PROJECT:
DOCUMENT TITLE:
Rev. Acknowledge
Date Revision Details Prepared by Reviewed by Approved by
No. by
IMPORTANT:
The information contain herein is the propriety property of Messrs.
Pro-Matrix Private, Limited
The possessor agrees to the following:
1. Not to reproduce or copy it,
2. Not to reveal or publish it in whole or part, and
3. To maintain this document in confidence.
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 1 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
1. Content
Introduction
References
Material / Equipment
Permit Application / Requirements
Work Execution Procedures
Unloading Equipment
Description of works
Risk Assessment and Control Measures
Inspection
2. Introduction
This method of statement is prepared prior to performing the activity of Installation Chilled
Water Pipes and it’s support system and brackets. The purpose of this work method statement is to
ensure that all installation pipe is carried out in proper, control condition and safe environment. all
of the personnel involve in this activity shall read and understand fully this document and agree to
obey and follow strictly before starting works.
3. References
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 2 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
3.1.22 JKT-3-DWG-M-101.7
3.1.21 JKT-3-DWG-M-101.8
3.1.22 JKT-3-DWG-M-101.9
3.1.23 JKT-3-DWG-M-105
3.1.24 JKT-3-DWG-M-105.1
3.1.25 JKT-3-DWG-M-106
3.1.26 JKT-3-DWG-M-106.1
3.1.27 JKT-3-DWG-M-107
3.1.28 JKT-3-DWG-M-107.1
3.1.29 JKT-3-DWG-M-108
3.1.30 JKT-3-DWG-M-108.1
3.1.31 JKT-3/ACMV Particular Technical Specification.
4. Material / Equipment
4.1 Materials
1. CHW Pipe
2. Gate Valve
3. Coupling Joins and accessories.
4. Flange both connection.
5. UNP for bracket support
6. Dyna bolt / Dyna set.
4.2 Equipment
1. Hand tools
2. Cain Block and Pulleys
3. Scaffolding
4. Cutting Machine
5. Welding Machine
6. Threading Machine
7. Spirit level
8. Pipe Wrench
9. Spanner
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 3 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
5.2 Requirements
Ensure that all tools are in good and working condition and also have been inspected to
ensure its workability prior to any commencement of works.
All the material installation pipe and accessories delivered to side shall be inspected.
Ensure all the sleeves for installation pipe as per approved shop drawing and specification.
Adequate precautions and protection / isolation of all live systems along working area are
to be isolated before any work is carried out especially on the riser area.
Buddy system is required when working at the riser area (East & West).
Adequate precautions and proper protection are to be done before any work is carried out.
Housekeeping in to be done during and after work.
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 4 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 5 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
7. Unloading Equipment
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 6 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
8. Description of Work
8.1 Main Works
Installation of Chilled Water Pipe and Brackets.
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 7 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
Waterproofing and Water Pond Test will be conducted (kindly refer to water pond
testing)
Upon Completion of Water Ponding Test, grouting beneath the Bracket Support
(UNP)at all area will process before the installation/lay of Chilled Water Pipes.
There is no more drilling will be conducted on the installed Bracket Support (UNP) to
ensure that there will be no more vibration on the installed bracket it’s grout to
maintain it’s stability.
Angle bar to be welded into Bracket Support (UNP) to hold the Chilled Water Pipe
into position for it’s firmness and stability.
Delivery and installation/lay of Chilled Water will proceed.
Cutting Galvanized/Black Steel Pipe
Galvanized steel pipe, shall be used in cooling water piping, potable water supply
piping. Pipe shall be marked accurately and then cut according to dimensions shown
on drawing or the dimensions most suitable for the conditions of field installation.
Cutting shall be done using pipe cutting machine, but for big pipe cutting shall be
done by oxy-acetylene cutting outfit. Pipe ends shall be beveled using grinder. Oxy-
acetylene and arc cutting is acceptable only, if followed by grinding smoothly.
Welding Joint for Steel Pipe and Fitting
- Making Groove : Pipe thickness t≦4.0(Pipe size≦50A) I type Groove
Groove、t>4.0(Pipe size≧65A) V type Groove
I-type Groove SNI Standard(Pipe size ≤ 50A) V- type Groove SNI Standard(Pipe size ≥ 65A)
Figure 3 : Fit-up & Gap Welding Detail
- Cleaning : Take off lubricating (cutting) oil, dust and clean pipe
(Inside & Outside of Pipe) completely.
