You are on page 1of 27

Best Practice

SABP-L-002 19 May 2007


Design of Submarine Pipelines
Document Responsibility: Piping Standards Committee

Saudi Aramco DeskTop Standards


Table of Contents

1 Introduction................................................. 2
2 Applicable Codes and Standards............... 2
3 Production Data.......................................... 3
4 Pipeline Routings........................................ 4
5 Pipeline Wall Thickness Calculations
(Best Practice 1).................................. 5
6 Allowable Bending Stresses (Best
Practice 2)........................................... 7
7 Corrosion Allowance................................... 8
8 Determination of Concrete Weight
Coating (Best Practice 3)..................... 8
9 Preparing Data for Pipeline Free Spans,
Crossings & Other Miscellanies
Calculations.......................................... 9
10 Maximum Allowable Free-Spans
(Best Practice 4)................................. 10
11 Revising Maximum Allowable Free-
Spans (Best Practice 5)..................... 10
12 Pipeline Crossing (Best Practice 6)........... 11
13A Installation Stresses (Best Practice 7)...... 12
13B Shear Stresses Between the Concrete
and Corrosion Coatings (Best
Practice 7).......................................... 14
14 Flange Selection (Best Practice 8)........... 15
15 Pipeline Scraping and Hydrotesting......... 16

Appendix-A........................................................ 18
Appendix B........................................................ 21
Appendix-C........................................................ 23

Previous Issue: New Next Planned Update: TBD


Page 1 of 27
Primary contact: Sharif, Talal Mahmoud on 966-3-8746146
Copyright©Saudi Aramco 2007. All rights reserved.
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

1 Introduction

There are 5 major constraints involved in Sub-Sea Pipeline Design.

Environmental, these required the definition of currents, waves, mudslides, fault


movements, soil profiles and bathymetry, which could affect the stability and integrity
of the pipeline during its economical life.

Constructional, fabrication and installation equipment, the specification of the


pipeline steels, welding and quality controls, and pipeline bidding, backfill and
protection.

Operational and Maintenance, these must consider the need for tie-in points, flow-
rates, pressure and temperature profiles and the corrosivity of transported fluids,
methods of pipeline surveillance and monitoring, the need for maintenance possibly
repair, means of controlling fluid escape and emergency procedure.

Design, method of analysis to be used, route guidelines, regularity requirements and


codes, allowable stresses and factors of safety.

Economics, cost of construction, operation, surveillance, maintenance, failure and


repair. Furthermore, the potential effects of the pipeline on other systems must be fully
explored for their economic, political, environmental and social effects, especially when
these are related to pipeline failure.

2 Applicable Codes and Standards

As per Saudi Aramco standards, the selection of material and equipment, and the
design, construction, maintenance, and repair of equipment and facilities covered by
this standard shall comply with the latest edition of the references listed below, unless
otherwise noted.

2.1 Saudi Aramco References

Saudi Aramco Engineering Procedure


SAEP-302 Instructions for Obtaining a Waiver of a
Mandatory Saudi Aramco Engineering
Requirement

Saudi Aramco Engineering Standards


SAES-H-002 Internal and External Coatings for Steel Pipelines
and Piping
SAES-H-202 Storage, Handling and Installation of Weight
Coated Pipe

Page 2 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

SAES-L-100 Applicable Codes and Standard for Pressure


Piping System
SAES-L-109 Metallic Flanges Gaskets and Bolts
SAES-L-310 Design of Plant Piping
SAES-L-410 Design of Pipeline
SAES-L-850 Design of Submarine Pipelines and Risers
SAES-L-133 Corrosion Protection Requirements for
Pipelines/Piping
SAES-W-012 Welding Requirements for Pipelines
SAES-X-300 Cathodic Protection of Marine Structures

Saudi Aramco Engineering Reports


SAER-5565 Red Sea Hindcast Study
SAER-5679 Arabian Gulf Hindcast Study
SAER-5711 Submarine Pipeline Engineering Guidelines

Saudi Aramco Materials System Specifications


01-SAMSS-012 Submarine Pipe Weight Coating
09-SAMSS-089 Shop Applied External FBE Coating
09-SAMSS-090 Shop Applied Extruded P. E. external Coating

2.2 Industry Codes and Standards

American Petroleum Institute


API RP 1111 Design, Construction, Operation and Maintenance
of Offshore Hydrocarbon Pipelines

American Society of Mechanical Engineers


ASME B31.4 Liquid Petroleum Transportation Piping System
ASME B31.8 Gas Transportation and Distribution Piping
System

3 Production Data

Please refer to Saudi Aramco standard SAES-L-410 for the particulars of each oil field.
As an example, this data sheet provides generalized design criteria for design of new oil
flowlines and trunklines. Since field conditions can vary, Area Production Engineers
should be requested to provide information on the most recent field conditions.

