Professional Documents
Culture Documents
!"
#$
% &'(
'$$
()$ )
$*))&
%$ )
)
$4
)5)$ &
0 //+.1,. 0 22 0 ---3
6
!"
6 76
"
Johanes Agus
Digitally signed by PSS100841
6
DN: dc=intranet, dc=saipem,
dc=saipemnet,
ou=ForeignSites, ou=Jakarta,
ou=Users, cn=PSS100841
Date: 2018.05.04 16:51:07
+07'00'
4-May-18
89%$
#$#%
$$#"$&"
'"
#"
#"
###
$
'
#
$
"'
"
&"
$
#
'$$
" (
""
#
$)$$'
&"
$
$
(#
$'#"
$
*"'
#'$
'
+$
$$#"
##"
(&'$$
"#
#
(#"
'*"(#
,#-#"
"
#
"#
(
#
$ ##""
###
#"$$
'$$(#
"
#&
$
".!##
) /
(
# (
0##'
)&""&#
((&
#"$
'$$("
###
)$
4
)
12 12 232143 +(& . *5 6*
14 14 40 2143 +(& . *5 6*
)
$4
8
)$:)
* )8
8 )
*"
###"#
#"$#$ #
Tangguh Expansion Project – LNG EPC
Meindo-Concreting Method Statement
Table of Contents
1 INTRODUCTION ..................................................................................................... 6
1.1 Project Overview ......................................................................................................................... 6
2 SCOPE .................................................................................................................... 6
2.1 General ....................................................................................................................................... 6
2.2 Specific Design Conditions ......................................................................................................... 6
3 Normative Reference ............................................................................................. 7
4 Term and Definitions ........................................................................................... 10
5 Symbols and Abbreviations ................................................................................ 11
6 Risk Assessment ................................................................................................. 11
7 General Requirement ........................................................................................... 11
8 Roles and Responsible ....................................................................................... 11
8.1 Construction Manager ............................................................................................................... 11
8.2 Site Engineer............................................................................................................................. 11
8.3 Construction Supervisor ............................................................................................................ 12
8.4 HSE Officer ............................................................................................................................... 12
8.5 Civil QC ..................................................................................................................................... 12
9 Product and Materials ......................................................................................... 12
9.1 General ..................................................................................................................................... 12
9.2 Split of Material ......................................................................................................................... 12
9.3 Cement...................................................................................................................................... 13
9.4 Aggregate.................................................................................................................................. 13
9.5 Reinforcement ........................................................................................................................... 13
9.6 Water......................................................................................................................................... 14
9.7 Admixture .................................................................................................................................. 14
9.8 Formwork .................................................................................................................................. 14
9.9 Concrete .................................................................................................................................... 15
9.10 Concrete Accessories .......................................................................................................... 15
9.10.1 Bonding Agent ................................................................................................................. 15
9.10.2 Moisture Barrier ............................................................................................................... 15
9.10.3 Surface Dustproofing and Hardening .............................................................................. 15
9.10.4 Surface Oil - Proofing ...................................................................................................... 15
9.11 Joint ..................................................................................................................................... 15
9.11.1 Joint Filler ........................................................................................................................ 15
9.11.2 Backup Material ............................................................................................................... 16
9.11.3 Joint Primer...................................................................................................................... 16
9.11.4 Joint Sealant .................................................................................................................... 16
9.11.5 Bond Breaker ................................................................................................................... 16
DOCUMENT NUMBER DOCUMENT TITLE REV. CODE ISSUE STATUS DOCUMENT STATUS
870310-S-1183573-CST-G99-0004 Concreting Method Statement 02 Issue For Review B
SUPPLIER
NO COMMENTS ORIGINATOR REASONS NAME &TITLE SECTION AFFECTED COMMENT STATUS
RESPONSE
Additional split of material item Epoxy grout and
non-shrink grout , For equipment & structure base
A. Agreed, Comment will Putut Eko /
1 plate by other sub-cont , For civil purpose ( with SI Johannes Agus Page 13 Agreed - Closed
be implemented Site Engineer
from CSTS, if not mentioned in contract ) by sub-
cont.
Additional split of material item Curing compound (
A. Agreed, Comment will Putut Eko /
2 if any )_item 23 and acid coating protection_item Johannes Agus Page 13 Agreed - Closed
be implemented Site Engineer
24. by sub-cont.
Change Sub-cont instead Contractor and A. Agreed, Comment will Putut Eko /
3 Johannes Agus Page 16 Agreed - Closed
Contractor's instead Company's be implemented Site Engineer
Change CONTRACTOR instead COMPANY and A. Agreed, Comment will Putut Eko /
7 Johannes Agus Page 36 Agreed - Closed
CONTRACTOR'S instead COMPANY'S be implemented Site Engineer
Change CONTRACTOR instead COMPANY and
A. Agreed, Comment will Putut Eko /
8 SUB-CONTRACTOR ( USI Concrete Supplier ) Johannes Agus Page 37 Agreed - Closed
be implemented Site Engineer
instead CONTRACTOR
Additional CONTRACTOR appointed A. Agreed, Comment will Putut Eko /
9 Johannes Agus Page 37 Agreed - Closed
representative be implemented Site Engineer
Revision History
Amendment Revision Amender Name Amendment
Date Number
Related documents
Document Document name Description of Content
number
1 INTRODUCTION
2 SCOPE
2.1 General
This specification covers the requirements for design and construction of Concreting Work within the
scope of work of Tangguh LNG Expansion Project – ORF, Product Storage, Product Loading,
Infrastructure and Existing Facilities.
