You are on page 1of 41



 
 



     

    !"
# $
%  &'( 
'$$
() $ ) 
$*))&
% $ )  
    

) $ )  +,-./-00//+.1,.00220---3

) 
$4 )5) $  &

  
      
  0 //+.1,. 0 22 0 ---3
6     !" 
6  76
   "   
  Johanes Agus
Digitally signed by PSS100841

 6 
DN: dc=intranet, dc=saipem,
dc=saipemnet,
ou=ForeignSites, ou=Jakarta,


ou=Users, cn=PSS100841
Date: 2018.05.04 16:51:07
+07'00'    
  4-May-18
89%$
  #$#% $$ #"$& "   '" #" #" 

# ##  $ '
 #  $  " '    " & " $ # '$$ 
" (  "" # $)$$ '  & "  $   $  ( #
$'#"   $ 
*" '    # '$ '  +$     $$#" ##"
 ( &'$$   "# #    ( #" '*"( # ,#-#"
" # 
 "#  (  #  $ ## " "     

# ##  
 #"$ $ '$$( #   " #&  $ ".!# #

) /  (  # ( 0##'    )&" "& #
 (( & #" $ '$$( "     # ##  

) $
4

)

12 12 232143 +  ( & . * 5 6 *
14 14 40  2143 +  ( & . * 5 6 *
) 
$4
8 
 
)$:) 
 * )8
8 )
*"  # ## " #  #"$#$ #
 
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

Table of Contents
1 INTRODUCTION ..................................................................................................... 6
1.1 Project Overview ......................................................................................................................... 6
2 SCOPE .................................................................................................................... 6
2.1 General ....................................................................................................................................... 6
2.2 Specific Design Conditions ......................................................................................................... 6
3 Normative Reference ............................................................................................. 7
4 Term and Definitions ........................................................................................... 10
5 Symbols and Abbreviations ................................................................................ 11
6 Risk Assessment ................................................................................................. 11
7 General Requirement ........................................................................................... 11
8 Roles and Responsible ....................................................................................... 11
8.1 Construction Manager ............................................................................................................... 11
8.2 Site Engineer............................................................................................................................. 11
8.3 Construction Supervisor ............................................................................................................ 12
8.4 HSE Officer ............................................................................................................................... 12
8.5 Civil QC ..................................................................................................................................... 12
9 Product and Materials ......................................................................................... 12
9.1 General ..................................................................................................................................... 12
9.2 Split of Material ......................................................................................................................... 12
9.3 Cement...................................................................................................................................... 13
9.4 Aggregate.................................................................................................................................. 13
9.5 Reinforcement ........................................................................................................................... 13
9.6 Water......................................................................................................................................... 14
9.7 Admixture .................................................................................................................................. 14
9.8 Formwork .................................................................................................................................. 14
9.9 Concrete .................................................................................................................................... 15
9.10 Concrete Accessories .......................................................................................................... 15
9.10.1 Bonding Agent ................................................................................................................. 15
9.10.2 Moisture Barrier ............................................................................................................... 15
9.10.3 Surface Dustproofing and Hardening .............................................................................. 15
9.10.4 Surface Oil - Proofing ...................................................................................................... 15
9.11 Joint ..................................................................................................................................... 15
9.11.1 Joint Filler ........................................................................................................................ 15
9.11.2 Backup Material ............................................................................................................... 16
9.11.3 Joint Primer...................................................................................................................... 16
9.11.4 Joint Sealant .................................................................................................................... 16
9.11.5 Bond Breaker ................................................................................................................... 16

TEP-1183573-G99-0004 Page 2 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

9.11.6 Waterstop ........................................................................................................................ 16


9.12 Curing Compounds and Accessories .................................................................................. 16
9.12.1 Liquid Membrane Curing Compounds ............................................................................. 16
9.12.2 Liquid Chemical Curing Compounds ............................................................................... 16
9.12.3 Polyethylene Film ............................................................................................................ 16
9.12.4 Absorptive mats ............................................................................................................... 16
9.13 Anchor and Embedment ...................................................................................................... 17
9.14 Grout .................................................................................................................................... 17
9.14.1 Epoxy Grout ..................................................................................................................... 17
9.14.2 Non-shrink Grout ............................................................................................................. 17
9.14.3 Standard Portland Cement Grout .................................................................................... 17
10 Execution Requirement ....................................................................................... 17
10.1 General ................................................................................................................................ 17
10.2 Formwork ............................................................................................................................. 17
10.3 Reinforcing and Embedments ............................................................................................. 19
10.3.1 Detailing and Fabrication ................................................................................................. 19
10.3.2 Concrete Cover ............................................................................................................... 20
10.3.3 Installation........................................................................................................................ 20
10.4 Joint ..................................................................................................................................... 21
10.4.1 Construction Joint ............................................................................................................ 21
10.4.2 Expansion Joint/ Isolation Joint ....................................................................................... 21
10.4.3 Construction Joint/ Control Joint...................................................................................... 22
10.5 Waterstops........................................................................................................................... 22
10.6 Proportioning and Mixing ..................................................................................................... 22
10.6.1 Trial Mixes ....................................................................................................................... 22
10.6.2 Batching and Mixing ........................................................................................................ 23
10.6.3 Slump and Consistency ................................................................................................... 24
10.7 Transportation...................................................................................................................... 24
10.8 Placing Concrete ................................................................................................................. 24
10.9 Surface Finishing ................................................................................................................. 26
10.10 Curing and Protection .......................................................................................................... 27
10.10.1 Curing / Moisture Retention ............................................................................................. 27
10.10.2 Protection from Mechanical Injury ................................................................................... 28
10.11 Repair of Surface Defects ................................................................................................... 28
10.12 Hot Weather Concreting ...................................................................................................... 29
10.13 Grouting ............................................................................................................................... 30
10.13.1 Type and Usage .............................................................................................................. 30
10.13.2 Preparation ...................................................................................................................... 30
10.13.3 Installation of Grout ......................................................................................................... 31
10.13.4 Installation of Epoxy Grout .............................................................................................. 31

TEP-1183573-G99-0004 Page 3 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

10.13.5 Installation of Non-shrink Grout ....................................................................................... 32


10.13.6 Installation of Standard Portland Cement Grout.............................................................. 32
11 Protection of Underground Concrete ................................................................. 32
11.1 General ................................................................................................................................ 32
11.2 Material ................................................................................................................................ 32
11.3 Application ........................................................................................................................... 33
12 Mass Concrete ..................................................................................................... 33
13 Quality Control ..................................................................................................... 33
13.1 Construction Tolerance ....................................................................................................... 33
13.1.1 General ............................................................................................................................ 33
13.1.2 Formwork ......................................................................................................................... 33
13.1.3 Reinforcement ................................................................................................................. 34
13.1.4 Concrete .......................................................................................................................... 34
Unless otherwise specified in the contract documents, embedments shall be installed in accordance
with the tolerances shown in bellow table. .......................................................................................... 35
13.2 Sampling for Test ................................................................................................................ 35
13.3 Concrete Not Meeting Specification .................................................................................... 36
14 Quality Management ............................................................................................ 37
15 Inspection, Testing and Certification ................................................................. 37
15.1 Inspection and Test Plan ..................................................................................................... 37
15.2 Inspection and Test Plan ..................................................................................................... 37
16 Packing, preservation, marking and shipping................................................... 37
17 Deliverables & Data Transfer .............................................................................. 37
18 Attachment ........................................................................................................... 38

TEP-1183573-G99-0004 Page 4 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
TANGGUH EXPANSION PROJECT

LNG EPC – PT MEINDO ELANG INDAH – 1183573

COMMENT RESOLUTION SHEET

DOCUMENT NUMBER DOCUMENT TITLE REV. CODE ISSUE STATUS DOCUMENT STATUS
870310-S-1183573-CST-G99-0004 Concreting Method Statement 02 Issue For Review B

SUPPLIER
NO COMMENTS ORIGINATOR REASONS NAME &TITLE SECTION AFFECTED COMMENT STATUS
RESPONSE
Additional split of material item Epoxy grout and
non-shrink grout , For equipment & structure base
A. Agreed, Comment will Putut Eko /
1 plate by other sub-cont , For civil purpose ( with SI Johannes Agus Page 13 Agreed - Closed
be implemented Site Engineer
from CSTS, if not mentioned in contract ) by sub-
cont.
Additional split of material item Curing compound (
A. Agreed, Comment will Putut Eko /
2 if any )_item 23 and acid coating protection_item Johannes Agus Page 13 Agreed - Closed
be implemented Site Engineer
24. by sub-cont.

Change Sub-cont instead Contractor and A. Agreed, Comment will Putut Eko /
3 Johannes Agus Page 16 Agreed - Closed
Contractor's instead Company's be implemented Site Engineer

A. Agreed, Comment will Putut Eko /


4 Change Table 4 instead Table 5 Johannes Agus Page 26 Agreed - Closed
be implemented Site Engineer

A. Agreed, Comment will Putut Eko /


5 Additional value -10 and -13 at tolerance column Johannes Agus Page 34 Agreed - Closed
be implemented Site Engineer

A. Agreed, Comment will Putut Eko /


6 Change Embedment instead Concrete at table 9 Johannes Agus Page 35 Agreed - Closed
be implemented Site Engineer

Change CONTRACTOR instead COMPANY and A. Agreed, Comment will Putut Eko /
7 Johannes Agus Page 36 Agreed - Closed
CONTRACTOR'S instead COMPANY'S be implemented Site Engineer
Change CONTRACTOR instead COMPANY and
A. Agreed, Comment will Putut Eko /
8 SUB-CONTRACTOR ( USI Concrete Supplier ) Johannes Agus Page 37 Agreed - Closed
be implemented Site Engineer
instead CONTRACTOR
Additional CONTRACTOR appointed A. Agreed, Comment will Putut Eko /
9 Johannes Agus Page 37 Agreed - Closed
representative be implemented Site Engineer

© BP p.l.c. Page 1 of 1 Project Internal


Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

Revision History
Amendment Revision Amender Name Amendment
Date Number

Related documents
Document Document name Description of Content
number

TEP-1183573-G99-0004 Page 5 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

1 INTRODUCTION

1.1 Project Overview


BP Berau Ltd., hereafter known as COMPANY, is the operator of Tangguh LNG, a two train natural gas
(NG) liquefaction facility in Bintuni Bay, Papua, Indonesia. The facility includes associated onshore
infrastructure, two offshore platforms, pipelines and twelve wells. These facilities are the Trains 1 and 2
development at Tangguh.
COMPANY has initiated the Tangguh Expansion Project to commercialise the incremental resource into
high margin gas markets based on a single LNG (liquefied natural gas) train expansion (Train 3).
Tangguh Expansion Project will consist of new offshore facilities, including wellhead platforms and
pipelines, and onshore development on the existing Tangguh brownfield site. The new onshore facilities
will include one additional natural gas liquefaction train of a similar design and capacity to the existing
trains, an onshore receiving facility (ORF), new LNG and condensate loading berth, additional boil off
gas (BOG) recovery, utilities, flares and the infrastructure to support logistics and the associated
increase in the temporary and permanent workforce.
The Tangguh Expansion Project comprises of the following new facilities:
 [New] Onshore Receiving Facilities (ORF)
 [New] LNG Train 3
 [New] Condensate Stabilization Train 3
 [New/Inter connection] Plan Utility Facilities
 [New] LNG Loading System
 [New] Condensate Loading System
 [Expansion] Integrated Control and Safety System (ICSS)
 [Expansion] Telecommunication System
 [New] Trestle Jetty Structure
 [Expansion] Onshore Infrastructure
 Hazardous and Non-hazardous Waste Management System
PT.MEINDO ELANG INDAH, hereafter known as SUBCONTRACTOR has been awarded by
CONTRACTOR (unincorporated Joint Operation established by Chiyoda Corporation, PT. Chiyoda
International Indonesia, PT. Saipem Indonesia, PT. Tripatra Engineers and Constructors, PT. Tripatra
Engineering, PT. Suluh Ardhi Engineering hereinafter called “CSTS” interchangeably) for the OSBL
General Civil Work of Tangguh Expansion Project.