Page 3 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

FIELD SAFANIYA
2070-4830 (300-700) as of 12/97.
Present SIWHP, Kpa (ga) (psig)
See Note #2
Maximum Expected SIWHP, Kpa (ga) (psig):
With full gas column N/A (See Note #1)
At reservoir maint. pressure 4658 (675)
Maximum flowing surface temp. deg C 66
Normal flowing pressure:
Well-head, Kpa (ga) (psig) 690-3445 (100-500)
Separator, Kpa (ga) (psig) 345 (50)
Flowline design pressure, Kpa (ga) (psig) 5175 (750)
Flowline design temperature deg C 66
NOTES:
1) No full gas column is expected.
2) Natural aquifer support maintains Reservoir pressure at or near the bubble point pressure.
3) Given shutin pressure data excludes Ratawi rsvr wells which currently have SIWHPs as high as 6210 Kpa
(ga) (900 psig). No Ratawi producing wells planned to be drilled in the foreseeable future.
4) The maximum injection pressure of future gas lift system is 12400 Kpa (ga) (1800 psig).
5) All offshore flowlines and trunklines are protected by ESD systems and a well and tie-in platforms.
6) Consult E&P Facilities & Technology Department for details of any further updates before final design.

4 Pipeline Routings

Preliminary pipelines routes shall be selected by studying the geophysical and


bathymetric survey (drawings can be obtained from the Saudi Aramco Hydrographic
Survey unit (HSU)). These routes shall be reviewed and approved by the Marine
department and proponent before they become final. Also the construction contractor
shall be responsible for performing a pre-construction survey of the route to identify
any obstruction which might affect the rout. Universal transverse Mercator (UTM) is
used for coordinates referencing.

4.1 Route Selection

Offshore routing shall be selected to avoid potential hazardous areas such as


pock marks, cap rock, and coral out-cropping; also efforts should be made to
avoid the need to trench pipelines in order to reduce cost and impact to the
environment.

Also future expansions of offshore oil fields and associated subsea pipelines net
work should be taken into consideration.

4.2 Route Criteria

As each routing normally has its own particular peculiarities, each pipeline and
power cable installations should be reviewed and approved on a case by case
basis by Marine Barge and Rig Operation Division's. This should be done at the
very early stage to avoid late and expensive modifications.

Page 4 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Following is a typical schematic illustrating pipelines and cables going to an


offshore jacket. There are three unobstructed sides that should be left for the
safe approach of:

1) Producing Department's well service, testing and maintenance jack-up


barges.

2) Drilling department's drilling and Work-Over rigs.

Offshore
Jacket

60-200 meters Clear Area = Circle


Pipelines and/or with
Cables Corridor 60-200 meters
Radius

5 Pipeline Wall Thickness Calculations (Best Practice 1)

The pipeline stresses calculation will start by identifying the followings:

1 Required Nominal outside Diameter of the Pipeline (OD) this is produced after
pipeline hydraulic simulation analysis is done utilizing special software.

2 Field Design Pressure (P), operating Temperature, product density and water cut
as a percentage (%) this can be obtained from current field data.

Page 5 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

3 Location design factors (F) refer to ASME-B31.8 table 841.114A per Saudi
Aramco standards (F=0.72 for pipeline and F=0.5 for Riser), longitudinal Joint
quality factors (E) refer to ASME-B31.8 table 841.115A and Temperature de-
rating factors (T) refer to ASME-B31.8 table 841.116A.

4 Specified Minimum Yield Strength (SMYS) for example using grade B, X-42, X-
52 or X-60 etc.

In summary:
Field Design Pressure Pf
Outside Diameter of Pipe OD
Specified Minimum Yield Strength S.M.Y.S
Location Design Factor F
Joint Quality Factor E
Temp. De-rating Factor T

The formula for calculating the minimum wall thickness per ASME-B31.8
paragraph 841.11.

This is derived from the hoop stress formula,


σH=PD/2t, D is = OD, please refer to Appendix “A”
to see how to drive hoop stress σH=PD/2t

min. wt. =P * OD/(2*F*E*T*SMYS) psi (2-1)

The above calculated wt. is the minimum; however in selecting the appropriate
wall thickness for the pipe, one should consider other parameters that affect the
wall thickness. For example pipe laying stresses, corrosion allowances, design
life of the pipe and potential change in operating pressure and temperature by
introducing different artificial lefts. However, per Saudi Aramco standards and
guidelines the minimum wall thickness is 0.375-in for sub-sea Pipeline and
0.5-in for Riser.

Based on the selected wall thickness, the Maximum Allowable Operating


Pressure should be calculated.

