You are on page 1of 22

Work Instruction: Structural Inspection Workpack

Document number: SD05wi1

Scope: Global

Date Revision Description Owner Approver

Executive
Contract Services
11 Oct 2018 0 New from Draft Director for
Group Manager
Global Services

General Manager
Updated references to Sparrows Chief Technical
01 Nov 2021 01 – Managed
inspection procedures Officer
Contracts

DELIVERY ASSURED
Structural Inspection Workpack

Table of Contents
1 Purpose ............................................................................................................................................... 3
2 Aim ....................................................................................................................................................... 3
3 References .......................................................................................................................................... 3
4 Example Site Work Instruction ............................................................................................................ 4

SD05wi1 Rev 01 01 Nov 2021 2 of 22


Structural Inspection Workpack

1 Purpose

The below example of a completed Site Work Instruction for a Structural Inspection of a Crane Boom. It
can be used to assist when creating workpacks for Structural Inspections.

It gives an example of the current best practice in complying with the SD05p8 and SD05p9 procedures.

2 Aim
The aim is to ensure that the inspection gathers all the requisite information to ensure a full
understanding of the condition of the crane and that the inspection team undertaking the work have all
the information required.

3 References

Crane Structural Inspection Management


Crane Load Path Guidance
Corrosion Identification Guidance
Pedestal Crane Structural Inspection Management
Crane Structural Thickness Measurement Report

SD05wi1 Rev 01 01 Nov 2021 3 of 22


Structural Inspection Workpack

4 Example Site Work Instruction

Document Number: [Document No.] Frequency: 4Y

Title: [Title]

Client: Sparrows Offshore Services

Site: [Site]

Equipment Details: [Equipment Details] Tag No: A-9800

Revision Control
Rev Revision Status Author Check App Date
[Rev]

Important Points
• It must be ensured that the Daily Defect Report is completed and passed to the onshore team.
• Where there is a critical defect discovered the client must be made aware immediately.
• Inspections must include the areas highlighted by the engineer and any points of corrosion,
damage or previous repair.
• If paint must be removed to complete the examination this must be noted as a defect.
Summary of Task:
Title – East Crane Boom Structural Inspection

Areas of Inspection

The following areas within the East Crane Boom will require inspection during the workscope execution.

• Boom Foot Section


• 1st Mid-Section
• 2nd Mid-Section
• 3rd Mid-Section
• Cathead Section
• Ancillary Equipment

Inspection Requirements

The following inspection techniques will be implemented during the workscope execution.

• Magnetic Particle Inspection (MPI)


• Eddy Current Inspection (ECI)
• Ultrasonic Inspection (UT)
• Close Visual Inspection (CVI)

Visual Inspection

The visual inspection should be used to assess the general condition with attention to areas of corrosion,
damage/indentations, wear and other notable defects. If there is any doubt about the condition of the
component contact Sparrows immediately and refer to INS02g1.

SD05wi1 Rev 01 01 Nov 2021 4 of 22


Structural Inspection Workpack

NDT (Non-Destructive Testing) Inspection

Where there are NDT requirements, the coating thickness on the weld or components must be assessed with
locations clearly identified on the drawings. The maximum coating thickness allowable for Eddy Current
Inspection (ECI) is 2.0mm.

Where there is a requirement for protective coatings to be removed, this should be done using suitable
means. Coating removal will only be required where Eddy Current shows a defect (e.g. needle gun, wire brush
etc.)

Note: Where protective coatings have been removed to allow MPI to be carried out, the affected areas must
be recoated to the clients minimum coating standard immediately on completion of NDT or repair of the defect.
If this cannot be completed, the area must be managed as a defect as per SD05p8.

The areas inspected by Eddy Current must adhere to test specification and acceptance to latest Sparrows
eddy current procedure – INS02pBS001E.

NOTE: ANY INDICATIONS FOUND FROM CARRYING OUT AN ECI WILL REQUIRE A FULL MPI CARRIED
OUT.

The areas inspected by MPI must adhere to test specification and Acceptance to latest Sparrows MPI current
procedure - INS02pBS001M.

Wall Thickness UT (Ultrasonic Testing)

Where UT wall thickness checks are required, the inspection should be carried out by a qualified technician
using the appropriate equipment. In particular, areas of evident material loss or corrosion should be targeted
for inspection.

