Professional Documents
Culture Documents
Owner’s Engineer
Contractor
Project
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
(2 X 600 MW)
Title
(Housing Complex)
Method Statement for Installation of Hume Pipe
NS2-DD09-P0UYK-770020 A 22 Pages
RECORD OF REVISIONS
4 PREPARATION..................................................................................................................................2
The statement consists of Site preparation, Equipment Supply and Installation, Material
Supply, Construction Procedure, Inspection Procedure, and Quality Assurance related to
Subcontractor’s responsibility for implementation of the whole Housing Complex Work
Package following requirements mentioned in Specification and Designs as well as the
relevant standard of the Project.
22TCN 266:2000 “Standard for construction and acceptance of bridges and culverts”;
No Description Q’ty
1 Excavator
2 Dump Truck
3 Compactor
5 Total Staion
6 Barrier
Position point coordinate must be set out by total station and marked by suitable stakes.
4.2 Material
All reinforced concrete hume pipes must be new and perfectly sound, free from cracks,
cylindrically straight and comply to design nominal diameter and length with even texture.
The strength of concrete sample reaches over 70% of designed strength (R28), those
products can be delivered to the site.
Only soft slings shall be used for lifting products. Steel chains, clamps or cables shall not
be allowed lifting purposes.
The product shall be protected during handling against impact, shocks and free fall to
avoid cracks and damages.
Any products found to be incorrectly fabricated shall be marked and set aside.
Any products damaged during delivery, storage or installation shall be marked by the
Contractor and set aside.
Transportation and stack of hume pipe must comply to safety requirement and under control
of contractor to minimize the inconvenience affected to the traffic and other construction
activities.
The subcontractor shall be fully responsible for the safety and security of materials transported
and stacked in the working area
5 EXECUTION
5.1 Excavation of trench
Excavation work will be performed as per approved method statement (Refer to NS2-
DD09-P0UYK-770002 “MS for Excavation and Backfill Work”).
Any unsuitable soil or rock, bounder, stone… which could cause point load on pipe
surface must be removed if they are encountered in trench bed. Replaced material
should be screened sand as general backfilling procedure.
Where:
W = Do + 0.8 for Rein. Concrete Pipe D400
The temporary drainage must be prepared and kept in whole time of installation work for
hume pipe.
The bell end should point upstream and the spigot or tongue should point downstream.
This helps prevent bedding material from being forced into the bell during jointing and
enables easier coupling of pipe sections;
Saddle shall be used for supporting pipes during installation. The elevation and slope of
pipeline is most determined by saddle;
The ends of the pipes shall be kept closed to keep dirt, mud and foreign materials out. In
case of flooding condition, contractor shall take into account to proper method to prevent
from floating of pipe;
Laying of pipes shall commence from the lowest point of the pipeline.
Each successive pipe shall be kept in alignment with the previous pipe. Proper care shall
be taken to maintain true alignment during pushing a new pipe into the edge of an
already laid pipe for ease of installation, as well as to avoid any damage to the sealing
Use only soft slings for lifting with position of sling as below:
Connecting bell and spigot joints that are sealed with rubber ring gaskets may require
substantial force to push the pipes together;
Clean Spigot
List of All Job Steps List of All Known Hazards How to Eliminate Hazards
1.Mobilization Driver Over speed/taking Traffic collision 4 4 U Truck is not to be o o M Injury/ fatality &
the during with other overloaded. damage equipment
Pedestrian
equipment to
transporting. equipment All equipment must be tied
the site.
Equipment on the and human. and wedged carefully.
trailer truck are not Equipment falling Truck shall move with low
secured. down from the speed and do not
trailer truck. overtake.
2. Survey Surveyor & Holding survey Instrument falling 3 4 M Holding instrument o o T Near Miss
work Supervisor instrument un down and hit carefully.
. carefully. workmen. Wearing full PPE & Full
Survey instrument set Fall from height. body safety harness.
up at un-safe location. Set up survey instruments
Un-safe survey at safe location.
making location.
Without fall protection
3. Lifting and Crane Non-compliance Falling object. 4 4 U S.T.A.R.T Meeting prior o o M Injury/ Damage
Unloading work. with lifting procedure. start lifting works. equipment/
Operator. Crane over-
Environment
Rigger. Using lifting devices turning. Comply with lifting contamination
improperly. Crane collision procedure/Prepared/
Signalman.
Poor supervision. with power line/ Planned.
Supervisor
Non-compliance with other equipment. Daily inspection for crane
Worker.
barricaded & warning Electrocution by & lifting devices prior start
area. lightning strike/ operation.
4. Installation Crane Non-compliance with Falling object. 4 4 U S.T.A.R.T Meeting prior o o M Injury/ Damage
work. lifting procedure. start Installation works. equipment.
Operator. Crane over-
Rigger. Un-inspection the turning. Comply with lifting
lifting equipment. Crane collision procedure/ Prepared/
Signalman.
Poor supervision. with power line/ Planned.
Supervisor
Non-compliance with other equipment. Daily inspection for crane
Worker.
barricaded & warning Electrocution by & lifting devices prior start
Welder. operation.
area. lightning strike/
In-competent rigger & collision with Follow load chard of crane.
operator. power line/ using Generator & electric
power tools. equipment must be
Weather in bad
condition Human caught inspected.
(strong wind ≥ 8- between moving Strict control &
10m/s,
Project : Nghi Son 2 BOT Thermal Power Plant( 2 x Page 19 of
600MW) Work Item : Infrastructure Works
(Housing Complex) Method Statement for Installation of Hume
Pipe
3: Quite Possible/Occasional 3: Moderate 6-9: Moderate/Acceptable with review 6-9: Moderate/Acceptable with review
S1: Severity as is
S2: Severity with mitigating controls in place