Max. Allow. Op. Pr. (M.A.O.P.) = 2*SMYS*wt.selected*F*E*T/OD psi (2-2)

Also, based on the selected wall thickness, the hydrotest pressure for the
pipeline should be calculated.

Hydrotest @ 90% SMYS = 0.9*2*SMYS* wt.selected/OD psi (2-3)

Page 6 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Hoop stress for the selected wall thickness should be calculated for both operation
and hydrotest pressures; this will be utilized when calculating the allowable
bending stress for the pipe.

The formula to calculate Hoop Stress

Hoop stress (SH) =P * OD/(2* wt.selected) psi (2-4)

Thermal Stress due to operational temperature should be calculated. This also will
be utilized. In order to be more Conservative the Corrosion Allowance should not
be included when Hoop Stress SH Due to Operational or hydrotesting Pressure is
obtained, this will REDUCE the Allowable bending Stress SB.

Formula (2.4) will become

Hoop stress (SH) =P * OD/ (2* (wt.selected – Cor)) psi (2.4.1)


P is the selected Hydrotest or operation pressure.

The formula to calculate Thermal Stress

St =Thermal Stress = E * α * ΔT psi (2-5)


E = Modulus of Elasticity of Steel psi (MPa)
α Thermal Coefficient of Expansion in. /in. /F (mm/mm/C)
ΔT = T2–T1 (Operating Temp. T2 – Surrounding SEA Temp. T1) °F (ºC)

6 Allowable Bending Stresses (Best Practice 2).

The following Equations govern the Maximum allowable bending Stresses:

The minimum of any one case (Operating or hydrotesting) will govern the associated
free-span and pipeline crossing calculations.

Please refer to Appendix-B to see how these equations have been derived from ASME
B31.4.

Restrained Pipelines – Operating Case:

SB <= 0.9 SMYS – 0.7 * SH – E * α * ΔT + SAX psi (MPa) (3-1)

Restrained Pipelines – Hydrotesting Case:

SB <= 0.9 SMYS – 0.7 * SH – E * α * ΔT + SAX psi (MPa) (3-2)

Un-restrained Pipelines – Operating Case:

SB <= 0.54 SMYS – 0.5 * SH psi (MPa) (3-3)

Page 7 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Un-restrained Pipelines – Hydrotesting Case:

SB <= SMYS – 0.5 * SH psi (MPa) (3-4)

Where:
SB = Allowable bending Stress psi (MPa).
E = Modulus of Elasticity of Steel psi (MPa)
α = Thermal Coefficient of Expansion in. /in. /F (mm/mm/C)
ΔT = T2–T1 (Operating Temp. – Surrounding SEA Temp.) oF (oC)

SAX = Residual axial Stress Due to Pipe lay tension psi (MPa). Please note that Axial
Tension due to the lay tension SAX increases the allowable bending stress. SAX is
unknown, for conservative approach it can be considered to be = 0.0

7 Corrosion Allowance

Corrosion allowance will not reduce the corrosion rate of the piping material. However,
the extra wall thickness of the pipe may provide a longer service life if the mode of
attack is uniform general corrosion.

Corrosion allowances are not effective against localized corrosion, such as pitting.
Please refer to SAES-L-133.

However, Excess pipe wall above the minimum wall thickness is considered as
corrosion allowance.

SAES-L-133 Par. 7.1. Recommend (3.0 mpy) 76 μm/yr. if a need is there. 1.6 mm
Corrosion Allowance. Based on this it is recommended to subtract these corrosion
allowances from the selected pipe wall thickness when calculating pipeline free-spans
and crossings.

8 Determination of Concrete Weight Coating (Best Practice 3)

The Pipe Research Committee International (PRCI) and American Gas


Association (AGA) Level-2 analysis computer program should be used to analyze the
subsea stability of the pipelines.

Analysis should be performed in accordance with SAER-5711, SAES-L-850 and


Arabian Gulf Hind-cast study to determine the required concrete weight coating
thickness to prevent pipeline movement during storms conditions.

An adequate number of points along each pipeline route should be analyzed to


determine the most severe combination of storm direction, tide and water depth.

Page 8 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Stability analysis for each selected point should be run for one (1) year storm with the
pipeline empty and for (100) year storm with the pipeline full of product.

The design density of the concrete coating for stability analysis should not be less than
3044 kg/m^3 (190 lbs/ft^3). This value dose not includes water absorption.

CONCRETE
PIPELINE COATING
WALL+ CC

9 Preparing Data for Pipeline Free Spans, Crossings & Other Miscellanies
Calculations:

Input data:

The following is an example of the required information that is required to generate data
for further calculations, please note that 3" of concrete is used based on stability
analysis that should be done once the selected wall thickness has been established.

