Professional Documents
Culture Documents
Dewatering
Sutitleubtitl
& Drying Contract 783830
Baker Hughes
IP Security Company Confidential Total number of Pages (including Cover sheet): 211
Contractor
For Contract No Contractor Document No Rev.
Contractor
Documents C783830 C-0141-13-PCD-066 2
CONTENT
HOLD SUMMARY
1.0 INTRODUCTION
The Wheatstone development comprises the Wheatstone and Iago offshore gas fields.
Production from these fields will be from subsea wells and manifolds, transported through
insulated Production Flowlines to the Wheatstone Platform (WP), where the gas and
condensate will be dehydrated and dewatered before being transported to the onshore
Wheatstone Liquefied Natural Gas Plant (WLNGP) via a 44″ Trunkline. The WLNGP is
located at Ashburton, south of Onslow, on Western Australia’s Pilbarga coast.
Chevron Australia Pty. Ltd. (COMPANY) has awarded Baker Hughes Australia Pty. Ltd.
(CONTRACTOR) to perform Dewatering, Drying and Inerting operations on the Trunkline
and Infield Flowlines
2.0 GENERAL
2.1 Description
On successful completion of hydrotest operations, the 44” Trunkline shall be bulk de-watered,
conditioned and prepared for the introduction of hydrocarbons. The 44” Trunkline shall be
dewatered utilising a specifically designed pig train shown below.
Trunkline Dewatering Pig Train
5 4 3 2 1
The pig train shall be designed to bulk dewater and remove residual water to a level
sufficient to commence drying operations. The internal surface of the 44” trunkline
shall be desalinated by pushing treated fresh water slugs through the 44” trunkline.
The pigs will be loaded and launched one at a time into the 44” pig launcher at the
onshore site in Onslow and propelled with dry air to the Wheatstone Platform.
On completion of the dewatering operation, air at -60 °C dew point will be blown through
the 44” trunkline until three consecutive readings of -40 °C or better have been taken. At
this point the blowing will cease and a 24 hour soak test will commence. On completion
of the 24 hour soak test, readings of the dew point will be taken to confirm the dryness
of the pipeline. The acceptance criteria of the Trunkline is -40 °C dew point or better.
Once the 44” trunkline has been dried to an acceptable level nitrogen will be injection
into the trunkline at 97% nitrogen 3% air until an nitrogen reading of 97% has been
achieved offshore. At this point the 44” trunkline will be isolated and packed with
nitrogen to 0.5barg.
The purpose of this document is to provide all personnel with a clear understanding of the
work scope individual steps, precautions and sign offs to ensure work is completed in a safe,
efficient and timely manner. Furthermore, it is designed to be an all-inclusive source of
information regarding the activities associated with the 44” Trunkline dewatering, drying and
purging activities.
This document contains the procedures to be followed for dewatering, drying and Nitrogen
purging operations as well as CONTRACTOR equipment diagrams and other relevant
information pertaining to the COMPANY - Wheatstone 44” trunkline dewatering, drying and
inerting at the Wheatstone site in Onslow.
This document is also the procedure to be used to execute the Dewatering, Drying and
Inerting operations of the offshore Wheatstone Trunkline from the Onslow site to the
Wheatstone platform.
2.4 Definitions
Definition Description
2.5 Abbreviations
Abbreviations Definition
Abbreviations Definition
ID Inside Diameter
ITP Inspection and Test Plan
IIF Incident and Injury Free
JHA Job Hazard Assessment
km Kilometre
KP Kilometre Point
LAT Lowest Astronomical Tide
LNG Liquefied Natural Gas
MEM Membrane
MOC Management of Change
MOV Motor Operated Valve
OD Outside Diameter
PDS Project Document Schedule
PHA Preliminary Hazard Analysis
PIC Person in Charge
PPE Personal Protective Equipment
PPS Process and Pipeline Services
PTW Permit to Work
QA Quality Assurance
QC Quality control
QHSE Quality, Health Safety and Environment
ROV Remote Operated Vehicle
SIMOPS Simultaneous Operations
SOP Safe Operating Procedure
SSIV Subsea Safety Valve
u/s Up Stream
WA Western Australia
WLNGP Wheatstone Liquefied Natural Gas Plant
WP Wheatstone Platform
XV Actuated control valve
3.0 REFERENCES
3.1 General
The latest revision of the listed COMPANY or CONTRACTOR documents shall be used in
conjunction with this procedure.
The agreed revisions of the listed codes and standards shall be used for the execution of the
Work.
3.4 Drawings
WS2-1250-PRO-PID-DME-000-00124-000
Export Trunkline Pig Launcher
Rev 5
During execution of the Work, all worksite internal/external communications will be done as
per the requirements of Figure 4.1.
As shown in below, CONTRACTOR Lead Engineers or his delegate will handle all external
communications with COMPANY Representative at WLNGP.
COMPANY COMPANY
Representative Representative
Project Manager
Supervisor Supervisor
Day Shift Night Shift Supervisor
Supervisor
X2 X2
Operator Operator
X2 X2
Operator Mechanical Tech Mechanical Tech Operator
X8 X2 X2 X8
4.1 Resources
4.1.1 Personnel
Table 4-2 outlines CONTRACTOR manning requirements for the 44" Trunkline dewatering
and drying operations.
WLNGP WP
Designation
Days Nights Days Nights Total
Site Manager 1 - - - 1
Engineer [1] 1 1 1 - 3
Supervisor 2 2 1 1 6
Operator 8 8 2 2 20
Mechanical Technician 2 2 - - 4
HES Specialist 1 1 - - 1
Total 15 14 4 3 35
Note:
1. Engineers will be trained to cover the Site Manager role for the night shifts and on the WP.
4.1.2 Equipment
Table 4-3 outlines CONTRACTOR’s major equipment required at WLNG to execute the
Work and is in compliance with COMPANY requirements outlined in the Dewatering, Drying
and Nitrogen Purging Specification (CS), WS2-3329-PPL-SPC-ITS- 000-00002-000.
For further information and details on the proposed equipment, refer to the Onshore
Dewatering Spread Mobilisation/Demob Plan, WS2-3000-SAL-PLN-BHA-000-00001-000.
When creating the proposed equipment list in table 4-3 and table 4-4 we have incorporated
contingency equipment on critical equipment. Service items and running spares for this
equipment will be captured in the Load out list.
16. Diesel Fuel Tanks c/w Diesel 100 m³ 3.5 x 14.4 x 4.2 20,000 2
Transfer Pump
Dimension
Item Description Specification (L x W x H) Weight Qty.
No. (kg)
(m)
20. Potable Water Tanks 790 m3 13.0 x 13.0 x 6.1 - 2
21. Water Storage Tank 20m3 5.18 x 2.4 x 2.38 4500 1
22. Silencer 20,000 cfm TBC TBC 1
23. 40′ Office 12.0 x 2.5 x 3.0 8,000 1
24. 40′ Messing 12.0 x 2.5 x 3.0 8,000 1
Dimension
Item Description Specification (L x W x H) Weight Qty.
No. (kg)
(m)
Control cabin c/w WP Based 6.1 x 2.4 x 2.4 4,000 1
1.
dewatering instrumentation
Pig removal equipment c/w - - - 1
2.
with tray
3. Digital pressure gauge - - - 2
Dimension
Item Description Specification (L x W x H) Weight Qty.
No. (kg)
(m)
5. Non-intrusive ultrasonic flow - - - 2
meter
6. Dew point probe c/w readout - - - 2
7. Oxygen probe c/w readout - - - 2
8. Ultrasonic Flowmeter 30 m3/min - - 2
9. Silencer 20,000 cfm TBC TBC 1
10. Pig Loading Tray 4.42 x 1.12 x 0.84 0.703 1
4.2 Chemicals
CONTRACTOR will treat all potable water used for desalination purposes with a combined
biocide and oxygen scavenger. The treatment regime shall provide protection for a period of
18 months.
The chemicals will be injected using an automated chemical injection pump into the fill pump
discharge line during the potable water pumping operation. The automated chemical
injection pump will take an electrical signal from the fill pumps flowmeter which will alter the
chemical injection pump rate, which in turn will alter the chemical injected into the discharge
line. This will ensure the chemicals are injected into the trunkline at the correct concentration.
All chemicals shall have gone through the ChemAlert system and the chemical proposed will
go through a Chemical Hazard Assessment and Risk Management. The following is
summary of the treatment chemicals proposed shows the approximate required volume.
Table 4-5: 44" Trunkline Dewatering and Drying Approximate Chemical Requirements
Total L 300
4.3 Mobilisation
Prior to mobilising the equipment to site it shall first be rigged up at the CONTRACTOR’s
facility in Perth. The function test will cover the suitability and functionality of the proposed
equipment, this detail is covered in the Trunkline Dewatering Equipment Pre-mobilisation
Inspection & Function Test, WS2-3000-PPL-PCD-BHA-000-00020-000. Upon COMPANY
acceptance of the function test the CONTRACTOR will quarantine the equipment until
mobilisation to WLNGP and the Wheatstone Platform
Prior to the commencement of the dewatering operations, the CONTRACTOR will have a
fully functional temporary site complete with offices, messing facilities and toilets. The site
preparation is covered under the Site Installation and Construction Procedure WS2-3000-
CNS-PCD-BHA-000-00001-000
The Project Manager based in in Welshpool, WA is responsible for all operational and fiscal
aspects of the Project and is empowered to make Project related decisions on behalf of
CONTRACTOR.
Other responsibilities include:
Overall responsibility for all contract administration and project management;
Ensuring all health, safety, quality and environmental systems are implemented and
adhered to;
Report to COMPANY as per Contract requirements;
Coordinate all personnel movements to and from site;
Coordinate all equipment movements to and from;
Act as Emergency director in the event of any incidents;
Maintaining adequate control of sub-contractors/suppliers, including establishment of
an appropriate audit/surveillance plan (if applicable);
Acting as the nominated contact for COMPANY documentation and all other
correspondence relating to the project;
Endorse and encourage IIF commitment and values to all CONTRACTOR personnel
involved with the scope of work;
Attending all meetings scheduled to discuss contractual or other matters pertaining to
the scope of work; and
Compliance with Work sites specific requirements set by other Contractors, such as
crane operators, diesel deliveries etc.;
Make sure the Work meets the requirements of this document.
Actively contribute to the IIF culture within the teams
5.5 Supervisors
6.1 General
Verify that the permits are in place if required and signed/understood by all relevant
parties;
Check equipment for damage, suitability and calibration;
Good housekeeping and avoid unnecessary slip, trip & fall hazards;
Personnel are competent to use equipment prior to use;
Step back 5x5 prior to starting a task or when any changes to procedure are
encountered;
Complete pre-job meetings, toolbox talks and Job Hazard Analysis (JHA) prior to
starting tasks;
Shift handover talks are practiced and effective;
Make yourself familiar with the work site prior to starting, including escape routes;
Wear appropriate PPE;
Familiarise the work crew with the MSDS data sheets prior to starting the task,
consider environmental impact if spilled and ensure the correct spill / firefighting and
medical aids are available and relevant to the risks on the MSDS;
Pay attention to HSE noticeboards;
Use Stop Work Authority to stop unsafe job;
Incorporate the IIF culture within the workforce
For all Health, Safety and Environment (HSE) matters and references, please refer to the
CONTRACTOR documents:
6.2 Emergencies
In order to eliminate or mitigate possible consequence(s) of the risks associated with the
CONTRACTOR SOW, the requirements of the CONTRACTOR Risk Management Plan,
WS2-3000-RSK-PLN-BHA-000-00001-000 will be implemented during execution of the
Work.
During the Dewatering, and Conditioning operations, documentation and logs will be
generated to verify the compilation of activities as detailed within this procedure. The
following documentation is required as a minimum and will be compiled to form the
Dewatering, Conditioning and Inerting MDR, WS2-3329-TEC-TOC-BHA-000-00002-000.
Any change to the requirements of this procedure shall be conducted in accordance with the
requirements of the CONTRACTOR Management of Change process, explained in the
Project Quality Management Plan, WS2-3000-QAC-PLN-BHA-000-00001-000.
The 44" Trunkline will be handed over to CONTRACTOR, filled with filtered, chemically
treated and dyed seawater, and left in a full condition at ambient pressure.
As shown in Figure 8.1, the Trunkline shall be dewatered by propelling a five (5) pig train
from the onshore (WLNGP) permanent pig launcher to the (WP) permanent pig receiver with
compressed dry air to a dew point of -60 °C °C.
5 4 3 2 1
• Pig No.1, Bi-di pig c/w with magnets and acoustic transmitter
• 150 m3 of filtered, chemically treated potable water slug
• Pig No.2, Bi-di pig c/w with magnets
• 150 m3 of filtered, chemically treated potable water.
• Pig No.3, Bi-di pig c/w with magnets and acoustic transmitter
• 150 m3 of filtered, chemically treated potable water.
• Pig No.4, Bi-di pig c/w magnets
• 5,000 linear meters of compressed dry air
• Pig No.5, Bi-di pig c/w magnets and EM transmitter
• Volume of compressed dry air
Upon successful completion of the final function and leak tests and obtaining COMPANY
confirmation, the dewatering operation will commence by launching the first, second and
third pigs with 150m3 of filtered and treated potable water. The fourth pig will be launched
with 5000 linear meter slug in order to allow sufficient time for any bypass water to pool and
subsequently be swept by the fifth pig. The fifth pig will then be launched and propelled
using compressed air dried to a dew point of -60 °C.
There shall be one 5,000 linear meter dry air slugs to allow sufficient time for any bypass
water to pool and subsequently be swept by the next pig. This will assist the subsequent
drying operations by removing as much free water as possible.
In addition to the above criteria the pig train design has also been based on allowing
sufficient spacing between pigs to allow for only one pig at a time to be travelling up through
the riser.
Throughout dewatering operation the following parameters shall be monitored, and recorded
at 30 minute intervals:
Launch and receipt of individual pigs;
Volume of potable water slug including pipeline length;
Volume of compressed air slug in terms of linear meters;
Volume of discharged seawater;
Volume of chemicals injected and stage ppms (15 min);
Total volume of compressed air injected;
Estimated pig location;
Pigging pressure;
Dew point of air (injected and discharged during depressurisation);
Back pressure; and
Samples of each potable water slug during discharge will be taken by BHA and
handed over for future analysis by COMPANY (Acceptance ≤ 200mg of chloride per
kilogram of water).
Depending on the time that is taken to load the pigs the decision will be made whether the
compressors will be shut down during this time.
During the dewatering operational phase, once the pigs reach KP 208.3, the Offshore
personnel will notify onshore personnel and the compressors will be shut down. The location
will be calculated by the flowmeter reading of the water discharged from pipeline offshore.
KP 208.3 has been chosen as it is the deepest part of the pipeline, meaning the pressure in
front of the train will on decrease from this point onwards and the existing pressure behind
the train shall be sufficient enough to drive the pigs home.