SD05p8 Sparrows Crane Integrity Management Procedure, Section 7.1.1, Defect Categorisation states as
guidance that the maximum limit of wear down and corrosion is <= 10% of the original thickness for non-load
path and <= 8% for load path items.

The areas inspected for Ultrasonic Thickness Measurement must adhere to test specification and Acceptance
to latest Sparrows UT current procedure - INS02pBS02U.

Nominal wall thicknesses have been specified for the boom chords and lattices are:

Boom Foot and Mid-Section Chords: 10.00mm (Minimum allowable thickness – 9mm); Cathead Chords –
11.00mm (Minimum allowable thickness – 9.9mm); Lattices: 5.00mm (Minimum allowable thickness – 4.5mm)

Coating Assessment Criteria

SD05wi1 Rev 01 01 Nov 2021 5 of 22


Structural Inspection Workpack

Coating Assessment – Linear Extent Coating Assessment – Localised Extent

Corrosion Assessment Criteria

SD05wi1 Rev 01 01 Nov 2021 6 of 22


Structural Inspection Workpack

Corrosion Assessment – Linear Extent Corrosion Assessment – Localised Extent

Pitting and Grooving Assessment Criteria

Manpower Required:

• 2-off NDT Inspectors (Rope Access)


• 1-off Level 3 Rope Access Supervisor

Work scope duration: 8 Days


References:
# Document Number Description
1. - Lloyds Code of Lifting - Table 12.3.3
2. 01 to 07 Weld ID Boom Drawings
3. 34/3089/7100 Arrangement of Boom Assembly – SHT 1
4. 34/3089/7101 Arrangement of Boom Assembly – SHT 2
5. INS02pBS01M Magnetic Particle Inspection Procedure
6. INS02pBS02U Ultrasonic Thickness Measurement
7. INS02pBS01E Eddy Current Inspection Procedure

SD05wi1 Rev 01 01 Nov 2021 7 of 22


Structural Inspection Workpack

8. TAQA-TI-009 Addendum E – Paint and Coating Systems


9. SD05p8 ******
10. SD05p9 ******
Safety Precautions:

• Hold and complete the Tool Box Talk form.


• Obtain necessary permits to carry out work scope.
• Ensure barriers are erected where required to prevent unauthorised access to the worksite during
maintenance activities.
• Ensure that the rope access risk assessment is reviewed by all personnel prior to commencing with the
workscope.
• Ensure all additional PPE is worn (Safety Goggles and Face Mask) are worn at all times when using
and preparing all paint and cleaners.
• Ensure Hand Arm Vibration (HAV) guidelines are followed when utilising the Air Drill and Needle Gun.
Platform /Site Services Required:

• Full Access to the East Crane.


• East Crane to be mechanically isolated prior to Inspection.
• Pneumatic Air Supply.
• Platform to provide a water supply for the preparation of the boom.
• All waste (paint and consumables) will require to be disposed of at the end of the workscope – the
platform is expected to facilitate this request.
Parts / Materials Required:
Qty Unit Description Part Number
5 NDT Consumables – (5 x White, 5 x Black)
1 Ultrasonic Couplant
1 Metric Sheave Gauge
1 10L Jotmastic Smart Pack HB (Part A & B) - Red
1 20L Jotun Thinner No. 17
1 5L Panel Wipe Degreaser
1 Various Paint Rollers, Sleeves, Brushes Wire Brushes and Scrapers
1 Plastic Sheet, Masking Tape
1 Mechanical Abrasives (Cup Wire Brush, Flapper Wheel, Spiral Wire Brush)
1 2L, 5L, 10L & 20L Sealable Plastic Pots
1 Safety Goggles - Uvex 9302-245 Ultrasonic
1 Safety Masks - Organic Vapour Half Face Mask - 4255-FFA2P3R
1 Microchem 3000 Yellow Suit
Equipment Required:
Qty Description
1 3 Man Rope Access Kit
1 Eddy Current Kit (Locator 2)
1 Ultrasonic set (A-scan representation)
1 Electromagnet (Y6 Yoke)
1 Tape Measure c/w Lanyard
1 Needle Gun c/w Airline
1 Air Drill
1 Pit Gauge

SD05wi1 Rev 01 01 Nov 2021 8 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value