1 Field Name SFNY


2 Field Design Pressure P 750 psi 51.7 bar
3 Field Design Temperature f 150.8 deg F 66.0 deg C
4 Nominal Diameter of Pipe NPD 20 in 508.00 mm
5 Outside Diameter of Pipe D 20.000 in 508.00 mm
6 Pipe Wall Thickness wt 0.625 in 15.88 mm
7 Corrosion Coat Thickness FBE tcc 0.020 in 0.51 mm
8 Corrosion Coat Density FBE ρcc 100.00 lb/ft^3 1.602 g/cm^3
9 Concrete Coat Thickness twc 3.00 in 76.20 mm
10 Density of Concrete Coat ρwc 190.00 lb/ft^3 3.044 g/cm^3
11 Density of Product ρp 24.00 lb/ft^3 0.384 g/cm^3
12 Density of Sea water ρsw 64.50 lb/ft^3 1.033 g/cm^3
13 Density of Steel ρs 0.28356482 lb/in^3 7.8490 g/cm^3
14 Pipeline Length L 17139.1 ft 5224.0 mt

Based on the above data one should be able to calculate the submerged weight of the
pipe with hydrocarbon product or with hydrotest water and the weight of the displaced
sea water. Also this calculation will provide the volumes of Oxygen Scavenger and
bactericide as required by SAES-A-007 sections 5.5.1 and 5.5.2.

Page 9 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Please note that Oxygen scavenger is required whenever water is introduced to the
piping system either for lay-up or hydrotesting. Bactericide is only required if the lay up
period is greater than > 90 days. The PPM (part per million) changes as a function of
time. The Sea Dye is required to be added to hydrotesting water in order to ease
locating any potential subsea leak.

10 Maximum Allowable Free-Spans (Best Practice 4)

Base on the calculated allowable bending stress for the subject pipeline, the freespans
should be calculated for the subject pipeline for two conditions:

1) Max straight free-span during operation.

2) Max curved free-span during operation.

3) Max straight free-span during hydrotesting.

4) Max curved free-span during hydrotesting.

The calculation should also define the Vortex Shedding frequencies envelop for the
straight freespans. Curved pipe will not be subject to Vortex Shedding.

11 Revising Maximum Allowable Free-Spans (Best Practice 5)

The pipeline calculated allowable freespan should be reevaluated due to concentrated


load additions such as, set of flanges or Instrument scrapers load moving through the
pipe span or both.

These additional loads will subject the pipeline at the freespan to bending stresses
beyond the allowable. Therefore to bring the bending stresses within the allowable
limits, the freespans need to be revised; this will result in shortening the allowable free
span.

Sub-sea pipeline Instrument scraper

Page 10 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

12 Pipeline Crossing (Best Practice 6)

Engineering of Submarine pipeline crossings profile will require the following:

touchdown Existing Pipeline

Max. Crossing
Height

1) % of Embedment of Crossed Pipe below seabed at location of crossing or height


of Crossed Pipe above seabed.

2) Diameter of Crossed Pipe.

3) Crossed Pipe Concrete Weight Coating thicknesses.

4) Separation between top of crossed pipe and bottom of new pipe. According to the
standard it should not be less than 12 inches.

5) Maximum Allowable Bending Stress of the new pipe.

6) Maximum Allowable Free spans during operations and hydrotesting.

7) Height of new pipe from Seabed +new pipe (Concrete coating+ OD/2) = height of
neutral axis, all pipeline profile calculation will be done with reference to neutral
axis.

8) Determination of the "Hypothetical Unit Weight": This is not the real unit weight
of the line. It is the unit weight resulting from limiting the bending stress in the
Hypothetical Weight Calculation so that it will not exceed the Maximum
Allowable Bending Stress during operation or hydrotest of the pipeline. This is
used for calculating the profile of the crossing and required support heights.
Hypothetical weight = (min(sb)*Z/1.414213562)^2*(1/ (E*I*h)) -- refer to
Appendix "C" equation # (10) to see the derivation of the subject equation.

9) Calculating of the load reaction at the ridge (Crossing) "Bo". The load reaction
at ridge resulting from the pipeline spanning over a ridge used only for
calculating the profile of the span assuming a single support in middle of span at
which the Maximum Allowable Bending Stress will not be exceeded.
Bo = 3.883934 *[(E*I*w*h)^0.25 (w)^0.5], please refer to Appendix "C" equation
# (5) for the derivation of the subject equation.

Page 11 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

10) "L" Distance from center of crossing (Ridge) to touchdown point of the pipe.
The equation # is (6.6.5 in SAER-5711); please refer to Appendix "C" equation
# (6) for the derivation of the subject equation.