Offshore personnel shall monitor the pipeline discharge flow / pressure to determine the pig
locations, speed and estimated arrival times. Sharp spikes in pressure along with positive
indication from tracking equipment shall confirm the receipt of the pigs.
Upon the receipt of the full train and confirmation that they have fully entered the offshore
receiver, the pipeline shall then be isolated and the pigs removed and inspected for wear
and tear. Any gauge plate(s) installed shall be photographed and inspected for damage.
On acceptance of the dewatering operation by COMPANY, the pipeline shall be
depressurised to ambient pressure via the dewatering discharge piping on the WP. At the
expected final pipeline pressure of a max of 19 barg, it is expected that depressurisation will
take circa 12 hours.
8.2 Drying
Upon completion of bulk dewatering and depressurisation of the line, the compressor spread
shall be reconfigured to deliver air with a dew point of -60 °C to commence drying operation.
Dry air will be injected into the pipeline at a -60 °C dew point with the expectation that the
dew point will degrade to achieve a dryness acceptance of -40 °C dew point or better.
Throughout the Drying operation, the following parameters shall be monitored, and recorded
at 30 minute intervals:
• Volume of dry air injected;
• Dew point of injected air;
• Pipeline pressure;
• Dew Point of discharged air at WP.
Drying operations is expected to take 13 days.
Once there are three (3) consecutive readings recorded of a dew point at -40 °C or better
and on confirmation from COMPANY, the compressed air spread shall stop and the system
shut-in for a 24 hour soak test.
On completion of the 24 hour soak test, the dew point of the pipeline shall be taken from the
WP end of the pipeline. If the dew point is worse than the acceptance criteria of -40 °C the
drying process shall be repeated until the pipeline is dried to the acceptable dew point and
the soak test repeated.
8.3 Inerting
Upon completion of the drying of the trunkline, the compressor spread shall be re-engaged,
the dry air will be routed through the membranes to deliver nitrogen at a purity of 97%
nitrogen 3% air mix to purge the trunkline of air.
Throughout the purging operation, the following parameters shall be monitored, and
recorded at 30 minute intervals:
• Volume of nitrogen injected;
• Purity of injected and discharged air; and
• Pipeline pressure.
Once the acceptable purity offshore has been witnessed by COMPANY the platform valves
will then be closed and the pipeline will be pressurised to 0.5 barg with 97% nitrogen
Purging and packing operations is expected to take approximately 40 hours.
The design data of the 44" Trunkline are detailed in the Table 9-1.
@ WLNGP +7.5 m
Elevation (LAT)
@ WP +30 m
Material of construction CS
ID Controlled 1068.4 mm
Length 223.3 km
Parameter Requirement
Acceptance Criteria
Maximum salinity content of last ≤ 200 mg of chloride per kilogram of water (200
potable water slug ppm)
Dewatering Pig Train All pigs arrive at the pig receiver in good condition
Gauge Plates No sign of damage, dents, flat spots, nicks or
gouging.
Acceptance Criteria
The BHA representative will check pigs for any damage that may have been sustained
during transit and also perform a cross-check of pig dimensions against the pig design
drawings and the Pig Inspection Report (OPS-0320-E) that was previously completed during
initial receipt of the pigs at the suppliers premises before shipment.
The 44" Trunkline will be dewatered by using a pig train of 5 Bi-Directional (Bi-di) pigs
complete with two sealing discs, two guide discs and two gauge plates at each end (95% of
ID, 6mm thick Aluminum) and pig signalling as detailed in Table 10-1.
Table 10-3: 44" Trunkline Dewatering and Drying Pig Train Requirements
During the engineering pig ability trials was carried out to verify that the pig design can
manoeuvre through the pipeline and SSIV freely. Below is the basic pig design.
The front pig will be fitted with an Online 1200 series acoustic pinger along with magnets to
enable to trace the pig in the event of it getting stuck in the pipeline. The third pig will be
CONTRACTOR No: C-0141-13-PCD-066 Page 30 of 181 REV 2
fitted with an Online 1200 series acoustic pinger to assist in verifying that the pig has entered
the receiver prior to pig removal. The rear most pig will be fitted with the Online 3007
electromagnetic transmitter along with magnets. Full details of the pig tracking equipment
can be found in the 44” Pig Design Report (WS2-3000-PPL-RPT-BHA-000-00005-000).
The pingers shall be activated and tested just prior to loading into the launcher.
All diesel fuel required to operate the equipment spread shall be supplied by CONTRACTOR.
CONTRACTOR will provide a storage capacity of 99,000 liters on site and a delivery system
required to ensure uninterrupted dewatering operations. The diesel tanks will be double
skinned tanks and they will be positioned 20 meters from any ignition sources
Once the dewatering operation has begun there will be two deliveries a day to maintain 24
hours contingency storage at all time.
COMPANY shall confirm in writing that the subsea safety valve and all relevant topside
valves are in the correct position and locked prior to dewatering operations.
The dewatering operations will be from the permanent pig launcher at the Onslow facility to
the permanent receiver on the Wheatstone platform. Prior to dewatering operations
COMPANY will install temporary 16” pipework from the pig receiver pipework to the
produced water caisson to discharge the hydrotest water during dewatering.
The below model shot drawing below shows the discharge pipework and the valves used to
control the water flow into the caisson.
124-02 124-04
124-05
Table 10-5: 16” Temporary Pipework from the Pig Receiver to the Produced water Caisson
During dewatering operations there will be an ultrasonic flowmeter fitted to the 16” discharge
line to enable the crew offshore to monitor the progression of the pigs and when to expect
the arrival of the pig train into the pig receiver.
During the preparation work for the dewatering operations the following work will need to be
completed before hand by COMPANY or COMPANY delegates.
Pig inspection reports signed off;
Completion certificate signed off;
WP discharge pipework to the produced water caisson to be in place;
WP closed drains to be available;
Silencer to be positioned on the WP;
Pig tracking equipment installed both onshore and offshore.
11.1 Onshore
As a minimum, the following will need to be removed to allow BHA to connect on to the
system for the dewatering operations to commence.
6” pipework coming off V-1110 (N5), Injection Point
2” Flange coming of the drain bleed valve (VA – 11870) of V-1110 (N3),
½” plug of the bleed valve of PT 11090 – Instrumentation Point
2” Pipework removed from N10 (HV-11106) to provide a balance for the pig.
11.2 Offshore
As a minimum, the following will need to be removed to allow BHA to connect on to the
system for the dewatering operations to commence.
2” check valve 124-22 off the purge connecting on 1250-KAH-0460
Remove 4” ball valve 124-11 to closed drains
Remove spec blind u/s of 124-11
Fit 2” hose to connect 100-DC-1250-003-DDCX2 to 150-PL-1807-004-AACA2
Plug on DBB 124-06 to be removed for instrumentation connection
Plug on DBB 124-17 to be removed for instrumentation connection
2’ Blind flange on 124 -27 low point bleed valve
The Inspection and Test Plan format (ITP) presented in this procedure summarises the different
parties involved and their responsibilities to take action(s) or their rights to have Hold, Witness,
Monitoring and Review points for the critical activities that are required to be performed during
execution of the Work.
The following sections contain several tables to detail the steps that shall be taken to perform the
dewatering and drying operations for the trunkline. The Inspection and Test Plan (ITP) presented in
Appendix A, the following acronyms are used throughout the following tables to describe
COMPANY/CONTRACTOR rights and responsibilities during execution of the Work.
A - Action Point - In any column that denotes “A”, the activity requires action by
that party.
H - Hold Point - In any column that denotes “H”, further activity is not possible
until all criteria have been met and all parties have signed.
W - Witness - In any column that denotes “W”, the activity should be witnessed
Point by that party.
M - Monitor - In any column that denotes “M”, the activity should be Monitored
Point by that party and provide feedback from an Operational Control
perspective or as a Subject Matter Expert. Due notice should be
given to ensure the party is on site. If said notice has been given
then further activity is possible even if that party is not on site or
does not sign. They can verify after the activity by
documentation review.
O - Observation - In any column that denotes “O” column indicates that the activity
Point should be Observed by that party. If said notice has been given
then further activity is possible even if that party is not on site or
does not sign. They can verify after the activity by
documentation review.
Any hold points within this document are identified by the
following symbol and will form the ITP for the Dewatering/Drying
and Conditioning operation as it is included in Appendix A.
Any stages that has this symbol within it highlights that there
Ab
ink
ut
Action
2. Raise a permit and ensure that it is signed off by the correct authority
A M
and that a copy has been placed at the work site.
3. All personnel shall have attended and actively participate in the Toolbox
A W
talk / JHA.
Confirm that BHA onshore and offshore equipment is rigged up and all
valves are tagged as per drawings:
WS2-1250-PRO-PID-DME-000-00124-000;
WS1-1100-PRO-PID-BEC-000-00101-000;
4. A M
C-0141-13-DWG-011-001
C-0141-13-DWG-011-005
Ab
ink
o
Th
ut
it
Confirm that all BHA temporary equipment has been function tested as
per:
Trunkline Onshore Dewatering Spread Equipment Installation
6. H H
and Function Test WS2-3000-PPL-RPT-BHA-000-00007-000
Action
Install correct pressure chart for recorder (check serial number) to the
pressure recorder. Charts will clearly indicate:
Date;
Time;
Phase of Operation;
8. Recorder Serial Number;
H H
Range.
Ensure that the clock is in the operating position, with clocks wound or
battery set.
Calibrate the offshore ultrasonic flowmeter for the use of water with the
below information
Outer diameter – 14”
11. Wall thickness – 0.375” A W
Pipe material – Titanium B862 UNS 50400 STD
Pipe lining, material and thickness – no liner
Pipe roughness – 0.3
Action
15. H H
Action
Ab
ink
o
Th
ut
it
BHA CVX
1. Valve ID Description Status
Check Check A M
Any trapped pressure or fluids shall be discharge into the BHA break
tank.
To ensure the PLR is fully isolated from the pipeline, a PBU test
(Pressure Build Up) will be performed prior to the door being opened.
BHA CVX
Valve ID Description Status
Check Check
Once fully closed monitor the internal PLR pressure for 15 minutes to
ensure full isolation, fill out the below table.
2. A A
Pressure BHA CVX
No. Description
(BarG) Check Check
1 Test start
2 5 minute
3 10 minute
4 15 minute
Action
BHA CVX
Valve ID Description Status
Check Check
3. A M
PLR 004 PLR Inlet Valve OPEN
PLR Drain / Balance
PLR 005 OPEN
Valve
PLR 006 PLR Balance Valve OPEN
Position a suitably sized drip tray under the PLR door to capture any
fluids that may remain inside the PLR.
7. Secure the pig loading tray to the end of the pig launcher. A M
BHA CVX
Carry out the following valve operations:
Check Check
BHA CVX
8. Valve ID Description Status
Check Check A M
9. Fluid Pump A.
A M
Begin slowly injecting potable water into the system while monitoring the
discharge into the tank in the PLR area.
Upon receiving a solid discharge into the break tank at the PLR, Shut
10. down & isolate: A M
Fluid Pump A.
Action
BHA CVX
11. Valve ID Description Status
Check Check A M
Carry out the following valve operations to allow the PLR to be topped
up via the Blagdon:
BHA CVX
Valve ID Description Status
Check Check
Start up the Blagdon pump and begin injecting water into the PLR.
13. Continue injection until a solid, unbroken discharge can be seen from IV A M
014.
Once the PLR is deemed free from air, shut down the Blagdon and
perform the below valve operations:
BHA CVX
Valve ID Description Status
Check Check
Action
Ab
ink
o
Th
ut
it
In preparation for pig launch, a leak teat must be performed on the PLR
door to 30 BarG by:
1. Ensure the test area is barriered off and only essential
personnel are present;
15. NOTE: Under no circumstances shall personnel shall enter the A W
PLR door vicinity until successful completion of the 5 minute hold.
2. Start up the air driven test pump and in a slow and controlled
manner raise the pressure to 30 BarG;
3. Upon reaching 30 BarG isolate and shutdown the test pump;
4. Perform a 5 minute hold in which NO personnel shall enter the
PLR door vicinity;
5. Upon a successful 5 minute hold essential personnel may
visually inspect the PLR and door for leaks. Should a leak be
found, the test will be depressuried via PLR 015, leak repaired
and steps repeated.
6. Upon a successful PLR leak test, depressurise via PLR 015.
BHA CVX
Valve ID Description Status
Check Check
Action
Due to the difference in the launcher and receiver elevations, the BHA
onshore system must first be charged to 1 BarG higher than the pipeline
prior to the operation of the inline valve to ensure the pig does not move
backwards out of the PLR throat.
Confirm the pipeline pressure downstream of MOV 11006 via PT 11001:
BHA CVX
Check Check
17. A A
Pipeline Pressure: BarG
BHA CVX
Check Check
o
Th
ut
it
Reset all flowmeters to zero and ensure all relevant chart recorders are
would and new charts installed with the relevant info:
Date;
19. Time; A M
Phase of Operation;
Recorder Serial Number;
Range.
Action
Inform all relevant parties that BHA Onshore are ready to Launch Pig #1
and await approval to start.
Perform a communication check between Onshore and Offshore,
20. ensuring back up communications are available. A M
NOTE: Should communications break down at any point during the
operations, injection shall cease and the pipeline will be isolated at
both ends until communications are regained.
BHA CVX
Valve ID Description Status
Check Check
21. M A
MOV Inline Valve OPEN
11005
MOV Inline Valve OPEN
11006
BHA CVX
Check Check
o
Th
ut
it
Action
Confirm the pig launch, by utilising the acoustic and magnetic pig
tracking equipment.
23. A M
Injection shall continue behind Pig #1 until 150 m³ has been injected, as
confirmed by both onshore and offshore flowmeters.
24. Confirm with COMPANY that 150 m³ has been injected behind Pig #1.
H H
On approval from COMPANY, isolate and shutdown:
Fluid Pump A;
Chem Pump A.
BHA CVX
Valve ID Description Status
Check Check
25. M A
MOV Inline Valve CLOSE
11005
MOV Inline Valve CLOSE
11006
To isolate the PLR from the BHA spread perform the below valve
operation:
o
Th
ut
it
27. A M
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Valve ID Description Status
Check Check
28. PLR 005 PLR Drain Valve OPEN A M
29. Start up the Blagdon pump and begin sucking the contents of the PLR
A M
out and into the PLR break Tank (approx. PLR volume of 13.7 m³).
Once the Blagdon has sucked the entire volume of the PLR out,
shutdown the pump and perform the below valve operations:
BHA CVX
Valve ID Description Status
30. Check Check A M
PLR 010 Blagdon (Drain) Inlet CLOSE
Action
To ensure the PLR is fully isolated from the pipeline, a PBU test
(Pressure Build Up) will be performed prior to the door being opened.