2 SCOPE

2.1 General
This specification covers the requirements for design and construction of Concreting Work within the
scope of work of Tangguh LNG Expansion Project – ORF, Product Storage, Product Loading,
Infrastructure and Existing Facilities.

2.2 Specific Design Conditions


Design conditions for this project including site conditions, basis of elevation, materials and other
matters depending on the local conditions, local regulations and project requirements are indicated on
TEP-900-SPE-CV-BP4-0005 Project Specification for Reinforced Concrete and Grouting Work .

TEP-1183573-G99-0004 Page 6 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

3 Normative Reference
The following documents are referenced in one or more requirements in this document. For dated
references, only the version cited applies. For undated references, the latest version of the referenced
document (including any amendments) applies.
Local Codes and Standards

No Doc Number Description

Persyaratan Beton Struktural untuk Bangunan Gedung (Building


1 SNI 2847: 2013
Code Requirements for Structural Concrete).
Agregat beton, Mutu dan Cara Uji (Aggregates for Concrete,
2 SNI 03-1750-1990
Specification and Test Method)
Tata Cara Pengadukan dan Pengecoran Beton (Code for Mixing
3 SNI 03-3976-1995
and Pouring of Concrete)
4 SNI 03-6880-2002 Spesifikasi Beton Struktural (Specification of Structural Concrete)
Jaring Kawat Baja Las untuk Tulangan Beton (Steel Wire Netting
5 SNI 07-0663-1995
for Concrete Reinforcement Bars)
6 SNI 07-2052-2002 Baja Tulangan Beton (Concrete Reinforcement Steel Bars)
7 SNI 15-2049-2004 Semen Portland (Portland Cement)
8 SNI 15-3758-2004 Semen Masonry (Masonry Cement)
9 SNI 1972:2008 Cara Uji Slump Beton (Test Method for Slump of Concrete)
Tata Cara Pengambilan Contoh Uji Beton Segar (Standard
10 SNI 2458:2008
Practice for Sampling Freshly Mixed Concrete)
11 SNI 15-0129-2004 Semen Portland Putih (White Portland Cement)

American Concrete Institute (ACI)

No Doc Number Description

Specifications for Tolerances for Concrete Construction and


1 ACI 117M-10
Materials and Commentary
2 ACI 201.2R Guide to Durable Concrete
Standard Practice for Selecting Proportions for Normal,
3 ACI 211.1
Heavyweight, and Mass Concrete
Standard Practice for Selecting Proportions for Structural
4 ACI 211.2
Lightweight Concrete
ACI 212.3R-10 :
5 Report on Chemical Admixtures for Concrete
212.3R-10
6 ACI 222R Protection of Metals in Concrete against Corrosion
7 ACI 224R Control of Cracking in Concrete Structures
8 ACI 301M-10 Specifications for Structural Concrete
9 ACI 302.1R Guide for Concrete Floor and Slab Construction
10 ACI 304R Guide for Measuring, Mixing, Transporting and Placing Concrete

TEP-1183573-G99-0004 Page 7 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

No Doc Number Description

11 ACI 304.2R Placing Concrete by Pumping Methods


12 ACI 305R Guide to Hot Weather Concreting
13 ACI 306R Guide to Cold Weather Concreting
14 ACI 308M-11 Specifications for Curing Concrete
Standard Practice for Details and Detailing of Concrete
15 ACI 315
Reinforcement
Building Code Requirements for Structural Concrete and
16 ACI 318M-11
Commentary
17 ACI 343R Analysis and Design of Reinforced Concrete Bridge Structures
18 ACI 347 Guide to Formwork for Concrete
Guide to the Concrete Capacity Design (CCD) Method -
19 ACI 349.2R
Embedment Design Examples
Code Requirements for Environmental Engineering Concrete
20 ACI 350R
Structures and Commentary
Seismic Design of Liquid-containing Concrete Structures and
21 ACI 350.3
Commentary
Report on Grouting Between Foundations and Bases for the
22 ACI 351.1R
Support of Equipment and Machinery
23 ACI 351.2R Report on Foundations for Static Equipment
24 ACI 351.3R-04 Foundations for Dynamic Equipment
Qualification of Post-Installed Mechanical Anchors in Concrete
25 ACI 355.2
and Commentary
Guide for Design of Anchorage to Concrete- Examples Using ACI
26 ACI 355.3R
318 Appendix D
Qualification of Post-Installed Adhesive Anchors in Concrete and
27 ACI 355.4M - 11
Commentary
28 ACI 504R Guide to Sealing Joints in Concrete Structures
29 ACI SP-15 Field Reference Manual Specifications for Structural Concrete
30 ACI SP-66 ACI Detailing Manual
31 ACI MCP Manual of Concrete Practice

ASTM International (ASTM)

No Doc Number Description

1 ASTM A36/A36M Standard Specification for Carbon Structural Steel


Standard Practice for Making and Curing Concrete Test
2 ASTM C31-12
Specimens in the Field

Standard Practice for Selecting Proportions for Normal,


ACI 211.1
3 Heavyweight, and Mass Concrete

TEP-1183573-G99-0004 Page 8 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

No Doc Number Description

4 ASTM C33/C33M-13 Standard Specification for Concrete Aggregates

Standard Test Method for Compressive Strength of Cylindrical


5 ASTM C39M-14a
Concrete Specimens

6 ASTM C94/C94M-14b Standard Specification for Ready-Mixed Concrete

Standard Test Method for Compressive Strength of Hydraulic


7 ASTM C109/C109M
Cement Mortars (using 2-in. or [50-mm] cube specimens).

8 ASTM C143/C143M Standard Test Method for Slump of Cement Concrete

9 ASTM C150/C150M-12 Standard Specification for Portland Cement

10 ASTM C171-07 Standard Specification for Sheet Material for Curing Concrete

11 ASTM C172/C172M Standard Practice for Sampling Freshly Mixed Concrete

12 ASTM C191 Test for Time of Setting Hydraulic Cement by Vicat Needle

Standard Specification for Liquid Membrane-Forming Compounds


13 ASTM C309-11
for Curing Concrete

14 ASTM C494-13 Standard Specification for Chemical Admixtures for Concrete

Standard Test Method for Splitting Tensile Strength of Cylindrical


15 STASTM C496-11
Concrete Specimens
Standard Test Methods for Compressive Strength of Chemical
16 ASTM C579
Resistant Mortars, Grouts.
Standard Specification for Blended Hydraulic Cements Monolithic
17 ASTM C595/C595M
Surfacing and Polymer Concretes.
Standard Specification for Coal Fly Ash and Raw or Calcined
18 ASTM C618-12a
Natural Pozzolan for Use in Concrete.
Standard Test Method for Change in Height at Early Ages of
19 ASTM C827-10
Cylindrical Specimens of Cementitious Mixtures
Standard Test Method for Compressive Strength of Concrete
20 ASTM C873-10a
Cylinders Cast in Place in Cylindrical Moulds.
Standard Test Method for Length Change of Hydraulic-Cement
21 ASTM C1012
Mortars Exposed to Sulfate Solution
Standard Test Method for Temperature of Freshly Mixed
22 ASTM C1064-12
Hydraulic-Cement Concrete
Standard Specification for Packaged Dry, Hydraulic-Cement Grout
23 ASTM C1107/C1107M
(Non shrink)
Standard Specification for Mixing Water Used in the Production of
24 ASTM C1602
Hydraulic Cement Concrete

Standard Test Methods for Vulcanized Rubber and Thermoplastic


25 ASTM D412
Elastomers-Tension

TEP-1183573-G99-0004 Page 9 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

No Doc Number Description

Standard Specification for Preformed Expansion Joint Filler for


26 ASTM D1751 Concrete Paving and Structural Construction (Nonextruding and
Resilient Bituminous Types)
Standard Specification for Preformed Sponge Rubber Cork and
27 ASTM D1752 Recycled PVC Expansion Joint Fillers for Concrete Paving and
Structural Construction
Standard Specification for Joint Sealants, Hot Applied, Jet Fuel
28 ASTM D7116
Resistance Types, for Portland Cement Concrete Pavements
Standard Specification for Preformed Polychloroprene Elastomeric
29 ASTM D2628
Joint Seals for Concrete Pavements
Standard Specification for Lubricant for Installation of Preformed
30 ASTM D2835
Compression Seals in Concrete Pavements
Specification for Joint Sealant, Hot-Applied, Elastomeric-Type, for
31 ASTM D3406
Portland Cement Concrete Pavements
Standard Specification for Cold Applied, Single Component,
32 ASTM D5893 Chemically Curing Silicone Joint Sealant for Portland Cement
Concrete Pavements

Project Specification and Report

No Doc Number Description

1 TEP-900-DBS-CV-BP4-0001 Onshore Civil and Structural Design Basis

4 Term and Definitions


For the purpose of this Specification, the following terms and definitions apply:
COMPANY
BP Berau Ltd., an associate or subsidiary, or other organisation acting as owner, purchaser, or
customer as designated in the Purchase Order.
COMPANY RESPONSIBLE ENGINEER
Company engineer responsible for the technical requirements of the item.
CONTRACTOR
The organization named CSTS who responsible to carry out a proposal engineering works at FEED
Stage and continue to EPC Works after awarded by Company.
SUB CONTRACTOR
Any person, company, manufacturer or supplier of equipment including Vendors’ services for erection,
training and commissioning of any such equipment.
SUPPLIER
Entity entering into a contract with Company to provide materials, goods, supplies, equipment, or plant
and includes the successors and (or) permitted assigns of such entity.
SHALL
Mandatory

TEP-1183573-G99-0004 Page 10 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

SHOULD
Discretional

5 Symbols and Abbreviations


For the purpose of this Specification, the following symbols and abbreviations apply:
ITP Inspection and test plan
PO Purchase Order
QA Quality assurance

6 Risk Assessment
Before site project execution, it is require to perform an assessment to identify the risk level that will
appear during site project execution, every step of job have its own risk, therefore early identification of
risk shall be done in order to support the overall project execution.
Below step shall be done in order to identify the risk level :
- Gathering information and identify the issue
- Assessment to all facts
- Action plan based on assessment
- Communication of action plan
- Implementation
- Monitoring

7 General Requirement
Concrete supply and construction shall be in accordance with all requirements of ACI 301, except as
modified or supplemented in this specification or by the contract documents.
The following ACI documents are acceptable practices and may be helpful in meeting requirements of
this specification and ACI 301-05, i.e.: ACI 211.1, ACI 211.2, ACI 302.1R, ACI 304.2R, ACI 306R, ACI
308R, ACI 347, ACI 504R, ACI SP-15.

8 Roles and Responsible

8.1 Construction Manager


He responsible to manage site facilities and utilities as required during construction works or as per
project condition, communicate with CONTRACTOR site representative about related issue of the work.
Prepare, support and maintain requirement of all construction activities. Coordinate with Client and in-
house related field counter parts.

8.2 Site Engineer


He responsible to ensure that the work of cleaning, grading, cutting, filling and compaction operations
are done as per COMPANY requirement and specification.

TEP-1183573-G99-0004 Page 11 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

8.3 Construction Supervisor


Perform construction activities according to the latest drawing, specification and procedure. Perform the
construction activities as are pre construction schedule. Manage the construction equipment utilized
properly and effectively. Ensure that the work follow the proper safety work method, regulation and
requirements.

8.4 HSE Officer


The HSE Officer shall be responsible for implementation of the HSE plan and compliance with statutory
regulation.

8.5 Civil QC
A Civil QC shall perform daily inspection on earth work activity, conduct joint inspection with COMPANY
representative and prepare inspection report as required.

9 Product and Materials

9.1 General
Unless authorized in writing by COMPANY, materials that are not in accordance with this specification
or the contract documents shall not be permitted.
Materials shall be in accordance with applicable local volatile organic compound regulations.