11) Deflection of the pipeline with respect to the reference crossing height can be
calculated by the following equation:

4
1 3 1 1 Bo 3
Y = ( α 2
− α 3
+ α 4
) 3
, where .( 0 ≤ α ≥ ) − − ( 11 )
EI 64 12 24 w 4

for the derivation of the subject equation, please refer to Appendix "C" equation
# (11). Alpha (α) is the deflection variable, its range is from "0" zero which is
the value @ central of the crossing to "3/4" at which the pipeline makes a
touchdown. Equation # (11) will be utilized to calculate the height of the
submarine pipeline from the seabed at any distance from the crossing as a
function of [F (α)].

12) The required height of pipe support can be calculated by subtracting (1/2 of pipe
O D + the thicknesses of the concrete weight coating) from the height of the
neutral axis above the seabed. Please note that, when this value reaches zero
(0.0) this will indicate the concrete weight coating touchdown point.

13) Distance from the support to the center of the crossing of the pipeline with
respect to the reference crossing point can be calculated by the following
equation

Bo 3
from (1 a ), do = α = L , when α =
w 4
For the derivation of the Subject equation; please refer to Appendix "C"
equation # (1 &1a). Alpha (α) is the deflection variable, its range is from "0"
zero which is the value @ central of the crossing to "3/4" at which the pipeline
neutral axis makes a touchdown. Equation # (1a) will be utilized to calculate
the distance from the center of the submarine pipeline crossing to concrete
coating touchdown and/or any supports of any height from the seabed as a
function of (α).

13A Installation Stresses (Best Practice 7)

There are various methods of submarine pipeline installations including the lay-barge,
reel, bottom–pull, tow, and other methods. Some of these methods are more suited for a
particular application than others.

Page 12 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Certain installation method such as reel is particularly suited for small diameter pipe
with no concrete weight coatings; others are particularly suited for big diameter pipe
and deepwater installations.

Generally in the Arabian Gulf area the most common and predominate method for
submarine-pipeline installations is the lay-barge. There are three different types of lay-
barges exist, including conventional box hull, ship-shaped barge, and semi-submersible.

The above conventional box-hull type is used in the Gulf area; the maximum depths to
which conventional lay-barges can operate are governed by:

1) Capacity of the barge mooring system.


2) Stinger size.
3) Tensioner system capacity.
4) Pipe diameter, wall thickness and steel grade.
5) Pipe concrete weight coating.

Traditional marine pipeline design often assumes that the dynamic stresses which occur
during installation will not exceed one third of the static stresses. As the industry
moves into more exacting environments, this assumption become less tenable and
careful analysis of the dynamic stresses becomes essential in order to define the limiting
weather conditions which could result in failure and overloading of a pipeline.

Page 13 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Therefore pipelay dynamic stress analysis shall be done to insure that the submarine
pipeline do not exceed the allowable stress limit during installation. The combined lay
stresses shall not exceed (80%) of the Specified Minimum Yield Strength (SMYS) of
the pipe.

Because stress analysis is a function of the lay-barge's particularities, the dynamic lay
stress analysis should be performed by the Construction/Installation contractor utilizing
sophisticated finite element method based computer programs such as OFFPIPE or
Dynamic Seapipe, that been specifically developed for the modeling and structure
analysis of nonlinear problems encountered in the installation of offshore pipelines.

The pipe string extending from tentioner/s on the lay barge to the seafloor is subject to
dynamic actions due to barge motions and to direct hydrodynamic action on the pipeline
and the lay barge stinger.

In summery there are (6) possible dynamic motions of the pipe Lay-Barge (surge,
heave, sway, roll, yaw and pitch).

HEAVE
ROLL

YAW

SURGE

PITCH

Lay barge Center


of Gravity

SWAY

13B Shear Stresses Between the Concrete and Corrosion Coatings


(Best Practice 7)

One of the important issues during subsea pipe lay is the shear stresses between the
corrosion coating (Fusion Bond Epoxy (FBE)) and the concrete weight coating.

Page 14 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Therefore in order to prevent breaking the bond between the concrete and the pipe
corrosion coatings during installation, the maximum tensioning force that the pipe can
be subject to shall be calculated as a function of; FBE coated section area that has been
covered by the linear tensioner and the maximum allowable shear stresses between the
corrosion and the concrete coatings in kips/ft2 or kN/m2.