3 Normative Reference
The following documents are referenced in one or more requirements in this document. For dated
references, only the version cited applies. For undated references, the latest version of the referenced
document (including any amendments) applies.
Local Codes and Standards
10 ASTM C171-07 Standard Specification for Sheet Material for Curing Concrete
12 ASTM C191 Test for Time of Setting Hydraulic Cement by Vicat Needle
SHOULD
Discretional
6 Risk Assessment
Before site project execution, it is require to perform an assessment to identify the risk level that will
appear during site project execution, every step of job have its own risk, therefore early identification of
risk shall be done in order to support the overall project execution.
Below step shall be done in order to identify the risk level :
- Gathering information and identify the issue
- Assessment to all facts
- Action plan based on assessment
- Communication of action plan
- Implementation
- Monitoring
7 General Requirement
Concrete supply and construction shall be in accordance with all requirements of ACI 301, except as
modified or supplemented in this specification or by the contract documents.
The following ACI documents are acceptable practices and may be helpful in meeting requirements of
this specification and ACI 301-05, i.e.: ACI 211.1, ACI 211.2, ACI 302.1R, ACI 304.2R, ACI 306R, ACI
308R, ACI 347, ACI 504R, ACI SP-15.
8.5 Civil QC
A Civil QC shall perform daily inspection on earth work activity, conduct joint inspection with COMPANY
representative and prepare inspection report as required.
9.1 General
Unless authorized in writing by COMPANY, materials that are not in accordance with this specification
or the contract documents shall not be permitted.
Materials shall be in accordance with applicable local volatile organic compound regulations.
15 Waterstop X
Liquid chemical curing X
16
compounds
17 Polyethylene Film X
18 Absorptive mats X
19 Epoxy Grout X X For equipment &
structure base plate by
other sub-cont.
20 Non-shrink Grout X X For civil purpose ( with SI
CSTS, if not mentioned in
contract )
21 Standard PC Grout X
22 Reinforcing & Embedment X
23 Curing compound ( if any ) X
24 Acid coating protection X
9.3 Cement
Unless otherwise specified in the contract documents, Portland cement shall be in accordance with SNI
15-2049-2004, Type I or Type V.
Type-I cement shall be used for all concrete works not in contact with soil or water.
Type-V cement shall be used for concrete works in contact with soil or water, such as footing, septic
tank, ditches, paving slab, curb, trenches, pile, pile cap, ground beam etc.
Unless otherwise specified in the contract documents, fly ash may be used in accordance with ACI 301
and shall conform to ASTM C 618, Class C or Class F. If Class C fly ash is used in a moderately to
extremely aggressive sulphate environment, the mix design shall be tested in accordance with ASTM C
1012 to verify sulphate resistance.
9.4 Aggregate
Aggregate shall be in accordance with ASTM C 33. Fine and coarse aggregates from different sources
of supply shall not be mixed or stored in the same stockpile. All aggregates used for the same structure
shall be obtained from one source.
All aggregate shall be clean, inert, hard, non-porous and free from excessive quantities of dust,
laminated particles and splinters.
The proportion of thin or elongated pieces having lengths greater than five times the average thickness
shall not exceed 15%. Fine Aggregate shall consist of clean, washed, natural or crushed sand of
uniform gradation. Coarse Aggregate shall consist of washed gravel or washed crushed stone, having
hard, strong, durable piece, free from adherent coating, or other weak, deleterious substances.
Maximum size of coarse aggregate shall be 20 mm for general use and 10 mm for fireproofing.
The source of material shall not be changed without written approval.
9.5 Reinforcement
Unless otherwise specified in the contract documents, deformed reinforcing bars shall be in
accordance with SNI 07-2052-2002 grade BjTS 40 with minimum yield strength fy = 390 MPa. Plain
Reinforcing bars shall conform to SNI 07-2052-2002 BjTP 24 with minimum yield strength fy = 235
MPa.
Welded wire fabric shall be plain or deformed wire fabric and in accordance SNI 07-0663-1995 with
minimum yield strength 490 MPa.
Steel strand for pre-stressed concrete shall conform to ASTM A416 Grade 250 or 270 as shown the
drawings.
Tie wire shall be black annealed wire, 16 gage minimum.
Unless otherwise specified in the contract documents, all reinforcing shall be uncoated.
Additionally, reinforcement designed to resist earthquake-induced flexural and axial forces in frame
members and in wall boundary elements shall fulfil the following conditions:
The actual yield strength based on mill tests does not exceed the specified yield strength by more
than 124 MPa. Retests shall not exceed this value by more than an additional 20.7 MPa.