9.2 Split of Material


Table 1 – Split of Material

NO MATERIAL CTR SUB-CTR REMARKS

1 Cement X Part of mortar concrete


2 Aggregate X Part of mortar concrete
3 Reinforcement X
4 Water X
Admixture X Plasticizer &
5
waterproofing
6 Formwork X
7 Concrete X
8 Bonding Agent X
9 Moisture Barrier X
Surface Dustproofing and X
10
Hardening
11 Surface Oil - Proofing X
12 Joint Primer X
13 Joint Sealant X
14 Bond Breaker X

TEP-1183573-G99-0004 Page 12 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

NO MATERIAL CTR SUB-CTR REMARKS

15 Waterstop X
Liquid chemical curing X
16
compounds
17 Polyethylene Film X
18 Absorptive mats X
19 Epoxy Grout X X For equipment &
structure base plate by
other sub-cont.
20 Non-shrink Grout X X For civil purpose ( with SI
CSTS, if not mentioned in
contract )
21 Standard PC Grout X
22 Reinforcing & Embedment X
23 Curing compound ( if any ) X
24 Acid coating protection X

9.3 Cement
Unless otherwise specified in the contract documents, Portland cement shall be in accordance with SNI
15-2049-2004, Type I or Type V.
Type-I cement shall be used for all concrete works not in contact with soil or water.
Type-V cement shall be used for concrete works in contact with soil or water, such as footing, septic
tank, ditches, paving slab, curb, trenches, pile, pile cap, ground beam etc.
Unless otherwise specified in the contract documents, fly ash may be used in accordance with ACI 301
and shall conform to ASTM C 618, Class C or Class F. If Class C fly ash is used in a moderately to
extremely aggressive sulphate environment, the mix design shall be tested in accordance with ASTM C
1012 to verify sulphate resistance.

9.4 Aggregate
Aggregate shall be in accordance with ASTM C 33. Fine and coarse aggregates from different sources
of supply shall not be mixed or stored in the same stockpile. All aggregates used for the same structure
shall be obtained from one source.
All aggregate shall be clean, inert, hard, non-porous and free from excessive quantities of dust,
laminated particles and splinters.
The proportion of thin or elongated pieces having lengths greater than five times the average thickness
shall not exceed 15%. Fine Aggregate shall consist of clean, washed, natural or crushed sand of
uniform gradation. Coarse Aggregate shall consist of washed gravel or washed crushed stone, having
hard, strong, durable piece, free from adherent coating, or other weak, deleterious substances.
Maximum size of coarse aggregate shall be 20 mm for general use and 10 mm for fireproofing.
The source of material shall not be changed without written approval.

9.5 Reinforcement
Unless otherwise specified in the contract documents, deformed reinforcing bars shall be in

TEP-1183573-G99-0004 Page 13 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

accordance with SNI 07-2052-2002 grade BjTS 40 with minimum yield strength fy = 390 MPa. Plain
Reinforcing bars shall conform to SNI 07-2052-2002 BjTP 24 with minimum yield strength fy = 235
MPa.
Welded wire fabric shall be plain or deformed wire fabric and in accordance SNI 07-0663-1995 with
minimum yield strength 490 MPa.
Steel strand for pre-stressed concrete shall conform to ASTM A416 Grade 250 or 270 as shown the
drawings.
Tie wire shall be black annealed wire, 16 gage minimum.
Unless otherwise specified in the contract documents, all reinforcing shall be uncoated.
Additionally, reinforcement designed to resist earthquake-induced flexural and axial forces in frame
members and in wall boundary elements shall fulfil the following conditions:
 The actual yield strength based on mill tests does not exceed the specified yield strength by more
than 124 MPa. Retests shall not exceed this value by more than an additional 20.7 MPa.
 The ratio of the actual ultimate tensile strength to the actual tensile yield strength is not less than
1.25.

9.6 Water
Water used for mixing water, curing, or any other function relating to placement of concrete shall
comply with the requirements of ASTM C1602. Other water may be used if tested for suitability in
accordance with ASTM C94/C94M. Water shall be free from injurious amounts of oil, acid, salt, alkali,
organic matter, and other deleterious substances. Seawater shall not be used for mixing concrete.
Wash water from mixer washout operations shall not be used as mixing water.
If galvanized and/or aluminium material is embedded in concrete, water for concrete mix shall not have
more than 200 ppm of chloride ions.

9.7 Admixture
Admixtures shall conform to the requirements given in ACI 212.3R, 212.4R, ASTM C260 (liquid air-
entraining admixture), ASTM C494 (water reducing and retarding), ASTM C618 or ASTM C1017.
Admixtures containing calcium chloride or soluble chlorides shall not be used. Only one manufacturer
for each admixture shall be used. Admixture shall not be used to replace cement. The CONTRACTOR
shall demonstrate the suitability of admixtures for their intended purposes.
Roof concrete and trenches with concrete floors shall have waterproofing additives, subject to
COMPANY approval.

9.8 Formwork
Forms shall be suitable for the work to be performed and may be of dressed lumber, plywood, metal, or
other suitable materials.
Plywood forms should be grade marked Exterior Grade with minimum thickness of 12 mm. Metal Forms
should use smooth metal plate free of surface irregularities.
Form ties should be factory fabricated snap-off metal type of adequate design to minimize form
deflection and preclude concrete spalling upon removal.
Form ties should be fabricated so that set back in the concrete is such that the portion of the tie
remaining after snap-off and removal of the exterior portions is at least 3.8 mm back from the concrete
surface.
Form coating will be non-grain-raising and non-staining resin or polymer type that will not leave residual
matter on the surface of the concrete or adversely affect bonding to concrete of paint, plaster, mortar,
protective coatings, waterproofing or other applied materials. Coatings containing mineral oils, paraffin,
and other non-drying ingredients are not permitted. For concrete surfaces contacting potable stored

TEP-1183573-G99-0004 Page 14 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

water, the coatings and form release agents shall be completely non-toxic and approved by the EPA for
the intended use.

9.9 Concrete
The specified compressive strength of a designed mix shall be the 28 day compressive cylinder
strength. The minimum 28-day compressive strength, f’c, shall be in accordance with the contract
documents. If high early-strength concrete is specified, compressive strength shall be 7-day strength.
Unless as otherwise provided in this specification, ready-mixed concrete shall conform to ASTM
C94/C94M, Alternative No. 2, which requires the Supplier to assume full responsibility for the selections
of the proportions of the concrete mixture.
Unless otherwise specified in the contract documents, maximum water-soluble chloride ion
concentrations in hardened concrete shall be 0.30 % by weight of cement, in accordance with ACI 301-
05, Table 4.2.2.6, for other reinforced concrete construction.

9.10 Concrete Accessories

9.10.1 Bonding Agent


Subject to compliance with requirements, products that may be incorporated in the Work include, but
are not limited to the following:
1. Polyvinyl Acetate
a. Euco Weld; Euclid Chemical Co.
b. Rheomix 121; Master Builders, Inc.
c. P.V.A 9910; Cormix Construction Chemicals Co.
d. P.V.A; Falcon Chemicals.
2. Acrylic or Styrene Butadiene
a. Sika Latex; Sika Corp.
b. SBR Latex; Euclid Chemical Co.
c. Daraweld C; W.R. Grace & Co.
d. Rheomix 141; Master Builders, Inc.

9.10.2 Moisture Barrier


Moisture barrier shall be 6 mil (0.15 mm) polyethylene films. Seams shall be lapped 150 mm.

9.10.3 Surface Dustproofing and Hardening


Liquid surface treatment for dustproofing or hardening concrete paved areas shall be Fosroc "Nitoflor
Lithurin".

9.10.4 Surface Oil - Proofing


Liquid surface treatment for oil-proofing concrete paved areas shall be Fosroc "Concure CR".

9.11 Joint

9.11.1 Joint Filler


Joint filler strips for expansion joints shall not extrude when compressed and must return to at least
70% of their original thickness after compression and shall conform to ASTM D994 (bituminous

TEP-1183573-G99-0004 Page 15 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

impregnated fibreboard), ASTM D1751 (asphalt impregnated cork, with asphalt saturated glass-fibre felt
liners), or ASTM D1752. Joint filler shall be 12.5 mm thick minimum unless otherwise shown on the
drawings.

9.11.2 Backup Material


ASTM D1056, round closed cell foam rod, oversized 30 to 50 % larger than joint width.

9.11.3 Joint Primer


A two-components penetrating liquid urethane based primer, for use with urethane and epoxy sealant.

9.11.4 Joint Sealant


Joint sealant materials and their application shall conform to ASTM D2628, ASTM D2835, ASTM
D3406, or ASTM D5893.
Expansion and isolation joints shall be self-levelling, two-components polyurethane sealant conforms to
ASTM D1751.
Control and construction joints: Corrosion resistant, two-component resin hardener for joints cut with
Soft-Cut saws.

9.11.5 Bond Breaker


Bond breaker shall be polyethylene tape 2 mils (0.05 mm) thickness minimum.

9.11.6 Waterstop
Waterstop shall be polyvinyl chloride with high polymer resins, 150-mm heavy duty ribbed, with centre
bulb or Heavy Duty Dumb-Bell type in accordance with ASTM D412, or as shown on the drawings.

9.12 Curing Compounds and Accessories


In areas that require VOC (Volatile Organic Compounds) compliance for curing compounds, SUB -
CONT shall select a product and submit for CONTRACTOR approval.

9.12.1 Liquid Membrane Curing Compounds


ASTM C309, Type I, ID, Class A and B; shall be water clear, styrene acrylate type, and minimum solid
content 30%. Maximum moisture loss shall not exceed 0.55 kg/m2 in 72 hours when applied at a
coverage rate of 18.5 m2 per gallon. Application rate shall not exceed that as stated by the
manufacturer, which shall meet the moisture retention requirements.

9.12.2 Liquid Chemical Curing Compounds


ASTM C309, Type I, ID, Class A and B, have minimum solid content of 14%.

9.12.3 Polyethylene Film


ASTM C171, 0.10 mm (4 mil) thick, clear, white opaque colour or black.

9.12.4 Absorptive mats


ASTM C171, cotton fabric or burlap-polyethylene, minimum 305 g/m2, bonded to prevent separation
during handling and placing.

TEP-1183573-G99-0004 Page 16 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

9.13 Anchor and Embedment


Embedded plates, angles, channels, etc. shall conform to ASTM A36.
Concrete drilled anchors shall be galvanized chemical anchors or expansion anchor manufactured by
HILTI. Diameters shall be as shown on drawings. Anchors shall be installed in accordance with the
manufacturer's recommendations

9.14 Grout

9.14.1 Epoxy Grout


The epoxy grout shall be non-metallic and formulated with thermosetting resins and inert fillers. The
cured grout shall be unaffected by oils, synthetic lubricants, water, or chemical. Epoxy Grout shall be,
self-levelling, non-staining, no-shrinkage, high vibration & impact resistance, and good adhesion to
concrete and steel. Epoxy grout shall have a minimum working time of 45 minutes at 24oC. The non-
shrink epoxy grout shall show no shrinkage (0.0 %) and a maximum of 4.0 % expansion at all ages
when tested in accordance with ASTM C827 (modified). The volume change of epoxy grout tested in
accordance with ASTM C827 (modified) requires an indicator ball with a specific gravity between 0.9
and 1.1. The grout shall be flow able.
The ultimate compressive strength of any epoxy grout material shall be a minimum of 35 MPa at 24
hours and 97 MPa at 28 days when tested according to ASTM C579, Method B, and tested at the
equipment operating temperature and loads.

9.14.2 Non-shrink Grout


Non-shrink, self-levelling, non-staining grouts are composed of aggregate and expanding binder or
expanding aggregate and stable binder. Non-shrink Grout shall comply with ASTM C1170. The
ultimate compressive strength shall be a minimum of 20 MPa at 24 hours and 55 MPa at 28 days.

9.14.3 Standard Portland Cement Grout


The mixture shall be of one part Portland cement and two parts clean fine sand. Compressive strength
shall not be less than the compressive strength of the foundation concrete.

10 Execution Requirement

10.1 General
Storage, handling, measuring, mixing, transporting, and placing of concrete materials shall follow the
methods and means outlined in ACI 304R and comply with manufacturer’s recommendation for
handling, storage, and protection.