Effective length of
linear tensioner “LT”

PIPING TENSIONER

Calculation for a 20 inch pipe with 0.02 inch FBE corrosion coating

Linear Tensioning
Pipe OD + CC = D + 2 * tcc ODC 20.040 in 0.5090 mt
length of Concrete Coated Section L 39.0 ft 11.8872 mt
Area of coated section A = ODC * L* π A 204.612 ft^2 19.01 mt^2
Mean Shear Stress between the Concrete and
Corrosion Coatings (TESTED VALUE) S 1.09 kips/ft^2 52.24 kN/m^2
Max Shear Stress for the Total Pipe Length =A*S 223.24 kip 993.03 kN
Concrete Section Length covered by the linear
pipe tensioner (FUNCTION OF TENSIONER) LT 18.0 ft 5.49 mt
Area of coated section Covered by tentioner AT AT=ODC*LT*π 94.436 ft^2 8.77 mt^2
Max Allowable Applied Shear Stress =S*AT 103.4 kip 458.32 kN

14 Flange Selection (Best Practice 8)

Ring joint weld neck flanges are used for offshore piping system. Selecting the
appropriate flange should be in accordance to ASME/ANSI B-16.5 (PIPE FLANGES
AND FLANGE FITTINGS), SAES-L-109 (Metallic flanges, Gaskets and Bolts for

Page 15 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Low and Intermediate Temperature Service) AND 02-SAMSS-001 (Forged Steel Weld
Neck Flanges for Low and Intermediate Temperature Service).

The following items control the selection:

A) System design pressure and temperature; based on the field design pressure and
temperature the appropriate flange CLASS can be selected using ASME/ANSI B-
16.5 Table-2 (Pressure-temperature ratings). for example to decide the proper
flange for MARJAN offshore oil field that suitable for:

1) 2800 psi design pressure,

2) 150.8ºF operating temperature,

3) 20" inch size X60 pipe with 0.75" wt (assuming that, the pipe design is
already done for the subject pressure and temperature)

From ASME/ANSI B-16.5 Table-2, Class 1500 flange is the one which meet the
above requirements, however there are material group No's that need to be chosen
from. Go to B.

B) Pipe size and pipe material grade; such as grade B, X42, X52, X60, etc; based on
both, pipe size and pipe material grade, flange Material CODE & GROUP can be
selected according to 02-SAMSS-001 Table-1 and/or SAES-L-109 Table-3. Back
to the above example, Class 1500 Flange with 20 inch X60 pipe material grade
will result in Material CODE K and ASME B16.5 Material GROUP 1.7.

C) Based on ASME B16.5 Table-2, Class 1500 flange with Material GROUP 1.7
and 150.8ºF operating temperature will give a pressure rating of 3750 psi; this is
the maximum operating pressure for the giving temperature.

D) The Hydrotest pressure for the subject flange can be calculated by multiplying the
operating pressure at ambient temperature time 1.5, for the case in hand the
operating pressure at ambient temperature as per ASME B16.5 Table-2 is also
3750 psi, this will result 3750*1.5 = 5625 psi Hydrotest pressure.

E) Please note that if the calculated Hydrotest pressure for example came to be 5557
then this should be round up to the next 25 i.e. it will be 5575 and so on.

15 Pipeline Scraping and Hydrotesting

All submarine pipelines with associated corridor and tie-ins spools shall be cleaned and
gauged with scraper after installations. This to assure that they are free of debris and
pipe buckles. The scraper shall be selected to be able to negotiate the 3d bends.
Gauging plats should have a diameter ½ inch less than the minimum inside diameter
along the pipeline system taking manufacturing tolerances into consideration. One

Page 16 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

should refer to the appropriate pipe, flange and fitting standards to determine the
allowable manufacturing tolerances for wall thickness and diameter. For cleaning and
gauging temporary launchers and receivers shall be provided for each pipeline size.

If the gauging plate shows the existence of any obstruction or pipeline damage, the
obstruction or damage shall be located and repaired as necessary. A scraper with a
gauging plate shall be passed through the pipeline again after the repair has been
completed. This sequence shall be repeated until the scraper passes through the
pipeline with the gauging plate undamaged.

During the pipeline scraping/gauging operation the line will be filled with water
containing dye and oxygen scavenger. Bactericide shall be added where specifically
required for pipe lay-up. The concentrations of these additives shall be in accordance
with SAES-A-007.

For Hydrotesting pressure please refer to section five (5) for Hydrotesting and hoop
stress calculations, the strength test pressure shall be maintained for two hours in
compliance with SAES-A-004. Also baseline instrument scraping is also required.

Revision Summary
19 May 2007 New Saudi Aramco Best Practice.

Page 17 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Appendix-A

Hoop & Longitudinal Stresses Formulas:

Hoop Stresses:

π/2

Steel Edge
Area1 = t * L

Steel Edge
Area 2 = t * L

-π/2

The ratio of pipe wall thickness to the radius t/r is < 1/10, therefore if the
circumferential strain is uniform, an analysis of the above free body diagram will show
the relationship between applied pressure and circumferential stress.

σc= Circumferential Stress (σH Hoop Stress) due to internal pressure.


