Professional Documents
Culture Documents
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 1/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
ISSUED FOR
0 30 SEP 14 K. Y. KO J. S. KIM Y.S.KIM B.H.SHIM H.S.HWANG
CONSTRUCTION
A 27 JUN 14 ISSUED FOR REVIEW K. Y. KO J. S. KIM Y.S.KIM B.H.SHIM H.S.HWANG
Joint Venture of Hyundai Engineering & Construction Co., Ltd., GS Engineering & Construction Co., Ltd., SK Engineering
Note :
a) Revision bar(vertical line) shall be placed in the right hand margin to indicate where the changes has been made
b) PRPD = Prepared by, CHKD = Checked by, REVD = Reviewed by, APPRD = Approved by, CONFD = Confirmed by
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 2/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
REVISION HISTORY
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 3/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
TABLE OF CONTENTS
1. GENERAL ...................................................................................................................................................6
1.1. Introduction ................................................................................................................................... 6
1.2. Purpose ......................................................................................................................................... 6
1.3. Scope of Application .................................................................................................................... 6
1.4. Objective & Strategy .................................................................................................................... 6
1.5. Definition ....................................................................................................................................... 7
2. REFERENCE ..............................................................................................................................................8
3. PHASES TO COMPLETION.......................................................................................................................8
3.1. MECHANICAL COMPLETION ...................................................................................................... 9
3.2. PRE-COMMISSIONING ................................................................................................................. 9
3.3. COMMISSIONING ........................................................................................................................10
3.4. START-UP .................................................................................................................................... 11
3.5. PERFORMANCE TEST ............................................................................................................... 11
3.5.1. PERFORMANCE TEST ......................................................................................................12
3.5.2. PROVISIONAL ACCEPTANCE ........................................................................................12
3.6. FINAL ACCEPTANCE .................................................................................................................12
5. UNICCS .....................................................................................................................................................14
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 4/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
7. COMMISSIONING METHODOLOGY.......................................................................................................16
7.1. Scope of Work and Activities ....................................................................................................16
7.2. Activating All Utilities .................................................................................................................16
7.3. Functional Test of Rotating Equipment / Electric Motors ......................................................16
7.4. Ready for Start-up & Start-up ....................................................................................................16
7.5. PUNCHLIST (during COMMISSIONING) ...................................................................................17
7.6. COMMISSIONING DOSSIER ......................................................................................................17
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 5/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
ATTACHMENTS
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 6/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
1. GENERAL
1.1. Introduction
This document provides general guidelines for execution of PRECOMMISSIONING and
COMMISSIONING to be carried out by HDGSK JV(hereinafter “CONTRACTOR”). This document
was prepared to comply with the EPC Agreements between the STATE COMPANY FOR OIL
PROJECTS (SCOP) of the Ministry of Oil, Baghdad, Iraq (hereunder “EMPLOYER” or “SCOP”)
and CONTRACTOR for Karbala Refinery Project.
1.2. Purpose
The purpose of this document is to ensure that the PRECOMMISSIONING and
COMMISSIONING work are correctly planned, executed and controlled in accordance with
EMPLOYER requirements specified in the contract documents including Contract
Documents( Volume3 – Section1 – Para8, Volume5 – AA00 – JSM900, 901, 902, 903, 904).
To facilitate smooth and trouble-free completion of PRECOMMISSIONING and COMMISSIONING
followed by Initial Operation and PROVISIONAL/FINAL ACCEPTANCEs, CONTRACTOR will
develop necessary documents including PRECOMMISSIONING & COMMISSIONING schedules,
relevant plans and procedures. These documents will be used as the basic guidelines and tools to
obtain a smooth transfer of the installations from the Construction Team to
PRECOMMISSIONING & COMMISSIONING Team and then to the EMPLOYER, as quickly as
possible, in full confidence, and with all the required quality and safety requirements.
Flawless Start up
Faultless Operation
First, for the Flawless start up, COMMISSIONING team shall, without limitation:
Second, for the Faultless Operation, COMMISSIONING team shall, without limitation:
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 7/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
1.5. Definition
Contract means the Contract Agreement, the Conditions, the Employ’s requirements, the Tender,
and the further documents (if any) which are listed in the Contract Agreement.
