CGK 063
3.0 DEFINATIONS
Terms Definition
Project CGK 063
JO PT Jaya Obayashi
MOS Method of Statement
MSA Material Submission Approval
Table 1: Definitions
4.0 REFERENCE
The following Standards of Practice shall be applicable to the works:
SNI 8153:2015 : System plumbing pada bangunan gedung (Plumbing
System in Building).
SNI 7511:2011 : The Procedure for Installing Transmission Pipes and
Distribution Pipes and Pipe Crossing Buildings.
SNI 03-1745-2000 : Concerning procedures for planning and installing vertical
pipe systems and hoses for the prevention of fire hazards in
buildings
5.0 RESPONSIBILITIES
No Designation Qty Responsibility
.
Responsible for overall commercial, contractual
& technical performances associated with
1 Project Manager 1
specific project. Reporting to the Project
Director.
2 M&E Engineer 4 Planning and supervising installation activities.
Inspect, verify, and prepare work statement for a
quality installation works. Material storage, fit
3 QA / QC Engineer 2
for use tools and equipment, and installation
works
To provide toolbox and guidance to work and to
4 Safety Officer 1
ensure that work is carried out in a safe manner.
Obtain permit to work, control the sequence
according to MOS, approved shop drawings, and
MSA, ensure mechanical aspects of the work are
according to the specifications, ensure safe
practices are followed and ensure quality of
workmanships during execution. Ensure material
5 Supervisor 3-5
temporary storage and protection meet vendor
and standards requirement
6.0 PROCEDURE
6.1 General Description
The mechanical work for filtration system installation to be carried out at
CGK063.
6.2 Material
Materials are as below:
6.4 Manpower
The actual manpower of each type of installation may vary according to the site
condition and requirement.
All workers shall wear appropriate PPE (Hard Hat, Protective Boots, Goggles,
High Visibility Vest and Protective Gloves) and safety harness when working
above 2 meter in height.
Install the filling relief valve and seeding point must be into the pipe
before and after the contact water meter respectively with a sleeve
socket (not provided). The seeding point is connected to the dosing
pump via the pressure/dosing pipe.
Attach the Dosing Pump to an electronically controlled dosing
container with operating/measurement frequency display and empty
indication display and auto shut-off device when unit is empty (dry
running protection).
The seeding point must be installed in such a way that the outlet
opening of the hose rubber seal is in the zone flowed through of the
pipe.
Install An R 1/2" threaded sleeve with welded into the pipe on the
inlet and outlet of the water meter, when using conventional fittings,
an R 1/2" threaded connection must be available.
Connect to the sewage system for flushing water nearby. Flushing
water hoses must be attached to the sewage connection with a safety
spacing of at least twice the interior diameter of the flushing water
hose or min.
Support spacing to be executed as per the approved drawing and site
condition. Spacing between others services shall be coordinated on
the site.
Install cable tray/trunking with enough space to permit access for
installing cables. Install the cable tray/trunking with proper alignment
with other services.
Install the control panel & terminate the cables at the control panel as
well as the equipment and pumps.
After all equipment filtration has been installed, follow up to call the
technician to check and carry out inspections together with the
consultant.
8.0 APPENDICES
8.1 DRAWING
As attached drawing
8.2 RISK ASSESSMENT (RA)