BHA CVX
Valve ID Description Status
Check Check
Once fully closed monitor the internal PLR pressure for 15 minutes to
31. A A
ensure full isolation, fill out the below table.
1 Test start
2 5 minute
3 10 minute
4 15 minute
BHA CVX
Valve ID Description Status
Check Check
Action
Position a suitably sized drip tray under the PLR door to capture any
chemically treated water that may remain inside the PLR.
33. CAUTION: Any escaping water will be chemically treated and as A M
such any personnel involved in the door opening operation should
first fully understand and act on the information contained within
the MSDS.
36. Wheatstone operations to CLOSE and LOCK the pig launcher door. M A
Carry out the following valve operations to allow the PLR to be topped
up via the Blagdon:
BHA CVX
Valve ID Description Status
37. Check Check A M
PLR 011 Blagdon (Fill) Inlet OPEN
38. Start up the Blagdon pump and begin filling the PLR. Continue injection
A M
until the solid, unbroken discharge can be seen from IV 014.
Once the PLR is deemed full and free from air, shut down the Blagdon
and perform the below valve operations:
BHA CVX
Valve ID Description Status
Check Check
Action
In preparation for the PLR door test perform the below valve operations:
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
In preparation for pig launch, a leak teat must be performed on the PLR
door to 30 BarG by:
1. Ensure the test area is barriered off and only essential
personnel are present;
41. NOTE: Under no circumstances shall personnel shall enter the A W
PLR door vicinity until successful completion of the 5 minute hold.
2. Start up the air driven test pump and in a slow and controlled
manner raise the pressure to 30 BarG;
3. Upon reaching 30 BarG isolate and shutdown the test pump;
4. Perform a 5 minute hold in which NO personnel shall enter the
PLR door vicinity;
5. Upon a successful 5 minute hold essential personnel may
visually inspect the PLR and door for leaks. Should a leak be
found, the test will be depressuried via PLR 015, leak repaired
and steps repeated.
6. Upon a successful PLR leak test, depressurise via PLR 015.
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Check Check
43. A A
Pipeline Pressure: BarG
BHA CVX
Check Check
o
Th
ut
it
Reset all flowmeters to zero and ensure all relevant chart recorders are
wound and new charts installed with the relevant info:
Date;
45. Time; A M
Phase of Operation;
Recorder Serial Number;
Range.
Action
Inform all relevant parties that BHA Onshore are ready to Launch Pig #2
and await approval to start.
Perform a communication check between Onshore and Offshore,
46. ensuring back up communications are available. A M
NOTE: Should communications break down at any point during the
operations, injection shall cease and the pipeline will be isolated at
both ends until communications are regained.
BHA CVX
Valve ID Description Status
Check Check
47. M A
MOV Inline Valve OPEN
11005
MOV Inline Valve OPEN
11006
BHA CVX
Check Check
o
Th
ut
it
Action
Confirm the pig launch, by utilising the magnetic pig tracking equipment.
49. Injection shall continue behind Pig #2 until 150 m³ has been injected, as A M
confirmed by both onshore and offshore flowmeters.
Confirm with COMPANY that 150 m³ has been injected behind Pig #2.
50. H H
On approval from COMPANY, isolate and shutdown:
Fluid Pump A;
Chem Pump A.
BHA CVX
Valve ID Description Status
Check Check
51. M A
MOV Inline Valve CLOSE
11005
MOV Inline Valve CLOSE
11006
To isolate the PLR from the BHA spread perform the below valve
operation:
o
Th
ut
it
Action
BHA CVX
Valve ID Description Status
Check Check
54. PLR 005 PLR Drain Valve OPEN A M
55. Start up the Blagdon pump and begin sucking the contents of the PLR
A M
out and into the PLR break Tank (approx. PLR volume of 13.7 m³).
Once the Blagdon has sucked the entire volume of the PLR out,
shutdown the pump and perform the below valve operations:
BHA CVX
Valve ID Description Status
56. Check Check A M
Action
To ensure the PLR is fully isolated from the pipeline, a PBU test
(Pressure Build Up) will be performed prior to the door being opened.
BHA CVX
Valve ID Description Status
Check Check
1 Test start
2 5 minute
3 10 minute
4 15 minute
BHA CVX
Valve ID Description Status
Check Check
58. A M
PLR 004 PLR Inlet Valve OPEN
PLR Drain / Balance
PLR 005 OPEN
Valve
PLR 006 PLR Balance Valve OPEN
Action
Position a suitably sized drip tray under the PLR door to capture any
chemically treated water that may remain inside the PLR.
59. CAUTION: Any escaping water will be chemically treated and as A M
such any personnel involved in the door opening operation should
first fully understand and act on the information contained within
the MSDS.
62. Wheatstone operations to CLOSE and LOCK the pig launcher door. M A
Carry out the following valve operations to allow the PLR to be topped
up via the Blagdon:
BHA CVX
Valve ID Description Status
Check Check
64. Start up the Blagdon pump and begin filling the PLR. Continue injection
until the solid, unbroken discharge can be seen from IV 014. A M
Once the PLR is deemed full and free from air, shut down the Blagdon
and perform the below valve operations:
BHA CVX
Valve ID Description Status
Check Check
Action
Ab
ink
o
Th
ut
it
In preparation for pig launch, a leak teat must be performed on the PLR
door to 30 BarG by:
1. Ensure the test area is barriered off and only essential
personnel are present;
66. NOTE: Under no circumstances shall personnel shall enter the A W
PLR door vicinity until successful completion of the 5 minute hold.
2. Start up the air driven test pump and in a slow and controlled
manner raise the pressure to 30 BarG;
3. Upon reaching 30 Ba rG isolate and shutdown the test pump;
4. Perform a 5 minute hold in which NO personnel shall enter the
PLR door vicinity;
5. Upon a successful 5 minute hold essential personnel may
visually inspect the PLR and door for leaks. Should a leak be
found, the test will be depressuried via PLR 015, leak repaired
and steps repeated.
6. Upon a successful PLR leak test, depressurise via PLR 015.
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Check Check
68. A A
Pipeline Pressure: BarG
BHA CVX
Check Check
o
Th
ut
it
Reset all flowmeters to zero and ensure all relevant chart recorders are
wound and new charts installed with the relevant info:
Date;
70. Time; A M
Phase of Operation;
Recorder Serial Number;
Range.
Action
Inform all relevant parties that BHA Onshore are ready to Launch Pig #3
and await approval to start.
Perform a communication check between Onshore and Offshore,
71. ensuring back up communications are available. A M
NOTE: Should communications break down at any point during the
operations, injection shall cease and the pipeline will be isolated at
both ends until communications are regained.
BHA CVX
Valve ID Description Status
Check Check
72. M A
MOV Inline Valve OPEN
11005
MOV Inline Valve OPEN
11006
BHA CVX
Check Check
o
Th
ut
it
Action
Confirm the pig launch, by utilising the acoustic and magnetic pig
tracking equipment.
74. A M
Injection shall continue behind Pig #3 until 150 m³ has been injected, as
confirmed by both onshore and offshore flowmeters.
Confirm with COMPANY that 150 m³ has been injected behind Pig #3.
75. H H
On approval from COMPANY, isolate and shutdown:
Fluid Pump A;
Chem Pump A.
BHA CVX
Valve ID Description Status
Check Check
76. M A
MOV Inline Valve CLOSE
11005
MOV Inline Valve OPEN
11006
To isolate the PLR from the BHA spread perform the below valve
operation:
o
Th
ut
it
78. A M
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Valve ID Description Status
Check Check
79. PLR 005 PLR Drain Valve OPEN A M
80. Start up the Blagdon pump and begin sucking the contents of the PLR
A M
out and into the PLR break Tank (approx. PLR volume of 13.7 m³).
Once the Blagdon has sucked the entire volume of the PLR out,
shutdown the pump and perform the below valve operations:
BHA CVX
81. Valve ID Description Status
Check Check A M
Action
To ensure the PLR is fully isolated from the pipeline, a PBU test
(Pressure Build Up) will be performed prior to the door being opened.
BHA CVX
Valve ID Description Status
Check Check
Once fully closed monitor the internal PLR pressure for 15 minutes to
ensure full isolation, fill out the below table.
1 Test start
2 5 minute
3 10 minute
4 15 minute
BHA CVX
Valve ID Description Status
Check Check
83. A M
PLR 004 PLR Inlet Valve OPEN
PLR Drain / Balance
PLR 005 OPEN
Valve
PLR 006 PLR Balance Valve OPEN
Position a suitably sized drip tray under the PLR door to capture any
chemically treated water that may remain inside the PLR.
84. CAUTION: Any escaping water will be chemically treated and as A M
such any personnel involved in the door opening operation should
first fully understand and act on the information contained within
the MSDS.
Action
87. Wheatstone operations to CLOSE and LOCK the pig launcher door. M A
88. Inform all relevant parties that the water injection SOW has been
A M
completed and that preparations shall begin to inject compressed air.
Disconnect the Blagdon pump and associated hoses from the PLR area
ensuring drip trays are present under connections as they are broken to
capture any trapped fluids.
Rig-up PLR area as per:
91. C-0141-13-DWG-011 (Sheet 2 of 4) - PLR Area Air Injection A M
Start-up Diesel Tank A’s internal pumps - to charge the fuel pipework;
92. A M
Ab
ink
o
Th
ut
it
93. A M
Ab
ink
o
Th
ut
it
Action
One at a time bring the compressors online while closely monitoring the
discharge flow rate on the flow meter upstream of the silencer and the
discharging dew point from sample point IV 004.
The order the compressors shall be brought online shall follow:
BHA CVX
Valve ID Description Status
Check Check
The above order promotes the highest efficiency from the compression
spread.
NOTE: To isolate and shutdown units the order should be reversed
i.e. starting with Unit S and ending with Unit A.
Action
Closely monitor the dew point from IV 004 until -60°C has been
reached.
97. H H
BHA CVX
Valve ID Description Status
Check Check
In preparation for the PLR door test, isolate BUT retain operational
status on the following compressors in the following order:
BHA CVX
Valve ID Description Status
Check Check
Action
In preparation to test the PLR door, open up the jumper line over the
system NRV to allow the PLR to be depressurised via the main silencer
in case of an emergency, to achieve this:
BHA CVX
Valve ID Description Status
Check Check
100. A M
PLR 003 PLR Vent OPEN
Action
NOTE: The following step shall use Comp A to perform a PLR door
test to 24 BarG. This will be achieved by SLOWLY cracking PLR
001 just enough to allow air through and no more.
In the event of a leak anywhere in the system during this phase:
CLOSE AV 002 & OPEN AV 127.
Ab
ink
o
Th
it ut
BHA CVX
Valve ID Description Status
Check Check
CRACK
PLR 001 Injection Line Choke
OPEN
101. 3. Allow the pressure to build / equalise to 24 BarG downstream of A M
PLR 001;
4. Upon achieving 24 BarG complete a 5 minute hold period, in
which time no personnel shall enter the PLR door vicinity under
any circumstances;
5. After a successful 5 minute hold period, authorised personnel
may enter the PLR area to visually / audibly inspect the PLR
door for signs of leaking. Should a leak be found CLOSE AV
002 and OPEN AV 127 to depressurise the PLR. Once at
ambient repairs can be made and this step shall be repeated
from the beginning;
6. Perform a “soapy bubble” leak test on the PLR door;
7. On confirmation that the PLR door is leak free:
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Check Check
102. A A
Pipeline Pressure: BarG
Confirm the pressure BHA shall charge the PLR to prior to opening the
inline valve MOV 11006 (+ 1 BarG):
BHA CVX
Check Check
BHA CVX
Valve ID Description Status
Check Check
Reset all flowmeters to zero and ensure all relevant chart recorders are
wound and new charts installed with the relevant info:
Date;
104. Time; A M
Phase of Operation;
Recorder Serial Number;
Range.
Action
Inform all relevant parties that BHA Onshore are ready to Launch Pig #4
and await approval to start.
Perform a communication check between Onshore and Offshore,
105. ensuring back up communications are available. A M
NOTE: Should communications break down at any point during the
operations, injection shall cease and the pipeline will be isolated at
both ends until communications are regained.
BHA CVX
Valve ID Description Status
Check Check
106. M A
MOV Inline Valve OPEN
11005
MOV Inline Valve OPEN
11006
BHA CVX
Valve ID Description Status
Check Check
Action
Perform the below valve operation to launch and begin driving Pig #4
into the pipeline:
109. Confirm the pig launch, by utilising the magnetic pig tracking equipment. A M
BHA offshore to closely monitor the discharge rate and regulate the
discharge via choke valve 124-04 to 26.9 m³ / min (this rate equates to
0.5 m/sec pig train speed).
The below table details the relation between discharge rate and pig train
speed:
Action
BHA onshore shall continue injection behind the train until informed by
offshore that the pigs have travelled 5000 linear m.
The below table details how many compressors should be online based
on back pressure seen:
**Number of
Pressure Seen
*scfm Required Compressors
Onshore
Required
7 BarG 7,610 10
8 BarG 8,560 11
9 BarG 9,510 12
10 BarG 10,460 13
111. 11 BarG 11,410 14 A M
12 BarG 12,359 16
13 BarG 13,309 17
14 BarG 14,259 18
15 BarG 15,209 19
Once the train has travelled 5000 linear m (4482.5 m³ ejected) BHA
offshore shall perform the below valve operation:
BHA CVX
Valve ID Description Status
Check Check
112. A M
124-04 Discharge Line Choke CLOSE
Action
Upon confirmation from offshore that the train has reached its
destination, Wheatstone operations to perform the below valve
operations:
BHA CVX
Valve ID Description Status
113. Check Check M A
MOV
Inline Valve CLOSE
11006
MOV
Inline Valve CLOSE
11005
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
BHA CVX
Valve ID Description Status
Check Check
Action
To ensure the PLR is fully isolated from the pipeline, a PBU test
(Pressure Build Up) will be performed prior to the door being opened.
BHA CVX
Valve ID Description Status
Check Check
Once fully closed monitor the internal PLR pressure for 15 minutes to
ensure full isolation, fill out the below table.
119. A A
Pressure BHA CVX
No. Description
(BarG) Check Check
1 Test start
2 5 minute
3 10 minute
4 15 minute
BHA CVX
Valve ID Description Status
Check Check
120. A M
PLR 004 PLR Inlet Valve OPEN
123. In preparation for the PLR door test, Start up Compressor A and allow it
A M
to warm to operating temperatures.
Action
Perform the below valve operations to make the BHA onshore system
ready for PLR testing:
BHA CVX
Valve ID Description Status
Check Check
Perform the below valve operation to begin injecting air into BHA
onshore’s closed system:
Action
NOTE: The following step shall use Comp A to perform a PLR door
test to 24 BarG. This will be achieved by SLOWLY cracking PLR
001 just enough to allow air through and no more.
In the event of a leak anywhere in the system during this phase:
CLOSE AV 002 & OPEN AV 127.