The ratio of the actual ultimate tensile strength to the actual tensile yield strength is not less than
1.25.
9.6 Water
Water used for mixing water, curing, or any other function relating to placement of concrete shall
comply with the requirements of ASTM C1602. Other water may be used if tested for suitability in
accordance with ASTM C94/C94M. Water shall be free from injurious amounts of oil, acid, salt, alkali,
organic matter, and other deleterious substances. Seawater shall not be used for mixing concrete.
Wash water from mixer washout operations shall not be used as mixing water.
If galvanized and/or aluminium material is embedded in concrete, water for concrete mix shall not have
more than 200 ppm of chloride ions.
9.7 Admixture
Admixtures shall conform to the requirements given in ACI 212.3R, 212.4R, ASTM C260 (liquid air-
entraining admixture), ASTM C494 (water reducing and retarding), ASTM C618 or ASTM C1017.
Admixtures containing calcium chloride or soluble chlorides shall not be used. Only one manufacturer
for each admixture shall be used. Admixture shall not be used to replace cement. The CONTRACTOR
shall demonstrate the suitability of admixtures for their intended purposes.
Roof concrete and trenches with concrete floors shall have waterproofing additives, subject to
COMPANY approval.
9.8 Formwork
Forms shall be suitable for the work to be performed and may be of dressed lumber, plywood, metal, or
other suitable materials.
Plywood forms should be grade marked Exterior Grade with minimum thickness of 12 mm. Metal Forms
should use smooth metal plate free of surface irregularities.
Form ties should be factory fabricated snap-off metal type of adequate design to minimize form
deflection and preclude concrete spalling upon removal.
Form ties should be fabricated so that set back in the concrete is such that the portion of the tie
remaining after snap-off and removal of the exterior portions is at least 3.8 mm back from the concrete
surface.
Form coating will be non-grain-raising and non-staining resin or polymer type that will not leave residual
matter on the surface of the concrete or adversely affect bonding to concrete of paint, plaster, mortar,
protective coatings, waterproofing or other applied materials. Coatings containing mineral oils, paraffin,
and other non-drying ingredients are not permitted. For concrete surfaces contacting potable stored
water, the coatings and form release agents shall be completely non-toxic and approved by the EPA for
the intended use.
9.9 Concrete
The specified compressive strength of a designed mix shall be the 28 day compressive cylinder
strength. The minimum 28-day compressive strength, f’c, shall be in accordance with the contract
documents. If high early-strength concrete is specified, compressive strength shall be 7-day strength.
Unless as otherwise provided in this specification, ready-mixed concrete shall conform to ASTM
C94/C94M, Alternative No. 2, which requires the Supplier to assume full responsibility for the selections
of the proportions of the concrete mixture.
Unless otherwise specified in the contract documents, maximum water-soluble chloride ion
concentrations in hardened concrete shall be 0.30 % by weight of cement, in accordance with ACI 301-
05, Table 4.2.2.6, for other reinforced concrete construction.
9.11 Joint
impregnated fibreboard), ASTM D1751 (asphalt impregnated cork, with asphalt saturated glass-fibre felt
liners), or ASTM D1752. Joint filler shall be 12.5 mm thick minimum unless otherwise shown on the
drawings.
9.11.6 Waterstop
Waterstop shall be polyvinyl chloride with high polymer resins, 150-mm heavy duty ribbed, with centre
bulb or Heavy Duty Dumb-Bell type in accordance with ASTM D412, or as shown on the drawings.
9.14 Grout
10 Execution Requirement
10.1 General
Storage, handling, measuring, mixing, transporting, and placing of concrete materials shall follow the
methods and means outlined in ACI 304R and comply with manufacturer’s recommendation for
handling, storage, and protection.
10.2 Formwork
The design and construction of the formwork shall be in accordance with ACI 347R Manual, and shall
be the responsibility of the SUB-CONTRACTOR.
Formwork shall be designed, erected, supported, braced, and maintained so that it will sustain all
vertical and lateral loads until such loads can be supported by the concrete structure itself. Forms shall
have sufficient strength to withstand the wind loads, pressure resulting from placement and vibration of
the concrete, the loads and operations incidental to placing and curing the concrete, as well as other
forces resulting from the movement of the forms, and shall have sufficient rigidity to maintain specified
tolerances. Forms and their supports shall be designed so as not to damage previously placed
concrete. The forms shall be sufficiently tight to prevent leakage of cement paste and shall be so
constructed that the surfaces of the finished concrete will be reasonably free from ridges, fins, offsets,
or similar defects. The forms material for concrete material expose to view shall produce smooth, hard
and uniform texture on the concrete unless different texture requirement shown on the drawings, and
shall be free of defects likely to cause imperfections on the surface of the concrete. The formwork shall
be true in every respect to produce hardened concrete to the required shape, dimensions, grade, and
alignment as indicated on the Drawings. Forms shall be constructed to facilitate their removal without
damage to the concrete and so that their removal can.be in the following orders: (1) columns, (2) sides
of beams and girders, (3) bottoms of slabs, beam and girders.
