TABLE OF CONTENT
Page
1 OBJECTIVE.................................................................................................................... 2
2 REFERENCE .................................................................................................................. 2
7 PREPARATION ............................................................................................................. 5
10 INSPECTION FLOW..................................................................................................... 8
i
Construction Method for Install Separator
Document No : Origin Rev No. Contract No :
JEL A
1 OBJECTIVE
This method is an explanation method installation project to Project Owner, Work Execution
Plan for Installation Separator at Muara Laboh Stage-2 Geothermal Power Plan Project.
2 REFERENCE
3.1 Equipments
No Description Quantity
1 Mechanical Engineer 1 Person
2 Rigging Engineer 1 Person
3 Mechanical SI 1 Person
4 Rigging Supervisor 1 person
5 QC Inspector 1 Person
6 Safety Officer 1 Person
7 Surveyor 1 Person
8 Rigger 4 Person
Construction Method for Install Separator
Document No : Origin Rev No. Contract No :
JEL A
5 WORKS OF SQUENCE
Start
Erection Separator
Aligment
Grouting
Install Accessories
Inspection
End
Construction Method for Install Separator
Document No : Origin Rev No. Contract No :
JEL A
This method statement covered detailed explanation for lifting procedure of Muara Laboh
Stage-2 Geothermal Power Plan Project
Construction Method for Install Separator
Document No : Origin Rev No. Contract No :
JEL A
7 PREPARATION
This has to be done by the construction manager. Field engineer, superintendent and
supervisor to determine the correct resources needed to perform the job.
Checking and inspection of the materials and equipment including the spare part is to
be done by the material control. He will make sure that all materials, equipment and
spare part in the packing list or shipping.
In the early stage of planning, these resource has been already identified. The schedule
of mobilization is as planed schedule made by the construction manager and engineer.
4. Checking of labour
Labour requirement for every stage of erection job is prepared by the engineer and his
erection team, which is in accordance to their planning.
On foundation separator must approval from client and subcontractor, before erection
begin.
For erection squence we need reinforce of ground condition becouse actual ground
condition now doesn’t allow for crane position.
8.1 Ensure JSA and permit to work (PTW) has been released before start to work.
8.2 Time of work follow permit to work and permit to work must be approved first.
8.3 Perform pre-job safety meeting before doing activities and review all the preparation
including all equipment.
8.6 Managed/controlled traffic properly, provide sign board before the working area in two
directions.
a. All work areas shall be kept clean on an ongoing basis or at a minimum daily
b. Containers for scrap metal shall be provide and utilized.
c. No job is complete until tools have been cleaned and properly stored, scrap and waste
material disposed of, and the equipment and work locations is in good orderly condition
9 WORK IDENTIFICATION
Before installation equipment, ensure all work civil foundation at separator area shall be release
or handover .These is work fronts that shall be release from other disciplines. Surveyor to verify
centre line and elevation equipment on install foundation.
Construction Method for Install Separator
Document No : Origin Rev No. Contract No :
JEL A
10 INSPECTION FLOW
SUBMIT APPLICATION
FOR INSPECTION
REKIND
SEML
JOINT
INSPECTION
REPAIR WORK
(JEL, REKIND
AND SUPREME)
CONTINUE TO NEXT
STEP