Ab
ink
o
Th
it ut
BHA CVX
Valve ID Description Status
Check Check
CRACK
PLR 001 Injection Line Choke
OPEN
126. 3. Allow the pressure to build / equalise to 24 BarG downstream of A M
PLR 001;
4. Upon achieving 24 BarG complete a 5 minute hold period, in
which time no personnel shall enter the PLR door vicinity under
any circumstances;
5. After a successful 5 minute hold period, authorised personnel
may enter the PLR area to visually / audibly inspect the PLR
door for signs of leaking. Should a leak be found CLOSE AV
002 and OPEN AV 127 to depressurise the PLR. Once at
ambient repairs can be made and this step shall be repeated
from the beginning;
6. Perform a “soapy bubble” leak test on the PLR door;
7. On confirmation that the PLR door is leak free:
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Check Check
127. A A
Pipeline Pressure: BarG
Confirm the pressure BHA shall charge the PLR to prior to opening the
inline valve MOV 11006 (+ 1 BarG):
BHA CVX
Check Check
BHA CVX
Valve ID Description Status
Check Check
BHA CVX
Valve ID Description Status
Check Check
128. A M
AV 127 Silencer Isolation CLOSE
Action
Reset all flowmeters to zero and ensure all relevant chart recorders are
wound and new charts installed with the relevant info:
Date;
129. Time; A M
Phase of Operation;
Recorder Serial Number;
Range.
Start-up Diesel Tank A’s internal pumps - to charge the fuel pipework;
130. A M
Ab
ink
o
Th
ut
it
131. A M
Ab
ink
o
Th
ut
it
Inform all relevant parties that BHA Onshore are ready to Launch Pig #5
and await approval to start.
Perform a communication check between Onshore and Offshore,
133. ensuring back up communications are available. A M
NOTE: Should communications break down at any point during the
operations, injection shall cease and the pipeline will be isolated at
both ends until communications are regained.
BHA CVX
Valve ID Description Status
Check Check
134. M A
MOV Inline Valve OPEN
11005
MOV Inline Valve OPEN
11006
Action
BHA CVX
Valve ID Description Status
Check Check
Perform the below valve operation to launch and begin driving Pig #5
into the pipeline:
138. Confirm the pig launch, by utilising the electromagnetic & magnetic pig
A M
tracking equipment.
Action
BHA offshore to closely monitor the discharge rate and regulate the
discharge via choke valve 124-04 to 26.9 m³ / min (this rate equates to
0.5 m/sec pig train speed).
The below table details the relation between discharge rate and pig train
speed:
Action
BHA onshore shall continue injection behind the train until informed by
offshore that Pig #1 has reached KP 210.
The below table details how many compressors should be online based
on back pressure seen:
**Number of
Pressure Seen
*scfm Required Compressors
Onshore
Required
8 BarG 8,560 10
9 BarG 9,510 11
10 BarG 10,460 12
11 BarG 11,410 13
12 BarG 12,359 14
13 BarG 13,309 15
14 BarG 14,259 16
15 BarG 15,209 17
140. A M
16 BarG 16,159 19 (0.47 m / sec)
141. Once Pig #1 has reached KP 210 (185,269 m³ ejected) BHA offshore
A M
shall inform onshore and request injection to cease.
Action
BHA CVX
Valve ID Description Status
Check Check
142. M A
MOV Inline Valve CLOSE
11006
MOV Inline Valve CLOSE
11005
Action
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
Action
As Pig #1 climbs the riser the pressure in front of the train will begin to
drop, 124-04 should progressively choked in to maintain a slow pig
speed and ensure safety.
Ab
ink
o
Th
ut
it
149. Confirm the receipt of Pig #1 by utilising the acoustic and magnetic pig
A W
detection equipment.
Action
151. Confirm the receipt of Pig #2 by utilising the magnetic pig detection
A M
equipment.
153. Confirm the receipt of Pig #3 by utilising the acoustic & magnetic pig
A M
detection equipment.
On confirmation that Pig #3 has been received, perform the below valve
operations to cease dewatering and isolate the PLR:
BHA CVX
Valve ID Description Status
Check Check
XV
WP PLR Isolation Valve CLOSE
046032
XV
WP PLR Isolation Valve CLOSE
046031
Action
BHA CVX
Valve ID Description Status
Check Check
BHA CVX
Valve ID Description Status
Check Check
Action
To ensure the PLR is fully isolated from the pipeline, a PBU test
(Pressure Build Up) will be performed prior to the door being opened.
BHA CVX
Valve ID Description Status
Check Check
Once fully closed monitor the internal PLR pressure for 15 minutes to
ensure full isolation, fill out the below table.
1 Test start
2 5 minute
3 10 minute
4 15 minute
NOTE: Should the PBU fail and a pressure increase seen over the
course of the test, Inline valves XV 046031 & XV 46031 should be
checked they are fully closed. The test should be repeated.
Action
NOTE: The following step shall use the N2 Quad to perform a PLR
door test to 24 BarG. This will be achieved by attaching a 24 Bar
regulated quad to 124-18 and opening 124-18.
In the event of a leak anywhere in the system during this phase:
OPEN 124-04 & CLOSE 124-18.
Ab
ink
o
Th
it ut
BHA CVX
Valve ID Description Status
Check Check
CRACK
124-18 WP Sample/ Purge Point
OPEN
163. A M
3. Allow the pressure to build to 24 BarG inside the PLR;
4. Upon achieving 24 BarG complete a 5 minute hold period, in
which time no personnel shall enter the PLR door vicinity under
any circumstances;
BHA CVX
Valve ID Description Status
Check Check
BHA CVX
Valve ID Description Status
Check Check
Action
In preparation for continuing the dewatering run and receiving Pig #4 &
#5, perform the below valve operation:
BHA CVX
Valve ID Description Status
Check Check
165. M A
XV
WP PLR Isolation Valve OPEN
046032
XV
WP PLR Isolation Valve OPEN
046031
Action
BHA CVX
Valve ID Description Status
Check Check
The below table details the relation between discharge rate and pig train
speed:
o
Th
ut
it
Action
BHA CVX
Valve ID Description Status
167. Check Check A M
BHA CVX
Valve ID Description Status
Check Check
168. A M
WP 001 Silencer Isolation Valve OPEN
Recalibrate the 2no. Ultrasonic Flowmeters for the use of air.with the
below line details
Outer diameter – 14”
Wall thickness – 0.375”
169. A M
Pipe material – Titanium B862 UNS 50400 STD
Pipe lining, material and thickness – no liner
Pipe roughness – 0.03
Action
Once the silencer has been opened, perform the below valve operations
to restart the dewatering train and bring home Pig #5:
BHA CVX
Valve ID Description Status
Check Check
Action
Continue venting the pipeline pressure through the silencer until the
172. system is at ambient. Valve 124-04 can be opened to allow a maximum A W
of 30,000 scfm through the silencer.
BHA CVX
Valve ID Description Status
Check Check
XV
WP PLR Isolation Valve CLOSE
046032
XV
WP PLR Isolation Valve CLOSE
046031
To ensure the PLR is fully isolated from the pipeline, a PBU test
(Pressure Build Up) will be performed prior to the door being opened.
BHA CVX
Valve ID Description Status
Check Check
Once fully closed monitor the internal PLR pressure for 15 minutes to
ensure full isolation, fill out the below table.
1 Test start
2 5 minute
3 10 minute
4 15 minute
NOTE: Should the PBU fail and a pressure increase seen over the
course of the test, Inline valves XV 046031 & XV 46031 should be
checked they are fully closed. The test should be repeated.
Action
Action
NOTE: The following step shall use the N2 Quad to perform a PLR
door test to 24 BarG. This will be achieved by attaching a 24 Bar
regulated quad to 124-18 and opening 124-18.
In the event of a leak anywhere in the system during this phase:
OPEN 124-04 & CLOSE 124-18.
Ab
ink
o
Th
it ut
BHA CVX
Valve ID Description Status
Check Check
CRACK
124-18 WP Sample/ Purge Point
OPEN
179. 3. Allow the pressure to build to 24 BarG inside the PLR; A W
4. Upon achieving 24 BarG complete a 5 minute hold period, in
which time no personnel shall enter the PLR door vicinity under
any circumstances;
BHA CVX
Valve ID Description Status
Check Check
BHA CVX
Valve ID Description Status
Check Check
Action
2. Where necessary raise a permit and ensure that it is signed off by the
A M
correct authority and that a copy has been placed at the work site.
5. Raise a permit and signed off by the correct authority and that a copy
A W
has been placed at the work site.
Install correct pressure chart for recorder (check serial number) to the
pressure recorder. Charts will clearly indicate:
Date;
Time;
Phase of Operation;
8. Recorder Serial Number;
H H
Range.
Ensure that the clock is in the operating position, with clocks wound or
battery set.
Carry out pre-start checks on all major equipment as per service manual
9. A M
Ab
ink
o
Th
ut
it
Action
12. Start Diesel Tank A’s internal pump and allow the fuel header to charge. A M
13. A M
Ab
ink
o
Th
ut
it
Action
One at a time bring the compressors online while closely monitoring the
discharge flow rate on the flow meter upstream of the silencer and the
discharging dew point from sample point IV 004.
The order the compressors shall be brought online shall follow:
BHA CVX
Valve ID Description Status
Check Check
The above order promotes the highest efficiency from the compression
spread.
NOTE: To isolate and shutdown units the order should be reversed
i.e. starting with Unit S and ending with Unit A.
Action
Closely monitor the dew point from IV 004 until -60°C has been
reached.
18. H H
Inform all relevant parties that BHA Onshore are ready to air dry the
pipeline and await approval to start.
Perform a communication check between Onshore and Offshore,
19. ensuring back up communications are available. A M
NOTE: Should communications break down at any point during the
operations, injection shall cease and the pipeline will be isolated at
both ends until communications are regained.
Perform the below valve operations to begin injecting super dry air into
the pipeline:
BHA CVX
Valve ID Description Status
20. Check Check A M
Complete:
21. Air Drying Log – OPS-350E. A M
Logging readings on a 15-minute basis.
Action
BHA CVX
Valve ID Description Status
23. Check Check A M
Action
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Valve ID Description Status
Check Check
27. M A
MOV Inline Valve CLOSE
11006
MOV Inline Valve CLOSE
11005
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
30. Once the onshore system is fully depressurised, begin a 24-hour soak
A M
test.
Action
Upon completing a 24 hour hold / soak test, dew point readings shall be
taken from 124-18.
The acceptance criteria for the soak test is a dew point reading of ≤ -
31. 40°C. H H
32. In the event the soak test was unsuccessful, repeat steps 5 – 31 until a
A M
soak test wields dew point of -40°C.
BHA CVX
Valve ID Description Status
Check Check
BHA CVX
Valve ID Description Status
Check Check
2. Where necessary raise a permit and ensure that it is signed off by the
A M
correct authority and that a copy has been placed at the work site.
5. Raise a permit and signed off by the correct authority and that a copy
A W
has been placed at the work site.
Install correct pressure chart for recorder (check serial number) to the
pressure recorder. Charts will clearly indicate:
Date;
Time;
Phase of Operation;
6. Recorder Serial Number;
H H
Range.
Ensure that the clock is in the operating position, with clocks wound or
battery set.
Carry out pre-start checks on all major equipment as per service manual
7. A M
Ab
ink
o
Th
ut
it
Action
BHA CVX
Valve ID Description Status
Check Check
11. Start Diesel Tank A’s internal pump and allow the fuel header to charge. A M
Action
BHA CVX
Valve ID Description Status
Check Check
13. A M
Ab
ink
o
Th
ut
it
15. Bring the dryers online in accordance with the manafactures SOP. A M
Action
One at a time bring the compressors online while closely monitoring the
discharge flow rate on the flow meter upstream of the silencer.
The order the compressors shall be brought online shall follow:
BHA CVX
Valve ID Description Status
Check Check
The above order promotes the highest efficiency from the compression
spread.
NOTE: To isolate and shutdown units the order should be reversed
i.e. starting with Unit S and ending with Unit A.
Action
Closely monitor the discharge flow rate and N2 content being produced
until the below criteria are met:
5400 scfm;
18. 97% Nitrogen. H H
Inform all relevant parties that BHA Onshore are ready to N2 Purge and
Pack the pipeline and await approval to start.
Perform a communication check between Onshore and Offshore,
19. ensuring back up communications are available. A M
NOTE: Should communications break down at any point during the
operations, injection shall cease and the pipeline will be isolated at
both ends until communications are regained.
BHA CVX
Valve ID Description Status
Check Check
20. A M
124-04 WP Choke Valve OPEN
BHA CVX
Valve ID Description Status
Check Check
21. M A
MOV Inline Valve OPEN
11006
MOV Inline Valve OPEN
11005
Perform the below valve operations to begin injecting super dry air into
the pipeline:
BHA CVX
Valve ID Description Status
22. Check Check A M
Action
Complete:
23. Pipeline N2 Inerting/Displacement Report OPS-0365-E. A M
Logging readings on a 15-minute basis.
o
Th
ut
it
BHA CVX
Valve ID Description Status
Check Check
26. M A
XV
WP PLR Isolation Valve CLOSE
046032
XV
WP PLR Isolation Valve CLOSE
046031
Continue to inject N2 into the pipeline until a pressure of 0.5 BarG can
has been reached as confirm by offshore personnel.
27. A M
NOTE: Based on an injection rate of 5400 scfm, this operation will
take 23 hours.
Action
Upon successfully pressurising the pipeline to 0.5 BarG with 97% pure
N2, Isolate and shutdown the compressors by performing the below
valve operations:
BHA CVX
Valve ID Description Status
Check Check
Action
BHA CVX
Valve ID Description Status
Check Check
30. M A
MOV Inline Valve CLOSE
11006
MOV Inline Valve CLOSE
11005
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
BHA CVX
Valve ID Description Status
Check Check
o
Th
ut
it
Action
o
Th
ut
it
Before making any request for permission to start operations, BH representative shall carry
out a safety audit, the relevant details of which shall be recorded on the following safety
audit checklist.
The BH representative shall be responsible for the maintenance of the conditions verified in
the safety audit checklist.
Description Yes No
BH personnel aware of all identified safety hazards.
Mitigations identified during the HAZID implemented.
Toolbox talk meeting held and risk assessment job site review completed.
Mitigations identified during the risk assessment job site review implemented.
Flexible hoses suitably pressure rated, secured and test certificates available on
site and checked.
Are all temporary fittings suitably pressure rated and whip checks installed in all
the hose joints?
Are all instrument used on the job are suitably rated, certified and checked?
Are barriers erected and relevant warning signs and flagging posted around the
agreed working area?
Personnel operating equipment identified and briefed on the operational
parameters.
Chemical/oil spill kits and temporary drip tray are available and accessible.
Safety showers and eye wash in place and functional.
Emergency muster points identified and notified.
If there is any change to procedure, is the relevant Management of Change form
completed and signed.