Employer means the person named as Employer in the Contract Agreement and the legal
successors in title to this person. The “Employer” and reference to “Engineer” means the Director
General of SCOP or any person authorized by him.
Contractor means the person(s) named as contractor in the contract Agreement and the legal
successors in title to this person(s).
Employer’s Personnel means the Employer’s Representative, the assistants referred to in Sub-
Clause 3.2 [Other Employer’s Personnel] and all other staff, labor and other employees of the
Employer and of the Employer’s Representative; and any other personnel notified to the
Contractor, by the Employer or the Employer’s Representative, as Employer’s Personnel.
Contractor’s Personnel means the Contractor’s Representative and all personnel whom the
Contractor utilizes on Site, who may include the staff, labor and other employees of the
Contractor and of each Subcontractor; and any other personnel assisting the Contractor in the
execution of the Works.
Subcontractor means any person named in the Contract as a subcontractor, or any person
appointed as a subcontractor, for a part of the Works; and the legal successors in title to each of
these persons.
Commencement Date means the date of notification to the Contractor’s bank of the opening of
the activated L/C referred to in clause 14.16.1, unless otherwise defined in the Contract
Agreement (date upon which Letter of Credit is opened). “Contract Effective date” means the
date of signature of the Contract.
Materials means things of all kinds (other than Plant) intended to form or forming part of the
Permanent Works, including the supply-only materials (if any) to be supplied by the Contractor
under the Contract.
Plant means the apparatus, machinery and vehicles intended to form or forming part of the
Permanent Works.
Temporary Works means all temporary works of every kind (other than Contractor’s Equipment)
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 8/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
required on Site for the execution and completion of the Permanent Works and the remedying of
any defects.
Works means the Permanent Works and the Temporary Works, or either of them as appropriate.
Contractor’s Documents means the calculations, computer programs and other software,
drawings, manuals, models and other documents of a technical nature supplied by the Contractor
under the Contract; as described In Sub-Clause 5.2 (Contractor’s Documents).
Site means the places where the Permanent Works are to be executed, including storage and
working areas, and to which Plant and Materials are to be delivered, and any other places as may
be specified in the Contract as forming part of the Site.
Variation means any change to the Employer’s Requirements or the Works, which is instructed or
approved as a variation under Clause 13 [Variation and Adjustment].
2. REFERENCE
3. PHASES TO COMPLETION
There are several major Phases to be passed by which leads to completion of the facilities during the
period after erection and before they are finally handed over to the EMPLOYER. These Phases include
MECHANICAL COMPLETION, PRECOMMISSIOING, COMMISSIONING and START-UP,
PERFORMANCE TEST, PROVISIONAL and FINAL ACCEPTANCE.
Especially, among these Phases, phase classification of detail activities related with phase of
PRECOMMISSIOING, COMMISSIONING and START-UP are made and developed clearly from “2342-
AA00-JSM-903 CHECKLIST FOR PLANT COMPLETION PRE-COMMISSIONING AND START-UP”
(See Attachment-2 CHECK LIST FOR MC). The developed contents of the Attachment-2 are
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 9/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
3.2. PRE-COMMISSIONING
PRECOMMISSIONING means all checks, cleaning and testing of Plant and its implementation
without introducing hydrocarbons or permanently energizing or pressuring said Plant.
PRECOMMISSIONING includes all activities implemented between the completion of construction
activities and Ready for COMMISSIOING. PRECOMMISSIONING is a series of activities
consisted of cleaning, checking, testing, adjustment, etc.
PRECOMMISSIONING activities will be started as soon as system installation works are
completed. But, category “A” punch list items should be rectified perfectly before starting the
PRECOMMISSIONING activities.
From the PRECOMMISSIONING phase, the EMPLOYER’s operators and maintenance personnel
shall be involved and work with the CONTARACTOR’s COMMISSIONING team under control of
CONTRACTOR’s COMMISSIONING manager.