Boom Foot Section

1. Ensure all permits are in place prior to staring the workscope.

Locate the boom in the rest, isolate crane and place a notice of work in operator’s cab.
(Sparrows resident to assist).
2.
Note: Ensure overside cover is available when working along the boom.
A visual inspection of the corrosion and coating present at each section of the boom
should be carried out and assessed as per the assessment criteria contained within the
task summary section of this procedure. Condition to be marked up on copies of the
boom drawings by the following criteria and accompanied with photographs:
a) Good condition – Minor spot rusting (0-2 Score)

b) Fair condition – Local breakdown at weld connectors and/or light rusting over
20 percent or more of areas under consideration (3-4 Score)
3.
c) Poor condition – General breakdown of coating over 20 percent or more of
areas, or hard scale at 10 percent or more at areas under consideration (5-6
Score)

Note: In the event that any defects are found further consultation should be held with
Sparrows onshore personnel.

Note: Refer to Corrosion Identification and Mitigation Procedure contained within the
appendix of this workpack.
Photograph the boom foot section. These are to include stand-off photos of this
4. section, all auxiliary equipment inspected and photos of any anomalies or defects
noted during the inspection.
Carry out Eddy Current inspection of welds detailed within weld ID drawings. Suspect
5. welds (paint flaking, corroded or cracked) should be inspected in addition to these
highlighted areas.
Carry out an Eddy Current inspection on 100% of welds at boom connection flanges
and picture frame lattice welds, noting any defects found.
6.
Note: If any weld defects are found it is important that time be taken to determine the
depth, length and orientation of defects and mark up the appropriate drawing

7. Carry out Eddy Current Inspection (100%) of all plate work to main chord welds.

Any dents or bent sections of lattice or main chords highlighted in (3) above, should
have a full MPI carried out, noting both the location of any defects and their size.
8.
Note: Where any dents or bent sections are found at category 3 or above, consultation
should be held with Sparrows onshore personnel to determine required actions.

SD05wi1 Rev 01 01 Nov 2021 9 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Carry out UT wall thickness check every 1m along the boom chord. The checks should
be carried out on all four main chords at the 12, 3, 6 and 9 o’clock positions, with the
thickness being noted in the inspection report. This is the minimum requirement, if there
are any further areas of corrosion further UT thickness checks must be carried out the
confirm the extent of wall thickness loss.

9. Note: Any areas of corrosion that falls out with the 1m location must also be UT tested.

Note: Ensure all local areas have been prepared properly for UT to allow an accurate
reading.

Note: In the event that any defects are found or more than 10% material loss at any one
location is found further consultation should be held with Sparrows onshore personnel.
Carry out UT wall thickness checks on the 10% of lattices referenced in the weld ID
drawings on each section and 100% of picture frame lattices. In addition to this, any
lattices which show corrosion will require UT thickness measurements to confirm the
10. extent of corrosion.

Note: Ensure reference is made to the lattice numbers detailed on the OS200 Weld ID
Drawings supplied.
Using a pit gauge, complete a pitting and grooving assessment of the boom foot section
making reference to the assessment criteria contained within the task summary section
of this procedure.
11.
Pitting is usually seen on horizontal components while grooving is a linear corrosion
which occurs at structural intersection in welds or heat affected zones.
Visually inspect all boom ancillary equipment noting any defects found. These defects
could include missing bolts, bent, damaged or badly corroded brackets and unsecured
equipment. A close visual inspection (CVI) should also include reports on items in good
serviceable condition.
Equipment to be checked should include but not be exclusive to the following: -
12.
• Walkways: including, grating, handrails stanchions, fasteners, etc.
• Electrical Conduit
• Cable Trays
• Limit Switches
• Light Brackets
• Flange connection bolts
Carry out physical test of the boom foot pins by the crane operator raising / lowering the
13. boom under visual observation. Any anomalies either visual or audible during operation,
consult crane operator.
Carry out 100% NDT of boom foot clevis / connection lugs where accessible.

14. Note: In the event that any defects are found using these inspection methods, further
consultation should be held with Sparrows onshore personnel.