10.2 Formwork
The design and construction of the formwork shall be in accordance with ACI 347R Manual, and shall
be the responsibility of the SUB-CONTRACTOR.
Formwork shall be designed, erected, supported, braced, and maintained so that it will sustain all
vertical and lateral loads until such loads can be supported by the concrete structure itself. Forms shall
have sufficient strength to withstand the wind loads, pressure resulting from placement and vibration of
the concrete, the loads and operations incidental to placing and curing the concrete, as well as other
forces resulting from the movement of the forms, and shall have sufficient rigidity to maintain specified
tolerances. Forms and their supports shall be designed so as not to damage previously placed
concrete. The forms shall be sufficiently tight to prevent leakage of cement paste and shall be so
constructed that the surfaces of the finished concrete will be reasonably free from ridges, fins, offsets,
or similar defects. The forms material for concrete material expose to view shall produce smooth, hard

TEP-1183573-G99-0004 Page 17 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

and uniform texture on the concrete unless different texture requirement shown on the drawings, and
shall be free of defects likely to cause imperfections on the surface of the concrete. The formwork shall
be true in every respect to produce hardened concrete to the required shape, dimensions, grade, and
alignment as indicated on the Drawings. Forms shall be constructed to facilitate their removal without
damage to the concrete and so that their removal can.be in the following orders: (1) columns, (2) sides
of beams and girders, (3) bottoms of slabs, beam and girders.
Formwork shall be provided to the top faces of sloping works where the slope exceeds 15o from the
horizontal. Positive means of adjustment (wedges, jacks, etc.) of shores and struts shall be provided
and all settlement shall be taken up during concrete placing operation.
Forms shall be securely braced against lateral deflections. Adjustable type shoring can be used for
supporting roof forms or elevated floors.
Form accessories that remain embedded in the concrete (e.g., ties and hangers) shall be a
commercially manufactured type.
All side and bottom surfaces of structures that will be exposed shall be formed. Vertical surfaces of
subgrade structures and pavements shall be formed at least to a depth of 300 mm below grade, unless
otherwise approved by COMPANY. The concrete below this level may be placed against earth.
Chamfer strips shall be placed in the corners of forms to produce 20 mm chamfer bevelled edges on
permanently exposed surfaces. Chamfer strips are not required on interior corners of such surfaces, the
edges of formed joints, tops of piers supporting horizontal vessels, and concrete edges providing direct
support for flooring, or to which steel will be attached for flooring support.
Temporary openings shall be provided at the base of column forms and wall forms and at other points
where necessary to facilitate cleaning and inspection immediately before concrete is placed.
All surfaces of forms and embedded materials shall be cleaned of all accumulated mortar or grout from
previous concreting and of all other foreign material before concrete is placed.
Form material which is to be reused shall have damaged parts repaired and the concrete side
thoroughly cleaned before reusing. Forms shall not be reused if there is any evidence of surface wear
and tear or defects which would impair the quality of the surface.
Before placing the reinforcing steel or the concrete, the surfaces of the forms shall be covered with an
acceptable coating material that will effectively prevent absorption of moisture, prevent bond with the
concrete, and not stain the concrete surfaces. A field applied form release agent or sealer of acceptable
type or factory applied non-absorptive liner may be used. Care shall be taken that the parting agent
does not get on concrete or reinforcement, which is to bond with new concrete.
Form-release agents shall not be applied if concrete surfaces receive special finishes or where the
agent may affect applied coverings. Alternately, inside surfaces of untreated formwork shall be soaked
with clean water and kept moist before placing concrete.
Removal of forms and supports shall be in accordance with ACI 347.
When repair of surface defects or finishing is required at an early age, forms shall be removed as soon
as the concrete has hardened sufficiently to sustain the load and resist damage from removal
operations.
Formwork for columns, walls, sides of beams and other parts not supporting the weight of the concrete
may be removed as soon as the concrete has hardened sufficiently to resist damage from removal
operations.
Forms and shoring in the formwork used to support the weight of concrete in beams, slabs and other
structural members shall remain in place until the concrete has reached the required strength to support
the weight of concrete and anticipated imposed loads. Field-cured specimens shall be used to estimate
the strength of concrete. When field-cured specimens cannot be used to determine the time of the form
removal, forms and shoring shall be remain in place for a period of time not less than that specified in
ACI 347R/ ACI 301.

TEP-1183573-G99-0004 Page 18 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

Table 1 - Formwork Removal

No Structure Member Time Remarks

1 Walls 12 hours the concrete strength


is at least 25 % of the
2 Columns and Pedestals 12 hours specified 28-day
3 Sides of Beams, Girders and Footings 12 hours strength

4 Bottom of slabs 14 days

No Structure Member Time Remarks


5 Joist, Beam or Girder Soffits : the concrete strength
is at least 80 % of the
Beams perpendicular to Main Pipe 14 days specified 28-day
Track or Equipment Supporting strength
Other Beams 21 days

Results of suitable control tests shall be used as evidence that concrete has attained sufficient strength
to permit removal of supporting forms.
Forms shall not be left permanently in place, unless otherwise authorized by COMPANY.
When forms are removed before the end of the required curing period, the concrete shall be cured after
removal of the forms by suitable methods.

10.3 Reinforcing and Embedments

10.3.1 Detailing and Fabrication


Reinforcement placing drawings and bending schedules shall be prepared in accordance with ACI SP-
66. Drawings and schedules shall show number, grade, size, length, mark, location, and bending
diagrams for reinforcing bars. Fabrication drawings shall indicate the related PO number, release
number, and design drawing number.
Reinforcement shall be tagged with weather-resistant metal tags. Each bundle of fabricated bars shall
be tagged. The tags shall indicate drawing number, release number, mark number, grade, bar quantity,
and bar size. Each bundle of stock-length straight bars shall be tagged to indicate bar quantity, grade,
bar size, and bar length.
Splices in reinforcement shall be detailed, fabricated, and located as shown on the drawings only. If
splicing of bars other than shown on the detail drawings is found to be necessary, details of the
proposed splices shall be submitted to COMPANY for approval. Such splices shall be staggered. The
splice length should be in accordance with Contract Documents. Splice length for unequal size bars (or
wires in fabric) may be based upon the smaller bar.
Reinforcement bars shall be cut and bent to the dimensions shown on the Schedules.
All cutting of reinforcement bars shall be carried out using a high speed abrasive cutting wheel, friction
saw or other mechanical method approved by the COMPANY. Cutting by torch will not be permitted
without the prior approval of the COMPANY.
Reinforcement shall be bent cold by the gradual and uniform application of pressure so that they are
not damaged, except that where approved by COMPANY bars may be heated to a heat not exceeding
450°C. Bars bent hot shall not be cooled by quenching.
Straightening or re-bending of reinforcement shall not be carried out unless approved by COMPANY.
Where it is necessary to bend mild steel reinforcement projecting from concrete, the internal radius of
bend shall not be less than twice the diameter of the bar.

TEP-1183573-G99-0004 Page 19 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

Reinforcement with rust shall be considered satisfactory, provided the minimum dimensions (including
height of deformations) and weight of a hand-wire-brushed test specimen aren't less than applicable
ASTM specification requirements.

10.3.2 Concrete Cover


Except otherwise noted on the drawings, the minimum concrete cover shall refer to TEP-900-DBS-CV-
BP4-0001 “Onshore Civil and Structural Design Basis” as recited herein.

Table 2 – Concrete Cover

No
Description Remarks

Concrete exposed to adverse environmental conditions, 75 mm


1 such as wash down water or process spillage

2 Concrete cast against and permanently exposed to earth 75 mm


3 Concrete exposed to earth or weather 50 mm
Concrete not exposed to earth, other than slab, wall and 40 mm
4
joist
5 Concrete slab, wall and joist not exposed to ground or water 20 mm

For the purpose of determining cover, all concrete elements with a protective coating shall be treated as
being not exposed to adverse environmental conditions. Concrete cover for pits shall be decided based
on their exposure categories and as per ACI 318.

10.3.3 Installation
Reinforcing bars, anchor bolts and other embedded items shall be free from mud, dirt, loose rust, loose
mill scale, oil, grease, and any other foreign coating that may reduce the bond between bars and
concrete.
Reinforcement shall be accurately placed in accordance with design drawings and secured in position
with concrete or metal chairs and spacers. Intersections and splices of reinforcement shall be securely
tied with annealed steel wire 16 gage or heavier and securely held in position during concrete placing.
All ties, links, stirrups etc. shall be taut, and the bars properly braced and tied. Bars in lapped splices
shall be in contact unless otherwise shown on the design drawings. Cementitious spacers shall be of
similar strength, durability, porosity and appearance to the surrounding concrete. Tie wire shall be
finished tight with free ends bent inwards away from formwork.
Unless specifically indicated on the design drawings, splicing by means of proprietary mechanical
splices shall not be used.
Reinforcing bars projecting from existing, hardened concrete may be bent or straightened, subject to
approval by COMPANY, and provided it is done in accordance with ACI 301-05 section 3.3.2.8.
Exposed reinforcing bars intended for bonding with future extensions shall be protected from corrosion
by concrete or other adequate covering. Type of covering requires written COMPANY approval.
Welded wire fabric used in structural concrete shall be supported, in the same manner as reinforcing
bars, to place the fabric in its proper location within the concrete member.
Anchor bolts, anchors, inserts, sleeves, drains, curb and seat angles, nosing, and other embedded
items shall be installed before placing concrete. Welding of these items to the reinforcing bars shall not
be permitted without COMPANY approval. Voids in those embedded items shall be filled temporarily
with readily removable material to prevent the entry of concrete into the voids. Other embedded items
shall be installed as shown on design drawings and they shall be supported against displacement

TEP-1183573-G99-0004 Page 20 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

during placement and consolidation of concrete. Anchor bolt sleeves shall be capped or plugged to
keep out water, concrete, and debris.
Embedded aluminium items shall not be permitted. Conduits, pipes and other items made from
aluminium shall not be embedded in structural concrete unless effectively coated to prevent aluminium-
concrete reaction.
Anchor bolt threads shall be protected from damage and kept free of concrete.

10.4 Joint
Joints not specified on the design drawings, shall be in accordance with ACI 301-05, Chapter 2 Section
2.2.2.5 and Chapter 5, Sections 5.1.2.3a, 5.2.2.1 and 5.3.2.6. ACI 504R, "Guide to Joint Sealants for
Concrete Structures" shall be used to prepare and select proper material for all installations.
The surface of the concrete at all joints shall be rough, thoroughly cleaned and all laitance shall be
removed prior to placing adjoining concrete. The laitance shall be removed by brushing, chipping, wet
sandblasting or high pressure water-blasting down to sound mortar matrix, leaving clean, sound
aggregate exposed over the entire joint surface, but not undercutting the large aggregate particles. The
surface of the concrete shall then be washed thoroughly to remove all loose material. All concrete joint
surfaces to receive new concrete shall be free of surface water but shall be in a saturated surface dry
condition.
Where shown on the drawings, joint sealant shall be applied according to the manufacturer’s
recommendations. The joint sealant shall not be thicker than half the width of the joint.

10.4.1 Construction Joint


Construction joints shall be made as shown on the drawings and per ACI 301. Construction Joints not
indicated on the construction drawings may be provide at SUBCONTRACTOR's option, except that
they must meet the requirements of ACI 301. Joints shall be perpendicular to the main reinforcement.
Construction joints shall not be made in horizontal framing members unless called for on the drawings.
Construction joints in elevated slabs should be located preferably at mid span between adjacent
supporting members. Paving or slab construction joints not specified on the drawings shall be located at
column centrelines and intermediate intervals.
Construction joints of which strength is critical against shear, or which requires water-tightness should
be covered with 12 mm mortar immediately before the concrete placing, or provided with keys having
1/3 width of the smallest joined member and 50 mm depth.
Formwork to provide vertical stop ends in reinforced concrete shall be firmly fixed and scribed around
reinforcement. Concrete which passes through the stops shall be hacked off and removed after setting.
When the concrete has reached an initial set, the surface of each joint shall be prepared by removing
the outer mortar skin using a stiff brush and a fine spray of water, to the extent that the large pieces of
coarse aggregate are exposed but not damaged or dislodged. If the concrete is hard, sand blasting,
wire brushing or scrabbling may be necessary. Alternatively, expanded metal mesh may be used, the
mesh being removed with care within 24 hours of casting to form a roughened surface.
The prepared joint surface shall be cleaned with compressed air or other equal method and then jetted
with clean water shortly before adjacent concrete is placed. Care shall be taken to compact new
concrete thoroughly against old.
Concreting abutting construction joints shall not take place until an initial set has occurred in the
previously cast concrete.