The integration from (-π/2) to (π/2) of; the internal gage pressure P, multiplied by (*)
the arc length (r dθ) * L * Cos θ , will result in the Σ of the perpendicular vector
components of the pressure in the pipe with respect to Areas 1 & 2 plan.
The force on # 1& 2 steel edges due to hoop strain = 2 * σc* t *L

The integration of (Cos) is (Sin)

Page 18 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

The integration of [(P L r d θ) Cos θ] from (-π/2) to (π/2) will result in


P L r * (Sin (π/2) - Sin (-π/2)) = P L r * {(1) - (-1)} = 2 P L r

Thus, Σ F = 0

Therefore, 2 P L r - 2 * σc* t *L = 0 2 P L r = 2 * σc* t *L

σc = 2 P L r /2 * t *L σH = σc = P * D /2 * t (1)

Longitudinal Stresses

In Closed end system and contain a fluid under a pressure P, the wall of the Vessel will
have longitudinal stress as well as circumferential stress.

Inside Pipe
Area =
((π/4)*D2)

P = Inside pipe Pressure


t = pipe wall thickness
D average approximately = D internal when t is very small when comparison with D internal

Pipe average Circumference = π D average


Pipe Cross Section Steel Area = π D average * t
And σL= Longitudinal Stress due to internal pressure.

Σ Forces = 0

Page 19 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Thus, P * ((π/4)*D2) = σL* π D average * t

Since D average approximately = D internal when t is very small when comparison with D
internal.

σL= P * ((π/4)*D2) / (π*D*t) P *D / (4*t) (2)


From (1) & (2) it can be seen that:
Longitudinal Stress = 0.5 Hoop Stress
σL= P *D / (4*t) = 0.5 σH = 0.5 P * D /2 * t

Page 20 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Appendix B

Restrained pipelines – Operating Case:

Per ASME B-31.4, Para.402.3.2 (C) & 419.6.4(B),

SA = 0.9 SMYS >= SH+SL


SH= Hoop Stress (tension)
SL= Longitudinal Compressive Stress

Restrained Condition
Compression Tension Compression Tension
Thermal Stress Bending Stress Residual Stress
SL = E * α * ΔT – ν * SH + SB – SAX

Where
E = Modulus of Elasticity of Steel psi (MPa)
α = Thermal Coefficient of Expansion in. /in. /F (mm/mm/C)
ΔT = T2–T1 (Operating Temp. – Surrounding SEA Temp.) °F / °C
ν = Poisson's Ratio = 0.3 for steel
SB = Allowable bending Stress psi (MPa).
SAX = Residual axial Stress Due to Pipe lay tension psi (MPa).
This formula is for an element at the top of the pipeline

0.9 SMYS >= SH + E * α * ΔT – ν * SH + SB – SAX

Therefore:

SB <= 0.9 SMYS – SH – E * α * (T2–T1) + 0.3 * SH + SAX


SB <= 0.9 SMYS – 0.7 SH – E * α * (T2–T1) + SAX

It can be seen from the equation, that Axial Tension due to the lay tension SAX increases
the allowable bending stress.

SAX is unknown, for conservative approach it can be consider to be = 0.0


SB <= 0.9 SMYS – 0.7 SH – E * α * (T2–T1) + 0.0

Un-Restrained pipelines – Operating Case:

Per ASME B-31.4, Para.402.3.2 (D) & 419.6.4(C)

The allowable stress range is SA= 0.72 SMYS, also the sum of the longitudinal stresses
due to pressure SL, and other sustain external loadings SB shall not exceed 0.75 SA .

Page 21 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

i.e. 0.75 SA >= SL+ SB

0.75 SA = 0.72 SMYS * 0.75 = 0.54 SMYS


SL = PD/ (4 * wt) = SH /2 = 0.5* SH

Therefore 0.54 SMYS >= 0.5* SH+ SB

And SB <= 0.54 SMYS - 0.5* SH

Restrained pipelines – Hydrotesting Case:


SAX is unknown, for conservative approach it can be consider to be = 0.0
During hydrotest T2=T1 and E * α * (T2–T1) = 0.0
SB <= SMYS – 0.7 SH – 0.0 + 0.0

Un-Restrained pipelines – Hydrotesting Case:

SMYS >= SH - SL + SB
SMYS >= SH - 0.5* SH + SB
And SB <= SMYS - 0.5* SH

Page 22 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Appendix-C
Crossing
Sub-Sea Pipeline
Bo/2 reaction at Moment at crossing profile
ridge ridge = Mo
Deflection at X

x
δ
y
y

SEABED

do
Y = Distance from Touchdown
Seabed to Pipe do = distance from
Crossing to Point
Centerline
Touchdown Point

Assumptions:

1) The deflection angle of the pipe is small


2) The Bottom (SEABED) is flat

From differential equation of the Elastic Curve REA (Research & Educational
Association) page 573.

E.I.Y"= M = E.I/R

Where

Y"= 1/R, where R= the radius of curvature, Y"=d2y/dx2

Stress ⋅ Per ⋅ Unit ⋅ Area


E = Modulus of Elasticity =
Deformatio n ⋅ Per ⋅ Unit ⋅ Length
I = Moment of Inertia.
M = Bending Moment, which is causing the deformation.

Page 23 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

E.I = Stiffness (rigidity) of the pipe.


w = Submerged unit weight.

For the pipeline going over a ridge in the above diagram the following equation apply:

Bo 1
E . I .Y ' ' = Mo − x + wx 2

2 2

At x = 0 and x = do,

Bo 1
E . I .Y ' ' = M = Mo − . do + . w . do 2
= 0 ......( 1 )
2 2

Solving Equation # (1)

3 .Bo
do = − − − − (1a ),
4 .w
3 ⋅ Bo 2
Mo = − − − (1b ).and .
32 ⋅ w
4
Bo = .do .w − − − (1c )
3

By integrating EIY'', will get Y' which is the slope of the pipe curvature:

Βο 1
∫ ( )dx
x 2
Ε* Ι* Y' = Μο − x + w x
0 2 2
Bo 1
E* I* Y' = Mox x 2 + −
wx 3 + C − − − ( 2 )
4 6
→ Y ' = 0 & C = 0 . at . x = 0 , and . at , x = do = L

Page 24 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Also, by integrating E.I.Y' will get Y which is the deflection of the pipe.

⎛ x Bo 2 1 ⎞
E . I .Y =∫0 ⎜⎝ Mo . x −
4
. x + w . x 3 ⎟dx
6 ⎠
Mo 2 Bo 3 1
E . I .Y = x − x + w.x 4 + C 1 − − − (3)
2 12 24
Y = 0 @ .x = 0 → C1 = 0

Substitute with (1a) and (1b) into (3) above.

3 Bo 3 Bo 2
do = , and . Mo =
4 w 4 w
27 Bo 4 27 Bo 4 81 Bo 4
EIY = − +
1024 w 3 768 w 3 6144 w 3
6 * 27 − 8 * 27 + 81 Bo 4 27 Bo 4
= =
6144 w 3 6144 w 3
27 Bo 4 1
∴ deflection = Y = − − − − (4)
6144 w 3 EI

From (4) above one can get

6144 6144
(Bo )4 = EIw 3Y → Bo = 4 4
EIw 3Y
27 27
Bo = 3 . 883934 .4 EIw 3Y − − − − − − − − − − ( 5 )
3 Bo 3 4
EIw 3Y
from (1a ), do = L = = * 3 . 883934 *
4 w 4 w
EIY 3 6144 4 EIY
L = 2 . 9129506 .4 = *4 * − − − (6)
w 4 27 w

Page 25 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

Formula # (6) is the free span length that has been used in SAER-5711

From equation (1)

3 Bo 4
do = , let → L = do , ∴ Bo = Lw − − − − (7 )
4 w 3

Substitute with (7) above into (1b)

3 ⋅ Bo 2
Mo = − − − (1 b ).
32 ⋅ w
3 16 2 2 wL 2
Mo = * L w = − − − (8 )
32 * w 9 6

Formula # (8) is the maximum bending moment that has been used in SAER-5711

2I
Elastic . Section . Modulus .Z =
D
M wL 2
Stress = = − − − − − − (9 )
Z 6 .Z
From equation (6) substitute for L in (9) one can obtain the maximum bending stress σb.

M w (2.9129506) 2 EIY 1.414265


σb = = = EIwY − −(10)
2
Z Z 6 w Z
Formula # (10) is the maximum bending stress that has been used in SAER-5711.

In order to determine the deflection of the submarine pipeline as a function of the


touchdown point at a distance L from the crossing point and as a function of α the
deflection variable.

Page 26 of 27
Document Responsibility: Piping SABP-L-002
Issue Date: 19 May 2007
Next Planned Update: TBD Design of Submarine Pipelines

The maximum for do is L.

Bo 3
from ( 1 a ), do = α = L , when α =
w 4

3
Let α = deflection variable where (0 ≤ α ≥ )
4
Substitute the value of do from (1a) and the value of Mo from (1b) into Equation (3)

1 1 1
EIY = Mo.do 2 − Bo.do 3 + w.do 4 − − − − − −(3)
2 12 24
1 3 Bo 2 2 Bo
2
1 3 Bo
3
1 4 Bo
4
EIY = * *α − * Bo *α + w *α
2 32 w w2 12 w3 24 w4
1 3 2 1 3 1 4 Bo 4 3
Y= ( α − α + α ) 3 , where.(0 ≤ α ≥ ) − −(11)
EI 64 12 24 w 4
Equation (11) will be utilized to determine the height of the submarine pipeline from the
SEABED at any distance from the crossing.

Page 27 of 27

You might also like