Professional Documents
Culture Documents
in the different types of industries. These are done by processing the limestones
to form a certain processed output that can either be used for cement industries,
overall sedimentary rocks in the world are being mined to be further processed
temperature.
derived from lime, which has many industrial applications. PCC is made by
hydrating high-calcium quicklime and then reacting the resulting slurry, or “milk-
of-lime”, with carbon dioxide. The resulting product is extremely white and
U.S., the Food and Drug Administration has affirmed precipitated calcium
slaking as its climatic stage. Calcination is also a main process in the production
of PCC for during this stage, limestones are decomposed to become quick limes.
These quick limes are then sent to a vessel to where it will be slaked to become
slaked limes. Finally, the finishing touch of the production of PCC is where the
These produce PCCs are usually dried using filter press for it to fully form as
powdered form, which are practically used in the different industries as additives.
of it by the different local industries. It is known that the supply of PCC in the
Philippines mostly comes from imports from India, Japan, and Malaysia.
be reasonably viable to resolve this unbalance supply – demand system for PCC
in the Philippines.
2
LOCATION
plant was determined by considering different factors, these factors were the
Since the raw materials of the PCC Production Plant is limestones, the
3
mining rate of 2 million tons per year. Moreover, the chosen location for the PCC
On regards to the road accessibility of the chosen location for the plant,
the path to the location were visibly accessible for it is adjacent to the main road
The chosen location for the plant also considered its availability of water
Batangas Bay. The Batangas Bay will serve as the plant’s primary source of
water, taking regards to the treatment of the water from Batangas Bay before
Furthermore, the chosen location would mean that it would offer job
location would be estimated 350 meters to the nearest residential houses, those
who live from that specific area would be the priority in these job opportunities,
RAW MATERIALS
Limestones will be the raw materials of the PCC Production Plant. These
which will supply the mined limestones as raw materials for the plant. The overall
4
hectares, that can supply the plant for an estimated time of 50 years, considering
PRODUCT
Paper coating
Rubber additive
PVC/Plastic additive
Electrical insulators
Toothpaste making
Pharmaceuticals
Food packaging
Moreover, the plant aims to produce a high-quality PCC product that will
5
Soluble Alkali <0.15
Solution Test Clear
pH Level 9.5 – 10.2
Particle size (D50) Different Grades 2 – 8 microns
Purity as CaCO3 % 98%
Table 1. Standard Specifications of Precipitated Calcium Carbonate
(PCC)
In addition, the main target customer of the product of the plant will be
D&L Industries, Inc., which is a plastic manufacturing industry that specializes the
PLANT CAPACITY
The PCC Production Plant capacity will be based on the demand for PCC
statistically stated that the global market for PCC is projected to reach 98.7
million tons by 2020, driven by robust demand from paper and plastics end – use
sectors. Moreover, 6.6% CAGR of that global market comes from the Asia, to
which 17% of it is at South East Asia (SEA), the Philippines shares 5% of that
The plant is considering supplying 15% of the PCC locally, therefore the
DEMAND
6
The demand for PCC is booming, statistically it is stated that the global
billion by 2022 with a CAGR of 4.6% from 2017 to 2022. This growth owing to
rising demand from end-use industries including rubber, plastic, and paper.
2015. Rising product use in the plastics industry coupled with growing application
expected to drive the demand over next eight years. Furthermore, rising use of
drive the growth. Figure 2 shows the global PCC market revenue, by application,
2013 – 2024.
7
Figure 2. Global Precipitated Calcium Carbonate (PCC) Market
Industries, Inc.’s demand for PCC shares 8.3% of that demand for PCC locally,
MARKET SHARE
The market share of the PCC Production Plant of PCC in the Philippine
Market will be at 10% of the total annual market of the PCC in the local market.
8
CHAPTER II
DESIGN OBJECTIVES
Carbonate (PCC) Production Plant that will process the raw material, limestone
aspects that will justify the viability of the proposed project designs.
3. To assign the proper technical design specifications for the equipment of the
4. To determine the capacity and efficiency of each unit of the plant by the
9
5.1 Capital Expenditures
sections of the plant at the plant’s manufacturer’s site, and the sequence and
10
CHAPTER III
TECHINCAL ASPECTS
This chapter includes the complete equipment layouts planned taking into
units under standard specifications, mass balances and energy balances for
each unit, and the provisions for the ancillary buildings and services needed for
DESIGN BASIS
2013 - 2024.
tons/day, to which will supply 15% of the PCC market demand locally. Moreover,
8.3% of the PCC produced by the plant will be sold to D&L Industries, Inc.,
market. Furthermore, the required plant capacity of the PCC Production Plant will
of PCC.
processing limestones that is currently the industry standard for PCC production.
Moreover, calcination process would only process the limestones to a quick lime,
11
before being sent to the slaking process and precipitation process to which will
The basis for the process of the production of PCC is shown at figure 3.
Figure 3 shows the block flow diagram for processing PCC. The process shows
slaking, precipitation, and compression and drying, to all which focuses on the
production of PCC.
12
The chemical reaction involves in the production of PCC usually are in the
apart, forming quick lime (CaO) and carbon dioxide gas (CO2). The carbon
Afterwards, the produced quick lime will be added with water in the cooling
and slaking process to form calcium hydroxide (Ca(OH)2) or slaked lime. These
is shown in reaction 2.
precipitation process to which the captured carbon dioxide will be added with the
precipitation process it will be sent out to the compression and drying process to
which will be dried of moisture and will then be sent out for packaging.
