Professional Documents
Culture Documents
20 years experience
SS tube
Our goal is to wholesale the world market with quality goods and prices in 2023.
sdwfmetal.com
METHOD OF STATEMENT
Ads by
inless pipe manufacturer - SS square tube
Stop seeing this ad Why this ad?
24/10/2022 OPE
ce
oal is to wholesale the world market with quality goods and prices in 2023. sdwfmetal.com
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 1/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
0
SHARES
Share (https://www.facebook.com/sharer.php?
u=https%3A%2F%2Fengineersblog.net%2Fmethod-statement-for-underground-
hdpe-piping-installation%2F)
Tweet (https://twitter.com/intent/tweet?
text=METHOD%20STATEMENT%20FOR%20UNDERGROUND%20HDPE%20PIPING
%20INSTALLATION&url=https://engineersblog.net/method-statement-for-
underground-hdpe-piping-installation/)
CONTENT:
1. Introduction
1. Purpose
1. Scope of Work
1. Location
1. Definitions
2. EXECUTION
Materials
Tools & Equipments
Procedure of Work
Responsibilities
3. QA / QC
Reference Standard
Responsibilities
Test and Measurement
Inspection
4. SAFETY
Guidelines
Responsibilities
Hazard Analysis
5. ATTACHMENTS
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 2/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
1. GENERAL INFORMATION
1.1 Introduction
TECNIMONT Arabia Ltd. (TAL) has awarded KETTANEH Construction Saudi Arabia Ltd. the
subcontract for the construction of PC3 Plant of Rabigh Development Project, Rabigh K.S.A.
1. Purpose
To provide a procedure to be perform throughout the project to ensure conformity with
project specifications and approved drawings.
1. Scope of Work
This method statement outlined the procedure of the installation of underground HDPE
piping for Sanitary Sewers and Industrial Drainage System in the Rabigh Development
Project – PC3 in accordance with project specifications and approved drawings.
1. Location
The HDPE pipes shall be used for underground piping, above ground piping and within the
building plumbing system as specified in the approved drawings for the HDPE & Butene Area
of PC3 Plant – Rabigh Development Project, Rabigh K.S.A.
1. Definitions
SAES : Saudi Aramco Engineering Standard
EXECUTION
2.1 Materials
7. Compactors
Procedure of Work
Pipe Installers
Installation of HDPE piping shall be done by trained personnel in the proper handling and usage
of applicable tools and equipments prior to start of installation.
HDPE pipe installer shall assemble a trial joint with the same type of materials and techniques to
hours.
Loading and Unloading of pipes shall be properly controlled by using guide ropes and proper
lifting procedures. Straps, slings and ropes shall be used. Manual loading & unloading can also
HDPE pipes and fittings shall be stored out of direct sunlight in a building or under a cover that
allows free air circulation.
Racks shall conform to factory shipping packages for each pipe size. Shelves shall be provided
shall be spaced at 3 meters center maximum with the first support 1.5 meters from the end of
the pipe.
HDPE Pipes and fittings shall not be stored direct from the ground.
All supporting surfaces shall be free from sharp objects.
Pipes and fittings shall be properly protected from impact especially on their ends.
Pipe inside surfaces shall be cleaned by rags or by purging air from an air compressor before
assembly.
HDPE piping shall be socket fusion welded in accordance with the manufacturer’s instruction
HDPE piping shall be cut square using pipe cutter or fine toothed hand saw.
Chamfer or deburr pipe using files or sand papers before jointing.
HDPE pipes and fittings mating surfaces shall be clean and dry before welding.
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 4/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
Piping larger than 250 mm nominal pipe size shall be assembled in the trench.
Crane and (or) labors shall be used for placing pipes into the trench using proper tools and
equipments such as ropes, straps and slings to control and maintain proper handling procedure.
Before start of the pipe laying, the bottom of the trench shall be dry, continuous, smooth, free of
rocks and to the line and grade shown on the installation drawings.
The clean sand bedding shall be compacted according to SAES-S-070.