Formwork shall be provided to the top faces of sloping works where the slope exceeds 15o from the
horizontal. Positive means of adjustment (wedges, jacks, etc.) of shores and struts shall be provided
and all settlement shall be taken up during concrete placing operation.
Forms shall be securely braced against lateral deflections. Adjustable type shoring can be used for
supporting roof forms or elevated floors.
Form accessories that remain embedded in the concrete (e.g., ties and hangers) shall be a
commercially manufactured type.
All side and bottom surfaces of structures that will be exposed shall be formed. Vertical surfaces of
subgrade structures and pavements shall be formed at least to a depth of 300 mm below grade, unless
otherwise approved by COMPANY. The concrete below this level may be placed against earth.
Chamfer strips shall be placed in the corners of forms to produce 20 mm chamfer bevelled edges on
permanently exposed surfaces. Chamfer strips are not required on interior corners of such surfaces, the
edges of formed joints, tops of piers supporting horizontal vessels, and concrete edges providing direct
support for flooring, or to which steel will be attached for flooring support.
Temporary openings shall be provided at the base of column forms and wall forms and at other points
where necessary to facilitate cleaning and inspection immediately before concrete is placed.
All surfaces of forms and embedded materials shall be cleaned of all accumulated mortar or grout from
previous concreting and of all other foreign material before concrete is placed.
Form material which is to be reused shall have damaged parts repaired and the concrete side
thoroughly cleaned before reusing. Forms shall not be reused if there is any evidence of surface wear
and tear or defects which would impair the quality of the surface.
Before placing the reinforcing steel or the concrete, the surfaces of the forms shall be covered with an
acceptable coating material that will effectively prevent absorption of moisture, prevent bond with the
concrete, and not stain the concrete surfaces. A field applied form release agent or sealer of acceptable
type or factory applied non-absorptive liner may be used. Care shall be taken that the parting agent
does not get on concrete or reinforcement, which is to bond with new concrete.
Form-release agents shall not be applied if concrete surfaces receive special finishes or where the
agent may affect applied coverings. Alternately, inside surfaces of untreated formwork shall be soaked
with clean water and kept moist before placing concrete.
Removal of forms and supports shall be in accordance with ACI 347.
When repair of surface defects or finishing is required at an early age, forms shall be removed as soon
as the concrete has hardened sufficiently to sustain the load and resist damage from removal
operations.
Formwork for columns, walls, sides of beams and other parts not supporting the weight of the concrete
may be removed as soon as the concrete has hardened sufficiently to resist damage from removal
operations.
Forms and shoring in the formwork used to support the weight of concrete in beams, slabs and other
structural members shall remain in place until the concrete has reached the required strength to support
the weight of concrete and anticipated imposed loads. Field-cured specimens shall be used to estimate
the strength of concrete. When field-cured specimens cannot be used to determine the time of the form
removal, forms and shoring shall be remain in place for a period of time not less than that specified in
ACI 347R/ ACI 301.
Results of suitable control tests shall be used as evidence that concrete has attained sufficient strength
to permit removal of supporting forms.
Forms shall not be left permanently in place, unless otherwise authorized by COMPANY.
When forms are removed before the end of the required curing period, the concrete shall be cured after
removal of the forms by suitable methods.
Reinforcement with rust shall be considered satisfactory, provided the minimum dimensions (including
height of deformations) and weight of a hand-wire-brushed test specimen aren't less than applicable
ASTM specification requirements.
No
Description Remarks
For the purpose of determining cover, all concrete elements with a protective coating shall be treated as
being not exposed to adverse environmental conditions. Concrete cover for pits shall be decided based
on their exposure categories and as per ACI 318.
10.3.3 Installation
Reinforcing bars, anchor bolts and other embedded items shall be free from mud, dirt, loose rust, loose
mill scale, oil, grease, and any other foreign coating that may reduce the bond between bars and
concrete.
Reinforcement shall be accurately placed in accordance with design drawings and secured in position
with concrete or metal chairs and spacers. Intersections and splices of reinforcement shall be securely
tied with annealed steel wire 16 gage or heavier and securely held in position during concrete placing.
All ties, links, stirrups etc. shall be taut, and the bars properly braced and tied. Bars in lapped splices
shall be in contact unless otherwise shown on the design drawings. Cementitious spacers shall be of
similar strength, durability, porosity and appearance to the surrounding concrete. Tie wire shall be
finished tight with free ends bent inwards away from formwork.
Unless specifically indicated on the design drawings, splicing by means of proprietary mechanical
splices shall not be used.
Reinforcing bars projecting from existing, hardened concrete may be bent or straightened, subject to
approval by COMPANY, and provided it is done in accordance with ACI 301-05 section 3.3.2.8.
Exposed reinforcing bars intended for bonding with future extensions shall be protected from corrosion
by concrete or other adequate covering. Type of covering requires written COMPANY approval.
Welded wire fabric used in structural concrete shall be supported, in the same manner as reinforcing
bars, to place the fabric in its proper location within the concrete member.