13
DESIGN OPTION 1
Fig
installation of a pre – heater and the rotary kiln will maximize the formation
14
Primarily, this process flow diagram option 1 starts with the
greater than 100 Mesh (149 micron) or 0.0058 inches. To assure the
installed, to which will screen the crushed limestones whether they met
the required particle size and if the particle size is larger than the 100
design involves three (3) heating units; the pre – heater assembly, the
calciner, and the rotary kiln. The pre – heater will initially heat the crushed
the release of 25 – 35% of the CO2 from the limestones. The heat that will
be applied to the pre – heater will come from the heat exiting the calciner.
After the pre – heater assembly, the limestones will be sent to the calciner
to 3632°F. In the calciner, the release of CO2 from the limestone would
have a cumulative percent of 50 – 80%. And the end of the calciner, the
limestones will now be sent to the rotary kiln where the final heating
process will be done, this is done to ensure that the yield for CaO will be
at its maximum. Moreover, in the rotary kiln, the limestone will be heated
content, to which the overall CO2 release would be at 90 – 95%. The final
15
output in the rotary kiln would be the calcium oxide (CaO) or the quick lime
that will be sent to the cooling vessel to where it will be cool down and
In the cooling vessel, the quick lime will be cooled down by means
of adding water from the cooling tower. The quick lime will be subjected
and slaked with cooled water for it form a calcium hydroxide (Ca(OH)2) or
slaked lime. The exhaust of the cooling vessel will be sent out to the rotary
kiln to where its exhaust would be sent to the calciner and which will be
260°F. The exhaust will be sent out to the gas filter and scrubber for
treatment to which the cleaned gas or CO2 will be sent to the precipitation
reactor.
will occur in the precipitation reactor where the slaked lime is subjected to
the captured CO2 from the scrubber to form calcium carbonate (CaCO3).
unit so that the water will be fully drained from the PCC. Furthermore, the
PCC will be fully dried and formed in the filter press to which then be
16
filtered in the gas filter to remove the remaining CO2 content from the
PCC.
Crusher
rocks, gravel, or rock dust. Crushers may be used to reduce the size, or
change the form, of waste materials so they can be more easily disposed
Vibrating Sieve
17
mesh; thus the screen housing only takes a static function. It also
Rotary Kiln
Source: Nmlindia
18
Air Preheater
combustion air by means of flue gas, steam, water or thermal oil. Air
are particularly high. This extracts the hot exhaust valuable energy, which
Figure 8. Pre -
Heater Assembly
Source: Ljustrom
Industrial Furnace
19
designs vary as to its function, heating duty, type of fuel and method of
pollutants from a furnace flue gas or from other gas streams. In a wet
scrubber, the polluted gas stream is brought into contact with the
20
Figure 10. Scrubber Unit
water are brought into direct contact with each other in order to reduce the
Source: Kolmetz
Calciner
21
when processing finely divided solids, or where temperature must be
Figure 12.
Calciner Unit
particles from the fuel, normally made into cartridges containing a filter
22
Figure 13. Gas Filter Unit
Source: Restek
Precipitation Reactor
the slaked lime and CO2 will yield CaCO3 or calcium carbonate. The
extracted.
standards that are recognized worldwide and that ensure the quality
performance of the process units. The following are the different units with
23
SPECIFICATIONS OF JAW CRUSHER
AMPLITUDE (MM) 6P – 9; 8P – 10
Source: Nmlindia
24
SPECIFICATIONS OF AIR PREHEATER
SIZE 2 x 30
AREA (M²) 97
Source: Ljustrom
SPECIFICATIONS OF FURNACE
FURNACE WEIGHT 48 kg
NUMBER OF ELEMENTS 8
SPECIFICATIONS OF SCRUBBER
25
Vertical packed-bed wet scrubber with liquid
TYPE
scrubbant tank
HEIGHT
M3/HR
CIRCURATING FLOW
DESIGN), %
Source: Kolmetz
26
SPECIFICATIONS OF CALCINER
MOTOR POWER 30 HP
CAPACITY 78 inches
RATES
to
grey
Source: Restek
SPECIFICATIONS OF REACTOR
27
MAXIMUM PRESSURE 14 barg 200 21 min 44 min
28
PIPING AND INSTRUMENTATION DIAGRAM
The P & ID diagram of PCC Production Plant shows the complete cycle
process of all components, flow lines, valves, and indicators of all operating
conditions used.
The start of the P&ID is with the limestone as the feed that will be sent to
the crusher unit to which it will be crushed to a particle size of not greater than
100 Mesh (149 micron) or 0.0058 inches. The precision of the particle size of the
crushed limestones that will enter the calcination stage will be screened by a
29
vibrating sieve. Moreover, when the crushed limestone is less than or equal the
specific particle size, it will be sent to the bin via conveyor belt for the preparation
will aid maximizing the yield output of CaO from the crushed limestones. These
heating process includes the pre – heater assembly, calciner, and the rotary kiln.
