Pipeline Tie-In
Constructability Review Report
Lead
Sr. Project Facilities
Prepared Checked Approved Unit Owner
Engineer Modification
Reason for
Rev Status Issue Date Projects
Issue
Printed initials in the approval boxes confirm that the document has been signed.
The originals are held within Document Management.
Constructability Review Report ID-N-CG-YY4-PRT-PL-25-0001_Rev.1
EPC Grissik – Pertagas Ultrasonic Custody metering And
Pipeline Tie-In
ConocoPhillips (Grissik) Ltd. Page 2 of 16
Revision Sheet
ConocoPhillips (Grissik) Ltd.
Table of Content
1. INTRODUCTION............................................................................................................................ 4
2. PROJECT DESCRIPTION............................................................................................................. 4
2.1 Summary Scope of Works....................................................................................................... 4
2.2 Shutdown Scope of Works...................................................................................................... 7
3. HIGH LEVEL STRATEGY.............................................................................................................. 7
3.1 Provision of Shutdown Tie-in................................................................................................... 7
3.2 Pre-fabrication and Pre-cast Works......................................................................................... 8
4. WORKING SEQUENCE................................................................................................................. 8
4.1 Site Works Activity Before Shutdown......................................................................................8
4.2 Site Works Activity During Shutdown......................................Error! Bookmark not defined.
4.3 Site Works Activity After Shutdown......................................................................................... 9
4.4 Pre-Commissioning................................................................................................................. 9
4.5 Commissioning and Start-up................................................................................................. 99
5. CRITICAL ACTIVITY...................................................................................................................... 9
5.1 Critical Lifting of Shutdown Manual Ball Valve.........................................................................9
5.2 Critical Lifting of Fabricated Spool Header (for PERTAGAS).Error! Bookmark not defined.3
6. CONSTRUCTIBILITY REVIEW SUMMARY..............................................................................155
6.1 Input Register and Path Forward......................................................................................... 155
6.2 Operation Supports Required.............................................................................................. 155
Constructability Review Report ID-N-CG-YY4-PRT-PL-25-0001_Rev.1
EPC Grissik – Pertagas Ultrasonic Custody metering And
Pipeline Tie-In
ConocoPhillips (Grissik) Ltd. Page 4 of 16
1. INTRODUCTION
The existing Grissik-Duri USM(s) Metering QSonic Series Ill are used to measure loading
gas for PT. Chevron Gas Indonesia (CPI) and gas sales to PT PGN ARGSPA and PT
ENERGASINDO has been in service since 2002.
Elster-lnstromet as an existing ultrasonic meter Supplier has announced the obsolescence
of the existing Q-Sonic Series Ill in 2008. The spare part and its support were no longer
provided. The latest series of Elster-lnstromet QSonic has been release. The migration to
the latest series of QSonic will allow maintaining the unit in the field for the next minimum 10
years.
ConocoPhillips (Grissik) Ltd. conducted the obsolescence study of the Grissik DURI USM(s)
meter and the results shows that the potential risk of USM reliability will reach high risk level
in 2018¬2019.
According to Regulation of Republic Indonesia's Minister of Trade, No. 70/M-
DAG/PER/10/2014 that governs the period of "Wet Calibration" for Ultrasonic Gas Flow
meter every 5 years. The existing USM has been wet calibrated during project phase
installation/construction in 2002.
* This Documents is refer to “Construction Execution Plan” Rev.B
2. PROJECT DESCRIPTION
2.1 Summary Scope of Works
Grissik DURI USM(s) Upgrade Project consist of procurement and installation of metering
isolation valves and USM metering package with detail as follows:
A. 5 Units Isolation valves replacement (Total Shutdown Corridor Block)
• Site personal mobilization, site transportation, PTW, etc.
• Preparation work before shutdown date.
• Dismantle and reinstall existing shelter/ roof, bridge, etc.
• Dismantle existing limit switch and existing valves
• Replacement existing isolation valves with new isolation valves
• Tightening, QA/QC inspection, flange management, etc.
• Function testing, SAT, and start up.
B. Engineering. procurement. fabrication and assembly of 2 unit new USM(s)metering
• Engineering, procurement, fabrication and assembly of 2 unit new USM(s) metering.
• Dry calibration at the USM manufacturer and transportation to the international
recognized calibration facilities for Wet Calibration
• Procurement and fabrication of 2 unit flow conditioners.
• Procurement all the piping material (pipe, flanges, fittings, gaskets, stud and bolts,
washer, etc.)
• Engineering, Fabrication and honing of the upstream / downstream spool in
Indonesia fabricator including hydrotest witnessed by MIGAS.
• Temporary Export, custom clearance of the calibration spool to the International
recognized calibration facilities for Wet Calibration Meter.
Constructability Review Report ID-N-CG-YY4-PRT-PL-25-0001_Rev.1
EPC Grissik – Pertagas Ultrasonic Custody metering And
Pipeline Tie-In
ConocoPhillips (Grissik) Ltd. Page 5 of 16
• Conducted dry and wet calibration of 2 (two) unit new ultrasonic meter package at
internationally recognized calibration facilities.
• Proper packaging and preservation during transportation
• Deliver the 2 unit USM(s) metering completed with spools from the recognize
calibration facilities country origin to Indonesia (Grissik warehouse)
• As-built project documentation.
• Re-instatement of the shelter, structural, piping, civil, de-mobilization and closing
• Dry calibration at the USM manufacturer and transportation to the international
recognized calibration facilities for Wet Calibration
Preservation of the USM(s) Metering in Grissik warehouse after Wet Calibration.
Constructability Review Report ID-N-CG-YY4-PRT-PL-25-0001_Rev.1
EPC Grissik – Pertagas Ultrasonic Custody metering And
Pipeline Tie-In
ConocoPhillips (Grissik) Ltd. Page 6 of 16
The schematic drawing for USM Duri Upgrade Project is as below, as for early PFD and PID
drawing can be seen in Attachment 2 – Early PFD and PID Drawing Layout.
Also to replace the Pertagas Header 30” with new fabricated spool header to accomodate
future tie-in for Pertagas line.
The shutdown tie-in provision itself need to be performed in total shutdown window since it
is tied-in to existing facility. The shutdown is confirmed will be executed on 10 December
2017.
4. WORKING SEQUENCE
4.1 Site Work Activity Before Shutdown
USM DURI
• Roof dismantling including lighting for Duri USM shelter
• Grating Removal for Duri USM skid
• Laying and test new cable for limit switch positioner from valves to JB
• Equipment and Tools Mobilization (crane, compressor, etc.)
• Install temporary facility (Shelter, warehouse, Portable toilets)
• Repair access way for heavy equipment
• Material (valves, gasket, stud bolt & nut) setting for shutdown position
• Access bridge removal from metering skid and modification
PERTAGAS HEADER
• Roof dismantling including lighting for SSWJ USM shelter
• Grating Removal for SSWJ USM skid
• Ground Scanning Area Pertagas Header Foundation
• Demolish conblock, excavation and backfill for installing Pertagas
• Header new foundation and pipe support (pre-cast at PPS Workshop)
• Material (valves, gasket, stud bolt & nut) setting for shutdown position
• Assembling pertagas header (spool & valves)
• Assembling internal panel wiring (mapping) c/w wire tagging
• Download, programming, function and integration test DCS/SIS and HMI
• Marking hole for gland plate (E/I) at raised floor, CCR and PCR 1
4.2 Site Works Activity During Shutdown
USM DURI
• Dismantling and replace 5 Unit of Ball Valves 20”- 600#
• Dismantling and install 2”-600# venting spools
• Re-configure 1”-600# equalizing spools
Constructability Review Report ID-N-CG-YY4-PRT-PL-25-0001_Rev.1
EPC Grissik – Pertagas Ultrasonic Custody metering And
Pipeline Tie-In
ConocoPhillips (Grissik) Ltd. Page 9 of 16
• Dismantling, replace and termination cable connection for valve limit switch
positioner
• Assessment USM Duri power junction box (Exd junction box)
PERTAGAS HEADER
• Dismantling and replace 30” header for SSWJ metering
• Dismantling and replace 2” flare line
• Dismantling and replace 2”-150# end flange for instrument air header
• Modification & Upload DCS SIS and HMI at CCR building
• E/I panel holing at PCR and CCR (on gland plate)
4.4 Pre-Commissioning
Closing punch list A
Loop test for instrument
Communication test between USM, Flowcom and DCS
Energize for electrical
N2 leak test and purging for piping
Flange management works
5. CRITICAL ACTIVITY
5.1 Critical Lifting of Shutdown of Manual Ball Valves
Shutdown Tie-in provision is considered as critical activity because of its lifting configuration.
From preliminary lifting plan lifting study, it was discovered that the lifting will need lifting
radius approximately 30 meter with lifting load of 3.4 ton. It is also classified as complex
lifting due to its location in existing facility.
Weight of 4.4 ton is rounded calculated value of the manual valves, and lifting accessories .
Combined with safety factor of SWL crane, it is early defined that the crane require to be
minimum at 160 ton capacity.