Anchor bolts, anchors, inserts, sleeves, drains, curb and seat angles, nosing, and other embedded
items shall be installed before placing concrete. Welding of these items to the reinforcing bars shall not
be permitted without COMPANY approval. Voids in those embedded items shall be filled temporarily
with readily removable material to prevent the entry of concrete into the voids. Other embedded items
shall be installed as shown on design drawings and they shall be supported against displacement
during placement and consolidation of concrete. Anchor bolt sleeves shall be capped or plugged to
keep out water, concrete, and debris.
Embedded aluminium items shall not be permitted. Conduits, pipes and other items made from
aluminium shall not be embedded in structural concrete unless effectively coated to prevent aluminium-
concrete reaction.
Anchor bolt threads shall be protected from damage and kept free of concrete.
10.4 Joint
Joints not specified on the design drawings, shall be in accordance with ACI 301-05, Chapter 2 Section
2.2.2.5 and Chapter 5, Sections 5.1.2.3a, 5.2.2.1 and 5.3.2.6. ACI 504R, "Guide to Joint Sealants for
Concrete Structures" shall be used to prepare and select proper material for all installations.
The surface of the concrete at all joints shall be rough, thoroughly cleaned and all laitance shall be
removed prior to placing adjoining concrete. The laitance shall be removed by brushing, chipping, wet
sandblasting or high pressure water-blasting down to sound mortar matrix, leaving clean, sound
aggregate exposed over the entire joint surface, but not undercutting the large aggregate particles. The
surface of the concrete shall then be washed thoroughly to remove all loose material. All concrete joint
surfaces to receive new concrete shall be free of surface water but shall be in a saturated surface dry
condition.
Where shown on the drawings, joint sealant shall be applied according to the manufacturer’s
recommendations. The joint sealant shall not be thicker than half the width of the joint.
solation joints shall be placed where the pavement adjoins vertical surfaces (e.g., walls, columns, catch
basins, manholes, and equipment foundations).
Isolation joints shall be located in accordance with the contract documents.
Isolation joints shall not be used to contain hydrostatic pressure.
10.5 Waterstops
Waterstops shall be installed in accordance with the contract documents and the manufacturer’s
recommendations.
10.7 Transportation
Concrete shall be transported from Batch Plant to discharge locations by methods which prevent
segregation, loss, or contamination of concrete ingredients so as to assure that the required quality of
the concrete is maintained.
A time for transportation from the time of adding cement till the final pouring shall not exceed good
concrete setting time determined during trial mixing
Aluminium and aluminium alloy material shall not be used in conveying equipment, including trucks,
pump lines, tremies, chutes, etc. Short pump lines, tremies and chutes to remove concrete from transit
truck mixers are excluded.
Concrete delivery tickets shall be maintained as a record for ready mixed concrete.
and accumulated water. The interior of wooden forms shall be wetted prior to concrete placing. The
work shall be surveyed for level and location prior to the placing concrete. Survey shall include
embedded items, top of concrete, widths, heights and the like.
When deposited, concrete shall have a temperature not below 10°C and not above 32°C. When the
concrete have temperature above 32°C, hot weather concreting methods shall be followed.
Concrete that has achieved initial set or has been contaminated by foreign matter shall not be
deposited in the structure.
Re-tempering or addition of water after concrete is first mixed shall not be permitted. The addition of ice
at the construction site shall be permitted only if it has been considered in the mix design. The concrete
manufacturer shall provide written instructions on the required amount of ice and the mixing procedure.
Discharge of the concrete shall be completed within 45 minutes after the introduction of the mixing
water to the cement and aggregates or the introduction of the cement to the aggregates. This time may
be extended up to 90 minutes with authorization of the COMPANY’s engineer.
The interval between concrete deliveries shall be such that no more than 30 minutes interruption
elapsed during placement of a single foundation or slab, unless authorized by the COMPANY’s
engineer. The placement rate shall be such that the concrete will remain plastic at all times, and will
flow readily into all spaces between the reinforcing bars, etc. Once placement has started, it must be
carried out continuously until the placing of the concrete for that panel or section is completed or until a
suitable construction joint is reached. Concrete placing for large or lengthy foundations and structures
shall be so performed as to avoid cold joints.
To prevent segregation of the coarse aggregate, the free fall of concrete shall not exceed 1.8 m. When
the drop exceeds 1.8 m, access hatches, chutes, tremie, or elephant trunk shall be used. Temporary
openings should be provided for tall forms to reduce the drop height and to enable easy vibration.
When it is necessary to deposit concrete under water or in deep forms or excavations, tremies, chutes,
pumps, or other techniques shall be used to avoid segregation of the concrete materials.
Concrete shall be deposited as near as possible in its final position to avoid segregation due to re-
handling or flowing. Concrete shall not be allowed to flow laterally a distance of more than 1.5 m from
point of deposit. Raking shall not be used for movement of concrete after placement. To ensure
sufficient vibration, concrete shall be placed in horizontal layers not exceeding 0.6 m in depth. Inclined
layers and cold joints shall be avoided. For monolithic construction, each concrete layer shall be placed
while the underlying layer is still responsive to vibration, and layers shall be sufficiently plastic to permit
the two layers to be knitted by proper vibration.
