Professional Documents
Culture Documents
Contractor Document Title
Document No.
Executive desk: Q1‐05,
Office ;094/C Sharjah
Airport International Rev
Scale
Free zone Sharjah , UAE ERG CAL EMM STE P01 324 15 010 A
Tel: +971 6557 0720
Co. Doc Disc. Unit Prj. Prj. Prj. DCC
Org. Type Code Code Type No Year SeqNo Page
Cod
Ergil Group Middle East
Installation Manul
CONTENTS
1 INTRODUCTION ....................................................................................................... 3
1.1 GENERAL ................................................................................................................. 3
2 INSTALLATION ........................................................................................................ 3
2.1 GENERAL ................................................................................................................. 3
2.2 MMO RIBBON & CONDUCTOR BAR ....................................................................... 3
2.3 SPOT WELDING PROCEDURE ............................................................................... 4
2.4 POWERFEED CONNECTORS ................................................................................. 6
2.5 POTENTIAL MONITORING FACILITIES .................................................................. 7
2.6 NEGATIVE TANK CONNECTION ............................................................................. 7
2.7 POSITIVE AND NEGATIVE HEADER CABLES ........................................................ 8
2.8 JUNCTION BOXES ................................................................................................... 9
2.9 TRANSFORMER RECTIFIER UNIT .......................................................................... 9
2.10 INTERNAL GALVANIC ANODE .............................................................................. 10
3 PRE-COMMISSIONING TESTS .............................................................................. 11
4 COMMISSIONING .................................................................................................. 12
5 MAINTENANCE SCHEDULE ................................................................................. 13
5.1 CRITERION FOR ACHIEVING CATHODIC PROTECTION .................................... 14
Installation Manual
1 INTRODUCTION
1.1 GENERAL
This document is the installation manual relating to the permanent cathodic protection
systems installed to protect the tanks at the Zubair Plant, Iraq.
2 INSTALLATION
2.1 GENERAL
All installation works associated with the Cathodic Protection system shall be conducted in
accordance with this specification and the appropriate design drawings. Any conflict between
this specification and the drawings and / or other project specifications and drawings shall be
brought to the attention of the CPCL Engineer in writing for clarification as soon as it is
discovered.
The membrane should be at least 50 mm below the proposed location of MMO ribbon grid. In
addition, it is essential that the membrane shall cover the entire inner face of the concrete
ringbeam foundations to isolate the reinforcing rebar from the anode network. The Tank
Construction Contractor shall confirm the membrane is a uniform depth below the proposed
bottom of the tank.
A layer of chloride free, clean washed sand shall be installed directly above the membrane
which shall be compacted as normal and the anode shall be installed in this layer. The pattern
of the anodes and conductor bar is shown in the design drawings. The Tank Construction
Contractor shall confirm the sand layer is uniform and at least 50 mm above the membrane
level.
Installation Manual
The anodes shall be rolled out onto the sand base layer in the pattern as shown in the
relevant design drawing. Where appropriate the anodes shall be temporarily weighed down to
avoid movement, however great care shall be taken to ensure that the coating of the anodes
is not scratched or damaged in any way.
As the anode ribbons are being laid out the conductor bars shall be placed over them in the
pattern shown in the relevant design drawing. At each and every crossover of the anode
ribbon with the conductor bar, the anode shall be resistance welded, (spot welded) to the
conductor bar. Prior to conducting the spot welding for each tank a sample spot weld shall be
made and inspected by Cathodic Protection Co Ltd Engineer or other suitably authorised
person. Refer to section below on spot welding procedure.
At each and every crossing of the perpendicular and parallel conductor bars, they shall be
resistance welded to each other. The welding equipment shall be operated in accordance with
the manufacturers Operation Manual. Where necessary, anodes and conductor bars shall be
extended using the same procedure.
The personnel used for welding must fulfill project certification requirements.
A recommended welding procedure that is compliant with the Project Specification API 650
Standard is required. API 650, Section 7-Welding Procedure and Welder Qualifications terms
relate to all welding shall be interpreted as defined in Section IX of the ASME Code.
The scope of the work for this procedure is responsibility of the installing contractor.