The first heating process that the crushed limestones will be sent to is the pre –
heater assembly, in the pre – heater assembly the crushed limestones will be
heated to a temperature ranging of 1850°F to 2003°F, this will cause the release
of CO2 from the crushed limestones of 25 – 35% of its content. To have control
on the temperature going in the pre – heater assembly, CV1 manipulates the
entering hot gas from the calciner. CV1 receives data from TY1 to which has
been processed by TC1, the temperature data gathered by the TI1 and TT1 were
3632°F. Moreover, the heat that supplies the calciner comes from direct
combustion of coal and the heat coming from the rotary kiln. The cumulative
controlled temperature condition, the heat coming from the rotary calciner is
controlled by a CV2, this is to ensure that there won’t be any overheating in the
calciner unit.
The rotary kiln ensures the optimum output of CaO in the calcination
30
cumulative release of CO2 from the limestone in the rotary kiln is about 90 –
95%. Moreover, the heat that supplies the rotary kiln comes from the exhaust of
hot gases in the cooling vessel, and the heat coming from the Furnace, both of
Calcium Oxide (CaO) or quick lime is the main product of the calcination
stage, to which will be sent to a cooling vessel that will be slaked and cooled with
water coming from the cooling tower. The temperature needed to be controlled in
the cooling vessel is approximately at 185°F and is controlled by the CV5. CV5
controls the flow of cooled water from the cooling tower to the cooling vessel.
Once the quick lime is cooled down and slaked, Ca(OH)2 or slaked lime will be
the output in this process. Furthermore, the water used will be sent back to the
Slaked lime will then be sent to a tank storage unit to where it will be
prepared for the precipitation stage. Precipitation stage requires the reaction of
Ca(OH)2 with CO2 to yield CaCO3 (Calcium Carbonate) and water. This reaction
will occur at two (2) precipitation reactors, this is to maximize the yield output
during this process. Since, CaCO3 is insoluble to water, the water will be drained
out in the precipitation reactor so that the precipitated CaCO3 will be sent down
where it will be filtered out with excess water. The screening unit will involve two
phases; the prescreen tank, and the screening tank, this is done to partial filter
31
The final touch for the PCC is done in the filter press. The filter press
compresses the PCC so that it will be dried of moisture. The dried PCC is finally
sent to a gas filter, to which it removes remaining CO2 from the PCC.
3D PLANT DESIGN
The PCC Production Plant were modelled and designed using Solidworks
and Blender.
32
Figure 17. 3D Plant Design of PCC Production Plant (Side View)
33
PLANT LAYOUT
The plant layout of the PCC Production Plant is shown in Figure 32. The
plant layout shows the physical arrangement of the equipment, facilities and
Since the overall change between each design options only varies to the
process of producing PCC, the overall plant layout would not be affected. The
processes in the plant is only a part of the plant layout, moreover any
modifications of the plant layout would be unnecessary, for the auxiliary facilities,
stations, area, and departments is the same for all design options.
Components of Plant
The following are the components and parts of the production plant:
A. Water Tank
34
A water tank is a container for storing water. Water tanks are
plant like supplementation of water for the hydrant, water for the
B. Pump House
specifically the pumps used to transfer water within the plant. The
the pumps that controls the flow of fluid throughout the plant.
C. Silo
The silo is where the produced PCC are stored. The silo
D. Loading Station
E. Calcination Process
the processes in the plant occurs. The calcination process holds all
production of PCC.
35
F. Fire and Safety
The fire and safety is the main area of where all the fire
this is where the division of pipes to the fire hydrant that are located
G. Laboratory
are used to test the quality of the produced PCC. Furthermore, this
or bad quality.
H. Machine Shop
produced by the plant are handled. This facility ensures that the
36
handle of the hazardous waste is in compliance with the legal
J. Court
K. Warehouse.
L. Parking Area
M. Assembly Area
where flag ceremonies are done each morning, and when there is
N. Inspection Area
37
The inspection area is a security facility in the plant, to where
the vehicles entering and exiting the plant are inspected externally.
and notice. This is also where the exiting trucks containing the
O. Admin
holds the receiving and waiting area, the canteen, infirmary, plant
P. Power Generator
can fully power up the entire plant during those emergency cases.
DESIGN CALCULATIONS
Material Balance
38
In order to have an analysis of the overall physical system in the
production plant, a material balance will be done. Material balance accounts and
with a realistic material balance with a basis of 100 tons of limestones as feed
per day.
