You are on page 1of 10

0

WORK PROCEDURE FOR THE INSTALLATION OF TOTAL 43 PAGES


INTAKE ELECT. BLDG. LOADING BAY (Including Cover)

● PROJECT CODE : B50532EA Purpose


● PROJECT NAME : MASINLOC POWER PLANT EXPANSION
□ For Information
PROJECT
□ For Review
● DOCUMENT NO.: 0 – WD865 – CA731 – 00027
● TITLE :Work Procedure for the Installation of Intake Elect. Building ■ For Approval
Loading Bay
□ For Construction
● OWNER : MASINLOC POWER PARTNERS CO.,LTD.
□ As Built

Dong
May 18, E.R. S.K
A For Approval E.R. Cortez Wook J.H.Lee H.S.Woo
2018 Cortez Hwang
Choi

Rev. PREPARED REVIEWED APPROVED CHECKED REVIEWED APPROVED


DESCRIPTION DATE
No. GTC VPCI
Owner

Contractor
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 2 of 43
ELECTRICAL BUILDING LOADING BAY

TABLE OF CONTENTS

1.0 PURPOSE………………………………………………………………….. 3

2.0 SCOPE……………………………………………………………………… 3

3.0 ROLES AND RESPONSIBILITIES……………………………………… 3

4.0 RESOURCES ……………………………………………………………… 4

5.0 PROCEDURE ……………………………………………………………… 5

6.0 ENVIRONMENT, HEALTH AND SAFETY………………………….……6

7.0 ATTACHMENT ………………………………………………………….…..7

Attachment # 01.Design Calculation of the Intake Elect. Building Loading Bay


Attachment # 02. Job Environmental Safety Analysis
Attachment # 03. Risk Assessment
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 3 of 43
ELECTRICAL BUILDING LOADING BAY

1.0 Purpose
This provides the procedure of installation Intake Electrical Building Loading Bay for Second
Floor to facilitate the handling and installation of Electrical Panels.

2.0 Scope
This procedure is applicable in accordance with the attached design calculation check for Intake
Elect. Building LoadingBay.

2.1 PROCEDURE
a. Pre-Installation
b. Installation
c. Post-Installation

3.0 Roles and Responsibilities


3.1 VPCI Project Manager - shall be the overall responsible for the implementation of this
procedure ensuring that works are completed on schedule and in conformity with
drawings and specifications.

3.2 VPCI Project EHS Manager shall ensure safe implementation of this procedure promoting an
Incident and Injury Free environment.

3.3 VPCI & GTC Global Inc. QA/QC Engineer shall be responsible for the implementation
of construction specification and standards and see to it that this written method
statement of the work shall be carried out.

3.4 GTCGlobal Inc. Construction Manager – shall have the overall responsibility for the
direction, monitoring, coordination and control of all the construction activities attached
and related to concrete works and the overall Health and Safety procedure.

3.5 GTCGlobal Inc. HSE Supervisor along with the Safety Officer shall ensure
implementation of all safety procedures, safety measures related to the nature of works
being carried out and in accordance with the HSE Plan.

3.6 GTCGlobal Site Engineer shall be directly involved in the planning and execution of the
activities. He shall be responsible for the preparation of work plan, safety action plan
and safety.
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 4 of 43
ELECTRICAL BUILDING LOADING BAY

4.0 Resources
4.1 Manpower

Construction Manager 1
Site Manager 1
QA/QC Engineer 1
Site Engineer 1
Safety Supervisor 1
Safety Officer 2
Surveyor 1
Survey Aide 2
First Aider 1
Foreman 1
Scaffolder 5
Rigger 2
Carpenter 4
Helper 4
Flagman 2
Crane Operator 1

4.2 Equipment & Tools

Crane 1
Auto level 1
Hammer -
Total Station 2
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 5 of 43
ELECTRICAL BUILDING LOADING BAY

5.0 Procedure
5.1 PRE – INSTALLATION WORK

5.1.1 Conduct pre–job orientation/briefing to all workers that would be involved in the
installation & erection of loading bay platform
5.1.2 Secure all work permits accordingly prior to start of work.

5.1.3 Check all materials which are to be used conformance & in compliance to
specifications & integrity of the material and shall be maintained in safe
condition.

