Professional Documents
Culture Documents
WATERPROOFING
OCC-SEC-MOS-C-016-Rev-0
Contract # 4400014870
This Method of Statement describes the method and scope for Survey Works.
3.0 REFERENCES
Only appropriate plant and equipment shall be used to ensure the following
criteria are met ;
1. Suitability to location and type of work ;
2. Competency of personnel involved in the actual operation ; and
3. Always maintained in good working condition.
The following equipment shall be utilized for and during the execution of the works ;
4. Torch
5. Knife or blade cutter
6. Trowel
7. Wheelbarrow
8. Roller Brush
9. Ordinary Brush
10. Drill (aluminum flashing)
11. Scaffolding system
12. Wheelbarrow or any other means of transporting the materials to the site from
the storage area, i.e., bobcat or forklift
4.2 Materials
Delivery and handling of major materials shall be handled in a careful manner with
deliberate scheduling to the shaded or covered storage area dry, clean and clear
of any other material or equipment that can cause damage or harm, of normal
room temperature for proper care and protected from damage due to excessive
heat and free form any other combustible materials, spark or flame. These shall
be recorded accordingly. At no time shall these materials be exposed to weather
except the estimated material quantity required corresponding or proportionally
to the required or utilized manpower to be used on a particular given time. All
excess materials shall be properly placed back into the storage room and all cut or
rubbish materials shall be disposed of or removed immediately from the work area
to keep it clean.
All materials delivered to site shall be initially inspected and shall be found to be
free from damage or defect, bearing the manufacturer’s name, brand or any
identity that shall prove it is the NG/SEC approved material.
1. Waterproofing membrane
2. Flashing Compound.
3. Geo-Textile
4. Aluminum Flashings
5. 100mm thick rigid extruded polystyrene
6. Filtration mate
7. 50mm washed aggregates or Precast cement tiles
8. Screed
a. Ensure that all material samples of all major materials that shall be used along
with its technical data shall be submitted to NG and SEC for approval prior to
any placement of order and any actual execution.
b. Ensure that any and all materials delivered to the project and eventually to site
that shall be used are the approved materials bearing the manufacturer’s name
or brand.
c. After blinding has been placed on top of double tee or hollow core slab as well
as with canopies, the concrete surface shall be prepared smoothly, free from
cracks, voids, hollow portions or honeycombs. It shall be thoroughly cleaned and
cleared of all dust and debris, form release agents, oil, grease, dirt, laitance,
loose materials, debris and other contaminants that can adversely affect the
bonding between membrane and concrete prior to application of primer.
d. On the joints between the lean concrete and the parapet, cants strips or beveled
strips at 40mm x 40mm angle shall be provided to allow the easy transition of
application of the waterproofing membrane.
e. Application of approved primer with sufficient time for drying or as per
manufacturer’s instruction. A representative of the manufacturer shall be
present at the site from the beginning to ensure that proper application is done, at
least until the first layer of membrane is applied.
f. Two layers of 4mm thick modified bituminous membrane shall be laid on the
blinding concrete fully torched using cylinder fed propane gas torch.
g. One layer of waterproofing membrane shall be laid directly over the horizontal
surface of lean concrete or blinding with a minimum of 100m end laps and
150mm side laps.
h. Trowels shall be used to seal the seams of the membrane and knife or blade
cutter for cutting. In cutting, ensure that the sheet is cut properly with the right
dimension to save for future use.
i. The membrane is then placed in the correct torching position then re-rolled for
about half of its length without changing its orientation. Torching shall be done
in the proper manner and timing, not over-heating or otherwise. (Please see
photo below)
a. The membrane is then un-rolled again and torched on pressing the melted area
against the substrate.
b. Repeat till the entire length of the membrane is bonded firmly onto the surface
then the second membrane is laid in the same way with an overlap of 150mm
at the end and 100mm at the side.
c. In the second layer, it would be better to start laying the membrane in the
opposite direction to ensure no space or gap has occurred. Laying in the same
direction as the first layer is also acceptable, or depending on the
manufacturer’s instruction.
d. An extra length of minimum 300mm of the horizontal membrane shall be left
to carry up the vertical surface of the parapet for closure.
e. After completion of actual waterproofing works, the top end portion being
exposed shall be protected by an aluminum flashing approved by NG/SEC and
applied with approved sealant.
f. Likewise, after all works are completed, there shall be a water leak or flood test
to be conducted for 72 hours at a minimum of 75mm head of clean or potable
water. The first 24 hours shall be monitored as initial leakage test and water
shall be retained for another 48 hours for the final test.
g. After testing has proven satisfactory, water shall be drained properly only by
cutting carefully at the floor drain (scupper drain) area with a smaller diameter
than the drain pipe and folding the excess downward into the pipe. A
perforated dome-type cover shall be placed on the floor drain pipe.
h. Always follow the elevations and percentage slope and directions indicated in
the drawings.
i. Prior to and after testing, the roof shall not be open for traffic of any kind in
order to protect the newly installed waterproofing except to those working on
the waterproofing and inspectors from NG/SEC and HHC engineer in charge.
j. Waterproofing protection shall be done by placing a 50mm thick screed,
properly sloping towards the floor drains. The whole area shall be covered by
precast concrete tiles 400mm x 400mm x 25mm thick.