Concrete shall be compacted by mechanical vibrators or by other means as authorized by ACI 301-05,
section 5.3.2.5 supplemented by hand spading, rodding or tamping. Equipment and procedure for
compaction of concrete shall be in accordance with ACI 309R. Unless otherwise specified, all concrete
shall be thoroughly compacted by vibrators during placing. Internal vibrators shall have a minimum
frequency of 8000 vibrations per minute and sufficient amplitude to consolidate the concrete effectively.
Vibrators shall be inserted and withdrawn at points approximately 450 mm apart. The duration of each
insertion shall be sufficient to consolidate the concrete but not sufficient to cause segregation, generally
from 5 to 15 seconds. The vibrators shall penetrate a minimum of 150 mm into the preceding layers.
The vibrators shall be inserted in a vertical direction into the concrete, and care shall be taken to ensure
that the concrete is thoroughly worked around the reinforcement, anchor bolts and other embedded
items, and into the comers of the forms to eliminate any air and stone pockets which may cause
honeycombing, pitting, or planes of weakness. A proper number of spare vibrators shall always be kept
at the site during all concrete placing operations. Contact of vibrators with reinforcement or formwork
shall be avoided. Vibrators shall not be used to move concrete inside forms. Vibrating screeds used for
concrete slabs shall be of sufficient power to compact the full depth over the length of the screed.
At all times when reinforced concrete is being placed, a competent steel fixer shall be in continuous
attendance on the concreter’s, he shall adjust and correct the position of any reinforcement which may
be displaced. Slabs shall be placed in alternating strips. Concrete for drilled piers shall be placed before
the end of the day the piers are drilled.
Anchor bolt threads spattered with concrete shall be cleaned during or immediately following the pour.
Concrete shall not be placed during rain unless adequate protection of the concrete is provided during
mixing, transporting and placing until it has hardened sufficiently so that it will not be damaged and
subject to COMPANY’s approval.
Any structure designated as a hydraulic structure in the contract documents shall comply with the
following:
Hydraulic structures shall be cured by a wet-cure procedure only (e.g., use of ponding, sprinkling,
or a moisture-retaining covering).
Moist wood forms in contact with concrete shall not be considered as curing for hydraulic
structures.
Curing shall occur for a minimum of 14 days.
Wall forms shall be loosened and water continually sprinkled between the wall and forms.
Moist Curing - Unformed surfaces shall be covered with burlap, cotton, or other acceptable fabric mats
kept in intimate contact with the concrete or with clean sand and shall be kept continuously wet for the
duration of the curing period.
Surfaces cured with sand shall be covered with a minimum uniform thickness of 50 mm of sand.
Where formed surfaces are cured while still in the forms, the forms shall be kept wet continually.
If the forms are removed before the end of the curing period, curing shall continue as for unformed
surfaces.
Burlap shall be used only on surfaces to be unexposed in the finished work.
Concrete shall be protected from the direct rays of the sun during the first 3 days of the curing
period.
Membrane Curing - Concrete may be cured with a curing compound of the surface membrane type in
lieu of moist curing with water.
The curing compound shall be applied to formed surfaces immediately after the forms have been
removed and the surface defects have been repaired.
The curing compound shall be applied to unformed surfaces immediately after finishing.
The surfaces shall be thoroughly covered with the curing compound applied in accordance with the
manufacturer’s recommendations.
Concrete surfaces which are subjected to heavy rainfall within 3 hours after the curing compound
has been applied shall be retreated.
Depth is greater than 75 mm at the maximum point and surface area is greater than 100,000
square mm.
Depth is greater than 1/4 the thickness of the member and greater than 150 mm in any other
direction.
Pre-packaged grouts and patching compounds or a patching mortar similar to the concrete mix without
coarse aggregate may be used with approval from COMPANY’s engineer. The patching material shall
match the colour of the original concrete as closely as possible. One-third of the gray cement may be
replaced with white Portland Cement to help in getting a colour match.
Out-of-tolerance slabs shall be repaired by grinding down high points and/or raising low points by using
a specified underlayment compound or repair topping if the areas are exposed.
Critical slab areas, identified in the contract documents shall be replaced if out-of-tolerance. A
demolition and replacement plan for the slab areas shall be submitted to the COMPANY’s engineer for
review and approval before proceeding.
Holes left by the withdrawal of tie-rods shall be filled solidly with cement mortar and be made flush with
the adjoining surface. It is recommended to refrain from using hole-through tie rods for liquid retaining
structures.
When the above measures are considered insufficient to avoid the adverse effects of hot weather, the
following additional measures may be taken:
1. Carrying out concrete placing in the evening, at night, or in the early morning
2. Spraying water onto the aggregate and considering new w/c ratio on design mix (Any water in the
aggregate must be accounted for in the water-cement ratio).