Appropriate Valve Status Checklist completed and signed.
All personnel has personal Oxygen meters
BHA
CVX
Before making any request for permission to start operations, BH representative shall carry
out a safety audit, the relevant details of which shall be recorded on the following safety
audit checklist.
The BH representative shall be responsible for the maintenance of the conditions verified in
the safety audit checklist.
Description Yes No
BH personnel aware of all identified safety hazards.
Mitigations identified during the HAZID implemented.
Toolbox talk meeting held and risk assessment job site review completed.
Mitigations identified during the risk assessment job site review implemented.
Flexible hoses suitably pressure rated, secured and test certificates available on
site and checked.
Are all temporary fittings suitably pressure rated and whip checks installed in all
the hose joints?
Are all instrument used on the job are suitably rated, certified and checked?
Are barriers erected and relevant warning signs and flagging posted around the
agreed working area?
Personnel operating equipment identified and briefed on the operational
parameters.
Chemical/oil spill kits and temporary drip tray are available and accessible.
Safety showers and eye wash in place and functional.
Emergency muster points identified and notified.
If there is any change to procedure, is the relevant Management of Change form
completed and signed.
Appropriate Valve Status Checklist completed and signed.
All personnel has personal Oxygen meters
BHA
CVX
Before making any request for permission to start operations, BH representative shall carry
out a safety audit, the relevant details of which shall be recorded on the following safety
audit checklist.
The BH representative shall be responsible for the maintenance of the conditions verified in
the safety audit checklist.
Description Yes No
BH personnel aware of all identified safety hazards.
Mitigations identified during the HAZID implemented.
Toolbox talk meeting held and risk assessment job site review completed.
Mitigations identified during the risk assessment job site review implemented.
Flexible hoses suitably pressure rated, secured and test certificates available on
site and checked.
Are all temporary fittings suitably pressure rated and whip checks installed in all
the hose joints?
Are all instrument used on the job are suitably rated, certified and checked?
Are barriers erected and relevant warning signs and flagging posted around the
agreed working area?
Personnel operating equipment identified and briefed on the operational
parameters.
Chemical/oil spill kits and temporary drip tray are available and accessible.
Safety showers and eye wash in place and functional.
Emergency muster points identified and notified.
If there is any change to procedure, is the relevant Management of Change form
completed and signed.
Appropriate Valve Status Checklist completed and signed.
All personnel has personal Oxygen meters
BHA
CVX
BHA
CVX
BHA
CVX
BHA
CVX
There is no requirement for COMPANY to sign to verify valve position where there are
shaded boxes
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position Checked By
Valve ID Description Required BHA CVX
Position
Signed on behalf of CVX by: :
There is no requirement for COMPANY to sign to verify valve position where there are
shaded boxes
Position Checked By
Valve ID Description
Required BHA CVX
Drawings: C-0141-13-DWG-009/WS2-1250-PRO-PID-DME-000-00124-000
BHA Valves
WP 001 Silencer primary isolation valve CLOSED
WP 002 Silencer Secondary isolation valve CLOSED
WP 003 BHA Gauge Isolation OPEN
Client System Valves
SSIV 746001 44” Subsea safety valve OPEN
TTV 1 44” Isolation Valve from Subsea Inline T OPEN
SDV 046041 44” Inline SDV OPEN
XV 046033 28” Actuated Valve from Trains 1 & 2 CLOSED
DB-50CUA PG 046003 DB Isolation valve OPEN
XV 046032 44” Inline MOV CLOSED
124-20 2” isolation valve to closed drains CLOSED
124-25 2” Bleed valve CLOSED
124-24 2” Isolation Valve to Flare CLOSED
XV 046031 44” Inline MOV OPEN
124-16 4” Valve on Balance Line [N5] CLOSED
124-19 4” PLR Drain Line Isolation [N4A] CLOSED
124-12 2” PLR Drain Line Bleed CLOSED
124-10 4” PLR Drain Line Isolation [N4B] CLOSED
124-17 2” PLR DBB [K2] CLOSED
124-18 2” Purge / Sample Point [N6] CLOSED
124-22 Check valve on purge connection REMOVE
124-14 2” PSV Bypass Valve CLOSED
PSV 046004 PSV INSTALLED
124-13 2” PSV Outlet Valve OPEN
124-09 4” Valve to Atmospheric Vent CLOSED
124-05 16” Production Ball Valve OPEN
124-04 16” Discharge Line Choke Valve OPEN
124-01 2” Production Isolation CLOSED
124-03 2” Valve to Flare CLOSED
124-02 16” Production Ball Valve CLOSED
Position Checked By
Valve ID Description
Required BHA CVX
Drawings: C-0141-13-DWG-009/WS2-1250-PRO-PID-DME-000-00124-000
There is no requirement for COMPANY to sign to verify valve position where there are
shaded boxes
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
There is no requirement for COMPANY to sign to verify valve position where there are
shaded boxes
Position Checked By
Valve ID Description
Required BHA CVX
Drawings: C-0141-13-DWG-009/WS2-1250-PRO-PID-DME-000-00124-000
BHA Valves
WP 001 Silencer primary isolation valve CLOSED
WP 002 Silencer Secondary isolation valve CLOSED
WP 003 BHA Gauge Isolation OPEN
Client System Valves
SSIV 746001 44” Subsea safety valve OPEN
TTV 1 44” Isolation Valve from Subsea Inline T OPEN
SDV 046041 44” Inline SDV OPEN
XV 046033 28” Actuated Valve from Trains 1 & 2 CLOSED
DB-50CUA PG 046003 DB Isolation valve OPEN
XV 046032 44” Inline MOV CLOSED
124-20 2” isolation valve to closed drains CLOSED
124-25 2” Bleed valve CLOSED
124-24 2” Isolation Valve to Flare CLOSED
XV 046031 44” Inline MOV OPEN
124-16 4” Valve on Balance Line [N5] CLOSED
124-19 4” PLR Drain Line Isolation [N4A] CLOSED
124-12 2” PLR Drain Line Bleed CLOSED
124-10 4” PLR Drain Line Isolation [N4B] CLOSED
124-17 2” PLR DBB [K2] CLOSED
124-18 2” Purge / Sample Point [N6] CLOSED
124-22 Check valve on purge connection REMOVE
124-14 2” PSV Bypass Valve CLOSED
PSV 046004 PSV INSTALLED
124-13 2” PSV Outlet Valve OPEN
124-09 4” Valve to Atmospheric Vent CLOSED
124-05 16” Production Ball Valve OPEN
124-04 16” Discharge Line Choke Valve OPEN
124-01 2” Production Isolation CLOSED
124-03 2” Valve to Flare CLOSED
124-02 16” Production Ball Valve CLOSED
Position Checked By
Valve ID Description
Required BHA CVX
Drawings: C-0141-13-DWG-009/WS2-1250-PRO-PID-DME-000-00124-000
There is no requirement for COMPANY to sign to verify valve position where there are
shaded boxes
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
Checked By
Position
Valve ID Description Required
BHA CVX
There is no requirement for COMPANY to sign to verify valve position where there are
shaded boxes
Position Checked By
Valve ID Description
Required BHA CVX
Drawings: C-0141-13-DWG-009/WS2-1250-PRO-PID-DME-000-00124-000
BHA Valves
WP 001 Silencer primary isolation valve CLOSED
WP 002 Silencer Secondary isolation valve CLOSED
WP 003 BHA Gauge Isolation CLOSED
Client System Valves
SSIV 746001 44” Subsea safety valve OPEN
TTV 1 44” Isolation Valve from Subsea Inline T OPEN
SDV 046041 44” Inline SDV OPEN
XV 046033 28” Actuated Valve from Trains 1 & 2 CLOSED
DB-50CUA PG 046003 DB Isolation valve OPEN
XV 046032 44” Inline MOV CLOSED
124-20 2” isolation valve to closed drains CLOSED
124-25 2” Bleed valve CLOSED
124-24 2” Isolation Valve to Flare CLOSED
XV 046031 44” Inline MOV CLOSED
124-16 4” Valve on Balance Line [N5] CLOSED
124-19 4” PLR Drain Line Isolation [N4A] CLOSED
124-12 2” PLR Drain Line Bleed CLOSED
124-10 4” PLR Drain Line Isolation [N4B] CLOSED
124-17 2” PLR DBB [K2] CLOSED
124-18 2” Purge / Sample Point [N6] CLOSED
124-22 Check valve on purge connection REPLACE
124-14 2” PSV Bypass Valve CLOSED
PSV 046004 PSV INSTALLED
124-13 2” PSV Outlet Valve OPEN
124-09 4” Valve to Atmospheric Vent CLOSED
124-05 16” Production Ball Valve CLOSED
124-04 16” Discharge Line Choke Valve CLOSED
124-01 2” Production Isolation CLOSED
124-03 2” Valve to Flare CLOSED
124-02 16” Production Ball Valve CLOSED
Position Checked By
Valve ID Description
Required BHA CVX
Drawings: C-0141-13-DWG-009/WS2-1250-PRO-PID-DME-000-00124-000
In the event of an emergency on the WP refer to the Emergency Response Plan, WS2-3000-
HES-PLN-BHA-000-00004-000 for relevant actions to be taken regarding the type of
emergency.
CONTRACTORs site induction and shift toolbox talks will provide the required steps to be
followed in the event of an emergency e.g. a hose / pipework failure, fire or any loss of
containment.
There will be sufficient contingency equipment to allow the repair of any faulty equipment
without impacting the performance of the spread.
There will be sufficient spares onsite to address any running repairs to the major equipment;
There will be mechanics on days and nights carrying out any running repair and preventative
maintenance during the operational phase of the project.
In the event of emergency during slug injection operations, the activities detailed below
should be initiated to make the system / equipment safe.
Close the suction and discharge valves on the liquid fill pumps.
Isolate the bulk liquid transfer system upstream of the failure, if required.
Close isolation valves on the pig launcher.
Activate the stop on the compressors supplying the compressed air to the liquid
transfer pump.
Depressurise the compressed air system / hose supplying the liquid transfer
pumps.
Close of air supply to the fuel pumps by shutting valve at the end of the air rail.
If practical inform WP and client reps of any shutdown.
In the event of emergency affecting the fuel distribution system, the activities detailed below
should be initiated to make the system / equipment safe.
Close the discharge valves on the fuel transfer pumps.
Close of air supply to the fuel pumps by shutting valve at the end of the air rail.
Close the storage tank outlet valves.
Contain and clean up any release
In the event of emergency during dewatering and conditioning operations, the activities
detailed below should be initiated to make the system / equipment safe.
In the event of emergency during depressurisation operations, the activities detailed below
should be initiated to make the system/equipment safe.
The 44” MOV 11005 required to be closed to isolate the pipeline onshore.
The 44” XV 046031 required to be closed to isolate the pipeline offshore.
Usually one of two conditions exist when a pig is stuck: fluid bypasses around the pig, or
there is a complete blockage of the flow, resulting in a jammed pig. These conditions can be
identified by the following:
A bypassing pig will exhibit movement which does not correlate with the total
volume of propellant pumped.
A jammed pig will cause an increase in pipeline pressure with decrease in flow
rate.
In the event of a “Stuck Pig” the equipment spread shall be shut down and the situation
assessed based on the below mentioned points.
The COMPANY and CONTRACTOR will agree to a maximum allowable pressure to try and
dislodge the pig based on the following:
APPENDIX A - ITP
Dewatering ITP
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Description: Wheatstone Trunkline Dewatering, Drying and N2 inerting
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
BHA Chevron
specification
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
No Visible Leaks
3
8m /min
20,000 cfm/m
Confirm that the Section compressed air. Trunkline Onshore
equipment has 12.2 Dewatering
WLNG Compressed air
1. been function This Procedure Spread Equipment N H H
& WP step 6 dried to 60 °C
tested (Onshore Installation &
and Offshore) Page 35 dew point deg C Function Test
5400cfm/m of
Nitrogen @ 97%
purity
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
BHA Chevron
specification
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
Section
Complete the 12.2
Commencement
2. Commencement WLNG This Procedure PPS-OPS-0375 Y H H
Step 7 Cert
Cert
Page 35
Section
Fit/Sign Chart in 12.2
3. Chart Recorder WLNG This Procedure Signed Pressure charts Y H H
and Wind-Up Step 8
Page 36
Section
12.2
4. Carry out Safety This Procedure Completed Checklist in N H H
Audit Checklist WLNG Step 15 Section 14
Page 37
Section
Confirm that 12.3
3
5. 150m has been WLNG This Procedure Fill report OPS-0310-F Y H H
Step 24
pumped
Page 44
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
BHA Chevron
specification
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
Section
Confirm that 12.3
3
6. 150m has been WLNG This Procedure Fill report OPS-0310-F Y H H
Step 50
pumped
Page 51
Section
Confirm that 12.3
3
7. 150m has been WLNG This Procedure Fill report OPS-0310-F Y H H
Step 75
pumped
Page 58
Section
12.3
8. Verify that the air WLNG This Procedure Daily Ops Report PPS-OPS-0030B N H H
is at -60 deg C Step 97
Page 63
Section
Confirm that 5000 12.3
Dewatering
9. linear meters has WLNG This Procedure OPS-0340-G Y H H
Step 112 Report
been pumped
Page 69
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
BHA Chevron
specification
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
Drying ITP
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Description: Wheatstone Trunkline Dewatering, Drying and N2 inerting
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
specification BHA Chevron
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
Section
Complete the 12.4
Commencement
1. Commencement WLNG This Procedure PPS-OPS-0375 Y H H
Step 4 Cert
Cert
Page 96
Section
Fit/Sign Chart in 12.4
2. Chart Recorder WLNG This Procedure Signed Pressure charts Y H H
and Wind-Up Step 8
Page 96
Section
12.4
3. Carry out Safety WLNG This Procedure Completed Checklist in N H H
Audit Checklist Step 10 Section 14
Page 97
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
BHA Chevron
specification
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
Section
Verify that the air 12.4
4. WLNG This Procedure Step 18 Daily Ops Report PPS-OPS-0030B N H H
is at -60 °C
Page 99
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Description: Wheatstone Trunkline Dewatering, Drying and N2 inerting
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
BHA Chevron
specification
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
Section
Complete the 12.5
Commencement
1. Commencement WLNG This Procedure PPS-OPS-0375 Y H H
Step 4 Cert
Cert
Page 104
Section
Fit/Sign Chart in 12.5
2. Chart Recorder WLNG This Procedure Signed Pressure charts Y H H
and Wind-Up Step 6
Page 104
Section
12.5
3. Carry out Safety This Procedure Completed Checklist in N H H
WLNG
Audit Checklist Step 8 Section 14
Page 104
Subcontractor: Baker Hughes Process & Pipeline Services Location: Onslow /WP Platform
Certifying or Verifying
Controlling Document Inspection / Surveillance Activities
Acceptance Criteria
or
Include in Final
Reference or
BHA Chevron
specification
Drawing or
Paragraph
Document
Location
Report?
