Professional Documents
Culture Documents
: -
HONING PROCEDURE
1 of 10
REVISION LOG
2 of 10
Doc. No. : 26071-100-V5A-JF21-40006
3 of 10
Doc. No. : 26071-100-V5A-JF21-40006
TABLE OF CONTENTS
1. SCOPE……………………………………………………………………………………………….5
2. PURPOSE……………………………………………………………………………………… …...5
3. DEFINITIONS………………………………………………………………………………………5
5. REFFERENCE………………………………………………………………………………………5
6. INTRODUCTION..............................................................................................................................
7. PREPARATION…………………………………………………………………………………….6
4 of 10
Doc. No. : 26071-100-V5A-JF21-40006
1. SCOPE
This document covers the minimum requirements of Pipe Honing and Surface Roughness for
Construction for Refinery Development Master Plan (RDMP) RU-V Balikpapan Project.
2. PURPOSE
Provide general guidance for Pipe Honing and Surface Roughness activity of construction
steel pipe used in the owner project.
3. DEFINITIONS
All manpower has been conducted the medical check up before starting the job.
All manpower must be conducted the safety induction and other training
5 of 10
Doc. No. : 26071-100-V5A-JF21-40006
5. REFFERENCE
6. INTRODUCTION
Honing classified as an industry process using grinder. Equipment for honing process is a honing
machine set. As the process using grinding machine, material is threw away from rough fiber work piece. In
this case, fiber is combined with adhesive to form grinder stone or abrasive. Honing is an industry process
which results work piece in the certain ways. Basically honing is used to increase the surface geometric
shaped, however it is also used to incr-ease the surface texture.
7. PREPARATION
6.1 Honing Procedure
a. Cleaning
Cleaning the cylinder or pipe which is will be honing.
b. Inspection
Inspection shall conduct by machining operator, contractor and company. Inspection and
measurement of the early dimension, give the deadline of honing work and other works (if
any), such as cleaning welding remains, scratch and etc.
c. Leveling
Leveling the welding remained with grinding or buffing without causing damages to other
components.
d. Buffing
e. Setting-out
Setting-out the honing machine adapted to work piece.
f. Put a work piece into honing machine and locking done the work piece thus that safe
accordance with the work procedure. All of the work preparation are execute accordance with
operation standard, the K3 laws (HSE regulation), and company policy regulation.
6.2 Refining/Honing Many Type of Cylinder
Refining is done for accomplish the final step, which accordance with preferred measure.
c. Cleaning the work piece.
d. Final measurement inspection, components are tested / measured by the proper tools to ensure
the compliance of specification.
e. Dimensional check for inner diameter of pipe after honing process. Measurement method is
vector X-Y and diagonal, and then divided by variable in several spots of checking area,
which shows on the checking table. Please see below, equipment of dimensional ID Pipe
checking (micrometer). The deviation is no more than 0,5 % of nominal ID Pipe.
All of the refine/honing works are execute accordance with operation standard, the K3 laws
(HSE regulation) and company policy regulation.
b. Inside and outside of piping shall be free from all dirt, debris, oil, rust, scale, paint and all
other foreign matter.
c. Prepare equipment for roughness test and ensure that full function and complete with
certificate calibration from the manufacture.
B. Safety
Safety shall be strictly observed all time during Roughness test. The area shall be
cordoned off with signed board or safety barrier. Are for testing shall be cleaned from dust,
rust, painting work and other foreign matter. Only authorized person is allowed in this area.
c) During applying the surface roughness tester, the range requirement for acceptance.
Specific for this pipe spool shall be as per American Gas Association No. 3 / MPMS 14.3.2
para 2.5.1.1 (max 250 Micro inches).
d) Installing detector roughness test instrument in the testing area.
8 of 10
Doc. No. : 26071-100-V5A-JF21-40006
e) Turn on the measurement tool to observe the test result accordance with measurement tool
work operation of roughness tester.
h) Repeat the testing process in several location thereby the results of testing and
measurement are completely accurate.
i) The roughness measurement will take about 8 (eight) spots internal pipe. Please see below
for the location of the spots.
D. Documentation
The roughness test report prepared by sub-contractor and shall be signed by client
representative on site after completion roughness test. The document stated above used in
roughness test shall become part of the manufacture data report.
9 of 10
Doc. No. : 26071-100-V5A-JF21-40006
8. ATTACHMENT
10 of 10