3. Providing wind breaks during concrete placing
4. Using flaked ice as a part of the mixing water
10.13 Grouting
Grout thickness for column base plates and equipment supports shall be as shown in the contract
documents.
10.13.2 Preparation
Foundation preparation shall be in accordance with the manufacturer’s written instructions. Foundations
shall be suitably prepared before installation of formwork for grout. Concrete foundation shall be cured
for a minimum of 7 days before surface preparation unless otherwise approved by COMPANY. Heavy
equipment shall not be set on foundations, nor grouting placed, before10 days after concreting the
foundations.
Concrete surfaces shall be prepared for grouting by chipping back to sound concrete or fractured
aggregate. The surface shall be cleaned of all laitance, grease, oil, and dirt or loose aggregate
removed prior to setting levelling plates.
All levelling plates shall be set to the proper elevation. The number and type of levelling plates should
be determined in accordance with the recommendations of the equipment manufacturer or other project
documents.
Concrete surfaces on which cement-based grout is to be placed shall be cleaned by vacuum cleansing,
or by blowing with compressed air. The surface shall then be scrubbed with clean water until the
puddles in the irregularities are clear. Scrubbing shall be done with fibre brushes only. All dirt and water
shall be removed from the anchor bolts holes. Concrete surfaces in contact with the grout shall be
saturated with clean water before grout placement. The surface of the concrete shall be damp but free
from standing water. All standing water shall be removed from anchor bolt sleeves.
Metal surfaces in contact with the grout shall be clean and free of oil and grease, and other foreign
substances. The presence of tightly bonded paints is not objectionable.
The formwork shall be constructed with adequate strength, rigidity, and dimension to permit grout
placement. Forms shall be of adequate strength to withstand the horizontal forces of the fluid grout, and
shall be caulked or sealed with tape to prevent excessive leakage. A bond breaker consistent with the
manufacturer’s recommendations shall be applied to the surface of the formwork in contact with the
grout. Forms shall not be butted against a base plate or equipment base but shall allow at least 25 mm
of space all around. The top of the forms shall be a minimum of 25 mm above the bottom of the
adjacent base plate. Forms shall have a chamfer strip attached where a chamfered edge is required.
Joints in grout shall be as located and shown in the contract documents or as recommended by the
grout manufacturer.
routing shall not be carried out until steelwork or equipment has been finally levelled and plumbed, the
bases being supported meanwhile by steel shims.
finishing will require grinding. The epoxy grout shall be maintained within the placing temperature range
for a minimum of 24 hours after placing. Epoxy grout shall not wet-cured.
11.1 General
Concrete shall be made so that it will perform satisfactorily when exposed to various atmospheric
conditions, to waters and soils containing chemicals, and to other kinds of chemicals. Chemical attack
on concrete is generally the result of exposure to sulphates or acids. Such environmental conditions
shall be taken into consideration for concrete mix designs and application of protective coatings on
concrete surfaces to ensure the required durability of concrete. Coating extent for underground
foundations shall be as shown on drawings.
11.2 Material
Asphalt, coal tar, coal tar epoxy, bituminous based coating materials are acceptable for concrete
surfaces contacting soil. Surface coating materials and application to underground foundations shall
meet the following definition and material vendor catalogues.
Table 5 - Underground Structure Protection
11.3 Application
The application procedure of a coating including surface preparation of concrete, weather restrictions,
a minimum thickness, number of coats, curing, inspection, and repair methods shall comply with
recommendations and instructions given by the coating manufacture/supplier. CONTRACTOR shall
submit a method statement for COMPANY approval.
Proper concrete surface preparation is essential for good performance of the coating. The surfaces of
concrete should be free of oil, grease, dirt, loose, weak and unsound materials. The recommendation
for concrete surface preparation given by the coating material manufacturer should be followed.
Appropriate safety requirements should be followed with respect to the coating material characteristic,
operations, procedures described in the instruction given by the manufactures.
12 Mass Concrete
When the concrete is considered as massive concrete, ACI 207.1R should be referred to.
13 Quality Control
13.1.1 General
Tolerance shall be based on ACI 117, ACI315 and ACI 347 in case not specified in this section or
unless otherwise specified in the design drawings.
13.1.2 Formwork
Table 6 - Tolerances for Formwork
No Measurement Tolerance
Variation from the plumb: (In the lines and surface ± 6 mm in any 3 m
1 of columns, piers and walls.)
± 25 mm for entire length
Where necessary to maintain this tolerance, the formwork shall be cambered to compensate for
anticipated deflections in the formwork due to the weight and pressure of the fresh concrete and due to
construction loads.
13.1.3 Reinforcement
Fabrication tolerances shall comply with the requirements of ACI 117.
Table 7 - Tolerances for Reinforcements
No Measurement Tolerance
13.1.4 Concrete
Table 8 - Tolerances for Concrete
No Measurement Tolerance
Variation from the plumb: (In the lines and surface ± 6 mm in any 3 m
1 of columns, piers and walls.)