Ref No.
Activity
detail
Sign Activity Sign Activity
Section
Verify that the N2 12.5
4. supply is at 97% WLNG This Procedure Daily Ops Report PPS-OPS-0030B N H H
Step 18
at 5400cfm/min
Page 108
Acceptance PPS-OPS-0376
Certificate
PPS-OPS-0030B
Daily Operations
Report Pipeline OPS-350E
Complete All the Section Nitrogen Inerting-
required OPS-351-E
12.5 Displacement
5. paperwork for N2 This Procedure OPS-0365-E Y H H
WLNG Report
displacement and Step 35
packing Pipeline Nitrogen OPS-0366-E
operations Page 112
Inerting-
Displacement
Acceptance PPS-OPS-0376
Certificate
APPENDIX B: DRAWINGS
PRV 2
IBC
WATER
PLR
1/2"
1/2"
1/2"
016
015
013
IV
IV
1/2" 1/2"
PLR PLR
016 014
PLR
1/2"
015
2"
TANK
20M3 PLR
PLR
PLR
012
011
009
2"
2"
SAMPLE
PLR
007
2"
POINT
PLR
003
2"
1/2"
1/2"
1/2"
PLR
017
011
010
009
PLR
PLR
1/2"
IV
IV
IV
010
008
BLAGDON
2"
2"
8" 3" CORI 8"
PUMP FLOW C-0141-13-DWG-011-001
PLR PLR
002 001
3" CORI
11328
3/4"
VA
1/2"
012
IV
3/4" 1/2" 1/2"
IBC
11004
MOV
44"
VA IV IV EMPTY
11291 013 014
PLR
004
11295
8"
3/4"
VA
PLR
006
2"
1"
11464-2
VA
2"
VA N11 P1
112606 N10
44" 44" 44" 44"
TO OFFSHORE
MOV MOV MOV MOV N3
11056 11003 11005 11006
112599
112596
3/4"
3/4"
VA
VA
11011
HV
4"
2" 2" 2"
11284-1
11293-1
11343-2
VA
VA
3"
3"
PLR VA VA
VA
4"
005 11870 112601
TO DRAINS
PLR
PLR
018
019
2"
2"
SAMPLE
POINT
PLR
PLR
003
020
2"
2"
1/2"
1/2"
1/2"
PLR
015
011
010
009
1/2"
IV
IV
IV
8" 3" CORI 8"
FLOW C-0141-13-DWG-011-001
PLR PLR
002 001
3" CORI
VA
1/2"
012
IV
3/4" 1/2" 1/2"
IBC
11004
MOV
44"
VA IV IV EMPTY
11291 013 014
PLR
004
11295
8"
3/4"
VA
PLR
006
2"
1"
11464-2
VA
2"
VA N11 P1
112606 N10
44" 44" 44" 44"
TO OFFSHORE
MOV MOV MOV MOV N3
11056 11003 11005 11006
112599
112596
3/4"
3/4"
VA
VA
11011
HV
4"
11293-1
11343-2
VA
VA
3"
3"
PLR VA VA
VA
4"
TO DRAINS
DEWATERING AND DRYING PAD
6"
1/2"
6" 6"
6"
COMP COMP COMP COMP COMP COMP COMP COMP COMP 10" 10"
UNIT Q UNIT O UNIT M UNIT K UNIT I UNIT G UNIT E UNIT C UNIT A WIV WIV
FLUID PUMP
WIV
008
UNIT A
6"
002 003
6" 10" 10" 1/2"
052
046
040
034
026
020
014
008
002
AV
AV
AV
AV
AV
AV
AV
AV
AV
FLOW FLOW
WIV
009
2"
2"
2"
2"
2"
2"
2"
2"
2"
6"
10" 10" LOW POINT
1/2"
WIV WIV
006 007 6" 6"
047
041
035
027
021
015
009
003
AV
AV
AV
AV
AV
AV
AV
AV
AV
2"
2"
2"
2"
2"
2"
2"
2"
2"
POINT 10" #300
LOW POINT
2" NPT D&T 50 MICRON
1/2"
060
054
048
042
036
032
028
022
016
010
004
AV
AV
AV
AV
AV
AV
AV
AV
AV
AV
AV
1/2"
1/2"
002
001
2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
IV
IV
1/2"
061
001
AV
AV
045
039
031
025
019
013
007
AV
AV
AV
AV
AV
AV
AV
057
051
AV
AV
100 033
2"
2"
2"
2"
2"
2"
2"
TANK
2"
2"
044
038
030
024
018
012
006
050
AV
AV
AV
AV
AV
AV
AV
AV
2"
2"
2"
2"
2"
2"
2"
2"
043
037
029
023
017
011
005
049
AV
AV
AV
AV
AV
AV
AV
AV
CHEM CHEM
2"
2"
2"
2"
2"
2"
2"
2"
PUMP A PUMP B
1/2"
1/2"
CIV
CIV
001
002
SET TO:
COMP COMP COMP COMP COMP COMP COMP COMP 31.5 BARG
PRV 1 1/2"
UNIT P UNIT N UNIT L UNIT J UNIT H UNIT F UNIT D UNIT B
CIV
003
1/2"
1/2"
CIV
CIV
005
004
1/2" 1/2"
1/2"
106
123
AV
1/2"
AV
LOW POINT
6" 6"
AV AV
105
109
112
115
118
121
129
AV
AV
AV
AV
AV
AV
AV
101A
6"
6"
6"
6"
6"
6"
6"
101
001
004
007
010
013
NV
NV
NV
NV
NV
6"
6"
6"
6"
6"
104
108
111
114
117
120
AV
AV
AV
AV
AV
AV
6"
6"
6"
6"
6"
6"
1/2"
007
IV
4" 4" 6" 6" 6"
6"
6"
6"
6"
6"
6"
1/2"
SAMPLE
POINT
IV
008
SILENCER
ADU ADU ADU ADU ADU ADU
UNIT A UNIT B UNIT C UNIT D UNIT E UNIT F
BURST DISC
NPU NPU NPU NPU NPU
6"
6"
6"
6"
6"
6"
6"
6"
UNIT A UNIT B UNIT C UNIT D UNIT E
BURST
DISC
1/2"
003
IV
2" NPT D&T
103
107
110
113
116
119
128
AV
AV
AV
AV
AV
AV
AV
6"
6"
6"
6"
6"
6"
6"
1/2"
3" CORI
FLOW
LOW POINT
AV
124
3" 3" 4" 4" 4" 1/2"
1/2"
1/2"
102
122
AV
AV
SAMPLE
POINT 6"
LOW POINT LOW POINT IV
004 WIV
014
WIV
125
012
SAMPLE
002
005
008
011
014
AV
NV
NV
NV
NV
NV
6"
6"
6"
6"
6"
6"
6"
POINT
WIV
127
126
013
AV
AV
003
006
009
012
015
NV
NV
NV
NV
NV
6"
6"
6"
6"
6"
6"
6"
6"
1/2"
1/2"
006
005
IV
IV
6" 6"
NV
NV WIV
016
013 016
TANK
65M3
CON CON CON
031 030 029
CONDENSATE
2"
028
CON
1/2" 1/2"
1/2"
CON IV
CON 027 017
LOW POINT
032
1/2"
CON
033 1/2"
6" 6"
CON
UNIT A
026
ADU
1/2" 1/2"
CON CON
034 025
1/2"
UNIT Q
CON
COMP
024
1/2"
UNIT P
CON
COMP 023
1/2"
2"
022
CON
CON
035
6" 6" 1/2"
UNIT O
UNIT B
CON
ADU
COMP
021
1/2"
1/2"
CON
CON
UNIT N
036
020
COMP
1/2"
UNIT M
CON
COMP
019
2"
037
CON
1/2"
UNIT L
CON
1/2"
COMP
018
CON
2"
017
CON
038
6" 6"
1/2" 1/2"
UNIT C
ADU
UNIT K
CON CON
1/2"
LOW POINT
COMP
016 015
CON 1/2"
039
UNIT J
CON
COMP
014
1/2" 1/2"
UNIT I
CON CON
040
COMP
013
6" 6"
1/2"
UNIT D
ADU
UNIT H
CON
COMP
1/2" 012
1/2"
CON
041
CON
UNIT G
011
COMP
2"
1/2"
010
CON
CON
043 1/2"
6" 6"
UNIT F
CON
COMP
009
UNIT E
ADU
1/2" 1/2"
UNIT E
CON
DEWATERING AND DRYING PAD
CON
COMP
044 008
2"
042
CON
1/2"
UNIT D
1/2" CON
COMP
007
CON
1/2"
045
6" 6"
UNIT C
CON
COMP
006
UNIT F
ADU
2"
005
CON
1/2"
CON 1/2"
046
UNIT B
CON
COMP
004
1/2"
UNIT A
1/2" CON
COMP
003
CON
1/2" 1/2"
049
UNIT A
NPU
1/2" CON IV
LOW POINT
002 018
CON
050 2"
1/2"
CON
001
UNIT B
CON
NPU
051
1/2"
CON
052
1/2"
UNIT C
NPU
CON
053
1/2" 1/2"
UNIT D
NPU
CON IV
LOW POINT
047 019
2"
CON
048
UNIT E
NPU
DEWATERING AND DRYING PAD
GENSET
GENSET
DRAIN/COMPRESSOR FEED TO ANOTHER LOW POINT/COMPRESSOR
UNIT Q UNIT O UNIT M UNIT K UNIT I UNIT G UNIT E UNIT C UNIT A FEED. THE FUEL IN DAY TANK ON THE COMPRESSOR WILL LAST A
UNIT C
UNIT D
MINIMUM OF 5 HOURS.
031
DI
2"
004
006
009
011
015
017
019
022
024
027
032
033
034
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
020
021
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
IV
IV
2" 2" 2" 2" 2"
DI DI DI DI DI
1/2"
1/2"
1/2"
003
014
030
005
007
010
012
016
018
021
023
026
028
029
DI
DI
DI
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
1/2"
002 008 013 020 025
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
LOW POINT LOW POINT
DIESEL
TANK
110M3
GENSET
GENSET
UNIT B
UNIT A
COMP COMP COMP COMP COMP COMP COMP COMP
UNIT P UNIT N UNIT L UNIT J UNIT H UNIT F UNIT D UNIT B
001A
001
1/2"
1/2"
DI
DI
Wheatstone Platform
16" 16"
16" WS2-1250-PRO-PID-DME-000-00124-000
400-PL-1807-017-BBCA2
124 ULTRASONIC 124
04 05
FLOWMETER
16"
SILENCER
14" PRODUCED WATER CAISSON 16" 6" 6" 6"
WP WP
001 002
1 2 3 4 5 6 7 8 9 10 11 12
V-1110 NOTES:
1. FOR GENERAL NOTES, SYMBOLS AND PIPING
INLET PIG RECEIVER DETAILS, SEE DOCUMENT NUMBERS
Diameter (ID): 1068 mm WS1-0000-PRO-LGN-BEC-000-00102-000 THRU
Length (T/T): 13716 mm WS1-0000-PRO-LGN-BEC-000-00105-000.
Design Press.: 149.00 barg/
A Design Temp.: 65.0 C/-7.0 C 2. PI-11080 TO BE READABLE FROM GLOBE VALVE, A
Insulation Purpose: N VA-11337.
Insulation Thickness (mm): 3. PROVIDE A CLEAR AREA 7.5m FROM PIG
Material: CS RECEIVER END FOR PIG EXTRACTION AND
Trim: 0HC-11092-9CS16-N FEED GAS TO V-1111A/B VEHICLE ACCESS.
1100-0HC-11073-9CS18-N
2333 WS1-1100-00102
TWO PHASE FLOW 4. PROVIDE 6mm WEEP HOLE.
113AC
113AX
O NO POCKETS
ZL
5. PIG RECEIVER BARREL CLOSURE AND VALVES
11026 HAVE MANUAL KEYED INTERLOCK SYSTEM.
C
6. PIGGABLE TYPE VALVE REQUIRED.
7. DELETED.
MIN
MIN
FL 25 VA-114569 NNF
9CS16 9CS16 VA-11334 20 11. MOV-11004 AND MOV-11027 TO HAVE INCHING
VA-114570 NOTE 5
15SA01 NOTE 5 NOTE 5 15SA01 20 CAPABILITY.
150-0FL-11034-1SA08-N
Bechtel Oil, Gas and Chemicals, Inc. 2013. All rights reserved. This document contains information that is confidential and proprietary to Bechtel Oil, Gas and Chemicals, Inc.
VA-114571 25
50-0HC-11091-9CS16-N
HV HV 150-0HC-11807-15SA01-N 12. VALVE TO BE PROVIDED WITH BUILT-IN OPEN/CLOSE
+
+ HV VA-11494 CALC
11162 + 11029 SWITCH.
11028 VA-11335 20 NOTE 2
NNF
VA-11337-2 13. DELETED.
50-0HC-11877-15SA01-N 2337
FL 14. MAKE FUEL GAS CONNECTION ON TOP OF LINE.
25 VA-112605 VA-11336-2 25
113AC WS1-1900-00109
VA-112603 15. MOV SHALL BE PROVIDED WITH LOCAL/REMOTE/OFF
113AX SELECTOR SWITCH AND LOCAL OPEN/CLOSE PUSH
25 VA-11872 25 BUTTON.
VA-11873
50-0HC-11087-9CS16-N
16. PROVIDE ADEQUATE DISTANCE BETWEEN VALVES
C NNF VA-113363 MOV-11005 AND MOV-11006 TO ACCOMMODATE PIG. C
VA-113370 20 20 17. THE PURPOSE FOR THIS COMPRESSED AIR
9CS16 15SA01 15SA01 1SA08 CONNECTION IS TO PROVIDE PIG LAUNCHING
F 20 VA-113364 CAPABILITY.
FI FT FE
+
18. ANCHOR FLANGE/BLOCK.
11129 11129 11129
20 VA-113419
19. LOCAL FLOW INDICATOR FT-11129 TO BE READABLE
F FROM MOV-11027.
VA-113374 20 20 SP-11063
FI
20. LENGTH OF PIPE FROM RELIEF VALVE TO HEADER
11129A VA-113369
MOV FIRE 1200-0FL-19900-1CA12-N MUST 3.5M MINIMUM.