Pipe location, elevation and slope shall be maintained by a surveyor. A survey report shall be
pipe being installed. The sand bed shall be then adjusted accordingly to maintain the pipe on
Pipe shall be installed continuously downhill without low points and high points.
Pipe is to be anchored by partial sand covering of the pipe to prevent floatation and to maintain
At the end of every work shift, personnel performing the pipe installation shall ensure that the
pipe ends are capped to prevent entry of foreign materials.
Suspended piping shall be supported with metallic hangers of sufficient strength at maximum 3
meters interval.
Plumber’s strap, pipe clamps and brackets shall be used for suspended piping.
Prior to start of excavation, make sure that the pipe line coordinates and elevation has been
checked and verified by the surveyor.
Excavation and sand bedding shall be done mainly by equipments (excavators and loaders).
Manual excavation is required in cases where equipments are not possible or are not allowed
due to safety reasons or where manual excavation is more convenient in a specific area.
Excavated materials shall be placed at a suitable distance from the edge of excavation so that
materials do not fall back into the trench or excavated materials will be put directly to a dump
truck and will be unloaded to a designated area away from the trench.
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 5/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
Loaders shall be used for placing sand bedding materials into the trench while labors will spread
manually to meet the correct elevation and slope throughout the trench.
The minimum trench width from the bottom to 300 mm above the top of the pipe shall be 300
mm for pipe size 90 mm & below and 300 mm + Outside Diameter for pipe size 100 mm &
above.
Depth of trench shall be dug deep enough to provide a ground bed of at least 150 mm from the
Clean sand bedding layer of 150 mm thickness shall be compacted to at least 70% relative
density or 95% Proctor density.
The trench bottom shall be continuous, smooth, free of rocks and to the line and grade shown
Backfilling
Make sure that Inspection & Testing has been done and approved before any backfilling works
starts.
Backfilling shall be done mainly by equipments (loaders & compactors) while some labors
The pipe shall be covered to at least 300 mm clean sand above the top of the pipe and shall be
compacted by water flooding and hand tamping only.
Backfill above 300 mm sand cover shall be on site excavation or borrowed materials.
Backfill above sand cover shall be compacted according to ‘SAES-S-070 Table-5 Minimum
Compaction’.
Minimum cover on top of pipe shall be in accordance with ‘SAES-S-070 Table-2’.
If it is impossible to achieve the minimum cover as specified, the piping shall be protected by
concrete slab or metallic casing in accordance with SAES-L-460.
Gravity Test
Gravity sanitary sewer and Industrial drainage system shall be tested with potable water, well
water or sea water.
Gravity test shall be done from manhole to manhole or a column of water equivalent to the rim
An extension pipe is provided on the test plugs at selected location for water filling and drain
points and at least one pipe riser for the water head required that shall be accessible for visual
inspection.
Plumber’s test plugs that are not used for other purposes shall be kept open while filling of
water to release air inside the system and shall be closed when the system has been properly
vented.
Water filling into the pipe being tested shall be from a water truck or a ground level water tank
with electric or engine-driven pump. A water hose shall be placed direct to the manhole, to the
pipe being tested or to a pipe connection provided at the plumber’s test plug.
Drain valve shall be provided at the lowest portion of the pipe being tested for safe draining
after inspection.
Water used for testing can be re-used for another gravity test, for water flooding of pipe sand
Site Engineer shall organize, manage and supervise all activities related to the installation of
HDPE piping with regards to safety, quality and productivity of the over-all performance of the
work.
Site Supervisor and Foreman shall arrange all the necessary manpower, tools and
equipments and implement the approved working procedure for a proper execution of the
work with regards to safety, quality and productivity.
Surveyor shall provide all necessary coordinates and elevation at the start of excavation up to
final installation of pipes.
3.0 QA / QC
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 7/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
Kettaneh QA / QC Plan
3.2 Responsibilities
QA / QC Inspector shall make sure that all activities related to the piping installation are carried
out in accordance with the project specification and approved drawings. He shall arrange
Inspection & Testing required with TECNIMONT and PETRO Rabigh in accordance with the
QA/QC Plan. He shall maintain and keep records for all QC Documents.
