width, depth, backfill and circuit separation. For
duct bank and manholes, refer to SECTION 02580.
B. Cables In Manholes
4. Manholes shall be provided with a minimum of one 760 mm (30 in.) man-way
cast into the top cover.
6. Cables shall be supported at all times without short bends or excessive sags
and shall not be permitted to lie on the manhole floor. Cable ends must not be
submerged. Cable racks, saddle supports or trays shall be provided for
permanent support. Temporary support required during placement shall be
with rope slings, timbers or an alternate method acceptable to the Royal
Commission.
C. Cable Pulling
1. Finishing and pulling shall be done with flexible round metal tape, CO2
propelled polyethylene cord, nylon rope or manila rope.
D. Cable Grips
1. Factory installed pulling eyes shall be used for pulling cable where they are
available. The area of the cable covered by the grip or seal plus 150 mm shall
be cut off and discarded when the pull is completed.
2. Woven wire cable grips shall be used to pull all multi-conductor cables, as well
as single conductor cable 70 mm2 (2/0 AWG) and larger, where pulling eyes
are not available.
3. Pulling loops shall be used to pull single conductor cable smaller than 70 mm2
(2/0 AWG). When pulling loops are used, the entire loop shall be cut off and
discarded when the pull is completed. As soon as the cable is pulled into
place, the pulling eyes, cable grips, or pulling loops shall be removed and any
cable that was sealed shall be resealed.
E. Swivels
F. Feeding Tubes
1. A 100 mm or larger flexible feeding tube, with a removable nozzle sized to fit
the ducts, shall be used in pulling all underground cable. The feeding tube
shall be long enough to extend from the duct entrance to the outside of the
manhole and shall be so arranged that it will be impossible for the cable to
drag across the edge of the manhole ring or any other damaging surface.
G. Lubricant
H. Inspection
1. Inspection shall be performed at the field before installation of the cable, the
outside of each cable reel shall be carefully inspected and protruding nails,
fastenings, or other objects which might damage the cable shall be removed. A
thorough visual inspection for flaws, breaks or abrasions in the cable sheath
shall be made as the cable leaves the reel, and the pulling speed shall be slow
enough to permit this inspection. Damage to the sheath or finish of the cable
shall be sufficient cause for rejecting the cable. Cable damaged in any way
during installation shall be replaced.
I. Pulling Tension
1. The axial and tangential forces applied during pulling process shall not
damage any component of the cable assembly during the installation of
cables.
4. The placement of all rollers that conforms to the radii bends and degree angle
curves shall be verified prior to commencing the cable pull.
5. The maximum pulling tension placed on a cable shall not exceed the following:
a) For cable equipped with a pulling eye or bolt attached to the conductor:
J. Sidewall Pressure
2. Detailed maximum pulling tension and sidewall pressure calculations with the
route drawings showing bending radius, roller placement and dimensions shall
be developed and submitted to the Royal Commission for each specific cable
pull within the cable route.
K. Cable Bends
1. Extreme care shall be exercised during the placement of all cables to prevent
tension and bending conditions in excess of the manufacturer's
recommendations. The permanent radius of bend after cable installation shall
be in accordance with the cable manufacturer's recommendations.
L. Supports
1. All cable supports and securing devices shall have bearing surfaces located
parallel to the surfaces of the cable sheath and shall be installed to provide
adequate support without deformation of the cable jackets or insulation.
Adequate cable end lengths shall be provided and properly placed in
manholes to avoid longitudinal strains and distorting pressures on the cable at
conduit bushings and duct end bells.
2. Final inspection shall be made after all cables are in place and where
supports, bushings, and end bells deform the cable jacket, additional supports
shall be provided. Additional cable protection such as a wrapping of light
rubber belting, friction tape, or similar material shall be provided when
required. Cables in vertical runs shall be supported by woven wire grips in
accordance with the NEC requirements.
M. Cable Racks
1. Where cable trays are not specified in manholes, cable racks shall be
furnished and installed according to the drawings and as required to provide
the proper cable support. Cable racks shall be installed at spacing not greater
than 1000 mm and shall be securely bolted to permanent wall surfaces with
self-drilling anchors or continuous slot concrete inserts.
1. The following requirements are meant to be used with facilities such as water,
sewer, gas, telephone, or any other than power cable.
TABLE 3A: CLEARANCES BETWEEN ROYAL COMMISSION (OR SEC) CABLES AND OTHER
UTILITY LINES
Water &
500 500 500 500 1000 500
Sewer
300 for 300 for
service service
telephone telephone
cable cable
Telephone 300 1000 5000 1000
or 500 for or 500 for
main main
telephone telephone
cable cable
Gas - 500 - 500 1000 500
O. Cable Identification
2. The primary purpose for identification of the circuit conductors and grounded
conductor terminals are for safety of person during maintenance and for the
ease of installations during new construction and installation.
3. The Contractor shall identify the ends of all power circuits and also identify all
circuits in manholes. At terminations, the Contractor shall identify each
conductor of power circuits. Each cable marker shall bear the number of the
corresponding circuit according to the drawings.