15. Inspect boom flange connection bolts for any visible signs of wear.

SD05wi1 Rev 01 01 Nov 2021 10 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value

Boom 1st Mid-Section

A visual inspection of the corrosion and coating present at each section of the boom
should be carried out and assessed as per the assessment criteria contained within the
task summary section of this procedure. Condition to be marked up on copies of the
boom drawings by the following criteria and accompanied with photographs:
a) Good condition – Minor spot rusting (0-2 Score)

b) Fair condition – Local breakdown at weld connectors and/or light rusting over 20
percent or more of areas under consideration (3-4 Score)
16.
c) Poor condition – General breakdown of coating over 20 percent or more of
areas, or hard scale at 10 percent or more at areas under consideration (5-6
Score)
Note: In the event that any defects are found or more than 10% material loss at any one
location is found further consultation should be held with Sparrows onshore personnel.

Note: Refer to Corrosion Identification and Mitigation Procedure contained within the
appendix of this workpack.
Photograph the boom 1st mid-section section. These are to include stand-off photos of
17. this section, all auxiliary equipment inspected and photos of any anomalies or defects
noted during the inspection.
Carry out Eddy Current inspection of welds detailed within weld ID drawings. Suspect
18. welds (paint flaking, corroded or cracked) should be inspected in addition to these
highlighted areas.
Carry out an Eddy Current inspection on 100% of welds at boom connection flanges and
picture frame lattice welds, noting any defects found.
19.
Note: If any weld defects are found it is important that time be taken to determine the
depth, length and orientation of defects and mark up the appropriate drawing

20. Carry out Eddy Current inspection on all butt welds on the main chords.

Any dents or bent sections of lattice or main chord highlighted in (16) above, should have
a full MPI carried out, noting both the location of any defects and their size.
21.
Note: Where any dents or bent sections are found at category 3 or above, consultation
should be held with Sparrows onshore personnel to determine required actions.

SD05wi1 Rev 01 01 Nov 2021 11 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Carry out UT wall thickness check every 1m along the boom chord. The checks should
be carried out on all four main chords at the 12, 3, 6 and 9 o’clock positions, with the
thickness being noted in the inspection report. This is the minimum requirement, if
there are any further areas of corrosion further UT thickness checks must be carried
out the confirm the extent of wall thickness loss.

Note: Any areas of corrosion that falls out with the 1m location must also be UT tested.
22.
Note: Ensure all local areas have been prepared properly for UT to allow an accurate
reading.

Note: In the event that any defects are found or more than 10% material loss at any
one location is found further consultation should be held with Sparrows onshore
personnel.
Carry out UT wall thickness checks on the 10% of lattices referenced in the weld ID
drawings on each section and 100% of picture frame lattices. In addition to this, any
lattices which show corrosion will require UT thickness measurements to confirm the
23. extent of corrosion.

Note: Ensure reference is made to the lattice numbers detailed on the OS200 Weld ID
Drawings supplied.
Using a pit gauge, complete a pitting and grooving assessment of the boom 1 st mid-
section making reference to the assessment criteria contained within the task summary
section of this procedure.
24.
Pitting is usually seen on horizontal components while grooving is a linear corrosion
which occurs at structural intersection in welds or heat affected zones.

Visually inspect all boom ancillary equipment noting any defects found. These defects
could include missing bolts, bent, damaged or badly corroded brackets and unsecured
equipment. A close visual inspection (CVI) should also include reports on items in good
serviceable condition.
Equipment to be checked should include but not be exclusive to the following: -
25.
• Walkways: including, grating, handrails stanchions, fasteners, etc.
• Electrical Conduit
• Cable Trays
• Light Brackets
• Flange connection bolts

26. Inspect boom flange connection bolts for any visible signs of wear.

Boom 2nd Mid-Section

SD05wi1 Rev 01 01 Nov 2021 12 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
A visual inspection of the corrosion and coating present at each section of the boom
should be carried out and assessed as per the assessment criteria contained within the
task summary section of this procedure. Condition to be marked up on copies of the
boom drawings by the following criteria and accompanied with photographs:
a) Good condition – Minor spot rusting (0-2 Score)

b) Fair condition – Local breakdown at weld connectors and/or light rusting over 20
percent or more of areas under consideration (3-4 Score)
27.
c) Poor condition – General breakdown of coating over 20 percent or more of
areas, or hard scale at 10 percent or more at areas under consideration (5-6
Score)
Note: In the event that any defects are found or more than 10% material loss at any one
location is found further consultation should be held with Sparrows onshore personnel.