The following material balance of each design are shown below. For
design option 1
CRUSHER
VIBRATING SIEVE
39
LIMESTONE BIN
m4
CALCINER
40
5.34 tons
m9 =
hour
1.84 tons m9
m10 =
hour
1.475tons
m11 =
hour
ROTARY KILN
FURNACE
GAS FILTER 1
41
Assumptions: 85% efficiency
m8 m18
m8 = m18 + m17
m17 = 0.15m8
m8 = m18 + 0.15m8
2.146 tons 2.146 tons
=m18+ (0.15)
hour hour
1.8241tons
m18 =
hour m17
0.3219 tons
m17 =
hour
SCUBBER
COOLING VESSEL
42
2.395tons
m24 =
hour m23 m24
4.9075 tons
m23 =
hour
1.8875tons
m22 =
hour
PUMP
COOLING TOWER
m24
PRECIPITATION REACTOR 1
43
Assumptions: 60%
1.5 tons/hour of recycle from PR 2 m28
0.5m28 + 0.5m21 + m29 = m31 + m30
1.5tons m29
m29 =
hour
m31 = 0.4m28
0.5m28 + 0.5m21 + m29 = 0.2m28 + m30
1.1975tons 1.906 tons 1.5tons
+ + = m21
hour hour hour
1.1975tons
( 0.4 ) +m 30
hour m31
4.1245 tons
m30 =
hour
0.479 tons m30
m31 =
hour
PRECIPITATION REACTOR 2
m33 m28
PRESCREEN TANK
44
m35 m30
Assumptions: 88% efficiency
1 ton/hour of recycle from ST
m30 + m35 = m34 + m33
m33
1tons
m35 =
hour
4.1245 tons 1 tons 0.5 tons
+ =m34+
hour hour hour
4.6245 tons
m34 =
hour m34
SCREENING TANK
m34
m36
FILTER PRESS
Assumption: 80%
m36 = m37 + m38 m36 m37
m38 = 0.2m36m36 = m37 + 0.2m36
3.6245 tons
3.6245 ¿ ns ¿ =m37+ ( 0.2)
hour hour m38
2.8996 tons
m37 =
hour
0.7249 tons
m38 =
hour
GAS FILTER 2
45
Assumption: 65%
m37 = m39 + m40 m37 m39
m39 = 0.35m36
m37 = 0.35m36 + m40
2.8996 tons 2.8996 tons
= ( 0.35 )+ m40
hour hour
1.88474 tons
m40 =
hour
1.01486tons
m36 =
hour m40
46
Energy Balance
kJ
Cpquicklime = 0.44194
kgK
kJ
CpCO2@1600K = 1.338
kgK
T1 = 273.15; T2 = 1600K
kg kJ kg kJ
(
Q T = 4167
hr )
(0.91
kgK
)( 1600 K −273.15 K)+ 4167
hr ( )
(1.338
kgK (
)(1600 K−273.15 K )+ 416
kJ 1 hr 1 min
Q T =14872635.0865 ( )
(
hr 60 mins 60 seconds
)
Q T =4131.28752402 kWh
Calciner
3.687795tons 1000 kg kg
mlimestones =
hour 1 ton (=3687.795 )
hr
kJ
Cplimestones = 0.91
kgK
kJ
Cpquicklime = 0.44194
kgK
kJ
CpCO2@2200K = 1.383
kgK
47
T1 = 273.15K ; T2 = 2200K
kg kJ kg kJ
(
Q T = 3687.795
hr )
(0.91
kgK (
)(2200 K−273.15 K )+ 3687.795
hr )
(1.383
kgK (
)(2200 K −273.15 K)+ 36
kJ 1 hr 1min
Q T =19434012.6717 ( ( )
hr 60 mins 60 seconds
)
Q T =5398.33685325 kWh
Rotary Kiln
kJ
CpCO2@2200K = 1.383
kgK
T1 = 273.15K ; T2 = 2200K
kg kJ kg kJ
(
Q T = 5340
hr)(1.383
kgK
)(2200 K−273.15 K )+ 5340
hr( )
( 0.44194
kgK
)(2200 K−273.15 K )
kJ 1 hr 1 min
Q T =18777499.3123 ( ( )
hr 60 mins 60 seconds
)
Q T =5215.97203118 kWh
Furnace
kJ
CpCO2@2200K = 1.383
kgK
48
T1 = 273.15K ; T2 = 2200K
kg kJ kg kJ
(
Q T = 260
hr )(
1.383
kgK )
( 2200 K −273.15 K ) + 260
hr
1.38 (
kgK )(
(2200 K−273.15 K ) )
kJ 1 hr 1 min
Q T =1384210.503 ( ( )
hr 60 mins 60 seconds
)
Q T =384.5029175 kWh
The plant’s total power requirement will be the summation of the Q T of all
Equipment Efficiency
Calciner 55%
℘
Furnace 60% Q= −(℘+Wpη)
η
℘
4131.28752402 kWh= −(℘+ 0.485℘)
0.485
49
℘=7161.74 kWh
Calciner
℘
5398.33685325 kWh= −(℘+ 0.55℘)
0.55
℘=20129.4 kWh
Rotary Kiln
℘
5215.97203118 kWh= −(℘+0.7237 ℘)
0.7237
℘=−15255.3 kWh
Furnace
℘
384.5029175 kWh= −(℘+ 0.6 ℘)
0.6
℘=5767.54 kWh
The plant’s total work produced will be the summation of the Wp of all the
The thermal efficiency of the plant will be calculated by the ratio of the
total produced work by the plant to the total power required by the plant
multiplied by 100%.
Thermal efficiency =( Plant total produced wor k /Plant total power requirement ) 100 %
50
CHAPTER IV
ECONOMIC ANALYSIS
This chapter presents the data and detailed calculations of the cost
estimations that the proposed PCC plant would incur in order to justify if the plant
is economically viable.
Capital Costs
involved in design and manufacturing with all the related service facilities.
Lang (l947b) introduced the first factorial method for capital cost
estimating, and proposed a relationship between the cost of plant equipment and
C = f (E)
51
Where: C = Fixed capital cost
f = Factor
fixed capital investment is determined using the factor, 3.10. According to Lang,
the computed capital cost is considered apparent and used as basis for the
DESIGN OPTION 1
To be able to compute for the capital cost, the total purchased cost of the
52
Precipitation Reactor 2 5,210,104.8
Screening tank units 1 2,605,052.40
Filter Press 1 5,207,424.18
Total Cost 144,816,477.2
C = f (E)
I. Direct Costs
a. Purchased Equipment
for the proposed plant is provided by a current price quote from a suitable
vendor.
