Professional Documents
Culture Documents
TABLE OF CONTENTS
PART 1 GENERAL............................................................................................................ 1
1.04 REFERENCES..................................................................................................... 2
1.05 DEFINITIONS....................................................................................................... 4
1.06 SUBMITTALS....................................................................................................... 4
3.02 INSTALLATION.................................................................................................. 13
PART 1 GENERAL
B. The Contractor shall be responsible to check the integrity of wires and cables
specified in the Contract Drawings/Documents. When this check indicates that the
specified wires and cables are not adequate, then the Contractor shall notify the
Royal Commission and take the necessary action/changes with the approval of Royal
Commission.
C. The Contractor shall also check and verify every requirements, aspect and detail
necessary for coordinating with new or existing systems of building wires and cables.
D. These Specifications define the minimum requirements for building wires and cables
as per SASO/IEC or North American based standards specified in par. 1.04.
E. Where works interface with Saudi Electricity Company - Eastern Operating Area
(SEC - EOA), the equipment/materials and installation system shall comply with
latest revision of SEC - EOA standards, and shall be submitted to SEC - EOA for
review and approval.
A. This Section covers furnishing, installing and testing of 600/1000 V insulated wires,
cables, conductors, and including splices and terminations, cable marking and
identification in utilities for commercial and residential buildings.
1.04 REFERENCES
A. The referred codes and standards are intended to provide an acceptable level of
quality for materials, products and workmanship. In case of conflict between these
standards and the text of this Specification, the Specification text shall govern.
B. The latest revision of the referred codes and standards shall be used wherever
applicable. In case of conflict, the Contractor shall propose equipment, materials and
processes conforming to one group of codes and standards.
1.05 DEFINITIONS
A. american wire gage (AWG): A round metallic plate which has the different size of
slots marked with decimal numbers for measuring the diameter of the wire physically.
B. annealed wire: Wire, which after final draw-down, has been heated and slowly
cooled to remove the effects of cold working.
C. branch circuit: The circuit conductors between the final overcurrent device
protecting the circuit and the utilization outlets.
D. building wire and cable: Wires and cables used permanently for lighting and power
circuits in buildings utilizing 600 V or less.
E. conduit: A long hollow cylindrical metallic or non metallic (PVC) tube which is used
for passing the insulated electrical wires and cables for the application of
underground and above ground system of cabling.
F. main incoming cable: A cable which is permanently used for getting connection
from source of electrical power supply company and extend up to the main circuit
breaker or main panel board of the customer of electrical power company premises.
G. thermoplastic: A material which softens when heated or reheated and becomes firm
on cooling.
I. thwn: A building wire which is suitable to use at maximum temperature 75°C, 600 V,
dry and wet locations, the insulation is made from thermoplastic with nylon jacket and
protected from moisture and heat resistant, flame retardant.
1.06 SUBMITTALS
A. The Contractor shall submit to the Royal Commission, under the provisions of
SECTION 01330, the following items for review and approval before commencing
Work:
1. Vendor drawings and original product data shall be provided as defined in and
particularly as listed below:
a) List of manufacturers.
g) Certificate of Compliance.
B. The Contractor shall submit field test reports after the completion of Testing and
Commissioning.
A. The Contractor shall be responsible for the quality of work and shall develop and
propose programs and methods of construction and testing to achieve the specified
quality to the approval of the Royal Commission in accordance with
SECTION 01450.
3. Contractor
B. In the absence of any of the above, best accepted industry practice shall be
employed throughout.
A. General
1. All wires and cables shall be tested at the factory in accordance with the latest
approved manufacturing codes and standards. The Contractor shall notify the
Royal Commission in writing not less than 30 days prior to the scheduled
starting date of the factory tests.
3. Upon completion of factory tests, and before shipment of the wires and cables,
the Contractor shall submit 5 certified copies of test reports not later than
10 days after the completion of all factory tests for review and approval by the
Royal Commission.
A. All wires and cables, and accessories installed indoor shall be suitable for
continuous operation under the following service conditions:
a) A maximum of 40°C.
b) A minimum of 0°C.
B. All wires and cables, and accessories installed outdoor shall be suitable for
continuous operation under the following service conditions:
a) A maximum of 50°C.
C. All wires and cables, and accessories to be installed in classified areas as indicated
A. The Contractor shall deliver, handle and store equipment and material units in
accordance with SECTIONS 01650 and 01660, as well as the following
requirements:
1. All equipment/materials such as wires and cables shall be delivered to the site
originally packed, securely wrapped and labeled by manufacturer in unopened
containers. Protect materials during delivery and comply with manufacturer’s
instructions.
PART 2 PRODUCTS
2.01 GENERAL
A. All goods and products covered by these Specifications shall be procured, whenever
available, from an in-Kingdom manufacturer. Procurement of all goods and products
manufactured out-of-Kingdom shall be approved by the Royal Commission.
B. Where Royal Commission utilities interface with power company Saudi Electricity
Company - Eastern Operating Area (SEC - EOA), the cables and related materials
shall be approved by SEC.
1. Low voltage power cables shall be rated of 600/1000 V and XLPE insulated.
5. The cables shall be designed for use in all low voltage power circuits and for
installation in conduits, underground ducts, cable trays, raceways or for directly
buried installations.
6. Cables shall be suitable for all service conditions as specified in par. 1.10
that occur in the areas where they are installed.
7. Cables shall be suitable for operation in wet or dry locations with alternately
wet and dry conditions. If exposed cable tray installations are used, cables
shall be suitable for operation in a sandy and salty atmosphere without
affecting its physical and electrical characteristics.