- Welding Rod : Use welding rod as shown in table-1, as follows.
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 8 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
Use dried and non-crumble welding rod. Welding rod should not be stored in
wetted room.
Table-2, Show recommended electric arc-welding machine setting for different pipe sizes.
(Sample
Pipe Size ~ 32A 40A ~ 65A 80A ~ 600A
current)
Current
60A ~ 100A 60A ~ 100A 80 ~ 120
(A)
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 9 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
Pipe Supporting
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 10 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
Detail pipe
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 11 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
Table 3 : Interval Support and Bolt Size for Horizontal & Vertical Pipe
Pipe Size ( A )
Item
15 20 25 32 40 50 65 80 100 125 150 ≥ 200
Additional Support
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 12 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
To double check and ensure the size of the Chilled Water Pipe is correct on a specific
location. May refer to approved Chilled Water Pipe under raised floor layout and
Schematic Diagram for accurate installation/lay of pipes.
To install a temporary short pipe (in-chian) on the valve location (note : the size and
dimension of the valve will be the exact dimension of short pipe. Contractor/PMX to
refer to approved Material selection for size and dimension)
Proper leveling of pipe to be carried out upon completion of all laid pipes.
Replacement of short pipe (in-chian) upon the arrival of gate valve on site with the
procedure of groove x groove connection of pipe with size Ø400mm and threaded
connection on the CRAC pipe with size Ø65mm and smaller. Also there will be an
occasional welding will be conducted (Bridging pipe whereby groove end and
threaded are not applicable).
To ensure that washer and spring washer will be installed especially at flange
connection.
Check for torque marking on every bolt for tightness and firmness of the installation.
For threaded connection, a Teflon tape are required to wrap on the groove of the pipe
prior to its connection, pipe adhesive will be an optional which is on the discretion of
Client
Upon checking all parameters and tightness of the pipe with gate valve, coupling and
all its accessories has been in place.
After Installation Chilled Water Pipe has been completed, prepare Work Inspection
Request (WIR) to ensure installation done as per drawing and technical specification.
And to getting approval documentation from main contractor/tenant.
Hydraulic pressure test will be conducted for at least 24 hours (refer to Hydraulic
Pressure Test MOS), after MIR approved. All welded piping shall be subjected to a
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 13 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
hydrotest 1.5 times the maximum working pressure, at which pressure all welded
joints shall be hammered with a pound hammer, the blow being struck hard enough to
jar the pipe without injuring it. Pinhole leaks shall be repaired by welding.
All equipment for making this test shall be prepared such as electric test pump,
temporary connection and appurtenances. See method and drawing below :
- Put the test plug into the pipe.
- The electric test pump will be installed to the lowest level of pipe.
- Fill water into the pipe and ensure water is visible of the top end of all branch
lines.
- Purge the air from the highest point of all branch lines.
- Plug the end points after venting.
- Turn-on the electric test pump to start pressure test.
- Check pressure gauge to ensure that water is filled into the pipe.
- Add pressure until the water pressure becomes 7 Kg/cm2 for Water supply and 15
Kg/cm2 for Fire hydrant ( See table Standard for Pipe test ), whichever is target by
supplying water into the pipe.
- Pump side valve must be closed from pressure gauge.
- Close the valve until the regulated time for maintaining pressure.
- Take a pressure reading at the gauge after reaching the time given.
- Check all connection and joints after 24 hours of holding.
- All leaks shall be repaired after draining of water by removal and replacement of
leaking area.
- Test shall be repeated after repaired.
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 14 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02
To Clear the area and remove all unwanted material& equipment on site when
conducting a pressure test with a visible signage to warn the people of activity
including the pressure that been engaged on the pipeline.
10. Inspection
Upon completion of works, respective supervisors, engineers must check the work if
it is complying with drawings and standards.
Client / consultant / inspector shall be present during the test and record the testing as
per attach check / test report
PMX QAQC in-charge must be checked with respective engineers.
PMX QAQC in-charge prepare form inspection checklist of installation unit chiller.
Document Title :MOS for Installation Chilled Water Pipe and Bracket
Page 15 of 16
Revision / Date : 00 / 28 July 2020
Produced by : Pro-Matrix Pte. Ltd.
Doc No : PMX/INEX-DC-L8/MECH/MS/02