4. Markers shall be attached where the first individual conductor is routed away
from the assembly. Each phase of multi-phase power circuits shall be
individually identified. In manholes, each cable shall be identified. Each marker
shall bear the number of the circuit according to the Contract Drawings.
P. Moisture Seals
1. Each cable shall be kept sealed except when termination and splicing work is
being performed. The ends of all cables shall be sealed with heat-shrinkable
caps. Cap sizes shall be as recommended by the cap manufacturer for the
2. Caps shall contain sufficient adhesive so that shrinkage of the cap during
application results in formation of a positive watertight seal capable of
withstanding complete immersion or total exposure without permitting the
entrance of moisture.
3. Before and after pulling, the leading end seal of each length of cable shall be
examined and repaired if necessary. All cut cable ends shall be promptly
sealed after cutting except those to be spliced or terminated immediately.
Q. Cable Arc-Proofing
2. The separate conductors of a single circuit may be grouped together under the
arc-proof covering if they are pulled into a single duct. Single conductors pulled
into single ducts shall be individually arc-proofed.
R. Splices
1. General
b) Splices shall not be made to utilize short lengths of cable nor shall they
be made to provide correct lengths on cable initially cut too short for a
particular circuit.
a) Splices or joints are not allowed in low voltage feeders or branch circuits
except at accessible splice or junction boxes and accessible raceway
fittings.
c) Split bolt type connectors, all joints shall be insulated to a voltage level
a) Splices shall have ratings that are at least equal to those of the cable.
a) All workmen who install terminations or splices greater than 600 V shall
be certified by the Contractor or relevant authorities.
S. Terminations
1. General
a) All conductor terminations for 1000 V power cable shall be made using
compression type connectors. Conductors in size 1.5 mm2 through and
including 25 mm2 shall be terminated with crimp type, full ring (or
rectangular) tongue terminal connectors having conductor insulation
gripping sleeves or nylon.
b) Diamond grip type or approved equal shall be used for conductor sizes
1.5 mm2 through and including 6 mm2, pre-insulated. Conductors in
sizes larger than 25 mm2 shall be terminated with 2-hole, long barrel,
double indent, crimp type lugs, or approved equal. Suitable crimping
tools shall be provided for the connectors used, in accordance with
recommendations of manufacturer of connector.
d) The Contractor shall provide all the necessary cable termination kits as
per the Contract Drawings to complete the cable terminations in the
switchgear/transformers. These splicing and termination kits are
required to be approved by the Royal Commission (or SEC where
required) before termination of the cables.
A. General
2. The route of cable trenches shall avoid above ground and below ground
obstructions so as to maintain a reasonable access to the buried cables.
Trenches in unpaved areas are preferred. A minimum clearance shall be
maintained between underground runs and parallel runs of underground
piping. Recommended clearances are show on Figures 3A to 3L.
3. Power and associated control circuits can be laid adjacent. 3 single conductor
cables comprising one 3-phase circuit (trefoil) shall be laid without spacing. In
order to achieve a reasonable derating factor, a minimum spacing shall be
determined between all 3-phase power circuits.
4. Where cables cross under main road, concrete slabs, paved areas, railroad, or
any areas that would require extensive or impractical excavations to replace,
then they shall be run in duct. Where such duct runs exceed 3 m, overall cable
ampacity shall be based on the duct portion of the run. Bell end or protective
bushing shall be provided on each duct where it terminates.
5. Direct buried cable coming up and through a concrete slab shall be encased in
type DB PVC conduits or PVC coated, tape wrapped, or fully concrete
encased hot-dip galvanized rigid steel conduits. The conduits shall start 90 mm
away from the bottom of the slab and extend above grade.
6. The conduits shall be sealed 30 mm above grade with extensions beyond this
depending on the area of classification and cable type in use. All conduits shall
have bell ends or protective bushings where the conduits terminate
underground.
7. Cables can be unreeled directly into the trench by means of a side boom and
large sheave mounted on a vehicle carrying the reel or a reel on a side-hoist
crawler crane. Caution shall be taken in using the roller system by checking
the pulling tension and sidewall pressure during direct buried cable
installations.
10. All direct buried conduits shall be rigid hot-dip galvanized steel or polyvinyl
chloride (PVC). For excavation and fill, refer to SECTION 02315.
B. Conduit
2. For paved roads, the grade level is the surface immediately below the
concrete or asphalt pavement. Subgrade is another term for this surface. For
unpaved roads or areas, the grade level is the road surface or natural ground
level.
3. On street railway crossings, the minimum cover between the conduit system
top and rail top shall be 900 mm. On an isolated railroad crossing, the
minimum cover between the conduit system top and rail top shall be
1300 mm.
1. All direct buried cables shall be installed with warning signs, markers and
cable identification in accordance with SECTION 16075.
A. General
1. The Contractor shall carry out all site tests in accordance with approved test
procedures to ensure that the cable and accessories comply with the
specifications and operational requirements. All tests are subject to witnessing
by the Royal Commission’s representatives.
2. At least 4 weeks prior to schedule tests, the Contractor shall submit to the
5. Care shall be taken that the test apparatus does not damage the cables and
accessories during the testing.
END OF SECTION