1.03 3/4 " Metal M-066 1.04 Hire of Mixer P-001 1.05 Water M-157 1.06 SK Labour L-003 1.07 U / SK Labourer L-007 Total for Rate for 1 Rate(Say) Rate(Say)
05.A.02 Mixing Concrete 1:3:6(1 1/2")
No Item Description Item Ref
1.01 Cement M-026 1.02 Sand M-113 1.03 1 1/2 " Metal M-065 1.04 Hire of Mixer P-001 1.05 Water M-157 1.06 SK Labour L-003 1.07 U / SK Labourer L-007 Total for Rate for 1 Rate(Say) Rate(Say)
05.A.03 Mixing Concrete 1:2 1/2 :5 (1")
No Item Description Item Ref
1.01 Cement M-026 1.02 Sand M-113 1.03 1 " Metal M-064 1.04 Hire of Mixer P-001 1.05 Water M-157 1.06 SK Labour L-003 1.07 U / SK Labourer L-007 Total for Rate for 1 Rate(Say) Rate(Say)
05.A.04 Mixing Concrete 1:2:4(3/4")- Grade 20
No Item Description Item Ref
1.01 Cement M-026 1.02 Sand M-113 1.03 3/4 " Metal M-066 1.04 Hire of Mixer P-001 1.05 Water M-157 1.06 SK Labour L-003 1.07 U / SK Labourer L-007 Total for Rate for 1 Rate(Say) Rate(Say)
05.A.05 Mixing Concrete 1:1:2(3/4")-Garde 30
No Item Description Item Ref
1.01 Cement M-026 1.02 Sand M-113 1.03 3/4 " Metal M-066 1.04 Hire of Mixer P-001 1.05 Water M-157 1.06 SK Labour L-003 1.07 U / SK Labourer L-007 Total for Rate for 1 Rate(Say) Rate(Say) Mixing Concrete
Analysis for 1 Cube
Unit Quantity Rate Amount
Bag 23 780 17940
Cube 0.42 8500 3570
Cube 0.82 9000 7380 Day 0.333 4500 1498.5 Gal 150 0.3 45 Day 0.333 2000 666 Day 2 2000 4000 0 Rate for 1 35099.5 Rate for 1 35099.5 1Cube 35100 1m3 12402.83
Analysis for 1 Cube
Unit Quantity Rate Amount Bag 13 780 10140 Cube 0.53 8500 4505 Cube 0.92 3500 3220 Day 0.333 4500 1498.5 Gal 110 0.3 33 Day 0.333 2000 666 Day 2 2000 4000 0 Rate for 1 24062.5 Rate for 1 24062.5 1Cube 24060 1m3 8501.767
Analysis for 1 Cube
Unit Quantity Rate Amount Bag 14 780 10920 Cube 0.6 8500 5100 Cube 0.9 0 0 Day 0.333 4500 1498.5 Gal 100 0.3 30 Day 0.333 2000 666 Day 2 2000 4000 0 Rate for 1 22214.5 Rate for 1 22214.5 1Cube 22210 1m3 7848.057
Analysis for 1 Cube
Unit Quantity Rate Amount Bag 18 780 14040 Cube 0.5 8500 4250 Cube 0.88 9000 7920 Day 0.333 4500 1498.5 Gal 120 0.3 36 Day 0.333 2000 666 Day 2 2000 4000 0 Rate for 1 32410.5 Rate for 1 32410.5 1Cube 32410 1m3 11452.3
Analysis for 1 Cube
Unit Quantity Rate Amount Bag 31 780 24180 Cube 0.44 8500 3740 Cube 0.96 9000 8640 Day 0.333 4500 1498.5 Gal 200 0.3 60 Day 0.333 2000 666 Day 2 2000 4000 0 Rate for 1 42784.5 Rate for 1 42784.5 1Cube 42780 1m3 15116.61 20 concrete 1:2:4, for grade 25 concrete 1:1.5:3 and for grade 30 concrete 1:1:2)
M15 1:02:04 15 MPa 2175 psi
M20 01:05.5 20 MPa 2900 psi
Standard Grade of Concrete
M25 1:01:02 Mixing Concrete Mixing Concrete 1:3:6(1 1/2")-G15 Analysis for 1 Cube No Item Description Item Ref Unit Quantity Rate Amount 1.01 Cement M-026 Bag 13 780 10140 1.02 Sand M-113 Cube 0.53 8500 4505 1.03 1 1/2 " Metal M-065 Cube 0.92 3500 3220 1.04 Hire of Mixer P-001 Day 0.333 4500 1498.5 1.05 Water M-157 Gal 110 0.3 33 1.06 SK Labour L-003 Day 0.333 2000 666 1.07 U / SK Labourer L-007 Day 2 2000 4000