Note: Refer to Corrosion Identification and Mitigation Procedure contained within the
appendix of this workpack.
Photograph the boom 2nd mid-section section. These are to include stand-off photos of
28. this section, all auxiliary equipment inspected and photos of any anomalies or defects
noted during the inspection.
Carry out Eddy Current inspection of welds detailed within weld ID drawings. Suspect
29. welds (paint flaking, corroded or cracked) should be inspected in addition to these
highlighted areas.

Carry out an Eddy Current inspection on 100% of welds at boom connection flanges
and picture frame lattice welds, noting any defects found.
30.
Note: If any weld defects are found it is important that time be taken to determine the
depth, length and orientation of defects and mark up the appropriate drawing

31. Carry out Eddy Current inspection (100%) on all butt welds on the main chords.

Any dents or bent sections of lattice or main chord highlighted in (27) above, should have
a full MPI carried out, noting both the location of any defects and their size.
32.
Note: Where any dents or bent sections are found at category 3 or above, consultation
should be held with Sparrows onshore personnel to determine required actions.

SD05wi1 Rev 01 01 Nov 2021 13 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Carry out UT wall thickness check every 1m along the boom chord. The checks should
be carried out on all four main chords at the 12, 3, 6 and 9 o’clock positions, with the
thickness being noted in the inspection report. This is the minimum requirement, if there
are any further areas of corrosion further UT thickness checks must be carried out the
confirm the extent of wall thickness loss.

33. Note: Any areas of corrosion that falls out with the 1m location must also be UT tested.

Note: Ensure all local areas have been prepared properly for UT to allow an accurate
reading.

Note: In the event that any defects are found or more than 10% material loss at any one
location is found further consultation should be held with Sparrows onshore personnel.
Carry out UT wall thickness checks on the 10% of lattices referenced in the weld ID
drawings on each section and 100% of picture frame lattices. In addition to this, any
lattices which show corrosion will require UT thickness measurements to confirm the
34. extent of corrosion

Note: Ensure reference is made to the lattice numbers detailed on the OS200 Weld ID
Drawings supplied.
Carry out UT wall thickness check every 1m along the boom chord. The checks should
be carried out on all four main chords at the 12, 3, 6 and 9 o’clock positions, with the
thickness being noted in the inspection report. This is the minimum requirement, if there
are any further areas of corrosion further UT thickness checks must be carried out the
confirm the extent of wall thickness loss.

Note: Any areas of corrosion that falls out with the 1m location must also be UT tested.
35.
Note: Ensure all local areas have been prepared properly for UT to allow an accurate
reading.

Note: In the event that any defects are found or more than 10% material loss at any
one location is found further consultation should be held with Sparrows onshore
personnel.
Carry out UT wall thickness checks on a minimum of 10% of lattices (selected prior to
mobilisation and referenced in the weld ID drawings) chosen at random on each section
and 100% of picture frame lattices. All lattices which show corrosion will require UT
thickness measurements to confirm the extent of corrosion.

36. Note: Minimum allowance – 10% = 4.5mm. All Readings of 4.5mm or less will require
further reading to confirm the extent of the area of corrosion/wall loss by means of
corrosion mapping.

Note: Ensure reference is made to the lattice numbers detailed on the OS200 Weld ID
Drawings supplied.

SD05wi1 Rev 01 01 Nov 2021 14 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Using a pit gauge, complete a pitting and grooving assessment of the boom 2 nd mid-
section making reference to the assessment criteria contained within the task summary
section of this procedure.
37.
Pitting is usually seen on horizontal components while grooving is a linear corrosion
which occurs at structural intersection in welds or heat affected zones.
Visually inspect all boom ancillary equipment noting any defects found. These defects
could include missing bolts, bent, damaged or badly corroded brackets and unsecured
equipment. A close visual inspection (CVI) should also include reports on items in good
serviceable condition.
Equipment to be checked should include but not be exclusive to the following:
38.
• Walkways: including, grating, handrails stanchions, fasteners, etc.
• Electrical Conduit
• Cable Trays
• Light Brackets
• Flange connection bolts

39. Inspect boom flange connection bolts for any visible signs of wear.

Boom 3rd Mid-Section

A visual inspection of the corrosion and coating present at each section of the boom
should be carried out and assessed as per the assessment criteria contained within the
task summary section of this procedure. Condition to be marked up on copies of the
boom drawings by the following criteria and accompanied with photographs:
a) Good condition – Minor spot rusting (0-2 Score)

b) Fair condition – Local breakdown at weld connectors and/or light rusting over 20
percent or more of areas under consideration (3-4 Score)
40.
c) Poor condition – General breakdown of coating over 20 percent or more of
areas, or hard scale at 10 percent or more at areas under consideration (5-6
Score)
Note: In the event that any defects are found further consultation should be held with
Sparrows onshore personnel.