CONTRACTOR will be responsible for all activities during PRECOMMISSIONING and shall work
in accordance with the PRECOMMISSIONING Procedures.
Provide PRECOMMISSIONING Procedures as well as activity schedule for safe and efficient
progression of PRECOMMISSIONING works.
Provide suitably experienced personnel to undertake PRECOMMISSIONING activities and to
resolve any problems that may occur.
Undertake PRECOMMISSIONING activities according to the approved
PRECOMMISSIONING Procedures.
Provide and manage the Vendor services as necessary
Promptly rectify any problems and/or defects found in the course of PRECOMMISSIONING
works.
Provide all records including check and test sheets.
Provide effective & strict training to manage trainee qualification for better training result and
operation and maintenance quality.
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 10/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
Make trials and adjustments and functional tests on switchgear, control panels and motor
control centers
Test-set switchgear relays for proper co-ordination
Check phase sequence and polarity
Energize the system after completion of all tests
Instruments/automation :
Calibration instruments with standard test equipment and make all required adjustments and
control point settings
Check settings of all alarm and shutdown switches
Check all shutdown systems
Check all safety valves and settings, ensure that safety valves isolation valves are
locked/open or locked/closed as per drawings
Check control panels for all signals
Instrument loop checks
Removal of temporary screens, strainers, and blinds and their replacement as necessary
Loading of vessels internals
Final equipment close-up
Fire and safety system pre-commissioning
Others as necessary
3.3. COMMISSIONING
COMMISSIONING is the testing and adjustment of an assemblies, system or subsystem, and will
mainly comprise of Operational Testing under real or simulated conditions to ensure that it meets
all applicable Rules, Regulations, Specifications, Codes and Standards, and fulfils its intended
duty.
COMMISSIONING covers all activities conducted from after MC to before READY FOR START-
UP. Subject to the terms and conditions of the Contract, the Plant or Subdivision of the Plant is to
be commissioned by CONTRACTOR, who will commence COMMISSIONING as soon as he
deems it possible, under approval by EMPLOYER that the Plant or Subdivision of the Plant is
ready for COMMISSIONING and any operational requirements of the EMPLOYER are fulfilled.
Check list for plant completion is to be used for the EMPLOYER to approve commencement of
COMMISSIONING.
CONTRACTOR shall be responsible for all activities during COMMISSIONING and shall work in
accordance with the COMMISSIONING Procedures.
CONTRACTOR shall, without limitation:
Provide COMMISSIONING Plans and Procedure as well as activity schedule for safe and
deficient progression of COMMISSIONING works.
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 11/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
3.4. START-UP
When COMMISSIONING activities are completed at EMPLOYER’s satisfaction, and all Punch List
items have been cleared, the status of the READY FOR START-UP shall be reached, and the
READY FOR START-UP CERTIFICATE shall be issued by EMPLOYER.
CONTRACTOR shall prepare procedures for units START-UP activities and perform START-UP
according to said approved procedures. START-UP procedures shall describe in step by step
manner the activities carried out by CONTRACT Commissioning team during START-UP.
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 12/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
4. SYSTEM METHODOLOGY
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 13/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
without priorities.
The transition of construction mode from ‘Area Basis’ to ‘System Basis’ usually starts from the point
when approximately 60% of piping work progress has been achieved. But considered from realistic
point of view, the sooner the transition could be started, the higher efficiency in execution of
PRECOMMISSIONING and COMMISSIONING works would be resulted.
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 14/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
Non-operational systems such as civil concrete work, structural steel, buildings, roads,
painting, insulation, etc.
Operational systems such as electrical substations, HVAC, plant lighting, cathodic protection,
etc.
The “System Definition” is one of the major engineering deliverables and may be subject to
revisions and updates until the PAC. PRECOMMISSIONING and COMMISSIONING operations
will be carried-out and reported by systems.