Site Engineer, Supervisor and Foreman shall assist the QA/QC Inspector whatever he required
in relation to the quality of works, procedures or documents.
3.3 Test and Measurement
No special device or equipment to be used for the gravity test of underground HDPE piping.
By simply marking the water level at the manhole or pipe being tested at the start of the test,
the piping being tested shall be considered satisfactory if no reasonable drop on the water level
after the specified test period and if no evidence of water leakage on the body of the pipes,
fittings and to the joints.
3.4 Inspection
Request for Inspection shall be issued to TECNIMONT / PETRO Rabigh Project Inspection 24
hours in advance on weekdays and 48 hours in advance for weekends and holidays.
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 8/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
Guidelines
Person working with HDPE piping shall wear the Personal Protective Equipments at all times on
the job site.
All trenches shall be provided with proper barricades such as physical barriers and safety tapes.
Warning sign boards and lights shall also be provided where necessary.
Proper access such as ladders and ramps shall be provided at designated areas where workers
can go in and out the excavated area.
Spotter shall be present at the job site whenever excavators and loaders are working.
Rigger shall be present at the job site whenever pipe is to be lifted by crane.
Spotter and Rigger shall wear reflective high visibility vest.
Safety Inspector / Officer in conjunction with the site supervisor or foreman shall physically
check and conform that all safety requirements had been provided and implemented.
Operators, riggers and spotters of heavy equipments shall follow and implement proper safe
working procedure at all times.
4.3 Hazard Analysis
1. Pipe cutting and 1.Injury to worker from 1. Only trained personnel Engineer, supervisor
grinding moving parts are allowed to operate and foreman
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 9/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
3. Excavation & 1. Injury to worker and 1. only licensed operator Engineer, supervisor
Backfilling by damage to structure are allowed to operate Foreman, operator
into the trench are allowed to operate Foreman, operator
3. physical barriers to be
4. Pipe laying by mobile 1. Injury to worker and 1. only licensed operator Engineer, supervisor
crane damage to structure are allowed to operate Foreman, operator
into the trench are allowed to operate Foreman, operator
3. physical barriers to be
Tags :
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 10/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
(https://engineersblog.net/tag/method-statement-for-underground-hdpe-piping-installation/)
LEAVE A REPLY
RECENT POSTS
and-password/)
What is Nickel Electrodes? Explain in details different types of Nickel Electrodes with examples.
(https://engineersblog.net/what-is-nickel-electrodes/)
What is Tungsten Electrodes? Explain in details different types of Tungsten Electrodes with examples.
(https://engineersblog.net/what-is-tungsten-electrodes/)
What is Flux-Cored Electrodes? Explain in details different types of Flux-Cored Electrodes with
examples. (https://engineersblog.net/what-is-flux-cored-electrodes/)
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 11/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
What is Aluminum Electrodes? Explain in details different types of Aluminum Electrodes with
examples. (https://engineersblog.net/what-is-aluminum-electrodes/)
CATEGORIES
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 12/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
ARCHIVES
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 13/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 14/15
7/3/23, 5:01 PM METHOD STATEMENT FOR UNDERGROUND HDPE PIPING INSTALLATION - The Engineer's Blog
(https://www.facebook.com/engineersblog2010)
(https://www.linkedin.com/company/engineers-blog)
(https://www.youtube.com/channel/UCXKDo1X3c0P4JAONnc9moSQ)
About (https://engineersblog.net/engineering-correspondence-method-of-statement-submittals-sample-
and-template/)
/ Cart (https://engineersblog.net/cart/) / Checkout (https://engineersblog.net/checkout/)
/
Contact (https://engineersblog.net/engineering-correspondence-method-of-statement-submittals-
sample-and-template-2/)
/ My account (https://engineersblog.net/my-account/) / Shop (https://engineersblog.net/shop/)
/
Sitemap (https://engineersblog.net/engineering-correspondence-method-of-statement-submittals-
sample-and-template-3/)
Copyright ©2023 The Engineer's Blog . All rights reserved. Powered by WordPress (https://wordpress.org/)
https://engineersblog.net/method-statement-for-underground-hdpe-piping-installation/ 15/15