Note: Refer to Corrosion Identification and Mitigation Procedure contained within the
appendix of this workpack.
Photograph the boom 3rd mid-section. These are to include stand-off photos of this
41. section, all auxiliary equipment inspected and photos of any anomalies or defects noted
during the inspection.
Carry out Eddy Current inspection of welds detailed within weld ID drawings. Suspect
42. welds (paint flaking, corroded or cracked) should be inspected in addition to these
highlighted areas.

SD05wi1 Rev 01 01 Nov 2021 15 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Carry out an Eddy Current inspection on 100% of welds at boom connection flanges and
picture frame lattice welds, noting any defects found.
43.
Note: If any weld defects are found it is important that time be taken to determine the
depth, length and orientation of defects and mark up the appropriate drawing.

44. Carry out Eddy Current inspection (100%) on all butt welds on the main chords.

Any dents or bent sections of lattice or main chord highlighted in (42) above, should have
a full MPI carried out, noting both the location of any defects and their size.
45.
Note: Where any dents or bent sections are found at category 3 or above, consultation
should be held with Sparrows onshore personnel to determine required actions.
Carry out UT wall thickness check every 1m along the boom chord. The checks should
be carried out on all four main chords at the 12, 3, 6 and 9 o’clock positions, with the
thickness being noted in the inspection report. This is the minimum requirement, if there
are any further areas of corrosion further UT thickness checks must be carried out the
confirm the extent of wall thickness loss.

Note: Any areas of corrosion that falls out with the 1m location must also be UT tested.
46.
Note: Ensure all local areas have been prepared properly for UT to allow an accurate
reading.

Note: In the event that any defects are found or more than 10% material loss at any
one location is found further consultation should be held with Sparrows onshore
personnel.
Carry out UT wall thickness checks on the 10% of lattices referenced in the weld ID
drawings on each section and 100% of picture frame lattices. In addition to this, any
lattices which show corrosion will require UT thickness measurements to confirm the
47. extent of corrosion.

Note: Ensure reference is made to the lattice numbers detailed on the OS200 Weld ID
Drawings supplied.

Using a pit gauge, complete a pitting and grooving assessment of the boom foot section
making reference to the assessment criteria contained within the task summary section
of this procedure.
48.
Pitting is usually seen on horizontal components while grooving is a linear corrosion
which occurs at structural intersection in welds or heat affected zones.

SD05wi1 Rev 01 01 Nov 2021 16 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Visually inspect all boom ancillary equipment noting any defects found. These defects
could include missing bolts, bent, damaged or badly corroded brackets and unsecured
equipment. A close visual inspection (CVI) should also include reports on items in good
serviceable condition.
Equipment to be checked should include but not be exclusive to the following:
49.
• Walkways: including, grating, handrails stanchions, fasteners, etc.
• Electrical Conduit
• Cable Trays
• Light Brackets
• Flange connection bolts

50. Inspect boom flange connection bolts for any visible signs of wear.

Cathead Section

A visual inspection of the corrosion and coating present at each section of the boom
should be carried out and assessed as per the assessment criteria contained within the
task summary section of this procedure. Condition to be marked up on copies of the
boom drawings by the following criteria and accompanied with photographs:
a) Good condition – Minor spot rusting (0-2 Score)

b) Fair condition – Local breakdown at weld connectors and/or light rusting over 20
percent or more of areas under consideration (3-4 Score)
51.
c) Poor condition – General breakdown of coating over 20 percent or more of
areas, or hard scale at 10 percent or more at areas under consideration (5-6
Score)
Note: In the event that any defects are found further consultation should be held with
Sparrows onshore personnel.