5. UNICCS
UNICCS is an “in-house” software solution and specially designed for the management of
COMMISSIONING activities, and available either as proprietary solutions. And UNICCS is a software
package that has been developed to manage the Preparation, Execution and Monitoring phases of
PRECOMMISSIONING, COMMISSIONING. CONTRACTOR will use the UNICCS to report a status of
MECHANICAL COMPLETION, PRECOMMISSIONING, COMMISSIONING activities. EMPLOYER also
can access to UNICCS for monitoring a various status and balanced actual work.
System is a functional grouping of piping, equipment, and instruments, which are logically
related to each other according to the process and which can be isolated from other Systems
for the purposes of managing MECHANICAL COMPLETION, PRECOMMISSIONING,
COMMISSIONING, and HANDOVER.
SUB-SYSTEM is a part of the SYSTEM that can be completed and commissioned as a
separate entity.
ITEM GROUP is a group of the Mechanical equipment, piping, Electrical Circuits, Instrument
Loops and Test Packages that are contained within the project.
ITEM is an Individual tagged items such as Equipment, Pipe lines, Valves, Vessels &
Instruments and may be a part of the ITEM GROUP.
6. PRECOMMISSIONING METHODOLOGY
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 15/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 16/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
main documents.
7. COMMISSIONING METHODOLOGY
All operations are organized by system and/or subsystem, following a sequence, basically
identical to that of PRECOMMISSIONING, which optimizes the COMMISSIONING phase.
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 17/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
To meet the Project Milestone agreed upon between the EMPLOYER and the CONTRACTOR, it is
mandatory to prepare a well organized schedule for PRECOMMISSIONING and COMMISSIONING
activities showing the right sequence and time for each Unit comprising the whole Karbala Refinery
Project (See IONE-AA00-PE-CM-0006 PRECOMMISSIONING and COMMISSIONING Schedule – to
be isseud)
But just preparing the schedule itself would not be sufficient. It will be even meaningless if a series of
managerial efforts to keep the schedule are not followed. Close coordination between the
PRECOMMISSIONING/COMMISSIONING and Construction Teams as well as expediting the lagged
activities and clarifying/adjusting the priorities of specific activities with potential problem based on the
analysis of critical path vs. overall progress status would have to be practiced on a daily basis.
In order to obtain satisfactory results with PRECOMMISSIONING and COMMISSIONING works, a very
close coordination between the EMPLOYER and the CONTRACTOR is utmost important. In addition to
this, clear-cut understanding regarding scope of roles and responsibilities for each concerned party is
also very important. A split of responsibilities between the CONTRACTOR and the EMPLOYER is
shown below:
9.1. CONTRACTOR
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 18/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
9.2. EMPLOYER
Verifying various kinds of check sheets and/or test records to be prepared for the
PRECOMMISSIONING, COMMISSIONING and Performance TEST RUN activities.
Providing 700 operation and maintenance personnel from 2 month before the
PRECOMMISSIONING as per contractor’s request and they will work with CONTRACTOR’s
COMMISSIONING team under control of CONTRACTOR’s COMMISSIONING manager.
In time approval of MECHANICAL COMPLETION, READY FOR TEST RUN, PROVISIONAL
and FINAL ACCEPTANCEs for each system, etc. as per CONTRACT DOCUMENTS
Volume3 – Section1 – Para8
PRECOMMISSIONING and COMMISSIONING Procedures review
Organizing Operations and Maintenance personnel
Any others agreed between the EMPLOYER and the CONTRACTOR
10. ORGANIZATION
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 19/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 20/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 21/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
Define and describe the detail activities and methods in step by step fashion all the activity
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 22/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
Pre-commissioning and
1 IONE-AA00-PE-CM-0001 PLAN CD+6M
Commissioning Execution Plan
2 IONE-AA00-PE-CM-0002 Training Plan PLAN CD+6M
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 23/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 24/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
procedure
Before
METHOD
35 Each activity (will be issued) commencement
STATEMENT
of each activity
※ CD : Commencement Date
P : Commencement of PRECOMMISSIONING
MC : Mechanical Completion
12. COMMUNICATIONS
13. SAFETY
13.1. Introduction
It is impossible to formulate rules applicable to every conceivable circumstance or combination of
circumstances that may encounter during the daily working hours in the complex units. So
Safety might be said as an outcome which can only be secured through the cooperative effort
exerted by all of the parties and personnel involved in the PRECOMMISSIONING and
COMMISSIONING works.
