Professional Documents
Culture Documents
Revision Record
All signed originals will be retained by the Project Document Control Centre and an electronic copy
will be stored in Livelink
Contents
1. Introduction.............................................................................................................................. 4
3. OR/CSU Management............................................................................................................. 8
6. Spare parts............................................................................................................................ 17
7. Handover Documentations..................................................................................................... 17
9. Preservation........................................................................................................................... 18
11. RACI...................................................................................................................................... 19
1.0 INTRODUCTION
The operations readiness management (ORMP) plan is a forward-looking document structured for the Jetty 2 Tower
Crane Replacement. It describes the activities that must be accomplished to achieve a right first-time commissioning of
the project and ascertains the state of preparedness of the asset owners to confidently take over the project to operate
and maintain it throughout its lifecycle. The overall objective of the ORMP is to assure future readiness and ensure
flawless project delivery.
To apply the principles of asset readiness and assurance for the optimal delivery of the Jetty 2 Tower Replacement in a
safe and environmentally friendly manner. The ORMP serves to ensure quality delivery of projects, risk mitigation,
accurate documentations that comply with the standard Asset Information requirements at handover to asset owners,
and training of end-users in readiness to operate and maintain the asset to ensure lifecycle benefits are realized.
This project relates to the replacement of the tower crane in NLNG Jetty 2. Upgrade signifies demolition and removal of
existing jib systems and installation of new jib, and refurbishment of the mast to support a 20-year life extension.
This is to restore the integrity, reliability, and availability of the tower crane at Jetty 2 on the NLNG Bonny Island LNG
plant.
The existing Tower Crane was commissioned in 2004. In 2016, the tower crane failed a load capacity test due to the level
of deterioration and was later derated from allowable load of 8.0 Tons to 5.9 Tons. Due to obsolescence and
unavailability of OEM support, the tower crane was tagged out of service in 2020 after being assessed and considered
unsafe for use with compromised integrity.
A project was initiated by NLNG to investigate options for replacing or restoring the existing tower crane. The concept
select phase has been completed and is documented in a separate Concept Selection Report.
Replacement of the jib was selected as preferred option based on the criteria for evaluation set out in the Jetty 2 Tower
Crane Replacement Project Concept Select Report. The viability of this option is based on an NDT assessment carried out
by a specialist vendor, which confirmed that the mast has a remaining life of more than 20 years and thus did not need
to be replaced.
A-3436-01.0 5 Cabinet
A-3436-02.02 Toolbox
A-3436-03.01 Trolley
The detail scope of work will include both static and dynamic aspects of commissioning and will to a greatest extent
possible represent a complete testing of systems and subsystems of the project.
These documents comprise the various steps that will be provided to demonstrate that the system is fit for purpose,
assembled correctly, tested completely, and preserved correctly and hand over to Operations.
Lessons learnt
Project team Lessons learnt focal point liaison with ORCSU coordinator will plan and execute lessons for the
define phase and share the outcome to project team and BOM for inclusion in the PEP and NLNG lessons
learnt database.
HSSE Management (Update Risk Register, HSE plans, HSE Case, etc.)
The Risk Register, HSE Plan and HSE Case have been developed and will be updated as required as we transit
from one phase of the project to another. HSE in transition from define phase to operate phase will also be
developed. The highest risk on the risk register. See Jetty 2 tower crane Replacement Risk register.
Key FPD Deliverables & Activities shall be applied to this headline size of project since project
is ranked as high risk/complex and could result in train trips or the turbines running without
fire-fighting protection.
Project Quality plan shall suffice to focus on selected quality areas inclusive of tightness of the
flange, integrity of welded joints, Integration and correct installation of instruments
monitoring systems, maintainability, and operability of the installed Jetty 2 equipment.
Pre-commissioning and commissioning for the Various system shall be subject to the approved site
acceptance testing plan developed by Vendor. This document shall be reviewed by our SMEs in PII
and PIR and approved for use.
Doc No: Revision: 0 Date: Page 8 of 11
<Operation Readiness Management Plan for Jetty 2 Tower Replacement Project>
Vendor’s will prepare site acceptance test document that will be used for pre commission and
commissioning. The acceptance criteria for each will be clearly defined and documented for audit
purpose.
7 SPARE PARTS
The minimum spares required for the critical items as identified in the project Material take off
shall be procured and handed over to the central warehouse after it has been inspected by the
different maintenance disciplines. This is an essential part of reliability of the assets after
handover. MESC Codes shall be provided for these new spares and the methodology of storage as
advised by the OEM adhered to. Commissioning spares shall be provided independent of the
operational spares. Commissioning spares shall be replacements of failed components during
commissioning activities. The surplus of the commissioning spares shall be handed over to the
warehouse for coding and storage to be added to the operational spares inventory.
8 HANDOVER DOCUMENTATIONS
The following documentation should be made available during handover. Mechanical Completion
Certificate (MCC) signed after punch list is done and all A and B punch list items closed, Pre-
Commissioning Certificate (PCC), pre start-up audit (PSUA), Statement of Fitness (SoF) checklist,
Ready-For-Start-Up (RFSU), Pre-Start Up Safety Review (PSSR), Tag Register, as built drawings and
documentations, updated procedures, work instructions, Transfer of Custody, Factory Acceptance
Test (FAT), Site Acceptance Test (SAT), Site Integration Test (SIT), Transfer of Ownership
documentation etc.
The asset owners’ preparedness to take over the project on completion the crane shall be tested to be sure
about its operating and performance ability. It is expected that all systems installed for this new asset shall
function as designed and it is expected that all systems installed for this new asset shall function as designed
and respond on demand without hiccups. This performance test is set by the ORCSU lead/engineer when the
asset assumes its KPIs’ at steady state operation. The following test must be carried-out to confirm the
installed equipment performance ability:
10 PRESERVATION
The Project Engineer shall ensure adequate preservation of all procured materials and equipment
in line with vendor’s advice to sustain asset integrity when they arrive site until time of installation.
The OEM shall provide a preservation manual/instruction to the Project Engineer prior to shipment
of the materials. On no account shall any procured materials and equipment be stored without
following OEM’s recommendation. A preservation audit will be carried out as part of the quality
plan.
R: Responsible
A: Accountable
C: Consult
I: Inform
POS/41
TPC/4
POP/5
TFF/4
POS
TPC
TFF
PSS
Crane Step Activity Description
Develop and implement asset readiness
ARP
plan R A I I I C I I
Develop, review and implement flawless
FPD
project delivery plan NOT APPLICABLE
Develop and review Commissioning and
Jetty 2 Tower Crane CSU
Start-Up philosophy R A C I R R I I
Replacement
AOR Ensure asset owners readiness R A C I R R I I
SoF Prepare and endorse Statement of Fitness NOT APPLICABLE
Start-Up Start-up the system I A R I R I R I
P2O Handover completed project to asset I A R I R I I R