SET@147.80 barg
CL300
+
150-0HC-11088-9CS16-N
HS FP
50-0VT-11001-1CS11-N
11000
BECHTEL CONFIDENTIAL - Bechtel Security Level 2
FL 100x50 LO
M
11004 2335 100-0FL-11035-1CA12-N
D FL NOTE 20 CL1500 D
NOTE 4
VA-11331-1
H ZSO WS1-1900-00109 VA-112604
PI 20 XV-11003 CANNOT BE OPENED IF
O 11004
11001 ZL 50x40 20 VA-11871 I THERE IS HIGH-HIGH PRESSURE
L DIFFERENTIAL ACROSS XV-11003
CRITICAL 11004 VA-112606 FP VA-111540-1
PALL PAHH CRITICAL C ZSC LO 11-16
25
11001 11001 11004 1CS11
25 VA-11629 ZI ZT
11027 11027 H 9CS16
50-0HC-11089-9CS16-N
ZA ZI ZT PI VA-11340-2 ESD
I MASTER EMERGENCY SHUTDOWN
11003 11004 11004 11090 25 VA-11709 CLOSES XV-11003
ZSC L
VA-113368
I O 25
ZL O 11027
50-0HC-11453-9CS16-N ZL VA-112602
NOTE 10
VA-11288-2
11003
F
50-0HC-11808-9CS16-N
C NNF 11027 C V-1111A HIGH-HIGH LEVEL (2oo3
NOTE 19
PI ESDF
200-0HC-11820-9CS16-N
VOTING) OR V-1111B HIGH-HIGH
50-0HC-11005-9CS16-N
TI ZSO PT I
IA 11048 LEVEL (2oo3 VOTING) OR LOW-LOW
H 11089 XY 11027 11090 NOTE 10
O L +
25 VA-113381 FEED GAS PRESSURE (2oo3 VOTING)
E 11003 E
20-0HC-11497-9CS16-N
M
YI ZL ZL 11027 2XV-11103, 2XV-11102, AND 1XV-61103
113AX
S
VA-11716
11003 20 VA-11287 NOTE 5
F 11-16 11032 11005 11006 VA-11328
VA-11713
C C 20
O/C DE VA-112620 NOTE 11,15 MOV HV HV
VA-11464-2
HS TT NOTE 5 + +
20 +
VA-113366
20 25 11027 11013 11012 NOTE 5
11056 11089 YIS
9CS18 9CS16
VA-11474 HV 25 VA-11285
+
11007 NOTE 5 VA-11291 9CS16
NOTE 15,21 11106
20 9CS18
VA-11715
SKIN 20 VA-11283-2 20 VA-11295
MOV ZSO ZSC THERMO-
+
VA-11042 NOTE 12
11056 11056 11056 COUPLE ZSC ZSO ZSO ZSC NOTE 12 ZSO ZSC 20
VA-11475
BARRED TEE
MIN
MIN
MIN
150x100
FL NOTE 8 FL FL HV
F 1100-0HC-11093-9CS18-N BEACH SP-11044 SP-11001 MOV
N2 N3
11016
F
MIN
VALVE +
NOTE 5 1% NOTE 5
20 20 11006 SLOP
9CS16 9CS18
NOTE 6
9CS16
T
CSC
UG AG
VA-11294
VA-112596
20-0HC-11498-9CS16-N
20-0HC-11499-9CS16-N
+
FI 11008 50 + 50
MIN
VA-112619 11011
11039
VA-11752 25 VA-112595 VA-112600 50 VA-11870
20 20 HOLD #1
25 VA-112594 VA-112598 H
F PDT VA-11673-2 VA-11343-2
CSC
FT VA-11293-1 11094
11039 100-0OW-11054-9CS16-N
c
NNF
50-0BW-11094-9CS16-N 4383
H
VA-11057 20 20 VA-11058 I PDI NNF BW
20 20
G VA-11126 11-16 11094 WS1-1900-00109 G
VA-11341
PDAHH 180-0OW-11005-12PD01-N
VA-11132 20 20 VA-11338 SLOPE
START-UP FUEL GAS 11094
TO E-2202 CSC HOLD RESP REL.
100-0HC-11026-9CS16-N 80-0HC-11157-15SA01-N HOLD DESCRIPTION REL'D
NO ENGR DATE
WS1-2200-00104 4650
TWO PHASE FLOW CALC
NNF VA-11282 25 CURB AND DRAINS
SNR 20-May-
112AC
112AB
113AX
112AA
1
FE VA-112607 CONFIGURATION 2013
+ OILY WATER TO Q-2921
11039 25
VA-11631 246 WS1-2900-00106
H
CLIENT BECHTEL
REV. NO. REV. NO. DATE REVISION
BY/
CHK
PE
EGS
PROC MECH
ENGR ENGR
C.S.
EGS
PD&P.
EGS MET
LNG
TECH LIC
APE/ CLIENT BECHTEL
PEM CLIENT REV. NO. REV. NO. DATE REVISION
BY/
CHK
PE
EGS
PROC MECH
ENGR ENGR
C.S.
EGS
PD&P.
EGS MET
LNG
TECH LIC
APE/
PEM CLIENT WHEATSTONE PROJECT TRAIN 0 H
MBP/ MDW/ MBP/ MT/ LNG PLANT BECHTEL DRAWING NO. REV.
NA 00A 07 Jan 2010 ISSUED FOR REVIEW SC
SRP - - - - - - -
FWV
- 0 00D 14 Apr 2011 ISSUED FOR FEED SC
SRP SP MP YP PRW RLC - -
FWV
-
25657-300-M6-0T11-00001 000
MBP/ MT/ DS/ MT/ Chevron
PIPING & INSTRUMENTATION DIAGRAM SCALE: NTS
A 00B 31 Mar 2010 ISSUED FOR CLIENT REVIEW SC
SRP JBC GBD YP RMB - - -
FWV
- 1 00E 15 May 2012 ISSUED FOR DESIGN MBP
SNR SP SF YP PRW DM RAZ -
FWV
-
BECHTEL INLET PIG RECEIVER CLIENT DOCUMENT NO. REV. 2
OG&C Australia
B 00C 19 Aug 2010 ISSUED FOR HAZOP
MBP/
SC
SRP TP GBD YP SJL - - -
MT/
FWV
- 2 000 11 Mar 2013 ISSUED FOR CONSTRUCTION
DS/
MBP
SNR IF SF YP SC SG RAZ -
BS/
CC
DA Pty. Ltd. V-1110 WS1-1100-PRO-PID-BEC-000-00101-000
CVX_ENG_A1_BDR.REF
2 3 4 5 6 7 8 9 10 11 A.C.N. 086 197 757
CAD DATE: 3/13/2013 1:03:09 PM BORDER: CVX_WSLNGPID_EPC.SYM
Chevron
Project Information
Client Baker Hughes Job No.
Project Client Contract No.
Location Client Work Order No.
Distribution: Original On Site Job File Report 1 Document No.: PPS / OPS / 0030B
Copy #1 Baker Hughes Office Revision No.: G
Copy #2 Client Revision Date: September 2012
© Baker Hughes Incorporated. All Rights Reserved.
Shift Handover #1
Project Information
Client Baker Hughes Job No.
Project Client Contract No.
Location Client Work Order No.
Work
Work Completed (Out Going Shift):
Work in Progress:
Work Planned (In Coming Shift) Issues to be Resolved (In Coming Shift)
System Status
Baker Hughes Rep. Name Job Title Signature Time and Date
Out Going Supervisor
In Coming Supervisor
Distribution: Original On Site Job File Shift Handover 1 Document No.: PPS / OPS / 0030F
Copy #1 Baker Hughes Office Revision Number: G
Revision Date: September 2012
© Baker Hughes Incorporated. All Rights Reserved.
Used Pig Report
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Pipeline Name: Location:
Operation:
Click icon to insert Pig Photo, if available. Click icon to insert Pig Photo, if available.
Resize photo over text as needed, to Resize photo over text as needed, to
maintain spacing. maintain spacing.
Description Description
before run: after run:
Comments
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0322
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: August 2012
Pig Register
MetricUnit 1
Project Information
Client: 0 Baker Hughes Job No.: 0
Pipeline Owner: 0 Client Work Order No.: 0
Project Name: 0 Client Contract No.: 0
Project Location: 0 Start Date: 0-Jan-1900
Operation: 0 Completion Date: 0-Jan-1900
Project Information
Length: 0.00 km Section No.: of
Outside Diameter: 0.00 mm Launcher Location: 0
Max. Wall Thickness: 0.00 mm Receiver Location: 0
Min. Internal Diameter: mm Pipeline Volume: m3
Min. Bend Radius: Target Pig Speed: m/sec
3
Volume/Unit Length: m /m Pipe Internal Material:
Drive Medium: Internal Coating:
Average
Pig # Pig Type Launched Received Run Time(a) Pig Remarks
Speed(a)
Date Time Date Time (hrs) (m/sec)
(a) Note - The default calculation for Run Time & Avg. Pig Speed can be replaced with a more representative value or formula by the user, if needed.
BHI Rep.: Client Representative: System Owner:
Signature: Signature: Signature:
Date: Date: Date:
Distribution: Original On Site Job File Page 1 of 2 Document No.: PPS / OPS / 0321
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: July 2012
Pipeline Dewatering Report
MetricUnit 1
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Project Location: Pipeline Volume: - m3
Target Pig Speed: m/sec Liquid Displacement Rate: #DIV/0! m3/hr
Length: km Volume/Unit Length: #DIV/0! m3/m
Internal Diameter: mm Start Date:
Section #: of Completion Date:
FALSE TRUE
Base Pig Location and Avg. Pig Speed estimates on: Gas Injected Liquid Removed
Note:Above values are estimated based on a constant flowrate. Replace with actual readings or most accurate information, if available.
BHI Rep.: Client Representative: System Owner:
Signature: Signature: Signature:
Date: Date: Date:
Distribution: Original On Site Job File Page 1 of 7 Document No.: PPS / OPS / 0340
Copy #1 Baker Hughes Office Revision No.: G
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: November 2013
SpaceMarker
Pipeline Fill Report
MetricUnit 1
Project Information
Client: BP Pipeline Baker Hughes Job No.: C-0134-11-USA
Pipeline Owner: BP Client Work Order No.: BP-1234-2011
Project Name: Olympus Client Contract No.: BP-3456-2134-CON
Project Location: GOM Pipeline Volume: 1,562.15 m3
Target Pig Speed: 0.61 m/sec Target Fill Rate: 401.43 m3/hr
Length: 8.54 km Volume/Unit Length: 0.183 m3/m
Internal Diameter: 482.60 mm Start Date: 5-Jun-2012
Section #: 1 of Completion Date: 5-Jun-2012
Average
Total Volume Stage Pig
Date Time Pressure Total Pig Speed(a)
Filled Volume Location(a)
Flowrate Comments
3
(dd-Mon-yyyy) (24:00) (barg) (m3) (m3) (m /hr) (km) (m/sec)
5-Jun-2012 16:45 200.0 Start Start Start Start
5-Jun-2012 17:45 201.0 201.0 201.0 201.00 1.10 0.31
5-Jun-2012 18:45 202.0 410.0 209.0 205.00 2.24 0.31
5-Jun-2012 19:45 203.0 615.0 205.0 205.00 3.36 0.31
5-Jun-2012 20:45 204.0 790.0 175.0 197.50 4.32 0.30
5-Jun-2012 21:45 205.0 1,004.0 214.0 200.80 5.49 0.30
5-Jun-2012 22:45 206.0 1,211.0 207.0 201.83 6.62 0.31
5-Jun-2012 23:45 207.0 1,399.0 188.0 199.86 7.65 0.30
6-Jun-2012 00:45 208.0 1,563.0 164.0 195.38 8.54 0.30
(a) Note - The default calculation for pig location and speed (based on fill volume), can be replaced with a more representative value or formula by the user, if needed.
BHI Rep: Jim Smith Client Representative: Bill Jones System Owner: Tony Mann
Signature: Signature: Signature:
Date: 5-Jun-2012 Date: 5-Jun-2012 Date: 5-Jun-2012
Distribution: Original On Site Job File Page 1 of 2 Document No.: PPS / OPS / 0310
Copy #1 Baker Hughes Office 1 Revision No.: F
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: October 2014
Pipeline Nitrogen Inerting/Displacement
Report
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Location: Pipeline Volume: gal
Length: mi Volume/Unit Length: gal/ft
Internal Diameter: in Start Date & Time:
Section #: Completion Date & Time:
Pig # Pig Type Launch Date & Time Receive Date & Time Remarks
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0365
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: August 2012
Pipeline Nitrogen Inerting/Displacement
Acceptance Certificate
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Location: Start Date & Time:
Service Description: Completion Date & Time:
Baker Hughes certifies that the described pipeline was inerted, purged and/or displaced with nitrogen to the
parameters represented within this document.
Instrumentation
Calibration Calibration
Description Range Serial # Unit # Manufacturer
Date Certificate
Comments
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0366
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: August 2012
Gauge Plate Acceptance Certificate
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Pipeline Name: Launch Site:
Section #: Receiving Site:
Location: Start Date & Time:
Operation: Completion Date & Time:
Baker Hughes certifies that the described gauge pig was run through the pipeline as detailed within this
document.
Photo(s) Before Gauge Pig Run Photo(s) After Gauge Pig Run
Click icon to insert Pig Photo, if available. Click icon to insert Pig Photo, if available.
Resize photo over text as needed, to Resize photo over text as needed, to
maintain spacing. maintain spacing.
Description Description
before run: after run:
Comments
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0323
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Date: August 2012
Commencement Certificate
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Pipeline Name: Launch Site:
Location: Receiving Site:
Service Description: Start Date:
Completion Date:
Baker Hughes certifies that the above described service can proceed on the described pipeline in
accordance with the procedures, relevant CVI’s, and parameters represented within this document. All
related activities required for commencement will be completed to the applicable standard.
Procedures
Comments
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0375
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Date: August 2012
Pipeline Air Drying Log
Project Information
Client: Length: km Baker Hughes Job No.:
Pipeline Owner: Internal Diameter: mm Client Work Order No.:
Project Name: Section #: Client Contract No.:
Project Location: Pipeline Volume: m3 Start Date:
Operation: Volume/Unit Length = m3/m Completion Date:
Compressors
Pig Received
Date Time
Online (No.)
Flow Total Air Travel Pig Dew
Pig Pig Pressure Temp. Rate Volume Time Speed Point Remarks
(Mon-dd-yyyy) (24:00) # Type
barg °C sm3/hr sm3/hr hr m/sec °C
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
☐ ☐
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0350
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: August 2012
Pipeline Air Drying Acceptance Certificate
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Project Location: Test Start Date & Time:
Pipeline Volume: gal Completion Date & Time:
Baker Hughes certify that the described pipeline was Air Dried as described within this certificate.
Instrumentation
Calibration Calibration
Description Range Serial # Unit # Manufacturer
Date Certificate
Pressure Recorder
Pressure Gauge
Temp. Recorder - Ambient
Dew Point Meter
Comments
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0351
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Revision Date: August 2012
Acceptance Certificate
Project Information
Client: Baker Hughes Job No.:
Pipeline Owner: Client Work Order No.:
Project Name: Client Contract No.:
Pipeline Name: Launch Site:
Location: Receiving Site:
Service Description: Start Date:
Completion Date:
Baker Hughes certifies that the described service to the pipeline was completed in accordance with the
parameters represented within this document.