10.4.2 Expansion Joint/ Isolation Joint


Expansion joints shall be made as shown on the drawings and per ACI 301. Expansion joints shall
extend the full width and depth of the concrete section. The sealer application shall confirm to ASTM
D1190. Dowels at expansion joints shall be properly aligned to prevent any restraint on expansion
movement at the joint.

TEP-1183573-G99-0004 Page 21 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

solation joints shall be placed where the pavement adjoins vertical surfaces (e.g., walls, columns, catch
basins, manholes, and equipment foundations).
 Isolation joints shall be located in accordance with the contract documents.
 Isolation joints shall not be used to contain hydrostatic pressure.

10.4.3 Construction Joint/ Control Joint


Contraction joint shall be made straight and uniform by forming, tooling or sawing. All joints shall be
located and constructed in accordance with the contract documents. Any variation from the location
specified shall be approved by the COMPANY.
Contraction joints to be cut with a saw shall be cut as soon as the concrete is hard enough to prevent
surface ravelling and aggregate dislodging, and within 12 hours after concrete placement.
 Contraction joints shall be cut in accordance with the saw manufacturer’s written recommendations.
 Sawing sequence shall be based on pour time and size of slab.
Contraction joints in slab toppings shall be located directly above and in line with the contraction joints
in the underlying concrete slab.

10.5 Waterstops
Waterstops shall be installed in accordance with the contract documents and the manufacturer’s
recommendations.

10.6 Proportioning and Mixing

10.6.1 Trial Mixes


The CONTRACTOR shall undertake and complete a test programme of trial mixes prior to the
placement of any concrete in the works to establish the precise mixes and their proportions which are
necessary to produce the performance requirements of this Specification for each part of the works.
Trial mixes shall be prepared before Works commence preferably under full-scale production conditions
or, if this is not possible, in an approved laboratory using a sufficient number of samples to be
representative of the aggregates and cement to be used. If ready mix supplies are available by an
approved ready-mix concrete supplier then the CONTRACTOR shall provide proof, not less than 30
days prior to the use of the concrete, that the proposed mixes will satisfy the specification requirements.
Records shall be made available for assessment and only if these prove adequate then trial mixes need
not be undertaken.
Unless otherwise specified in the contract documents, the water/cement ratio should be not more than
0.4 for liquid-retaining (hydraulic) structures, 0.45 for underground concrete structure and 0.5 for above
ground reinforced concrete.
When admixtures are used, trial mixes to be tested to ensure that the admixture does not have an
adverse effect on the properties of the concrete. The tests shall be repeated whenever the source of
cement or aggregate is changed. Trial mixes shall be prepared for all grades of reinforced concrete to
be incorporated in the Works before any structural concrete is placed. Each trial shall be carried out
using the same materials, type of plant and equipment as will be used in the Works.
Three separate trial mixes shall be prepared for each grade of concrete and six preliminary test
cylinders shall be made from each trial mix, three for testing 7 days after causing and three for testing
after 28 days. The sampling, making, curing and testing of the preliminary test cylinders shall be carried
out.
Reinforced concrete mix proportions will be determined by trial method and the final proportions will be
approved and will not be changed when:
1. The average strength on the nine cylinders at 28 days is not less than the specified
2. The difference above or below the mean strength is not more than 7 MPa.

TEP-1183573-G99-0004 Page 22 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

3. The standard deviation is less than 3.5 MPa.


The workability of each batch of the trial mixes shall be determined by slump test as described in ASTM
C143, or by an alternative agreed method. The free water/cement ratio shall be the minimum possible
having regard to the proposed method of compaction. The slump and compacting factor, when
measured in accordance with ASTM C143, shall be within the range ± 25 mm and ± 0.03 respectively,
of the optimum values.
The trial mix proportions maybe provisionally approved on the basis of the 7 day Design Strength
results. However, it remains the responsibility of the CONTRACTOR to ensure that the minimum
specified strength for each type of mix at 28 days will be achieved.
When the mix for each grade of concrete has been approved, no variation shall be made in the
proportions, the original source of cement or aggregate, or in the type, size and grading of the latter,
without the agreement of the COMPANY who may require further trial mixes to be prepared.
When the CONTRACTOR is satisfied by trial mixes or otherwise that he can achieve the performance
requirements of this Specification then he shall submit complete details of mixes and samples of fine
and course aggregates to the COMPANY for his examination and records.
No change shall be made to the mixes without the approval of the COMPANY. No concrete shall be
placed until such time as conclusive proof has been provided that the proposed mixes will produce
concrete of the required characteristics. Conclusive proof of the minimum characteristic compressive
strength shall mean the compressive test of a 28 day laboratory-cured test specimen.
The selection, proportioning and mixing of concrete materials shall be such as to produce a mix which
works readily into corners and angles of the forms and around reinforcement with the method of
placement employed on the work, but without permitting the material to segregate or excess free water
to collect on the surface. Special mix proportions for pumped concrete shall be submitted to the
COMPANY as appropriate.
The COMPANY reserves the right to enter the ready mix supplier's plant for the inspection of the plant
and materials and to take independent samples for testing.

10.6.2 Batching and Mixing


The batch plant shall be equipped with facilities for storing, handling, proportioning and mixing
materials. All concrete batching and delivery equipment shall be certified. Materials may be stored in
either storage bins or stockpiles.
Batching and mixing of concrete shall be as recommended in ACI 301 for batch mixing at the site.
Proportioning of cement, aggregates, and dry admixtures shall be by weight. Proportioning of water and
liquid admixtures shall be by volume or by weight.
The mixer shall be washed out with fresh water before mixing the first batch or, alternatively, the first
mix shall be discarded. Concrete shall be thoroughly mixed to a uniform consistency for a minimum of
two minutes after all materials have been added. Concrete shall be discharged onto a level, clean,
watertight platform or floor or into watertight receptacles. Concrete which has commenced to set shall
not be re-mixed or used. After every stoppage the mixer shall be thoroughly cleaned and washed out.
The CONTRACTOR shall anticipate and make allowance for a reduction of air content attributable to
method and duration of mixing, length of haul to job site, condition and type of ready-mix truck used,
and other factors over which he has control, in order to provide air-entrained concrete of the required
quality.
Unless otherwise specified in the contract documents, the maximum size of coarse aggregate in
concrete shall be in accordance with ACI 301-05 and shall not be greater than the sizes shown in
section 9.3.
Unless otherwise directed by the COMPANY’s engineer, all admixtures shall be added at the batch
plant.
Concrete envelopes for underground electrical ducts and cover slabs for direct-buried cables shall be
coloured red by adding 10 kilograms of red oxide powder per cubic meter of concrete applied at top 50
mm of concrete duct bank, unless otherwise noted in the contract documents.
Unless otherwise approved by COMPANY, job-mixed concrete shall not be permitted.

TEP-1183573-G99-0004 Page 23 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

10.6.3 Slump and Consistency


Concrete shall be proportioned so as to comply with the requirements of Table 4. These values will be
used to judge consistency prior to the addition of plasticizers.
The quality of total mixing water shall be limited to an amount producing the lowest slump concrete that
can be properly consolidated under existing placing conditions.
Table 3 – Slump Requirements

No Type of Construction Slump ( mm )

1 Lean Concrete Backfill 75


2 Mass Concrete 50
3 Plain Footing, Caissons and Substructure Walls 75
4 Pavements and Slabs on Grade 75
5 Underground Duct Concrete 75
6 Fireproofing 75
7 Reinforced Foundations, Footings, Grade Slabs 75
8 Reinforced Slabs, Beams, Walls, and Columns 100
9 Exposed Roof Slabs 75
10 Water Retaining Structures 75

10.7 Transportation
Concrete shall be transported from Batch Plant to discharge locations by methods which prevent
segregation, loss, or contamination of concrete ingredients so as to assure that the required quality of
the concrete is maintained.
A time for transportation from the time of adding cement till the final pouring shall not exceed good
concrete setting time determined during trial mixing
Aluminium and aluminium alloy material shall not be used in conveying equipment, including trucks,
pump lines, tremies, chutes, etc. Short pump lines, tremies and chutes to remove concrete from transit
truck mixers are excluded.
Concrete delivery tickets shall be maintained as a record for ready mixed concrete.

10.8 Placing Concrete


Concrete shall not be placed prior to a recorded pre-placement inspection and approval to proceed by
COMPANY. Materials and equipment for protection and curing shall be operational at the placement
site before placement begins. Equipment made of aluminium alloys shall not be used for pump lines,
tremies, or chutes used to discharge concrete from a truck mixer. Hardened concrete and foreign
materials shall be removed from the inner surfaces of the conveying equipment.
Subgrade soils shall be free from foreign materials and covered by a 50 mm minimum thickness layer
of blinding concrete or by moisture barrier before placing concrete. Moisture barrier shall comply with
Section 9.9.2 of this specification. Unless noted on the design drawings, existing concrete surfaces,
against which fresh concrete will be placed, shall be roughened, thoroughly cleared of loose material
and wetted. Concrete shall be placed on a clean surface. Standing water shall be removed prior to
placement of concrete.
Prior to placing concrete the reinforcement shall be secured in place, the embedded items shall be
positioned and the interior of all forms shall be thoroughly cleaned and made free from all foreign matter

TEP-1183573-G99-0004 Page 24 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

and accumulated water. The interior of wooden forms shall be wetted prior to concrete placing. The
work shall be surveyed for level and location prior to the placing concrete. Survey shall include
embedded items, top of concrete, widths, heights and the like.
When deposited, concrete shall have a temperature not below 10°C and not above 32°C. When the
concrete have temperature above 32°C, hot weather concreting methods shall be followed.
Concrete that has achieved initial set or has been contaminated by foreign matter shall not be
deposited in the structure.
Re-tempering or addition of water after concrete is first mixed shall not be permitted. The addition of ice
at the construction site shall be permitted only if it has been considered in the mix design. The concrete
manufacturer shall provide written instructions on the required amount of ice and the mixing procedure.
Discharge of the concrete shall be completed within 45 minutes after the introduction of the mixing
water to the cement and aggregates or the introduction of the cement to the aggregates. This time may
be extended up to 90 minutes with authorization of the COMPANY’s engineer.
The interval between concrete deliveries shall be such that no more than 30 minutes interruption
elapsed during placement of a single foundation or slab, unless authorized by the COMPANY’s
engineer. The placement rate shall be such that the concrete will remain plastic at all times, and will
flow readily into all spaces between the reinforcing bars, etc. Once placement has started, it must be
carried out continuously until the placing of the concrete for that panel or section is completed or until a
suitable construction joint is reached. Concrete placing for large or lengthy foundations and structures
shall be so performed as to avoid cold joints.
To prevent segregation of the coarse aggregate, the free fall of concrete shall not exceed 1.8 m. When
the drop exceeds 1.8 m, access hatches, chutes, tremie, or elephant trunk shall be used. Temporary
openings should be provided for tall forms to reduce the drop height and to enable easy vibration.
When it is necessary to deposit concrete under water or in deep forms or excavations, tremies, chutes,
pumps, or other techniques shall be used to avoid segregation of the concrete materials.
Concrete shall be deposited as near as possible in its final position to avoid segregation due to re-
handling or flowing. Concrete shall not be allowed to flow laterally a distance of more than 1.5 m from
point of deposit. Raking shall not be used for movement of concrete after placement. To ensure
sufficient vibration, concrete shall be placed in horizontal layers not exceeding 0.6 m in depth. Inclined
layers and cold joints shall be avoided. For monolithic construction, each concrete layer shall be placed
while the underlying layer is still responsive to vibration, and layers shall be sufficiently plastic to permit
the two layers to be knitted by proper vibration.
Concrete shall be compacted by mechanical vibrators or by other means as authorized by ACI 301-05,
section 5.3.2.5 supplemented by hand spading, rodding or tamping. Equipment and procedure for
compaction of concrete shall be in accordance with ACI 309R. Unless otherwise specified, all concrete
shall be thoroughly compacted by vibrators during placing. Internal vibrators shall have a minimum
frequency of 8000 vibrations per minute and sufficient amplitude to consolidate the concrete effectively.
Vibrators shall be inserted and withdrawn at points approximately 450 mm apart. The duration of each
insertion shall be sufficient to consolidate the concrete but not sufficient to cause segregation, generally
from 5 to 15 seconds. The vibrators shall penetrate a minimum of 150 mm into the preceding layers.
The vibrators shall be inserted in a vertical direction into the concrete, and care shall be taken to ensure
that the concrete is thoroughly worked around the reinforcement, anchor bolts and other embedded
items, and into the comers of the forms to eliminate any air and stone pockets which may cause
honeycombing, pitting, or planes of weakness. A proper number of spare vibrators shall always be kept
at the site during all concrete placing operations. Contact of vibrators with reinforcement or formwork
shall be avoided. Vibrators shall not be used to move concrete inside forms. Vibrating screeds used for
concrete slabs shall be of sufficient power to compact the full depth over the length of the screed.
At all times when reinforced concrete is being placed, a competent steel fixer shall be in continuous
attendance on the concreter’s, he shall adjust and correct the position of any reinforcement which may
be displaced. Slabs shall be placed in alternating strips. Concrete for drilled piers shall be placed before
the end of the day the piers are drilled.
Anchor bolt threads spattered with concrete shall be cleaned during or immediately following the pour.
Concrete shall not be placed during rain unless adequate protection of the concrete is provided during
mixing, transporting and placing until it has hardened sufficiently so that it will not be damaged and
subject to COMPANY’s approval.