53
Table 3. Installation Cost
54
i. Labor Cost (25% of PEC)
c. Piping Installation
This covers labors, valves, fittings, pipe, supports, and all other
terms involved in the complete erection of all piping used directly in the
process.
(KLM Group, 2014) Since the proposed plant is a fluid processing plant,
55
Total Piping Installation Cost = Php 23,170,636.35
This includes not only the instruments but also all auxiliaries for the
entire plant.
Group, 2014).
Since the proposed plant will use only few controls, it is estimated
56
e. Electrical Installation
Group, 2014)
f. Buildings
Since PCC plant is a new plant at a new site, the cost is estimated
57
g. Yard Improvements
This includes the utilities of the plant for supplying steam, water,
power, compressed air, and fuel. Waste disposal, fire protection, and
The costing for service facilities depend upon the type of services
that is used in the plant, either the use of minimum additional services, or
average services or the use of the complete new services, with their
58
i. Land
According to KLM Group (2014), the value of land does not usually
decrease with time that is why this cost should not be included in the fixed
depreciation.
Direct Costs
Component Cost (Php)
Purchased Equipment 144,816,477.2
Purchased Equipment Installation 62,271,085.2
Piping Installation 23,170,636.35
Instrumentation and Control Installation 7,240,823.86
Electrical Installation 21,722,471.58
Buildings 98,475,204.5
Yard Improvements 28,963,295.44
Service Facilities 108,612,357.9
Land 11,585,318.18
Total 506,857,670.2
II. Indirect Costs
communications cost.
59
This cost is normally considered an indirect cost in fixed capital
cost or 8 percent of the total direct costs of the process plant. (KPL Group,
2014)
b. Construction Cost
tools and rentals, home office personnel located at the construction site,
construction payroll, travel and living, and taxes and insurance of the
plant.
percent of the total direct costs for ordinary chemical process plants. (KLM
Group, 2014)
c. Contractor’s Fee
plant cost which is the sum of the fixed capital investment and
construction expense.
60
Contractor’s Fee = Php 40,548,613.62
d. Contingency
This includes extra costs added into the project budget for
the plant.
installation used.
Indirect Costs
Component Cost (Php)
Engineering and Supervision 40,548,613.62
Construction Cost 50,685,767.02
Contractor’s fee 40,548,613.62
Contingency 50,685,767.02
Total 182,468,761.3
61
True Fixed Capital Investment = Direct Costs + Indirect Costs
Working capital is the additional investment needed, over and above the
fixed capital, to start the plant up and operate it to the point when income is
1. Start-up.
Most of the working capital is recovered at the end of the project. The total
investment needed for a project is the sum of the fixed and working capital.
Working capital can vary from as low as 5 per cent of the fixed capital for a
high as 30 per cent for a process producing a diverse range of product grades for
Project, 2018)
62
Working Capital = Php 67,339,661.9
to make a product and to ready it for shipment. These expenses are divided into
three classifications as follows: direct production costs, fixed charges, and plant
overhead costs.
- Limestones
kg 1 ton tons 24 h
4166.67 × =4.167 × =100 TPD
h 1000 kg h d
- Coal
63
kg 1ton tons 24 h
125 × =0.125 × =3 TPD
h 1000 kg h d
- Water
Raw Materials
Material Requirement Base Cost Total Cost (330
days)
Limestone 100TPD Php 1565.64/ton Php 51666120
Coal 3TPD Php 2191.90/ton Php 2169981
Water 64.8 m3 Php 24.81/m3 Php 530537.04
Total Php 54366638.04
b. Operating Labor
of the plant.
64
Table 10. Detailed Manning Estimates
65
Mechanical 5 245,259 1,226,295 22,500.19 112500.95
/Electrical/ICE
Technician
Helpers, 6 181,757 1,090,542 22500.07 135000.42
Maintenance and
Repair Workers
Security 8 145,733 1,165,864 22500.01 180000.08
Janitor 4 96,000 384,000 8500.07 34000.28
Driver 5 149,222 746,110 22500.02 112500.1
Total 56 12861204 1876503.86
66
c. Direct Supervisory and Clerical Labor
d. Utilities
Utilities
This covers the amount of labor and materials associated with the
maintenance of the plant. For the plant operating and using complicated
investment.
f. Operating Supplies
68
This includes miscellaneous supplies that support daily
operation but not considered as raw materials. These are chart papers
for operators.
g. Laboratory Charges
the plant.
Group, 2014)
69
Table 12. Summary of Direct Operating Cost Estimated and Itemized
a. Depreciation
b.Local Taxes
70
Local Taxes = 0.02 x Php 689,326,431.5
c. Insurances
Fixed Charges
71
It considers all the costs associated with the operations of
plant.
1647705.021)
OPEX=Php 311145799.985
a. Administration Costs
72
It is consist of other salaries, other administration, buildings,
investment.
investment.
689,326,431.5
73
Table 14. Summary of Cost Estimates for the Computations of
Economic Indicators
a. Payback Period
Php 1153826475.21
Php 742500000/ year
¿ Php1153826475.21−Php742500000
NPV =411326475.21
c. Rate of Return
74
Total Capital Investment−Total Income
Total Capital Investment
RO R=35.65 %
75
CHAPTER V
ENVIRONMENTAL MANAGEMENT
the production of PCC to mankind and welfare, and the possible solutions,
The effect of the operation of the process plant upon the environment and
Law
Air Act of 1999, R.A. No. 8749, are directly enforceable federal regulations
issued for the categories of sources of air pollution that may reasonably be
chorofluorocarbons, and the like. Section 31 of the Philippine Clean Air Act of
1999, R.A. No. 8749 requires the control of the exhaust of those greenhouse
76
environmental conditions including ozone depletion and greenhouse gases are
area.
I. Waste Generation
The wastes that can be generated from the production of PCC will be
treated to ensure the safety of the environment, moreover the treated waste by –
products are tested to see if they meet the standard requirement to be discharge
in the environment, or it will then be recycled and be used again in the process.
The waste produced in the PCC Process Plant would be disposed once
they met the standard required properties. The produced Carbon Dioxide from
the heating units are treated using the gas filter and scrubber and will be sent to
the precipitation unit as its reactant to the slaked lime, moreover, the waste
produced during the treatment process of the carbon dioxide are disposed to the
The filter cartridges that are used in the gas filters are checked monthly
For the wastewater that were discharge from the cooling and slaker unit, it
will be disposed on a land fill provided by the plant. This wastewater will be first
cooled down and are considered mud that can be disposed on landfills.
77
Social and Environmental Impacts
One of the effects of the waste produced by the PPC Process Plant is that
the miniscule particulates that could harm the health of the residents living near
the plant if not wearing dust mask. In order to control these particulates, the
exhaust of the gases from the heating units are sent to the gas filters so that
these particulates are filtered out before sending the treated gas to the
atmosphere.
used cooling water or coolant in the plant serves as the main contributor to this
Moreover, in order to control and prevent this type of pollution, the waste water in
the coolant are first cooled down before disposing it the ocean or in landfills when
into the atmosphere. Particulates can cause lung irritation, which can lead to
severity of chronic lung diseases, and can increase susceptibility to viral and
78
to clear these infections. Residents near the plant should wear dust mask, so that
they would not intake any of the particulates release from the plant.
within the plant and any subsequent reaction products that could
clean up.
PCC
79
Section 2: Composition and Information on Ingredients
80
approved breathing apparatus with full face piece to protect
oxide.
Acids
dioxide.
81
Eyes: May cause eye irritation with discomfort or pain, local redness and
Wear clean, dry gloves, full length pants over booth, long sleeved shirt
buttoned at the neck, head protection and approved eye protection selected for
Gloves (Specify)
Respiratory (Specify)
82
Up to 100 mg/m3 : (APF=10) Any particulate respirator equipped with an N/R/95,
Up to 250 mg/m3 : Any powered, air purifying respirator equipped with N/R/95,
N/R/99 or 100 filter or supplied – air respirator with elastomeric half – mask /
facepiece.
Eyes
ANSI, CSA or ASTM approved safety glasses with side shields. Tight
fitting dust goggles should be worn when excessive (visible) dust conditions are
present. Do not wear contact lenses without fitting goggles when handling this
chemical.
Footwear
Usual protection.
Clothing
Other
Engineering Controls
exposure limits.
83
Waste Disposal
Avoid skin and eye contact. Minimize dust generation. Wear protective
mask. An eye wash station should be readily available where this product is
used.
Storage requirements
Keep tightly closed containers in a cool, dry and well-ventilated area, away
from acids.
Skin
remove all traces of Calcium Carbonate. Use a brush, cloth or gloves. Remove
Eyes
84
Inhalation
Move source of dust or move victim to fresh air. Obtain medical attention
physician immediately.
Ingestion
If victim is conscious, wash out mouth with water. Have conscious person
person.
General Advise
regulatory listings:
SARA Section 313 – Toxic Release Inventory. Toxic Chemical List : Not
Listed
85
CWA 311 – Clean Water Act List Hazardous Substances : Not Listed
Toxic Substances Control Act (TSCA): All naturally occurring components of this
List
Fire Hazard
Specific Hazard
CHAPTER VI
PROJECT EXECUTION MANAGEMENT
86
This chapter contains the project construction management and strategy
including the quality control and assurance, working scheduling and overall
Gantt Chart which takes into consideration the major activities and time allotted
to each activity. This also includes the preparation of simulation video of the
whole processing plant system highlighting the plant lay-out and processes
I. Preliminaries
This stage includes the will set the start-up processes for the project such
as the scope and nature of the project which includes the planning, feasibility
A. Planning Stage
Identification of the phases, activities, and tasks needed for the execution
of the plant are include the planning stage. Different key project controls will be
Feasibility study stage tests the viability of the project. The goal of this
construction and operation if the project is pursued and determine if, after all
87
C. Basis of Design Stage
describes the technical approach planned for the project as well as the design
parameters to be used.
Design layout stage includes the detailed construction plan which is the
Capital cost estimation for the proposed plant will be made and feasible returns
operating factors, material and energy balance will be considered in this stage.