This Safety Instruction is a general one in nature, offered only as a guideline, and does not, under
any circumstance, preclude any other instruction already issued for general use in the specific
field.
The purpose of this Safety Instructions is to prevent any possible accident in the plant or at least
minimize the possible damages on both the working personnel and the plant equipment. All
personnel must be familiar with these Safety Instructions and Procedures before starting any work
in the plant keeping in mind that ‘Safety is the First.’
Separate from this, Risk Assessment shall be carried out against PRECOMMISSIONING and
COMMISSIONING activities to reduce the possible risks of personal injuries and damages to the
equipment as well as to reduce the risks of negative impacts on the environment.
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 25/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
13.2.2. Precaution
Each Permit contains in itself a checklist of precautions against common hazards. But this
list being not able to cover entire precautions against all kind of hazards, it should be
commonly understood as a duty for both of the issuer and the receiver to review the job and
its probable hazards and see that extra precautions have been specified on the Work Permit
before it is signed.
One common precaution applicable to all work is to clear the area of people not required for
the job so as to avoid their being exposed to potential hazards.
If people enter an area where they could be exposed to danger, the work should be stopped
until the people are cleared out of the area.
(1) If conditions become unsafe in the course of work, the COMMISSIONING Supervisor
must stop the work and withdraw the Work Permit.
(2) Any employee is responsible to stop the work at any time he finds the actual work
conditions of the job is not safe enough to meet the required safety conditions for the
Work.
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 26/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 27/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 28/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
ATTACHMENT LIST
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 29/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
ATTACHMENT #1
COMMISSIONING
(1 Sheet)
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 30/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
Performance Test
PERFORMANCE TEST
PROVISIONAL ACCEPTANCE
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 31/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
ATTACHMENT #2
(17 Sheet)
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 32/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
1.1 manufacturer or vendor service assistance where
responsibility is not indicated in section 4:
a. obtain the assistance of the manufacturor vendor, as required,
X X X
for technical assistance
1.2 Permits
EPC Contractor shall prepare all documentation required by the
applicable provisions of the IRAQI law for the COMPANY to
X X
apply for, and obtain, all necessary permits by government and
regulatory agencies that are required for plant use and operation
1.3 Removal Of Rust Preventives
a. remove all rust preventives and oils used to protect the
equipment during the construction period whenever these X
protective materials will be detrimental to operation.
1.4 Lubricants
a. verify availability of all lubricants X
b. flush systems and install initial charge of all lubricants. dispose
X
of all flushing oil in accordance with the applicable regulations
c. maintain lubrication after initial charge X X X
1.5 Packing And Seals
a. install mechanical seals and accessories, as required X
b. install packing and accessories, as required X
c. adjust and replace mechanical seals, packing, and
X X
accessories, as necessary, during commissioning period
1.6 Removal Of Temporary Bracing
a. remove all temporary supports, bracing, or other foreign
objects that were installed in vessels, ducts, piping, transformers,
X
machinery, or other equipment to prevent damage during
shipping, storage, and erection and repair any damage sustained
1.7 Rotation And Alignment
a. check rotating machinery for correct direction of rotation
and for freedom of moving parts before connecting the X
driver
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 33/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
b. perform cold alignment to the manufacturer’s tolerances and
X
record
c. perform hot alignment X X
1.8 Leak Test
a. notify the owner of the schedule for leak tests X
b. provide any media for test purposes X
c. conduct all tests in accordance with applicable codes.
X
specifications, regulations, and the project instructions
d. dispose of all test media in accordance with the owner's
X
instructions
e. conduct all operational tightness tests X
f. system leak test before hydrocarbon feed-in X
1.9 Inspection
a. provide inspection of the plant to verify that erected facilities
conform to flow diagrams, construction drawings, vendor prints, X
and specifications
b. verify and approve the plant inspection. note any exceptions
X
on the punch list
c. provide for special inspections, such as those required by
insurance or governmental agencies
note: shop inspected equipment will not be reopened for X X X
inspection in the field except as specified by the owner or as
specifically noted in 4. 1.