TEP-1183573-G99-0004 Page 25 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

10.9 Surface Finishing


Unless otherwise specified in the contract documents, the surface finish and correlating tolerance
requirements shall be in accordance with ACI 301. Unless otherwise required on the design drawings,
concrete surfaces shall be finished as Table 4.
Finish to be provided shall be as called for on the drawings and shall conform to the following
requirements.
1. Screed finish shall be provided by screeding to the required level with a straight edge only.
2. Wood Float finish shall be provided by screeding to the required level with a straight edge and after
the water sheen has disappeared, the surface shall be floated with wood floats.
3. Steel trowel finish shall be finished by tamping the concrete with a wire mesh tamper to depress the
coarse aggregate sufficiently to bring the matrix fines to the surface, then screeding and striking with
straight edges to bring the surface to the required finished level. While the concrete is still green, but
sufficiently hardened to bear a man's weight without excessive imprint, it shall be floated either by hand
or mechanical means to a true, even plane, with no coarse aggregate visible. Sufficient pressure shall
be used on the float to bring moisture to the surface. After surface moisture has disappeared, the
surface shall be machine or hand troweled to a smooth, even finish.
4. Heavy broomed finish for vehicular traffic is to have a wood or metal float finish, followed by
brooming with a heavy broom, producing patterns perpendicular to traffic.
5. Light broomed finish for foot traffic is to receive a wood or metal float finish, followed by brooming
before the concrete has thoroughly hardened, with a steel wire or light broom in a direction
perpendicular to the main line of traffic. The depth of scoring shall not exceed 3 mm
6. Surfaces indicated to have abrasive finishing shall be finished as specified for trowel finish,
immediately following which, an abrasive material shall be evenly applied to the surface at a rate of
not less than 0.1 kg of abrasive material to each square foot of surface. The surfaces shall then be
hand steel troweled.
7. Top surfaces of concrete below finished grade shall be screeded to the specified elevation, tamped
with a grid tamper and given a wood float finish.
8. Unless otherwise specified on drawings, top surfaces of concrete foundations on which grout will be
installed shall be rough-finished to an elevation of 25 mm to 75 mm below finished elevation.
9. When concrete is to be left with the surface finish imparted to it by the forms, objectionable
irregularities shall be removed. No finish is required for surfaces exposed to forms other than
patching of surface defects.
Table 4 – Finishes

No Description Finish Remarks

1 Equipment bases Floating finish


2 Stairs, steps, ramps, and walkways Light broom finish
3 Roads, area paving, and exterior slabs Heavy broom finish
Building Floor and Roof Slabs receiving a Steel trowel finish
4
tile-floor or other type of finish
5 Other Building Floor Wood float finish
Equipment Foundations, Structure Wood float finish
6 Foundation, Building Foundations,
Trenches, Pits, Boxes, and Sumps

TEP-1183573-G99-0004 Page 26 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

10.10 Curing and Protection


Unless otherwise specified in this specification or in the contract documents, concrete shall be cured
and protected in accordance with ACI 301-05, section 5.3.6. Curing to maintain a satisfactory moisture
content and concrete temperature shall be performed using the applicable methods and procedures
recommended in ACI 305R, ACI 306R, and ACI 308.
Beginning immediately after placement, concrete shall be protected from premature drying, excessively
hot temperatures, and mechanical injury, and shall be maintained with minimal moisture loss at a
relatively constant temperature for the period necessary for hydration of the cement and hardening of
the concrete.
In hot weather, necessary arrangements shall be made in advance for protective measures needed to
prevent rapid drying of the concrete. These protective measures shall be started as quickly as finishing
and hardening will allow.
The temperature of the concrete shall also be prevented from rising above 70oF (21oC) during the
curing period.

10.10.1 Curing / Moisture Retention


For concrete surfaces not in contact with forms, one of the following procedures shall be applied
immediately after completion of placement and finishing:
Ponding or continuous sprinkling.
 Application of absorptive mats or fabric kept continuously wet.
 Application of sand kept continuously wet.
 Application of sheet materials conforming to ASTM C171. The sheets shall be lapped not less than
100 mm at edges and ends and be sealed with adhesive or pressure sensitive tape no less than 40
mm in width. The membrane shall be weighted to prevent displacement. Holes appearing in the
membrane during curing period shall be immediately patched. The membrane shall remain intact
for not less than the curing period.
 Application of other acceptable moisture-retaining covering.
 Application of a curing compound conforming to ASTM C 309.
The curing water used in the above methods shall be clean and free of contaminating substances that
will discolour the concrete.
Moisture loss from surfaces placed against wooden forms or metal forms exposed to heating by the sun
shall be minimized by keeping the forms wet until they can be safely removed. After form removal the
concrete shall be cured until the end of the curing time by one of the above methods.
Curing in accordance with this section shall be continued for at least 7 days in the case of all concrete
except high-early-strength concrete, for which the period shall be at least 3 days.
Abrupt changes in the temperature of the concrete shall be prevented.
Concrete not in contact with forms may utilize any of the methods indicated in ACI 301-05, section
5.3.6.4, for the preservation of moisture. However, for interior concrete slabs, ponding, sprayed water,
or wet sand shall not be permitted.
Unless otherwise specified in the contract documents, liquid membrane curing compounds shall not be
used on surfaces that shall receive bonded treatments, tiles, paint or other adhered finishes, epoxy
toppings, or additional concrete.
Curing of precast concrete sections by high pressure steam, steam vapour, or other means to
accelerate the hardening of concrete shall not be permitted unless authorized by COMPANY in writing.
Exposed concrete surfaces and formed concrete stripped earlier than 7 days after pouring shall be
treated with a concrete curing compound acceptable to COMPANY.
Where an interior slab receives no other covering or topping, it shall be coated with an acceptable
curing hardening compound applied in accordance with the manufacturer’s recommendations.

TEP-1183573-G99-0004 Page 27 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

Any structure designated as a hydraulic structure in the contract documents shall comply with the
following:
 Hydraulic structures shall be cured by a wet-cure procedure only (e.g., use of ponding, sprinkling,
or a moisture-retaining covering).
 Moist wood forms in contact with concrete shall not be considered as curing for hydraulic
structures.
 Curing shall occur for a minimum of 14 days.
 Wall forms shall be loosened and water continually sprinkled between the wall and forms.
Moist Curing - Unformed surfaces shall be covered with burlap, cotton, or other acceptable fabric mats
kept in intimate contact with the concrete or with clean sand and shall be kept continuously wet for the
duration of the curing period.
 Surfaces cured with sand shall be covered with a minimum uniform thickness of 50 mm of sand.
 Where formed surfaces are cured while still in the forms, the forms shall be kept wet continually.
 If the forms are removed before the end of the curing period, curing shall continue as for unformed
surfaces.
 Burlap shall be used only on surfaces to be unexposed in the finished work.
 Concrete shall be protected from the direct rays of the sun during the first 3 days of the curing
period.
Membrane Curing - Concrete may be cured with a curing compound of the surface membrane type in
lieu of moist curing with water.
 The curing compound shall be applied to formed surfaces immediately after the forms have been
removed and the surface defects have been repaired.
 The curing compound shall be applied to unformed surfaces immediately after finishing.
 The surfaces shall be thoroughly covered with the curing compound applied in accordance with the
manufacturer’s recommendations.
 Concrete surfaces which are subjected to heavy rainfall within 3 hours after the curing compound
has been applied shall be retreated.

10.10.2 Protection from Mechanical Injury


The concrete shall be protected from damaging mechanical disturbances, such as load stresses, heavy
shock, and excessive vibration. All finished concrete surfaces shall be protected from damage by
construction equipment, materials, or methods, by application of curing procedures, and by rain or
running water. Self-supporting structures shall not be loaded in such a way as to overstress the
concrete.
During the curing period, the concrete shall be protected from damage by construction equipment,
materials, rain, running water, heavy shock, and vibration.

10.11 Repair of Surface Defects


Defects of concrete such as honeycombing, cracking or condition(s) detrimental to strength, stability,
durability and water tightness of the concrete shall be repaired immediately after form removal per ACI
301, Section 5.3.7 or by approved repair procedure. All defects shall be removed down to a sound
surface. Curing procedures shall not be delayed or interrupted while making repairs.
Unless otherwise specified or permitted by the COMPANY’s engineer, fins, tie holes, honeycombs, and
other concrete surface defects shall be repaired promptly after form removal at a time and in a manner
that shall not delay, interfere with, or impair the proper curing of the fresh concrete. Defective areas
such as honeycomb shall be cut back to sound material before repair.
The COMPANY’s engineer shall be notified before proceeding with repair if the defect is either of the
following sizes:

TEP-1183573-G99-0004 Page 28 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

 Depth is greater than 75 mm at the maximum point and surface area is greater than 100,000
square mm.
 Depth is greater than 1/4 the thickness of the member and greater than 150 mm in any other
direction.
Pre-packaged grouts and patching compounds or a patching mortar similar to the concrete mix without
coarse aggregate may be used with approval from COMPANY’s engineer. The patching material shall
match the colour of the original concrete as closely as possible. One-third of the gray cement may be
replaced with white Portland Cement to help in getting a colour match.
Out-of-tolerance slabs shall be repaired by grinding down high points and/or raising low points by using
a specified underlayment compound or repair topping if the areas are exposed.
Critical slab areas, identified in the contract documents shall be replaced if out-of-tolerance. A
demolition and replacement plan for the slab areas shall be submitted to the COMPANY’s engineer for
review and approval before proceeding.
Holes left by the withdrawal of tie-rods shall be filled solidly with cement mortar and be made flush with
the adjoining surface. It is recommended to refrain from using hole-through tie rods for liquid retaining
structures.

10.12 Hot Weather Concreting


During hot weather, proper attention shall be given to ingredients, production methods, handling,
placing, protection, and curing to prevent excessive concrete temperatures or water evaporation that
could impair required strength or serviceability of the member or structure.
Concrete work is significantly affected by high temperatures in the concrete and in the air, or by a low
relative humidity, or by a high wind velocity. If these conditions are prevalent, the concrete work shall be
carried out in accordance with the requirements of ACI 305R. Where the concrete temperature exceeds
32°C, necessary preventive measures, as noted below, shall be taken. However, if the rate of
evaporation from the concrete surface as determined by ACI 305R is less than 9.6 N/m2/h that no
preventive measures are required even when the concrete temperature exceeds 32°C. In no case shall
the concrete temperature exceed 38°C. Exceeding the limiting water-cement ratio in order to have
sufficient slump for placing at concrete temperatures between 32°C and 38°C shall not be permitted.
Instead, the preventive measures noted below will be used to increase the slump.
The following preventive measures shall be taken to avoid the adverse effects of hot weather
1. The formwork and steel reinforcement shall be continuously sprayed with cold water in advance of
the concreting and excess water shall be removed from the inside of the forms immediately prior to
the placement of the concrete.
2. The reinforcement, and the formwork if metal forms are used, shall be protected from the effects of
hot winds and direct sunlight.
3. Suitable barriers shall be provided to protect the freshly placed concrete from wind, until the
concrete has hardened sufficiently to allow it to be covered.
4. Adding water-reducing and retarding admixture to concrete.
5. Using chilled water for mixing.
6. Painting storage facilities, batching plants, pipes, and agitating trucks white or silver and/or
insulating the same.
7. Keeping the transportation time to a minimum.
8. Checking mixer drums and blades frequently during hot weather, and ensuring that the interior of the
mixer is free of any accumulated matter that will interfere with the mixing action.
9. Providing sufficient equipment and workers to ensure quick placing and finishing, and so as to avoid
cold jointing and plastic shrinkage cracking. All plans for the arrangement of the equipment and
workers shall be submitted to COMPANY for approval.
10. Using a white pigmented material when a curing compound is applied.
11. Shading materials and facilities from the direct rays of the sun.

TEP-1183573-G99-0004 Page 29 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

When the above measures are considered insufficient to avoid the adverse effects of hot weather, the
following additional measures may be taken:
1. Carrying out concrete placing in the evening, at night, or in the early morning
2. Spraying water onto the aggregate and considering new w/c ratio on design mix (Any water in the
aggregate must be accounted for in the water-cement ratio).
3. Providing wind breaks during concrete placing
4. Using flaked ice as a part of the mixing water

10.13 Grouting
Grout thickness for column base plates and equipment supports shall be as shown in the contract
documents.

10.13.1 Type and Usage


The grouting type to be used, i.e epoxy grout, non‐shrink grouts, or standard portland cement grouts,
shall be in accordance with the contract documents. If the grouting type is not noted on the design
drawings or equipment vendor drawings, the usage of grouting type shall refer to TEP-900-DBS-CV-
BP4-0001 “Onshore Civil and Structural Design Basis”.

10.13.2 Preparation
Foundation preparation shall be in accordance with the manufacturer’s written instructions. Foundations
shall be suitably prepared before installation of formwork for grout. Concrete foundation shall be cured
for a minimum of 7 days before surface preparation unless otherwise approved by COMPANY. Heavy
equipment shall not be set on foundations, nor grouting placed, before10 days after concreting the
foundations.
Concrete surfaces shall be prepared for grouting by chipping back to sound concrete or fractured
aggregate. The surface shall be cleaned of all laitance, grease, oil, and dirt or loose aggregate
removed prior to setting levelling plates.
All levelling plates shall be set to the proper elevation. The number and type of levelling plates should
be determined in accordance with the recommendations of the equipment manufacturer or other project
documents.
Concrete surfaces on which cement-based grout is to be placed shall be cleaned by vacuum cleansing,
or by blowing with compressed air. The surface shall then be scrubbed with clean water until the
puddles in the irregularities are clear. Scrubbing shall be done with fibre brushes only. All dirt and water
shall be removed from the anchor bolts holes. Concrete surfaces in contact with the grout shall be
saturated with clean water before grout placement. The surface of the concrete shall be damp but free
from standing water. All standing water shall be removed from anchor bolt sleeves.
Metal surfaces in contact with the grout shall be clean and free of oil and grease, and other foreign
substances. The presence of tightly bonded paints is not objectionable.
The formwork shall be constructed with adequate strength, rigidity, and dimension to permit grout
placement. Forms shall be of adequate strength to withstand the horizontal forces of the fluid grout, and
shall be caulked or sealed with tape to prevent excessive leakage. A bond breaker consistent with the
manufacturer’s recommendations shall be applied to the surface of the formwork in contact with the
grout. Forms shall not be butted against a base plate or equipment base but shall allow at least 25 mm
of space all around. The top of the forms shall be a minimum of 25 mm above the bottom of the
adjacent base plate. Forms shall have a chamfer strip attached where a chamfered edge is required.
Joints in grout shall be as located and shown in the contract documents or as recommended by the
grout manufacturer.
routing shall not be carried out until steelwork or equipment has been finally levelled and plumbed, the
bases being supported meanwhile by steel shims.

TEP-1183573-G99-0004 Page 30 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

10.13.3 Installation of Grout


Grout shall be mixed, placed, and cured in strict accordance with manufacturer’s written requirements.
For some grouts, particular installation methods are restricted or prohibited by the grout manufacturer.
The CONTRACTOR shall read, understand, and comply with the manufacturer’s instructions as printed
on each unit. Grout shall be stored, mixed, placed, and cured at temperature ranges that are consistent
with the manufacturer’s recommendations. Grout may be dry packed, flowed, or pumped into place as
permitted by the manufacturer’s written instructions for the specific grout being installed. Re-tempering
of grout by adding water after stiffening is not permitted.
All grout shall be placed in only one direction to prevent trapping air. Grouting shall be quick and
continuous to avoid segregation, bleeding, or premature initial set.
The grout shall be cut back to the lower edge of the baseplate after it has reached its initial set. The
cutback shall be at a 45° angle, unless otherwise indicated in the contract documents.
If grout must be placed through grout holes, it shall be placed from one hole continuously until the grout
has passed a second hole. A liquid head pressure shall be maintained at the first access hole until a
head pressure has been established at the next hole. Grout placement shall continue from the next hole
in a similar fashion. Special care shall be taken to ensure that sleeves or bedding holes around anchor
bolts are completely filled with grout before placing grout under base plates.
Packers and shims used to level vibrating machinery, such as compressors and heavy pumps shall be
removed after the grout has set. The resulting pocket is to be made good with similar grout.

10.13.4 Installation of Epoxy Grout


Epoxy materials shall be mixed in a well-ventilated area, making certain that vapours are not inhaled or
that the materials do not come in contact with skin and eyes.
All epoxy grout components shall be conditioned to a temperature range between 21oC to 30oC prior to
mixing. The entire hardener shall then be added to the entire resin component and thoroughly mixed for
2 to 3 minutes with a low speed mixer. Mixed resin and hardener shall then be put into a clean mortar
mixer or wheelbarrow and the entire bag of aggregate added. Mix until aggregate is completely wetted.
Nothing else shall be added to the mixture. Mixing shall be adjacent to area being grouted, with
sufficient manpower and equipment available for rapid and continuous mixing and placing. Grout shall
not be mixed in quantities larger than that which can be placed during the working time specified herein.
Epoxy grout has a limited working time after mixing. The placing of grout shall be performed only during
the specified working time and any unused grout remaining beyond this time shall be discarded.
When placing epoxy grout, the temperature of the foundation, base plate and grout material shall be
within the temperature range of 5oC to 32oC as determined by a surface thermometer.
Epoxy grout shall be placed from one long side of an equipment base to the other, in one direction only.
The grout shall be poured into a movable head box having an inclined plane to direct the grout beneath
the equipment base in a manner that minimizes trapped air and bubble formation. The head box
should be about a 1 m cube to allow large volumes of grout to be poured continuously. The use of
vibrators is not permitted.
The use of steel straps is permitted to move grout into position but chaining is not permitted because of
air entrapment between the links. Pumping epoxy grout is permitted and eliminates the requirement for
a head box.
Epoxy grout placing shall be continued until it oozes out along the entire perimeter and up through
every interior air relief hole and grout holes. An exception occurs when grouting such equipment as
pumps having an elevated interior base plate. In these situations, fill under the entire equipment base
to the top of the exterior base plate and then stop grouting for a short period of time to allow the grout to
seal the periphery and then complete the grouting through one of the interior grout holes.
Expansion joints shall be installed in epoxy grout placements of long length or large area.
Finishing and curing shall be in strict accordance with the manufacturer's printed instructions.
Epoxies cannot be trimmed after set. They must be left at the finished level with required chamfer strips
built into the forms. Top surfaces may be trowelled with a steel trowel moistened with oil. All further

TEP-1183573-G99-0004 Page 31 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

finishing will require grinding. The epoxy grout shall be maintained within the placing temperature range
for a minimum of 24 hours after placing. Epoxy grout shall not wet-cured.

10.13.5 Installation of Non-shrink Grout


Mixing and placing of non-shrink grout shall be in accordance with grout Manufacturer's instructions. All
voids shall be eliminated. Precautions shall be taken to ensure that the temperatures of grout,
foundation concrete and baseplates are kept within the range instructed by the manufacturers.
A seal cap of sand-cement mortar shall be added around the non-shrink grout edges, to avoid
deterioration of non-shrink grout.

10.13.6 Installation of Standard Portland Cement Grout


Ingredients shall be thoroughly dry-mixed before adding water. Water-Cement Ratio shall be 0.4 or
less. After adding water, the batch shall be mixed for 3 to 5 minutes. Batches shall be sized to allow
continuous placement of freshly mixed grout. Grout not used within 1 hour after mixing shall be
discarded.
Grout shall not normally be vibrated, tamping only is permitted.
Grout shall slope downward and outward at 45 degrees from inside lower edge of plate.
When placing grout, the temperature of the foundation, base plate and grout material shall be within the
temperature range of 5oC to 32oC as determined by a surface thermometer. This temperature shall be
maintained for 3 days following grouting.

11 Protection of Underground Concrete

11.1 General
Concrete shall be made so that it will perform satisfactorily when exposed to various atmospheric
conditions, to waters and soils containing chemicals, and to other kinds of chemicals. Chemical attack
on concrete is generally the result of exposure to sulphates or acids. Such environmental conditions
shall be taken into consideration for concrete mix designs and application of protective coatings on
concrete surfaces to ensure the required durability of concrete. Coating extent for underground
foundations shall be as shown on drawings.

11.2 Material
Asphalt, coal tar, coal tar epoxy, bituminous based coating materials are acceptable for concrete
surfaces contacting soil. Surface coating materials and application to underground foundations shall
meet the following definition and material vendor catalogues.
Table 5 - Underground Structure Protection

Zone Cement w/c Ratio Sheet Barrier Coating


Type
Type-V Max.0.45 Plasticized PE sheet Chemical resistant
(0.2mm thick.), with impermeable
Foundation in Severe
sealing tape coating, Nitocote-
Zone
PE-135 or ET402
from Fosroc
Foundations in Mild Type-V max.0.45 No Bitumen, Coal tar,
Zone epoxy coating
Foundations in Low Type-V max.0.45 No No
Corrosive Zone

TEP-1183573-G99-0004 Page 32 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

Zone Cement w/c Ratio Sheet Barrier Coating


Type
Pile Type-V Max.0.45 No No
Note: Piles shall be coated to limit down drag frictional forces if required in contract documents.
Detail criteria for zone category shall refer to section 12.16.1 document no. TEP-900-DBS-CV-BP4-
0001 “Onshore Civil and Structural Design Basis”.
After excavation, the foundation subgrade shall be tested using pH test, with the following manner:
1. Provide approximately 50m grid covering whole areas
2. Address all grid lines with alphabetic and numeric combination
3. Measure the pH at each grid intersection points.
4. Map all points in each area of sectional plot plan.

11.3 Application
The application procedure of a coating including surface preparation of concrete, weather restrictions,
a minimum thickness, number of coats, curing, inspection, and repair methods shall comply with
recommendations and instructions given by the coating manufacture/supplier. CONTRACTOR shall
submit a method statement for COMPANY approval.
Proper concrete surface preparation is essential for good performance of the coating. The surfaces of
concrete should be free of oil, grease, dirt, loose, weak and unsound materials. The recommendation
for concrete surface preparation given by the coating material manufacturer should be followed.
Appropriate safety requirements should be followed with respect to the coating material characteristic,
operations, procedures described in the instruction given by the manufactures.

12 Mass Concrete
When the concrete is considered as massive concrete, ACI 207.1R should be referred to.

13 Quality Control

13.1 Construction Tolerance

13.1.1 General
Tolerance shall be based on ACI 117, ACI315 and ACI 347 in case not specified in this section or
unless otherwise specified in the design drawings.