5.1.4 Each system support and system components shall be capable of supporting
without failure.

5.1.5 Each platform on all working levels of scaffolds shall be fully planked or decked
with guard rail supports.

5.1.6 Start the work by bringing all material requirements on the area if possible on
the proposed nearest location of the working area.

5.1.7 Layout the location or boundaries of the proposed working scaffolding on site
and place safety barricades to ensure safe working area.

5.1.8 Lifting permit to be prepared prior to lifting if material lifting is necessary.

5.2 INSTALLATION WORKS

5.2.1 Check the location where the Loading Bay shall be installed.

5.2.2 Start the installation by erecting the system post 1.7 to 2.0 Vertical Post . Ensure
that the posts are resting on a base jack on flat and stable ground.

5.2.3 Starting 200 mm away from the Intake Concrete View Deck , install 2 or more
rows of vertical pipes spaced at 1200 mm and 1500 mm accordingly.

5.2.4 Secure all connection of system members.

5.2.5 Install U-head on top of the vertical pipes. Then, install the 75 x 125 x 6mm
sleeper to support the 50 x 100 mm wood joist. The wood joists must be spaced
at 200 mm to 600 mm. Tie the U-head, sleeper and joist using GI wires.

5.2.6 Lay the 19 mm phenolic board up to 3000 mm as the loading bay of second
floor. Using nails, fix the boards to 50 x 100 mm wood joist.

5.2.7 Provide handrails and toe boards on all sides for safety purposes.
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 6 of 43
ELECTRICAL BUILDING LOADING BAY

5.3 POST – INSTALLATION WORKS

5.3.1 Install life line for full body harness hooking during work if necessary.
5.3.2 Ensure that the structure is inspected & properly tagged (green tag) by certified
inspector prior to utilization.
5.3.3 System support shall be maintained and regularly checked.
5.3.4 In dismantling of system support, the erectors shall lower materials using a rope
& wheel or by the manual handling method known as the “handballing”.
Whichever method is used, the erectors must at all times, work from a minimum
of a decked working platform which has a handrail on all sides.

6.0 Environment, Health and Safety

6.1 All personnel must wear appropriate PPE at all times. Personnel are empowered to stop
work if safety precautions are not in place.

6.2 The Job Site Supervisor shall ensure that all Safety requirements are put in practice, copy of
MS and JHA (Attached) are available on site for guidance and consultation.

6.3 Contractor Safety Representative shall carry out the safety site inspection to ensure the
safety requirements laid out in the safe work plan are followed during and after the
completion of the works

6.4 Job Site Supervisor and Safety Representative shall be present at all time while works are in
progress.

6.5 Appropriate PTW to be prepared and implemented, modification without OWNER approval is
prohibited.

6.6 Assessed risk as necessary and communicated to concerned parties prior to start of any
work.

6.7 Safety briefing / Tool box talk must be conducted by Supervisors prior to start of work in the
language of workforce.

6.8 Incidents and injuries, damaged to property or near misses should be reported.

6.9 Good housekeeping to be maintained during the execution of activity.

6.10 A clear and good communication must be maintained by all personnel involved on the
activity.

6.11 Personnel must be trained/experienced and familiarized with the scope of works to be
undertaken. The location of marshalling point must be identified, emergency evacuation
procedure must be clear to all workers, exercises must be conducted.

6.12 Contractor Safety Manager / Representative shall review Safety Action Plan.
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 7 of 43
ELECTRICAL BUILDING LOADING BAY

5.0
7.0 Attachment

Attachment # 01.Intake Electrical Building Loading Bay Design Calculation Check

Attachment # 02.Job Environmental Safety Analysis

Attachment # 02. Risk Assessment


Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 8 of 43
ELECTRICAL BUILDING LOADING BAY

Attachment # 01.

INTAKE ELECT. BLDG. Loading Bay


Design Calculation Check
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 9 of 43
ELECTRICAL BUILDING LOADING BAY

11 of 43

Attachment # 02.

Job Environment and Safety


Analysis
Masinloc Power Plant Expansion Project Doc. No 0–WD865–CA731–00027
WORK PROCEDURE FOR THE Rev. No. A
INSTALLATION OF INTAKE
Page 10 of 43
ELECTRICAL BUILDING LOADING BAY

29 of 43

Attachment # 03.

Risk Assessment