1.10 Pressure/Vacuum Safety Relief Devices
a. transfer relief devices to and from the specified testing facility X
b. test and adjust all devices and seal wherever necessary or
X
desirable
c. install all devices after testing. adjusting, and tagging X
1.11 Flushing And Chemical/Mechanical Cleaning
a. except as specifically noted in the next section:
1. conduct all flushing. blowing, and mechanical(by hand tools)
cleaning operations where such operations can be accomplished
X
without using permanently installed equipment and providing
temporary equipment as necessary
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 34/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
2. conduct all flushing and blowing operations where
X(STEAM
permanently installed equipment must be used to obtain proper X
BLOWING)
line velocities
3. provide any media for flushing and for cleaning purposes X
4. dispose of all media X X
c. conduct chemical and special mechanical(e.g. hydro-jetting)
cleaning providing and disposing of all fluids used during X
execution
1.12 Temporary Screens, Strainers, And Blinds
a. provide and install all required temporary strainers X
b. clean strainers, as required, during circulation X X
c. remove temporary strainers when system is adequately
X
cleaned
d. provide, install, and remove all temporary blinds required for
X
flushing
X for
e. provide, install, and remove all temporary blinds require for process
X X
isolation fluids, as
necessary
1.13 Purging / Inerting
a. install purge/inerting connections X
b. provide purge materials and conduct necessary purging
X
operations
1.14 Drying Out
a. dry out facilities, as requested, to prevent contamination of
X
catalysts, operating materials, and/or product
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 35/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
b. install all materials, other than the materials specifically noted
X X
in section 4, such as chemicals, resins. Desiccants, Catalyst
c. inspect the vessel interior before and during loading to ensure
X(a) X(b)
proper installation
1.16 Housekeeping
a. at completion of construction, remove excess materials,
temporary facilities, and scaffolding; rough sweep or rake the
X
area: and pick up trash. erform washing or further cleanup, as
required
b. after mechanical completion maintain adequate housekeeping
X X
practices as required for safe operation
1.17 Maintenance, Spare Parts, And Special Tools
a. after pre-commissioning is complete protect equipment from
X
normal weather conditions, corrosion or damage
b. after pre-commissioning is complete provide adequate
maintenance for equipment, including the cleaning of strainers X
and the repairing of steam traps
c. after pre-commissioning is complete, maintain adequate spare
X X
parts and supplies
1.18 Noise Survey
a. conduct individual equipment noise surveys, as required X X
b. document all survey data X X
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 36/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
2.1 Vessels- Tower, Reactors and Drums
a. open the vessel and execute inspection of internals after
X
installation
b. open both internal and external man ways and execute final
X
inspection of the vessel, unless otherwise specified
c. mechanically clean the vessel internally, as required X
d. close after final inspection X
e. Check condition of equipment quality of installation and
cmpliance with Project drawings, manufacturer's instructions, X
safety rules and specifications and good practice.
f. Install all tower, reactor and drum internals and perform tray
X
leakage test and leveling adjustment as required
g. Issue to Contractor witten authority to close up each vessel X
h. Properly close up all vessel internal manways and openings
after final inspection or after loading of chemicals, catalystsm etc. X
is completed
i. Cure and dry out castable linings X
j. Inspect all towers and drums for cleanliness and dryness
X
before loading catalysts, etc.
k. Load all chemicals(including hot oil, amine, glycol, freon,
X
inhibitors), desiccants, catalysts, tower packings
l. Carry out air blowing if required X
m. Inspect after loading. Obtain samples of all catalysts loaded. X
n. Carry-out leak testing X
o. Conduct performance test X
2.2 Shell And Tube Exchangers
a. perform field inspection, if required, of exchangers X
2.3 Air-Cooled Exchangers
a. inspect exchangers to ensure that temporary shipping
X
supports and erection materials have been removed
b. adjust fan assemblies to obtain specified tip clearance and test X
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 37/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
c. install and adjust tensioning of belts X
d. