Professional Documents
Culture Documents
Owner’s Engineer
Contractor
Project
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
(2 X 600 MW)
Title
(Housing Complex)
Method Statement for Installation of Hume Pipe
4 PREPARATION ................................................................................................................ 2
No Description Q’ty
1 Excavator
2 Dump Truck
3 Compactor
5 Total Staion
6 Barrier
4.2 Material
All reinforced concrete hume pipes must be new and perfectly sound, free from cracks,
cylindrically straight and comply to design nominal diameter and length with even texture.
5 EXECUTION
5.1 Excavation of trench
Excavation work will be performed as per approved method statement (Refer to NS2-
DD09-P0UYK-770002 “MS for Excavation and Backfill Work”).
Any unsuitable soil or rock, bounder, stone… which could cause point load on pipe surface
must be removed if they are encountered in trench bed. Replaced material should be
screened sand as general backfilling procedure.
The dimensions and shape of trench as below (Table 9 of TCVN 4447:2012):
Where:
W = Do + 0.8 for Rein. Concrete Pipe D400
W = Do + 1.2 for Rein. Concrete Pipe D600 & D800
Do: The outer diameter of Rein. Concrete Hume Pipe
Clean Spigot
List of All Job Steps List of All Known Hazards How to Eliminate Hazards
1.Mobilization Driver Over speed/taking Traffic collision 4 4 U Truck is not to be o o M Injury/ fatality &
the equipment during transporting. with other overloaded. damage equipment
Pedestrian
to the site.
Equipment on the equipment and All equipment must be tied
trailer truck are not human. and wedged carefully.
secured. Equipment falling Truck shall move with low
down from the speed and do not
trailer truck. overtake.
2. Survey Surveyor & Holding survey Instrument falling 3 4 M Holding instrument o o T Near Miss
work Supervisor instrument un down and hit carefully.
. carefully. workmen. Wearing full PPE & Full
Survey instrument set Fall from height. body safety harness.
up at un-safe location. Set up survey instruments
Un-safe survey at safe location.
making location.
Without fall protection
3. Lifting and Crane Non-compliance Falling object. 4 4 U S.T.A.R.T Meeting prior o o M Injury/ Damage
Unloading work. with lifting procedure. start lifting works. equipment/
Operator. Crane over-
Environment
Rigger. Using lifting devices turning. Comply with lifting contamination
improperly. Crane collision procedure/Prepared/
Signalman.
Poor supervision. with power line/ Planned.
Supervisor
Non-compliance with other equipment. Daily inspection for crane
Worker.
barricaded & warning Electrocution by & lifting devices prior start
area. lightning strike/ operation.
4. Installation Crane Non-compliance with Falling object. 4 4 U S.T.A.R.T Meeting prior o o M Injury/ Damage
work. lifting procedure. start Installation works. equipment.
Operator. Crane over-
Rigger. Un-inspection the turning. Comply with lifting
lifting equipment. Crane collision procedure/ Prepared/
Signalman.
Poor supervision. with power line/ Planned.
Supervisor
Non-compliance with other equipment. Daily inspection for crane
Worker.
barricaded & warning Electrocution by & lifting devices prior start
Welder. operation.
area. lightning strike/
In-competent rigger & collision with Follow load chard of crane.
operator. power line/ using Generator & electric
power tools. equipment must be
Weather in bad
condition (strong Human caught inspected.
wind ≥ 8-10m/s, between moving Strict control &
5. Excavation Operator Non-compliance with Excavator 2 4 4 Ensure safe access is o o M Injury/ Damage to
works. Method statement. toppled down provided to personnel, use equipment
Supervisor
Un-authorized deep hole hard barricades, sign
Flagman
access. excavation. boards.
Worker
Un-authorized Human caught All power tools and