13.1.2 Formwork
Table 6 - Tolerances for Formwork

No Measurement Tolerance

Variation from the plumb: (In the lines and surface ± 6 mm in any 3 m
1 of columns, piers and walls.)
± 25 mm for entire length

Variation of the level in elevated slab and beam ± 6 mm in any 3 m


2 soffits
± 18 mm for entire length

TEP-1183573-G99-0004 Page 33 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

Where necessary to maintain this tolerance, the formwork shall be cambered to compensate for
anticipated deflections in the formwork due to the weight and pressure of the fresh concrete and due to
construction loads.

13.1.3 Reinforcement
Fabrication tolerances shall comply with the requirements of ACI 117.
Table 7 - Tolerances for Reinforcements

No Measurement Tolerance

Clear distance to formed surfaces :


Member Size ≤ 100 mm +7 mm, -10 mm
1 100 < Member Size ≤ 300 mm ± 10mm
300 < Member Size ≤ 600 mm ± 13 mm
Member Size > 600 mm ± 25 mm
Concrete cover measured perpendicular to concrete
2
surface:
Member Size ≤ 300 mm +0 -10mm
Member Size > 300 mm +0 -13mm
Distance between reinforcement: 1/4 of specified distance
3
± 25 mm
The minimum clear spacing between parallel bars  nominal diameter of rebar
on a layer
 4/3 times of nominal maximum
size of coarse aggregate
 ± 25 mm

13.1.4 Concrete
Table 8 - Tolerances for Concrete

No Measurement Tolerance

Variation from the plumb: (In the lines and surface  ± 6 mm in any 3 m
1 of columns, piers and walls.)
 ± 25 mm for entire length
2 Variation of the finishing level in elevated slab ± 20 mm for entire length
Variation of the finishing level of Surfaces to be ± 6mm in any 3 m
grouted
± 10 mm in any bay or in any 6m of
3
length
± 20 mm for entire length
Variation in the thickness of slabs and walls and in + 12 mm, -6 mm
4 the cross-sectional dimensions of beams and
columns
Misplacement of eccentricity of Footing  ± 2% of width in the direction of
5 misplacement.
 ± 50mm

TEP-1183573-G99-0004 Page 34 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

13.1.5 Embedment
Unless otherwise specified in the contract documents, embedments shall be installed in accordance
with the tolerances shown in bellow table.
The term “bolt group” used in bellow table . it is defined as the set of anchor bolts for a single fabricated
steel shipping piece, or a single piece of equipment or skid.

Table 9 - Tolerances for Embedment

No Measurement Tolerance

1 Anchor bolt projection + 6 mm, - 0 mm


2 Centre of bolt group ± 6 mm
Centre to centre of any two anchor bolts-without sleeves within a ± 3 mm
3
bolt group
Centre to centre of any two anchor bolts-with sleeves within a ± 5 mm
4
bolt group
5 Centre to centre between bolt groups ± 6 mm
6 Anchor bolt plumpness 4 mm in 1
Insert plate, horizontal and vertical location ± 6 mm horizontal and
7
± 6 mm vertical
8 Insert plate, alignment in any direction ± 2 mm in 300 mm

Unless specified otherwise in the contract documents, formed concrete surfaces shall be constructed in
accordance with the tolerances shown in ACI 117. Tolerances for concrete surfaces not specifically
mentioned in ACI 117 shall be in accordance with ACI 117, Section 4.

13.2 Sampling for Test


The sampling and slump test of freshly mixed concrete shall be performed at the point of delivery.
13.2.1 Slump Test
The slump tests shall be carried out in accordance with the following:
 All slump tests shall be carried out in accordance with the requirement of ASTM C143 and SNI
1972:2008.
 Slump test shall be performed at each delivery of concrete.
 The result of the tests shall show that the slump is within the range specified in the construction
drawing, or the concrete shall not be placed.
The temperature of fresh concrete shall also be checked at the time of slump test.

13.2.2 Compressive Strength Test


Compressive strength tests shall be carried out for each class of concrete, in accordance with the
following procedures:
1. Samples of concrete for making compressive strength test specimens shall be obtained in
accordance with the requirements of ASTM C 172 and SNI 2458:2008.

TEP-1183573-G99-0004 Page 35 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

2. A minimum of 3 specimens shall be moulded and cured in accordance with the requirements of
ASTM C 31.
3. Compressive strength tests of cylinders shall be carried out in accordance with the requirements of
ASTM C 39. These cylinders shall be tested as follows:
 One at 7 days for information
 Two at 28 days for determining acceptability of concrete strength
Evaluation and acceptance of concrete shall be in accordance with ACI 318.
Samples shall be taken from each complete pour for individual foundations or structures supporting
main processing units, heavy mechanical equipment, buildings, storage tanks, and from other important
concrete structures. At least two samples shall be taken from each full days concreting or not less than
required by the following.
Table 10 - Number of Samples to be Taken

No No. of Cubic Meters in Any Individual No. of Samples to be Taken


Foundation or Structure
(3 Cylinders per Sample)
1 0 – 38 One for each 20 cubic meters
2 39 - 150 One for each 40 cubic meters
3 151 - 270 One for each 60 cubic meters

13.2.3 Air Content Test


Air content tests shall be performed when the concrete samples are taken, and in accordance with the
requirements of ASTM C 138, ASTM C 173, or ASTM C 231. Determine temperature of concrete
sample for each strength test.
13.2.4 Reinforcement Test
The CONTRACTOR shall cut samples from any of the reinforcing bars or fabric and shall dispatch such
samples for testing, as the COMPANY may from time to time direct. Minimum sample length shall be
600 mm or 20 times the bar diameter whichever is greater.
13.2.5 Water Filling Test for Concrete Ponds/Pits
For concrete ponds/pits that are designed to retain contaminated water such as oil and chemicals, a
water-filling test shall be carried out before back filling of the pond. A water-filling test is not required for
seawater or cleans water ponds unless the high water level is higher than ground elevation. Water
shall be filled to the design high water level, a minimum of 24 hours before the inspection is due.
Concrete ponds shall be back filled only after obtaining the approval COMPANY.
The acceptance criterion for water-filling test is that no water leak is observed on the external surface of
the concrete pit. If the leakage is found, the defected parts shall be repaired according to the section
10.11 above, then inspect the parts again until no leakage is observed. Fresh water shall be used for
the test.
13.2.6 Test Report
All test report shall be submitted to COMPANY upon completion of test.

13.3 Concrete Not Meeting Specification


When cylinder test reports are unsatisfactory regarding the specified strength, the CONTRACTOR may
order :
1. A series of rebound hammer tests taken at locations directed by the CONTRACTOR's in accordance
with ASTM 805. Correlation between strength and rebound number shall be carried out using 150
mm x 300mm cylinder of the same concrete Mix Reference as the suspect concrete.

TEP-1183573-G99-0004 Page 36 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

2. Core samples be taken of the concrete placed and tested in accordance with ASTM C42/C42M. A
cover meter shall be used to determine locations where coring will cause least damage to
reinforcement. Core holes in concrete which is to remain in the Works shall be repaired by filling with
concrete or mortar of the strength specified for the surrounding concrete.
If the test reports are still unsatisfactory, defective material shall, if required CONTRACTOR may take
one of the following actions, all at the expense of the SUBCONTRACTOR ( USI Concrete Supplier ) :
1. Instruct that the section be cut out and replaced.
2. Instruct the SUBCONTRACTOR ( USI Concrete Supplier ) to carry out work or strengthen in an
acceptable manner to ensure the soundness of the structure.
3. Accept the work at a reduced price.
Following the failure of concrete to reach the required standard the SUBCONTRACTOR ( USI Concrete
Supplier ) shall take one or both of the following steps:
1. Alter the methods of making concrete so as to reduce its variability.
2. Alter the proportions of the concrete mix to increase its compressive strength to meet the
requirements.

14 Quality Management
The quality management system shall conform to ISO 9001, API Specification Q1, or other agreed
internationally recognised standard to ensure that the products and services provided conform to the
requirements for supplier quality identified in the Purchase Order.

15 Inspection, Testing and Certification

15.1 Inspection and Test Plan


a) Prior to the start of manufacture, an ITP shall be submitted for approval by Company responsible
engineer.
b) The ITP shall include inspection and testing activities to be performed, including those at sub-
suppliers’ works and shall make reference to all testing procedures, control documents, and resulting
records and reports.

15.2 Inspection and Test Plan


a) Company and the Company appointed representative and Contractor appointed representative shall
at all times have access to the workshops and testing facilities, including workshops of sub-suppliers
engaged in supplying material or in fabrication.
b) Company and the Company appointed representative and Contractor appointed representative shall
be granted permission to photograph the materials, equipment and activities in the scope of the
Purchase Order during fabrication and test.

16 Packing, preservation, marking and shipping


Preparation of equipment for transportation shall conform to the packing, marking, and shipping
instructions or other documents identified in the Purchase Order.

17 Deliverables & Data Transfer


Technical data, registers, documents, and drawings that together define the scope of the Purchase
Order shall conform to the requirements for supplier information identified in the Purchase Order.

TEP-1183573-G99-0004 Page 37 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement

18 Attachment
 Concrete pre-pouring Check List - 1
 Concrete pre-pouring Check List - 2

TEP-1183573-G99-0004 Page 38 of 38 Rev:02


870310-S-1183573-CST-G99-0004 BP Internal
FIELD INSPECTION REPORT REPORT NO. :
DATE :
PAGE : of
INSPECTION TYPE : PROJECT NO. :
ITEM NO. :
CONCRETE PREPOURING CHECK LIST LOCATION :
SIGNATURE
INSPECTION NOTICE NO. : SUBCONTRACTOR CONTRACTOR COMPANY
SUBCONT.'S INSPECTOR : / / / / / /
CONT'S INSPECTOR :
CPY.'S INSPECTOR :
INSPECTION ITEMS ACC REJ ACC REJ ACC REJ
FORMATION SURFACE CONDITION
FORMATING LEVEL
LAYOUT
REINFORCING
FORM WORK
ANCHOR BOLTS/POCKETS
TEMPLATES
INSERT
CLEAN OUT
PROPOSED FINISH LEVEL
OTHERS

CONCRETE QTY :
TIME : REMARKS :
METHOD :
EQUIPMENTS :
TRUCK MIXER :
CRT. PUMPS :
VIBRATOR :
CHUTE :
CHAMBER :
HAMMER :
LIGHT :
OTHERS :

Note :
ACC = ACCEPTABLE = COMPLY WITH REFERENCE DOCUMENT
REJ = REJECTED = IT IS NOT COMPLY WITH REFERENCE DOCUMENT
M
DISTRIBUTION SUBCONTRACTOR : COPY CONTRACTOR : COPY COMPANY : ORIGINAL
FIELD INSPECTION REPORT REPORT NO. :
DATE :
PAGE : of
INSPECTION TYPE : PROJECT NO. :
ITEM NO. :
CONCRETE POURING CHECK LIST (II) LOCATION :
SIGNATURE
INSPECTION NOTICE NO. : SUBCONT CONTRACTOR COMPANY
SUBCONT.'S INSPECTOR : / / / / / /
CONT'S INSPECTOR :
CPY.'S INSPECTOR :
CRT. GRADE : ACC REJ ACC REJ ACC REJ
TIME :
WEATHER CONDITON :

CHECK COMPLETED
INSPECTION ITEMS YES NO N/A REMARKS

A Control Pouring
1. Concrete grades proper to structures
2. Mixing time
3. Time between completion of mixing & placement
4. Concrete transporting and pouring method
(prevent segregation)
5. Placed rapidly enough to avoid formation of
cold joints
6. Prevent or correct movements of the form and
embedded item
7. Vibrating method and interval
8. Pouring schedule and order
9. Perform and maintain the scheduled control test
10. Provisions for the hot or colt weather concrete

B After Concrete Pouring


1. Proper method of initial curing and protect the
concrete from impact
2. Removal time of the form and supports
3. Surface condition after form removal & repairing
method of the defective areas
4. Accuracy of the size and gradient of the concrete
and draw and maintain the control diagram

Note :
ACC = ACCEPTABLE = COMPLY WITH REFERENCE DOCUMENT
REJ = REJECTED = IT IS NOT COMPLY WITH REFERENCE DOCUMENT
DISTRIBUTION SUBCONTRACTOR : COPY CONTRACTOR : COPY COMPANY : ORIGINAL

You might also like