Note: Refer to Corrosion Identification and Mitigation Procedure contained within the
appendix of this workpack.
Photograph the boom cathead section. These are to include stand-off photos of this
52. section, all auxiliary equipment inspected and photos of any anomalies or defects noted
during the inspection.
Carry out Eddy Current inspection of welds detailed within weld ID drawings. Suspect
53. welds (paint flaking, corroded or cracked) should be inspected in addition to these
highlighted areas.
Carry out an Eddy Current inspection on 100% of welds at boom connection flanges
and picture frame lattice welds, noting any defects found.
54.
Note: If any weld defects are found it is important that time be taken to determine the
depth, length and orientation of defects and mark up the appropriate drawing

55. Carry out Eddy Current Inspection (100%) of all plate work to main chord welds.

SD05wi1 Rev 01 01 Nov 2021 17 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Any dents or bent sections of lattice or main chord should have a full MPI carried out,
noting both the location of any defects and their size.
56.
Note: Where any dents or bent sections are found at category 3 or above, consultation
should be held with Sparrows onshore personnel to determine required actions.
Carry out UT wall thickness check every 1m along the boom chord. The checks should
be carried out on all four main chords at the 12, 3, 6 and 9 o’clock positions, with the
thickness being noted in the inspection report. This is the minimum requirement, if there
are any further areas of corrosion further UT thickness checks must be carried out the
confirm the extent of wall thickness loss.

57. Note: Any areas of corrosion that falls out with the 1m location must also be UT tested.

Note: Ensure all local areas have been prepared properly for UT to allow an accurate
reading.

Note: In the event that any defects are found or more than 10% material loss at any one
location is found further consultation should be held with Sparrows onshore personnel.
Carry out UT wall thickness checks on the 10% of lattices referenced in the weld ID
drawings on each section and 100% of picture frame lattices. In addition to this, any
lattices which show corrosion will require UT thickness measurements to confirm the
58. extent of corrosion.

Note: Ensure reference is made to the lattice numbers detailed on the OS200 Weld ID
Drawings supplied.

59. Carry out Eddy Current inspection on the sheave shaft mountings on the boom cathead.
Using a pit gauge, complete a pitting and grooving assessment of the boom foot section
making reference to the assessment criteria contained within the task summary section
of this procedure.
60.
Pitting is usually seen on horizontal components while grooving is a linear corrosion
which occurs at structural intersection in welds or heat affected zones.
Visually inspect all boom ancillary equipment noting any defects found. These defects
could include missing bolts, bent, damaged or badly corroded brackets and unsecured
equipment. A close visual inspection (CVI) should also include reports on items in good
serviceable condition.
Equipment to be checked should include but not be exclusive to the following: -
61.
• Walkways: including, grating, handrails stanchions, fasteners, etc.
• Sheaves
• Electrical Conduit
• Cable Trays
• Light Brackets
• Flange connection bolts

SD05wi1 Rev 01 01 Nov 2021 18 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Visually inspect the sheaves & pins on the Boom tip assembly for indications of damage
62. or corrosion noting any defects found. The rope groove of all sheaves should also be
examined around the section of the sheave which are accessible using sheave gauges.
Carry out Eddy Current inspection (100%) on the boom tip termination.

63.
Note: In the event that any defects are found using these inspection methods, further
consultation should be held with Sparrows onshore personnel.

64. Inspect boom flange connection bolts for any visible signs of wear.

Boom Preparation and Painting

To avoid further deterioration of the boom where paint/scale has been removed, a
solvent degrease, hand prep to ST2 (minimum) and coat with Jotun SmartPack will be
applied.
65.
With reference to the Repair Charts contained within section 4 of the Corrosion
Identification and Mitigation Procedure, the coating breakdown, general corrosion and
pitting and grooving scores for each section will determine the future repair requirements.

