: WIELLP/MSTE/01
WESTERN INDIA ERECTORS LLP Issue Date : 27/11/2019
Method Statement For Tank Erection Rev : 0
Submitted For
C1
Approval
Issued for
A2
Client Review
P. Manish
Issued For IDC 27.11.2019
A1 (Plng Engg)
Purpose of Date of
Prepared by Checked by Approved by
REV issue issue
Page 1 of 8
DOC NO. : WIELLP/MSTE/01
WESTERN INDIA ERECTORS LLP Issue Date : 27/11/2019
Method Statement For Tank Erection Rev : 0
1 Purpose 3
2 Scope 3
3 Reference Documents 3
4 Definitions 3
6 Environmental 3
8 Process 4
8.1 General 4
8.9 Scaffolding 7
Page 2 of 8
DOC NO. : WIELLP/MSTE/01
WESTERN INDIA ERECTORS LLP Issue Date : 27/11/2019
Method Statement For Tank Erection Rev : 0
PURPOSE
The purpose of this method statement is to explain the various steps involved in lifting the Tank shells
by Jack Lifting Method.
SCOPE
The scope of this method statement describes the method of lifting Tank using Jack Lifting Method at
2 X 660 MW Solapur Super Thermal Power Project, Solapur, Maharashtra, India.
REFERENCE DOCUMENT
DEFINITIONS
WIELLP - WESTERN INDIA ERECTORS LLP (SUBCON)
GEPIL - GE POWER INDIA LIMITED (CLIENT)
ENVIRONMENTAL
Page 3 of 8
DOC NO. : WIELLP/MSTE/01
WESTERN INDIA ERECTORS LLP Issue Date : 27/11/2019
Method Statement For Tank Erection Rev : 0
PROCESS
1. GENERAL
Prepare work permits, JSA and working procedure for GEPIL approval prior to commencing work.
Organize a pre job safety meeting with all concerned to brief the planned work activities and
discuss their associated risks. All lifting gears such as wire slings, web slings, shackles etc shall be
inspected and shall come with the valid load test certificate prior to lifting. All personnel that will
be involved with the works shall review the Job Safety Analysis, Work procedure and conduct
tool box meeting immediately before commencement of work. Ensure all personnel are
equipped with appropriate PPE for the right job especially for personnel working at height to
wear safety harness, hand gloves and vest. Barricade the work area with red and white tape,
sufficient warning sign boards, work permit and JSA at Work site. Only authorized personnel are
allowed to be within the area during the lifting and erection works. Erect Scaffolding/ install
temporary support and platform to ensure works accessibility.
For Auxiliary Absorbent Tank 00HTN40BB001 the Total Loads to be lifted shall be arrived from
the approved Drawings.
Before going for JACK capacity calculation Safe Working Load shall be derived from the actual
load calculation.
The Safe Working Load will be 1.5 times of the actual load.
Page 4 of 8
DOC NO. : WIELLP/MSTE/01
WESTERN INDIA ERECTORS LLP Issue Date : 27/11/2019
Method Statement For Tank Erection Rev : 0
4. DESCRIPTION OF EQUIPMENT
Mark the shell I/S diameter and fix the elevators on the annular plate @ 3.8 Mtr
Tack the guide on the elevators.
Weld the lifting cleats. (2 nos. /Jack; capacity of hydraulic jack-12 MT)
Weld the pad plates. (1 no for trestle & 2 no’s for stay member)
Install trestle and stay member. Length of the trestle to be checked according to shell
heights.
Connect the high pressure hosepipes from power pack to each jack.
Give electrical power connection to power pack and start jacking.
Page 5 of 8
DOC NO. : WIELLP/MSTE/01
WESTERN INDIA ERECTORS LLP Issue Date : 27/11/2019
Method Statement For Tank Erection Rev : 0
Continue jacking till the assemble is lifted to a height of 50 mm more than the width of the
shell course to be erected next.
Erect the shell course by using crane or by any mechanical means.
6. CLOSE OUT
All vehicles, tools & tackles shall be removed from the area after completion of the job.
7. PERSONNEL INVOLVED
Construction Manager
QA/Qc Manager / Engineer
Site Engineer
EHS Officer
Site Foreman
9. SCAFFOLDING
Scaffolding the is safety requirement is a temporary structure used to support people and
material in the construction or repair of buildings and other structures. It is usually a modular
system of metal pipes or tubes.
After the assembly of all internals OR if possible during the assembly of Internals to the
possible extent Scaffolding is being constructed inside the tank along the periphery of the tank
for activities related to welding and painting activities.
Scaffolding for roof welding and touch up paint for roof under side, shall be carried out with
the help of hanging platform constructed with girder clamps on roof structures and cross
girder.
Following are the testing methods for preassembly works are followed for quality controls.
Area and type to be tested.
Butt weld horizontal joints – DPT after back gouging and after completion of butt
welding 20%
All butt welds horizontal joints – One spot (75mm) in first 3mtr and then in 30 mtr
All T-Joints – 100% DPT & Radiography
Base plate to Shell plate – DPT inspection 20% (either inside or outside)
All fillet weld – Vacuum Box Test @ 100%
RF Pad for Nozzle – Pneumatic Leak Test
Page 7 of 8
DOC NO. : WIELLP/MSTE/01
WESTERN INDIA ERECTORS LLP Issue Date : 27/11/2019
Method Statement For Tank Erection Rev : 0
However other than tests mentioned above, as per standards, following additional test are
also taken up for higher quality standards. All fillet Welds and Butt welds – shall be provided
with 100% DPT to find the quality of weld.
Page 8 of 8