Mixing Concrete 1:2:4(3/4")- Grade 20
Analysis for 1 Cube No Item Description Item Ref Unit Quantity Rate Amount 1.01 Cement M-026 Bag 18 780 14040 1.02 Sand M-113 Cube 0.5 8500 4250 1.03 3/4 " Metal M-066 Cube 0.88 9000 7920 1.04 Hire of Mixer P-001 Day 0.333 4500 1498.5 1.05 Water M-157 Gal 120 0.3 36 1.06 SK Labour L-003 Day 0.333 2000 666 1.07 U / SK Labourer L-007 Day 2 2000 4000 Total for #REF! #REF! 32410.5 Rate for 1 #REF! 32410.5 Rate(Say) 1Cube 32410 Rate(Say) 1m3 11452.3
Mixing Concrete 1:1-1/2:3(3/4") -G25
Analysis for 1 Cube No. Item Description Item Ref Unit Quantity Rate Amount 1.01 Cement M-026 Bag 23 780 17940 1.02 Sand M-113 Cube 0.42 8500 3570 1.03 3/4 " Metal M-066 Cube 0.82 9000 7380 1.04 Hire of Mixer P-001 Day 0.333 4500 1498.5 1.05 Water M-157 Gal 150 0.3 45 1.06 SK Labour L-003 Day 0.333 2000 666 1.07 U / SK Labourer L-007 Day 2 2000 4000 Total for 0 Rate for 1 35099.5 Rate for 1 Rate for 1 35099.5 Rate(Say) 1Cube 35100 Rate(Say) 1m3 12402.83
Mixing Concrete 1:1:2(3/4")-Garde 30
Analysis for 1 Cube No Item Description Item Ref Unit Quantity Rate Amount 1.01 Cement M-026 Bag 31 780 24180 1.02 Sand M-113 Cube 0.44 8500 3740 1.03 3/4 " Metal M-066 Cube 0.96 9000 8640 1.04 Hire of Mixer P-001 Day 0.333 4500 1498.5 1.05 Water M-157 Gal 200 0.3 60 1.06 SK Labour L-003 Day 0.333 2000 666 1.07 U / SK Labourer L-007 Day 2 2000 4000 Total for 0 Rate for 1 42784.5 Rate for 1 Rate for 1 42784.5 Rate(Say) 1Cube 42780 Rate(Say) 1m3 15116.61 05.A.02 Mixing Concrete 1:3:6(1 1/2") Analysis for No Item DescrItem Ref Unit 1.01 Cement M-026 Bag 1.02 Sand M-113 Cube 1.03 1 1/2 " MetM-065 Cube 1.04 Hire of MixP-001 Day 1.05 Water M-157 Gal 1.06 SK Labour L-003 Day 1.07 U / SK LabL-007 Day 1 Cube Quantity Rate Amount 13 780 10140 0.53 8500 4505 0.92 3500 3220 0.333 4500 1498.5 110 0.3 33 0.333 2000 666 2 2000 4000 Mixing Concrete Mixing Concrete 1:3:6(1 1/2")-G15 Analysis for 1 Cube Item Description Item Ref Unit Quantity Cement M-026 Bag 13 Sand M-113 Cube 0.53 1 1/2 " Metal M-065 Cube 0.92
Add Waistage -10%
Mixing Concrete 1:2:4(3/4")- Grade 20
Analysis for 1 Cube Item Description Item Ref Unit Quantity Cement M-026 Bag 18 Sand M-113 Cube 0.5 3/4 " Metal M-066 Cube 0.88
Add Waistage -10%
Mixing Concrete 1:1-1/2:3(3/4") -G25
Analysis for 1 Cube Item Description Item Ref Unit Quantity Cement M-026 Bag 23 Sand M-113 Cube 0.42 3/4 " Metal M-066 Cube 0.82 Add Waistage -10%
Mixing Concrete 1:1:2(3/4")-Garde 30
Analysis for 1 Cube Item Description Item Ref Unit Quantity Cement M-026 Bag 31 Sand M-113 Cube 0.44 3/4 " Metal M-066 Cube 0.96