Before proceeding, the following conditions must be observed:

66. • Do not apply the coating if the substrate is wet or likely to become wet.
• Do not apply coating if the weather if deteriorating.
• Do not apply coating in high wind conditions.
Where paint/scale has been removed to complete the boom inspection and where any
areas of paint breakdown is evident, complete the following:

With reference to Document No. TAQA-TI-009 (Addendum E – Paint and Coating


Systems), prepare the applicable boom section surface using the following equipment to
ST2:

• Minor Areas of Rust – Utilise Sandpaper to remove all signs of mill scale or rust.
Ensure as little of the surrounding painting work is removed. Ensure all paint
edges are chamfered.
67. • Major Areas of Rust – Utilise a combination of the chipping hammer, wire
brushes, air drill c/w cup and spiral wire brush attachments and a needle gun for
areas with limited access.
• Flaked Paint – Utilise scrappers and wire brushes to remove all un-bonded
material back to a firm edge. Ensure the below surface is prepared using
sandpaper and/or air drill c/w flapper wheel.
• Glossy Finishes – Light abrasion to provide a physical key.

Note: When using a wire brush or abrasive attachments, be careful not to polish the
surface as this will reduce adhesion of the coating.

SD05wi1 Rev 01 01 Nov 2021 19 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Once all mill scale, rust and un-bonded material is removed from the boom surface,
degrease the complete surface using Panel Wipe and apply with rags / brush. Ensure all
surfaces are thoroughly cleaned with all dust and debris removed.
68.
Note: Ensure the MSDS for Panel Wipe is reviewed prior to application.

Note: Ensure full PPE including face mask and safety goggles are worn throughout.
On completion ensure all rags are disposed of as per platform requirements. Any
remaining panel wipe should be transferred back into the original container (using the
69.
funnels supplied to minimise any spills) and any plastic containers and brushes used
should be thoroughly cleaned.
Ensure the worksite below the applicable boom section is cleaned of any loose debris
70.
and tidy away all equipment and materials.
Ensure the applicable boom surface is dry with no signs of debris remaining from the
surface preparation stage.
71.
Note: If it has been longer than one full shift since the boom was prepared, clean all
surfaces with a rag / brush as a precaution.

Using the plastic sheeting and tape supplied, fully cover all electrical components,
72.
wiring (including cable trays) to protect against any paint spray or spills.
In order to mix the top coat paint, follow the following steps:

• Mix the base and curing agent inside the dry goods container to prevent any
contamination – it is recommended that the temperature during this process is
18 Degree Celsius or higher.
• Only start mixing paint if a minimum of 1 hour working time is available. Once
mixed the working pot life is 1 hour.
• Locate the paint – Jotmastic Smart Pack HB (A & B) - Red
73.
• Ensure all plastic containers are clear of any dust or debris before used for
mixing / storing paint.
• Measure out equal parts of A & B and empty into either a 20 or 10 Litre plastic
containers. Ensure the measurement is exact.
• Using the air drill and mixing paddle, thoroughly mix Part A then combine the
entire contents with Part B and mix until satisfied with the consistency.
• Once the paint has been thoroughly mixed, split the complete contents between
the 2L paint pots or roller trays.
Ensure the work site directly below the specified boom is barriered off due to potential
for paint spills.
74.
Note: If possible, cover any deck areas and equipment (not operational) with plastic
sheeting or rags to avoid any stains from paint spills.

SD05wi1 Rev 01 01 Nov 2021 20 of 22


Structural Inspection Workpack

Procedure
Tick on
# Instruction completion
or add value
Apply the paint to the boom surfaces using a paint brush (utilise the synthetic bristle
brushes supplied). Please note that all brush marks will flatten within 5-10 minutes after
application.

75.
Ensure a smooth coat is applied with uniform thickness (if possible) with no detrimental
bush marks. Paint must be worked into all corners and crevices.

Note: The surface will be touch dry within 7-10 hours (at 5 to 10 Degrees Celcuis).
Once all painting has been completed, complete the following:

76. • Dispose of any mixed paint in accordance with the platform procedure.
• Wash surfaces (where spills have occurred) with Jotun Thinner No. 17. Ensure
reference is made to the MSDS before using.
• Dispose of all rags, equipment (brushes or rollers) and used plastic containers.
Ensure all items - painting and NDT equipment have been removed from the worksite
77.
and prepared for backload.

SD05wi1 Rev 01 01 Nov 2021 21 of 22


Structural Inspection Workpack

On Completion of this Procedure please certify below. Date

I have carried out all of the steps as listed above Print Name
1 and have ticked or added a value to each step as
required Sign

Any anomalies that were found during Print Name


2 completion of the procedure steps are listed in
the Comments Section below Sign

Comments:

SD05wi1 Rev 01 01 Nov 2021 22 of 22

You might also like