± 25 mm for entire length
2 Variation of the finishing level in elevated slab ± 20 mm for entire length
Variation of the finishing level of Surfaces to be ± 6mm in any 3 m
grouted
± 10 mm in any bay or in any 6m of
3
length
± 20 mm for entire length
Variation in the thickness of slabs and walls and in + 12 mm, -6 mm
4 the cross-sectional dimensions of beams and
columns
Misplacement of eccentricity of Footing ± 2% of width in the direction of
5 misplacement.
± 50mm
13.1.5 Embedment
Unless otherwise specified in the contract documents, embedments shall be installed in accordance
with the tolerances shown in bellow table.
The term “bolt group” used in bellow table . it is defined as the set of anchor bolts for a single fabricated
steel shipping piece, or a single piece of equipment or skid.
No Measurement Tolerance
Unless specified otherwise in the contract documents, formed concrete surfaces shall be constructed in
accordance with the tolerances shown in ACI 117. Tolerances for concrete surfaces not specifically
mentioned in ACI 117 shall be in accordance with ACI 117, Section 4.
2. A minimum of 3 specimens shall be moulded and cured in accordance with the requirements of
ASTM C 31.
3. Compressive strength tests of cylinders shall be carried out in accordance with the requirements of
ASTM C 39. These cylinders shall be tested as follows:
One at 7 days for information
Two at 28 days for determining acceptability of concrete strength
Evaluation and acceptance of concrete shall be in accordance with ACI 318.
Samples shall be taken from each complete pour for individual foundations or structures supporting
main processing units, heavy mechanical equipment, buildings, storage tanks, and from other important
concrete structures. At least two samples shall be taken from each full days concreting or not less than
required by the following.
Table 10 - Number of Samples to be Taken
2. Core samples be taken of the concrete placed and tested in accordance with ASTM C42/C42M. A
cover meter shall be used to determine locations where coring will cause least damage to
reinforcement. Core holes in concrete which is to remain in the Works shall be repaired by filling with
concrete or mortar of the strength specified for the surrounding concrete.
If the test reports are still unsatisfactory, defective material shall, if required CONTRACTOR may take
one of the following actions, all at the expense of the SUBCONTRACTOR ( USI Concrete Supplier ) :
1. Instruct that the section be cut out and replaced.
2. Instruct the SUBCONTRACTOR ( USI Concrete Supplier ) to carry out work or strengthen in an
acceptable manner to ensure the soundness of the structure.
3. Accept the work at a reduced price.
Following the failure of concrete to reach the required standard the SUBCONTRACTOR ( USI Concrete
Supplier ) shall take one or both of the following steps:
1. Alter the methods of making concrete so as to reduce its variability.
2. Alter the proportions of the concrete mix to increase its compressive strength to meet the
requirements.
14 Quality Management
The quality management system shall conform to ISO 9001, API Specification Q1, or other agreed
internationally recognised standard to ensure that the products and services provided conform to the
requirements for supplier quality identified in the Purchase Order.
18 Attachment
Concrete pre-pouring Check List - 1
Concrete pre-pouring Check List - 2
CONCRETE QTY :
TIME : REMARKS :
METHOD :
EQUIPMENTS :
TRUCK MIXER :
CRT. PUMPS :
VIBRATOR :
CHUTE :
CHAMBER :
HAMMER :
LIGHT :
OTHERS :
Note :
ACC = ACCEPTABLE = COMPLY WITH REFERENCE DOCUMENT
REJ = REJECTED = IT IS NOT COMPLY WITH REFERENCE DOCUMENT
M
DISTRIBUTION SUBCONTRACTOR : COPY CONTRACTOR : COPY COMPANY : ORIGINAL
FIELD INSPECTION REPORT REPORT NO. :
DATE :
PAGE : of
INSPECTION TYPE : PROJECT NO. :
ITEM NO. :
CONCRETE POURING CHECK LIST (II) LOCATION :
SIGNATURE
INSPECTION NOTICE NO. : SUBCONT CONTRACTOR COMPANY
SUBCONT.'S INSPECTOR : / / / / / /
CONT'S INSPECTOR :
CPY.'S INSPECTOR :
CRT. GRADE : ACC REJ ACC REJ ACC REJ
TIME :
WEATHER CONDITON :
CHECK COMPLETED
INSPECTION ITEMS YES NO N/A REMARKS
A Control Pouring
1. Concrete grades proper to structures
2. Mixing time
3. Time between completion of mixing & placement
4. Concrete transporting and pouring method
(prevent segregation)
5. Placed rapidly enough to avoid formation of
cold joints
6. Prevent or correct movements of the form and
embedded item
7. Vibrating method and interval
8. Pouring schedule and order
9. Perform and maintain the scheduled control test
10. Provisions for the hot or colt weather concrete
Note :
ACC = ACCEPTABLE = COMPLY WITH REFERENCE DOCUMENT
REJ = REJECTED = IT IS NOT COMPLY WITH REFERENCE DOCUMENT
DISTRIBUTION SUBCONTRACTOR : COPY CONTRACTOR : COPY COMPANY : ORIGINAL