9. Conductor
b) Single core cables shall not be larger than 300 mm2. Conductors 4 mm2
and larger shall be stranded, while conductors below 4 mm2 may be
stranded or solid, as specified on the Contract Drawings.
10. Insulation
b) The insulation shall be heat and moisture resistant, flame retardant and
ozone resisting compound suitable for 85 (PVC insulated) to 90°C
(XLPE insulated) maximum conductor temperature under normal
operating conditions.
Conductor Insulation
Conductor Size No. of Thickness (mm2)
Strands
mm2 AWG or MCM PVC XLPE
70 2/0 19 1.4 1.1
95 3/0 19 1.6 1.1
120 4/0 37 1.6 1.2
150 300 37 1.8 1.4
185 350 37 2.0 1.6
240 500 61 2.2 1.7
300 600 61 2.4 1.8
400 800 61 2.6 2.0
500 1000 61 2.8 2.2
Insulation Insulation
Phase Neutral
Conductor No. of Thickness Conductor No. of Thickness
Size Strands Size strands
mm mm
mm2 AWG PVC XLPE mm2 AWG PVC XLPE
35 2 6 1.2 0.9 35 2 7 1.0 0.7
50 1 6 1.4 1.0 50 1 7 1.2 0.9
70 2/0 12 1.4 1.1 70 2/0 7 1.2 0.9
95 3/0 15 1.6 1.1 95 3/0 19 1.4 1.0
120 4/0 18 1.6 1.2 120 4/0 19 1.4 1.1
150 300 18 1.8 1.4 150 300 19 1.4 1.1
185 350 30 2.0 1.6 185 350 19 1.6 1.1
240 500 34 2.2 1.7 240 500 37 1.6 1.2
300 600 34 2.4 1.8 300 600 37 1.8 1.4
400 800 53 2.6 2.0 400 800 37 2.0 1.6
500 1000 53 2.8 2.2 500 1000 61 2.2 1.7
a) The jacket shall be black, ST 2 type, extruded PVC per IEC 60502-1 or
ICEA-S-66-524 with heat, moisture, oil, sunlight, acid, alkali and flame
resistant properties.
1. All the flexible building wires used for branch circuits shall meet the
requirements specified in pars. 2.02 A.1 to 8.
2. Conductor
3. Insulation
4. Jacket
A. Refer to SECTION 16110 for Terminal Lugs, Splices and Crimping Tools.
A. The jacket for all the cables shall be marked by embossing in English at intervals not
exceeding 1 m with the following minimum information:
1. Electric cable.
7. Year of manufacture.
8. Cumulative length at every 1 m with the highest length mark on the outer end
of the cable.
PART 3 EXECUTION
3.01 GENERAL
A. The Contractor shall provide all equipments and labor as deemed necessary for the
proper execution of the work.
D. All Saudi Electricity Company - Eastern Operating Area (SEC - EOA) direct interface
work shall be done with SEC - EOA prior approval and in strict accordance with
SEC - EOA standards.
E. The Contractor shall be fully responsible for any mechanical damage upon
installation of wires and cables and their related accessories.
3.02 INSTALLATION
A. General
1. All the building wires and cables shall be installed in accordance with latest
codes and standards as listed in par. 1.04, and as specified on Contract
Drawings/Documents.
2. Low voltage power cables may be installed in direct buried, duct bank
(concrete encased conduits) and trenches below grade, or installed in conduits
either concealed in slab/walls or exposed type as specified on Contract
Drawings/Documents.
3. All the electrical ratings and sizes of the main incoming cable and flexible wires
and cables shall be as specified in the Contract Drawing/Documents.
4. Special care shall be taken to avoid damaging the insulation or jacket while
pulling, bending and installation of wires and cables. Damaged wires and
cables shall not be acceptable for installation.
5. Where required, the wires and cables shall be pulled with approved fish wire,
cable rope, basket-weave wire/cable grips, and pulling compound.
1. Main incoming cables shall be installed from the source of power supply
company Saudi Electricity Company – Eastern Operating Area (SEC - EOA) to
the Royal Commission job site as indicated in the Contract Drawings/
Documents. Where SEC - EOA interface with the Royal Commission
premises, the Contractor shall follow the clauses specified in pars. 1.01 E,
2.01 B and 3.01 D.
3. Flexible wires shall be run in approved electrical metallic tubing (EMT), rigid
PVC, liquid tight flexible metallic or non-metallic (PVC) conduits as required in
Contract Drawings/Documents.
1. For installation of identification tags and labels for wires and cables, refer to
SECTION 16075.
A. General
1. The Contractor shall carry out all site tests in accordance with approved test
procedures, codes and standards to ensure that all the wires/cables and cable
2. 4 weeks prior to schedule tests, the Contractor shall submit to the Royal
Commission an outline of the plan and procedures to be used in performing
site inspection and tests. This outline shall include a brief description of the
test equipment, connection diagrams, proposed tests and procedures, test
sheets, calculations, reference drawings and minimum and maximum test and
performance values, in conformance with this Specification and acceptability of
the equipment and its installation.
4. The Contractor shall provide all test instruments, equipment and accessories
necessary for demonstration and putting the equipment into operation before
commissioning. All testing equipment shall be calibrated by approved
authorities and calibration certificates shall be submitted to the Royal
Commission for their review and approval.
5. Upon completion of all fields testing, the Contractor shall submit to the Royal
Commission 5 copies of a certified test reports attesting that each test has
been performed in accordance with the approved test procedures. The report
for each test shall include the name of the person in-charge of the test and the
date of performance. All factory and field test reports shall be included in
Operation and Maintenance Manuals.
6. Special care shall be taken during field testing including the safety of
personnel, and the test apparatus wires/cables and their accessories from
injuries and damages.
END OF SECTION