Construction Manager : 1
QA/QC Manager : 1
Safety Manager : 1
Civil Superintendent : 1
Civil Field Engineer : 1
Safety Officer : 1
Civil Quality Control Engineer : 1
Specialty Contractor’s Engineer : 1
Total 8
I. Project Manager
The Site Manager reports directly to the Project Manager. Site Manager is
responsible for :
Organization and control of site development and overall execution safely and
meeting the customer‘s quality requirements ;
Interfacing with safety, quality control, engineering, planning and procurement
departments
Coordination and scheduling of construction work ;
Assuring that the workforce as well as all Subcontractor’s workforce are qualified
in their assigned responsibilities and are capable of performing all assigned
duties right the first time.
The Construction Manager is responsible for notifying the QC Manager of the
schedule of work being completed and requiring inspection and/or testing.
The Construction Manager is responsible for arranging for repair, rework,
replacement, etc. necessary to correct any irregularity or deficiency of work or
products and to notify the QC Manager that corrections are complete and ready
for re-inspection/re-testing.
The QC Manager is assigned by the Quality Manager and has the responsibility
and authority to verify implementation of Project drawings, specifications and
standards.
The QC Manager shall have the organizational freedom and authority to
investigate work in order to assure compliance to specified Quality System
Requirements.
The QC Manager will report directly to the Quality Manager and has complete
authority to take any action necessary to ensure conformance with the contract
documents.
The QC Manager has equal authority and status in all aspects as the Project
Manager with full authority to instruct the removal and replacement of any
defective work in the project.
The QC Manager shall have no job related duties other than the quality control
of the OCC activities, and responsible for the implementation of theapproved
quality control program and ensuring conformance with the
requirement of the contract specification and drawings.
The QC Manager is responsible for the preparation of all quality control
inspection and testing procedures required of the implementation of the
approved QC program and conformance with the contract specification.
The QC Manager responsible for reviewing all construction drawings to ensure
that they contain the necessary quality related requirements prior to release for
construction and review of all as-built drawings prior to final acceptance and any
revision to the contract specs prior to use.
The QC manager will coordinate with 3rd party independent testing laboratories
in the performance of necessary tests and review of all test results.
The QC Manager shall verify that all test reports from laboratory and field testing
comply with the contract requirements.
QC Manager shall issue Non-Conformance reports when deviations from
contract requirements are identified during construction of the work, receipt of
storage of materials and equipment, fabrication, installation or testing and
implement and maintain a filing system for all QC procedures, records, reports.
QC Manager is responsible for obtaining, reviewing and retaining the quality
records received from the supplier, manufacturers, fabricators and the like to
ensure availability of date for assessment of quality.
QC Manager is responsible for maintaining this Document through periodic
review to ensure that its content accurately reflects the requirements of the
Quality Plan.
V. QC ENGINEERS :
The QC Engineers are independent of the construction production staff, and will
report directly to the QC Manager. QC Engineers will be qualified, experienced
and approved by the Client.
The QC Engineer will perform the inspection and testing activities directed by the
QC Program Procedures and/or the QC Manager and shall record results of
inspection and tests on the inspection format along with checklists and attached
in the Daily QC Report.
The QC Engineer shall coordinate and collect the test report conducted by a third
party technician for laboratory analysis of concrete samples, slump &
temperature test, soil compressive test and let the client field engineer to sign
and approve the raw data test reports.
The QC Engineer shall prepare a daily QC report, recording all in-process
inspection conducted daily, as per the daily schedule of activities in every
discipline at site.
QC Engineer, upon receipt of request for inspection from OCC fieldEngineers
thru E- mails and/ or written communication requesting inspection ofspecific
completed area of activity, before requesting client inspection, QCEngineer
must conduct internal inspection and if satisfied the result, he shallsend
request for Inspection (RFI) to the concern client field Engineer.
A QC Engineer should attach in his request (RFI) the approved drawings, sign &
attach the inspection checklist and to have the approved Method Statement &
ITP of concern work activity.
The first aid officer should be well experienced in first aid practices and NG/SEC
safety rules.
Will be responsible for fast treatment of any burns, injuries or any type of
accidents.
Conduct periodic inspections of all employees and check any signs of illness.
Ensures the availability of first aid kits in good conditions.
Inform any injury or accident to the Safety officer and write a report about the
injured employee.