II. CONSTRUCTION
having civil works, mechanical works, electrical works, automotive control the
Complete plant layout and blueprints will be the main consideration in this
88
B. Procurement and Construction Stage
In this stage managing activities and tasks are made. Availability, quality,
quantity and cost are the main factors to be considered. Equipment should will
operate efficiently during the production. Raw materials will be gathered and
properly stored while the machineries and equipment are being installed. Two
This stage will verify the process by ensuring that the subsystems including
requirements.
In this stage, the safety of running the plant processes and operations
must be practiced since safety is the most important thing to consider. The plant
will be tested to its efficiency and capacity to produce the products by a dry run.
Changes and adjustments regarding the processes or the product quality will be
done to avoid any unexpected accidents before and during the official start of the
this phase.
D. Operation Stage
89
The plant will start its normal operation after the, planning, compliance to
all the government and company requirements and specification, and ensuring
the safety of its processes and quality of its product. This stage contains the
In order to operate the plant safely and maintain specific conditions such
as temperature and pressure, the plant must be properly controlled. The control
of the process was broken down into three stages; crushing unit, heating unit,
and slaker and precipitation unit. The primary concern of the crushing unit of the
plant is maintaining a constant feed rate of limestone of 6.25 tons/hr. This feed
rate provides the jaw crusher to be less stress on its gears and crushing
materials. Maintaining the feed rate is important for also the intake rate the
heating unit takes from the crushing unit depends on the feed rate the crushing
unit crushes. Moreover, the feed rate is controlled by the operator who controls
In the heating unit, three main equipment are used which are the pre –
heater assembly, calciner, and the rotary kiln. The corresponding temperature of
each equipment should be maintained. The temperature for the pre – heater
90
controller and material used for construction. In the calciner, the temperature
dioxide from the pre – heated limestones to 50 – 80% of the cumulative carbon
limestones are properly cooked and not cause an undesired overcooked quick
lime. Moreover, the temperature in the rotary kiln should be kept similar to the
calciner’s temperature. The main role of the rotary kiln is to maximize the carbon
release of 90 – 95%.
In the slaker and precipitation unit, the process variables that are needed
to control is the temperature, pressure, and flow of cooling water. The slaker is
composed of the cooling and slaker vessel to which cools the quick lime from the
rotary kiln. The cooling process is done by adding cooling water to the quick lime
and slaking it. The control for the flow of cooling water is done by a control valve.
Controlling the water intake is necessary for the temperature inside the cooling
and slaker vessel depends on the amount of cooling water going in the vessel.
Moreover, the cooling water flow rate should be maintained at around 1.8875
reactor to which the precipitation reaction occurs between the slaked lime and
the carbon dioxide from the gas treatment unit. The process variables needed to
be controlled on that unit is the flow rate of carbon dioxide and the pressure
inside the reactor. The pressure depends on the carbon dioxide the reactor
intakes, to which the flow rate of carbon dioxide should be maintained at around
91
1.5 tons/hour. It is necessary to control the carbon dioxide flow rate, for
excessive intake could result to a poor-quality PCC product and may even cause
wear out of material of construction of the reactor. The flow rate is controlled by a
Organizational Chart
In order to accomplish all the project plan, there should always have
important aspects to consider about the goal of the business organization. These
unrecognized or behind the scene event). Ideally, these features are carefully
functional department.
It is in-charge in keeping the personnel information files and makes report on the
92
activities of the employees. It proceeds training for new applicants. Employee’s
services such as material and legal counsel also provided by the department.
production planning and also pricing. This will handle the advertising and
promotion program, and actual distribution of the product and public relation
developing a need for demand for the company’s goods and services. They also
consumers.
Production/Process Department
making necessary for carrying out the process. It establishes operations, its parts
and sequences and proper class of machines required for the operations.
Labour Requirements
These factors include the duty, nature of their work and according to their
capabilities.
93
General Manager
Executive Summary
95
responsibilities for the people who will Psychology
carry them out With at least 3 years of experience
General Account Responsible in handling financial matters, Male or Female
Manager performing accounting control and With at least 5 years of working experience
processes
77Secretaries Responsible for the safekeeping of the Female
management of all the transactions of the Graduate of Secretarial Course
department Computer Literate
Purchasing Officer Works closely with marketing and finance Male or Female
department, responsible for the BS Industrial Engineering
procurement function and considerable Economics Graduate
influence upon the purchase of the With at least 3 years of working experience
material, supplies, and facilitate as they related to said duty
facilitate or impede the production
process
Assistant Purchasing Generally concern with scheduling of raw Male or Female
Officer materials in the plant and delivery of BS IE or Commerce Graduate
finished product on the plant, warehouse
to either regional or the customer’s facility
Training and Responsible for securing the services of Male or Female
Employment the people with the knowledge and skill to BS Behavioural Science / Psychology
Assistance carry out necessary activities graduate
96
Assist HR Manager
Janitors Responsible for the cleanliness and Male
orderliness of the plant Agency member
Driver In-charge of the transportation of raw At least high school graduate
materials and delivery of products
Utility Men Acts as errand and responsible in Male
accomplishing assigned task At least high school graduate
Security Officer Responsible for the proper Male
implementation of security rules and Security agency member
regulation
Responsible in the routine check-up in Male or Female
the medical services of the company’s General Medicine Graduate ( preferably,
employees Licensed) 97
97
efficiently experience
Accountant Responsible for the custody and control of Certified Public Accountant
all the accounts and financial records of With at least 3 years of work-related
the company experience
Auditor Responsible for auditing all financial Certified Public Accountant
accounts and records of the company With at least 3 years of work-related
experience
Payroll Officer Responsible for the computation of BS Accountancy / Commerce Graduate
salaries and other financial aspects
concerning the employees
Advertising Officer Responsible for the formulation of Graduate of BS Business Management
advertising strategies to help make the major in Advertising
products more competitive With at least 2 years of work-related
experience
Advertising Assistant Assist the Advertising Officer Graduate of BS Business Management
major in Advertising
Sales Representative In charge of the implementation of Graduate of BS Business Administration
marketing strategies With good interpersonal skills.