Installation Manual
Installation Manual
Power feed connectors shall be field connected to the 1c 25 mm² PVDF/HMWPE stranded
cable using a line tap and splice kit with the instruction supplied with the splice kit. Once
installed in the correct location the conductor bar tail from the powerfeed cable encapsulation
shall be connected to the conductor bar using where appropriate resistance welding (spot
welding).
Installation Manual
Upon completion of the powerfeed assembly, the powerfeed cable shall be routed to the
chosen exit point from the foundations and routed out of the foundations via a suitable conduit,
(cast into the concrete ringbeam), as shown in the design drawings.
A 25 mm ‘sand bridge’ shall be made at each powerfeed cable / anode crossing location to
ensure that they are not in direct contact. Once the cables have been routed out of the
foundations, the entire anode, conductor bar and cable assembly shall be covered with
another layer of chloride free, clean washed sand, which shall be smoothed flat and
compacted. The installation contractor shall confirm the sand layer is uniform and at least 50
mm above the MMO Ribbon layer.
The powerfeed cables shall be routed from the tank to the location of the positive / negative
junction box installed adjacent to the tank, outside of the bunded area. At all times the cables
shall be laid in a single length without further splicing, free from kinks and excessive bends.
Inside the pipe a loop of 8 mm polypropylene rope to pull the reference electrode through
should be installed and connected to the end cap by the eyebolts.
Also the permanent reference electrodes should be buried and surrounded by 100 mm of soft
clean washed sand. Note each reference electrode has different length of cable tail and must
be installed in the correct location to allow termination in the test box. Cable tails to should be
routed appropriately back the test box without damage to insulation.
Installation Manual
Upon successful testing of the connection it shall be encapsulated taking care to avoid any
damage to either the cable connection and/or the cable.
A stress relief loop shall be left in cable prior to entering equipment to prevent damage to the
cable in the event that the junction box is accidentally displaced and the cables are pulled.
During construction and prior to installation of the test facilities to prevent accidental damage
to or theft of the cable, the cable shall be looped and buried at a depth of 500 mm and a
wooden board placed over the cable to prevent damage when the cable is retrieved.
The location of the buried cable shall be suitably marked on the surface to ease location of the
cable when it is required.
Installation Manual
The junction boxes shall be located in electrically rated locations according to their electrical
classification rating. The final location of the junction boxes shall be decided on site by the CP
Engineer in consultation with the Project Engineers. They shall, where practicable, be installed
in such a fashion that easy access to the junction boxes is maintained. Under no
circumstances shall a junction box unit be installed in a location where it could be damaged,
stolen and / or cause an obstruction or interference to the legitimate activities of the operator.
The DC output cables shall be installed in the Transformer Rectifier but not terminated.
Termination shall be done by an experience CP Engineer at the time of commissioning. The
DC output cables shall be routed to / from the Transformer Rectifier to the positive / negative
junction box, as per the details of the design drawings.
The unction boxes shall be located in electrically rated locations according to their electrical
classification rating. The final location of the Transformer Rectifier units shall be decided on
site by the CP engineer in consultation with the main contractor and client. The Transformer
Rectifier units shall, where practicable, be installed in such a fashion that easy access to the
Transformer Rectifier unit is maintained.
Installation Manual
Installation Manual
3 PRE-COMMISSIONING TESTS
The following sections outline the pre-commissioning tests and procedures that shall be used to
determine that the CP system and materials as installed shall operate correctly and provide the
tanks with a satisfactory level of protection. Any conflict between this specification and the
drawings and / or other project specifications and drawings shall be brought to the attention of
the Main Client Engineer in writing for clarification as soon as it is discovered.
All the results shall be properly documented and signed off by all the relevant parties. This
documentation will form part of the final handover documentation.
Installation Manual
4 COMMISSIONING
The purpose of the commissioning procedure should be used to show that the installed systems
operate as specified and that the required design criteria have been met.
A commissioning report will be prepared by CP Engineer, which shall include all commissioning
results. The report shall include a discussion of the results obtained giving conclusions. The
report shall also show the natural, “ON” and “instant OFF” potentials at all test stations in both
tabular and graphical formats.
Installation Manual
5 MAINTENANCE SCHEDULE
Transformer Rectifiers:
Structures:
Transformer Rectifiers:
Installation Manual