Instrumentation
Calibration Calibration
Description Range Serial # Unit # Manufacturer
Date Certificate
Comments
Distribution: Original On Site Job File Page 1 of 1 Document No.: PPS / OPS / 0376
Copy #1 Baker Hughes Office Revision No.: E
Copy #2 Client © Baker Hughes Incorporated. All Rights Reserved. Date: August 2012
TRUNKLINE DEWATERING,DRYING AND INERTING
PROCEDURE
APPENDIX D: MSDS
2 HAZARDS IDENTIFICATION
RISK PHRASES
R31 Contact with acids liberates toxic gas.
R34 Causes burns.
R50 Very toxic to aquatic organisms.
STATEMENT OF HAZARDOUS NATURE
HAZARDOUS SUBSTANCE (According to criteria of NOHSC). DANGEROUS GOODS (According to ADG Code).
DG CLASS
Class 8: Corrosive substances.
PACKING GROUP II
UN NO. 3265
HAZCHEM CODE 2X
3 COMPOSITION/INFORMATION ON INGREDIENTS
4 FIRST-AID MEASURES
INHALATION
Move the exposed person to fresh air at once. If respiratory problems, artificial respiration/oxygen. Get medical attention.
INGESTION
NEVER MAKE AN UNCONSCIOUS PERSON VOMIT OR DRINK FLUIDS! Immediately rinse mouth and drink plenty of water (200-300
ml). DO NOT induce vomiting. Get medical attention immediately. If vomiting occurs, keep head low so that stomach content doesn't get
into the lungs. Generates toxic gas in contact with acid.
SKIN CONTACT
Rinse the skin immediately with lots of water. Continue to rinse for at least 15 minutes. Remove contaminated clothes and rinse skin
thoroughly with water. Get medical attention immediately. Chemical burns must be treated by a physician.
1/ 5
REVISION DATE 05/04/2013
Hydrosure O-3670R
EYE CONTACT
Remove victim immediately from source of exposure. Make sure to remove any contact lenses from the eyes before rinsing. Promptly
wash eyes with plenty of water while lifting the eye lids. Continue to rinse for at least 15 minutes and get medical attention. To hospital or
eye specialist.
5 FIRE-FIGHTING MEASURES
EXTINGUISHING MEDIA
Water spray. Carbon dioxide (CO2). Dry chemicals, sand, dolomite etc.
SPECIAL FIRE FIGHTING PROCEDURES
Avoid water in straight hose stream; will scatter and spread fire. Cool containers exposed to flames with water until well after the fire is out.
Avoid breathing fire vapours. Keep run-off water out of sewers and water sources. Dike for water control.
UNUSUAL FIRE & EXPLOSION HAZARDS
May develop highly toxic or corrosive fumes if heated.
SPECIFIC HAZARDS
Fire or high temperatures create: Oxides of: Carbon. Nitrogen. Sulphur.
PROTECTIVE MEASURES IN FIRE
Wear full protective clothing. Use air-supplied respirator during fire fighting.
HAZCHEM CODE 2X
PERSONAL PRECAUTIONS
Wear protective clothing as described in Section 8 of this safety data sheet. Avoid inhalation of vapours and contact with skin and eyes.
ENVIRONMENTAL PRECAUTIONS
Do not discharge into drains, water courses or onto the ground.
SPILL CLEAN UP METHODS
Stop leak if possible without risk. DO NOT touch spilled material! Absorb in vermiculite, dry sand or earth and place into containers. Flush
area with plenty of water. Do not let washing down water contaminate ponds or waterways. Containers with collected spillage must be
properly labelled with correct contents and hazard symbol.
USAGE PRECAUTIONS
Avoid spilling, skin and eye contact. Ventilate well, avoid breathing vapours. Use approved respirator if air contamination is above
accepted level. Observe good chemical hygiene practices. Keep away from heat, sparks and open flame. Eye wash facilities and
emergency shower must be available when handling this product.
STORAGE PRECAUTIONS
Store in tightly closed original container in a dry, cool and well-ventilated place. Store separated from: Acids. Alkalis. Oxidising material.
DIPROPYLENE GLYCOL MONOMETHYL ETHER NOHSC 100 ppm 606 mg/m3 150 ppm 909 mg/m3 Sk
(DPM)
ETHANEDIOL NOHSC 20 ppm 10 mg/m3 40 ppm 104 mg/m3 Sk
PROCESS CONDITIONS
Provide eyewash, quick drench.
ENGINEERING MEASURES
Provide adequate general and local exhaust ventilation.
RESPIRATORY EQUIPMENT
In case of inadequate ventilation use suitable respirator.
2/ 5
REVISION DATE 05/04/2013
Hydrosure O-3670R
HAND PROTECTION
Use protective gloves made of: Rubber, neoprene or PVC. The most suitable glove must be chosen in consultation with the gloves
supplier, who can inform about the breakthrough time of the glove material. Be aware that the liquid may penetrate the gloves. Frequent
change is advisable.
EYE PROTECTION
Use approved safety goggles or face shield.
OTHER PROTECTION
Wear appropriate clothing to prevent any possibility of skin contact.
HYGIENE MEASURES
DO NOT SMOKE IN WORK AREA! Wash hands at the end of each work shift and before eating, smoking and using the toilet. Wash
promptly if skin becomes wet or contaminated. Promptly remove any clothing that becomes contaminated. When using do not eat, drink
or smoke.
APPEARANCE Liquid
COLOUR Colourless to pale yellow liquid
ODOUR Slight odour.
SOLUBILITY Soluble in water.
BOILING POINT (°C) >100°C
RELATIVE DENSITY 1.045 - 1.075 @ 20 °c
VAPOUR DENSITY (air=1) 0.9584
VAPOUR PRESSURE 17.3 mmHg 20°C
pH-VALUE, CONC. SOLUTION 4.0-6.0
VISCOSITY 16 cps 20°C
FLASH POINT (°C) 95
REFRACTIVE INDEX 39-41
STABILITY
Stable under normal temperature conditions.
CONDITIONS TO AVOID
Avoid heat, flames and other sources of ignition.
HAZARDOUS POLYMERISATION
Will not polymerise.
MATERIALS TO AVOID
Strong acids. Strong oxidising substances.
HAZARDOUS DECOMPOSITION PRODUCTS
Oxides of: Carbon. Nitrogen. Sulphur.
11 TOXICOLOGICAL INFORMATION
INHALATION
Gas or vapour may irritate respiratory system.
INGESTION
Causes burns. May cause chemical burns in mouth and throat. Generates toxic gas in contact with acid.
SKIN CONTACT
Causes burns.
EYE CONTACT
Causes burns. Risk of serious damage to eyes.
12 ECOLOGICAL INFORMATION
ECOTOXICITY
The product contains a substance which is very toxic to aquatic organisms.
MOBILITY
The product is soluble in water.
BIOACCUMULATION
No data available on bioaccumulation.
3/ 5
REVISION DATE 05/04/2013
Hydrosure O-3670R
13 DISPOSAL CONSIDERATIONS
GENERAL INFORMATION
Empty containers should be taken for local recycling, recovery or waste disposal
DISPOSAL METHODS
Recover and reclaim or recycle, if practical. Dispose of waste and residues in accordance with local authority requirements.
14 TRANSPORT INFORMATION
CORROSIVE
PROPER SHIPPING NAME CORROSIVE LIQUID, ACIDIC, ORGANIC, n.o.s. (contains quaternary ammonium chloride)
UN NO. 3265
ADG CLASS NO. 8
DG CLASS Class 8: Corrosive substances.
PACKING GROUP II
HAZCHEM CODE 2X
UN NO. SEA 3265
IMDG CLASS 8
IMDG PACK GR. II
EMS F-A S-B
UN NO. AIR 3265
ICAO CLASS 8
AIR PACK GR. II
15 REGULATORY INFORMATION
LABELLING
RISK PHRASES
R31 Contact with acids liberates toxic gas.
R34 Causes burns.
R50 Very toxic to aquatic organisms.
SAFETY PHRASES
S24/25 Avoid contact with skin and eyes.
S26 In case of contact with eyes, rinse immediately with plenty of water and seek
medical advice.
S36/37/39 Wear suitable protective clothing, gloves and eye/face protection.
S45 In case of accident or if you feel unwell, seek medical advice immediately
(show label where possible).
S57 Use appropriate containment to avoid environmental contamination.
S60 This material and its container must be disposed of as hazardous waste.
S61 Avoid release to the environment. Refer to special instructions/safety data
sheets.
4/ 5
REVISION DATE 05/04/2013
Hydrosure O-3670R
16 OTHER INFORMATION
REVISION COMMENTS
General revision.
ISSUED BY
LL
REVISION DATE 05/04/2013
REV. NO./REPL. SDS 5
GENERATED
RISK PHRASES IN FULL
R34 Causes burns.
R31 Contact with acids liberates toxic gas.
R22 Harmful if swallowed.
R36 Irritating to eyes.
R50 Very toxic to aquatic organisms.
DISCLAIMER
The information provided in this SDS is correct to the best of our knowledge, information and belief at the date of its publication. The information given is
designed only as a guidance for safe handling, use, processing, storage, transportation, disposal, and release and is not to be considered a warranty or
quality specification. The information relates only to the specific material designated and may not be valid for such material used in combination with any
other materials or in any process unless specified in the text.
5/ 5
TRUNKLINE DEWATERING,DRYING AND INERTING
PROCEDURE
APPENDIX E: CALCULATIONS
Dewatering
Dewatering Calculation
Elevation
Distance
The desalination acceptance criteria for the Trunkline is ≤ 200mg of Chloride per kilogram
of water, this is found in the Dewatering, Drying and Nitrogen Purging Specification (WS2-
3329-PPL-SPC-ITS-000-00002-000).
To achieve the dewatering and conditioning acceptance criteria, the slug volumes and
configuration of the pig train have been calculated to be as follows:
3 x 150 m3 Potable Water desalination slugs
The following parameters that were used to complete the desalination and conditioning
calculations:
-
Chloride Content of Fresh Water Slugs 20 ppm * (Total Salt / 1.8066 = Cl )
Flood / Fill water Salinity 3.5 %
Total Volume of Water Film 0.05 mm
Desalination Results
Venting
One the dewatering operation has been completed the Trunkline will then be vented down to
assist with the drying operations. Using the Baker Hughes software it has been calculated
approximately the venting duration before drying operation can proceed. Below shows the
results;
Venting Durations
Drying
Using the Baker Hughes software, we have calculated approximately the drying duration
assuming stable conditions.
Drying Results
The table below indicates the simulated time required to purge and pack the pipeline with
nitrogen gas. CONTRACTOR will run four nitrogen membrane units which will provide a
maximum injection rate of 13594 m3/hr (5400 scfm).
Pig Lading
3. Adjust the Pig loading tools height so that the tray marries up to the PLR opening;
4. Lock the Pig loading tools wheels and secure the tool to the PLR with ratchet straps;
5. Select the required pig for the upcoming operation as per the below table:
Pig Pig Type Tracking Drawing Ref.
No. Number
1 Bi-di gauge pig Magnets & Acoustic C-0141-13-DWG-012
Pinger
2 Bi-di pig Magnets C-0141-13-DWG-013
3 Bi-di gauge pig Magnets & Acoustic C-0141-13-DWG-014
Pinger
4 Bi-di pig Magnets C-0141-13-DWG-013
5 Bi-di pig Magnets & EM Pinger C-0141-13-DWG-015
6. Should the Pig require an Online tracking device (i.e. Pigs 1, 3 & 5) ensure the device is
installed and fully operational. Sign Required Check off box in procedure C-0141-13-
PCD-066;
7. Site Crane to lift the required Pig onto the Loading tray ensuring the pig is in the correct
orientation with the large pulling eye at the front and pinger (if included) at the rear;
Repeat this step until the Pig has been push 6790mm into the PLR and the front half
of the pig is fully engaged into the minor barrel of the PLR.
12. Once the Pig is in the Correct Position in the PLR, carry out dimensional checks with
the COMPANY representative as a witness, ensuring photographic records of the
pigs final position are taken.
13. Complete the Pig Loading Register;
14. On completion of the loading of Pig no. 5, ensure all paperwork and permits are
signed off and checked as per the QA/QC checklist on the next page.
Circle
PRE-SIGN OFF CHECKLIST
Answer
Are units consistent and correct (pipe ID’s & WT) Yes/No/n/a
Are pipeline details accurate (ie. lengths, diameters volumes, stroke/vol,
Yes/No/n/a
pressures etc.)
Does acceptance data correlate to pressurisation/flooding hold period Yes/No/n/a
and depressurisation reports?
Is each page of the pigging/flooding/pressurisation and hold period report
consistent throughout (date, dimensions, times, pressures and Yes/No/n/a
instrumentation used).
Are any corrections made to paperwork using whiteout initialled and Yes/No/n/a
dated by BHPPS Supv/Eng?
Are irrelevant sections within the ITP “red penned” with a single line Yes/No/n/a
signed and dated and replaced with any relevant info?
Are all reports requiring signature by all parties signed off prior to Yes/No/n/a
paperwork leaving site?
Date: _____________________
Pig Retrieval
5. Continue feeding in the retrieval rod and adding extensions until the Pig has been
reached;
6. Once at the pig, the retrieval rod can be rotated to allow the hook to match up to the pigs
pulling eye. Once matched up, push the hook onto the eye and complete the connection;
7. Once the hook is fully engaged, pull sharply on the rod to break the magnetic connection
between the rod and hook, begin pulling out the rod and breaking the connections as
available;
8. Once the rod is fully removed, position the tray in front of the PLR and begin operating the
chain block to bring the chain taught.
9. Slowly operate the chain block to begin pulling out the pig;
10. Pull the pig onto the tray, release the tension in the chain block and remove the hook;
11. Photograph the Pig and measure all the components for signs of excessive wear and
damage. Complete Gauge Plate Acceptance Cert OPS-0323 & Pig Register OPS-0321-
E;
Are units consistent and correct (pipe ID’s & WT) Yes/No/n/a
Are pipeline details accurate (ie. lengths, diameters volumes, stroke/vol,
Yes/No/n/a
pressures etc.)
Does acceptance data correlate to pressurisation/flooding hold period and Yes/No/n/a
depressurisation reports?
Is each page of the pigging/flooding/pressurisation and hold period report
Yes/No/n/a
consistent throughout (date, dimensions, times, pressures and instrumentation
used).
Are chart recorder graphs correctly marked up with location, project, Yes/No/n/a
workscope, instruments details, date time on/off, BHPPS & client signatures?
Are any corrections made to paperwork using whiteout initialled and dated by Yes/No/n/a
BHPPS Supv/Eng?
Are irrelevant sections within the ITP “red penned” with a single line signed and Yes/No/n/a
dated and replaced with any relevant info?
Are all reports requiring signature by all parties signed off prior to paperwork Yes/No/n/a
leaving site?
Date: _____________________