98
Process Engineer Responsible in controlling and implementing Male or Female
of policies and procedures in accordance with Licensed Chemical / Mechanical
the set standards Engineer
With at least 5 years of work-related
experience
Quality Control Responsible for insuring high quality products Licensed Chemical Engineer/
Manager and for setting up standards and procedures Registered Chemist
of the process With at least 3 years of work-related
experience
Production Engineer Responsible with the up keep and repair of Male or Female
production equipment, buildings, and plant Licensed Mechanical/Chemical
services and the design modification of the Engineer
plant and processes With at least 3 years of work-related
experience
Process Supervisor Furnishes production schedule and machine Male or Female
loading programs and has direct supervision Licensed Chemical / Mechanical
of the production operators Engineer
With at least 3 years of work-related
experience
Laboratory Analyst Responsible in conducting laboratory tests Male or Female
and chemical analysis icensed Chemical / Mechanical
99
Engineer
With at least 3 years of work-related
experience
Production Operator Responsibility includes inspection and Male
monitoring of assigned equipment processes Technical / Vocational Graduate
and finished products
Ensures proper operation
Field Operator In-charge of supervision of external operation BS Mechanical/Chemical Engineering
of the production and perform minor repairs graduate
Lead Operator In-charge of the control system and BS Mechanical/Chemical Engineering
procedures and perform minor repairs graduate
Mechanical Technician Responsible for overall maintenance and Male
repairs of the different equipment and Licensed Mechanical Engineer /
facilities, instrumentation and piping Certified Instrumentation Engineer
With at least 2 years of work-related
experience
Electrical Technician Responsible for overall repairs and Registered Electrical Engineer / Master
maintenance of the electrical facilities and Technician
wirings With at least 3 years of work-related
experience
Safety Engineer Responsible for checking the overall status of Registered Chemical / Mechanical
plant and its equipment for safety purposes Engineer
100
With at least 3 years of work-related
experience
Environmental Responsible for making necessary Graduate of BS Chemical Engineering
Engineer adjustments to meet the standards given by with Masters in Environmental
the government agencies regarding Management
environmental considerations
Research and Responsible for checking the new trends and Registered Chemical / Mechanical
Development needed adjustments of the plant for Engineer preferably with Master’s
Supervisor and optimization purposes Degree
Specialist With at least 3 years of work-related
experience
Quality Responsible for ensuring high quality BS Chemistry/Chemical Engineering
Control/Assurance products and for setting up standards and Graduate
Head procedures of the process With at least 3 years of work-related
experience
101
PROJECT SCHEDULING
GANTT CHART
Project Schedule
YEAR
Planning
Feasibility Study
Stage
Basis of Design
Phase
Design Layout
Stage
Complete Design
Stage
102
Project Schedule
YEAR
Working 2021 2022 2023 2043
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Activities A E A P A U U U E C O E A E A P A U U U E C O E A E A P A U U U E C O E
N B R R Y N L G P T V C N B R R Y N L G P T V C N B R R Y N L G P T V C
Procurement
and
Construction
Stage
Commissionin
g and Dry-run
Stage
Operation
Stage
103
Preparation of Simulation Video
The simulation video of the PCC Production Plant showcases the different
processes include the crushing stage which primarily is composed of the jaw
breaker; the heating stage which is composed of the pre – heating assembly,
calciner, and rotary kiln; the cooling and slaker stage which is composed of the
cooling and slaker unit; the precipitation stage which is composed of the
the filter press; and the storage and distribution stage which is composed of the
The simulation video also presents the raw materials and the source of
those raw materials needed for the production of PCC. Moreover, the global and
local demand for PCC are also presented to which the PCC Production Supply
104
CHAPTER VII
Summary of Findings
at Mabini, Batangas. The plant is considering supplying 15% of the PCC locally,
tons/day.
and supplier of PCC in the Philippines would be added since the supply of PCC
PCC plant reasonably viable to resolve this unbalance supply – demand system
105
Conclusions
mentioned above.
supply and demand; target customers, target location and market are
important which will serve as the foundation for the development of the
proposed plant.
6. This proposed design, which uses calcination process, which will emit
exhaust CO2 and dust will be subjected to gas treatment through the
106
Recommendations
deposit of limestone to account for the raw material requirement for the
production of PCC.
2. The use of renewable energy as the source of the plant’s energy since it
needed large amount of energy needed for each of the operations to run.
3. The use of more advanced gas filters for exhaust CO2 and dust is
advisable.
equipment.
5. Health, safety and environment must take into consideration during project
107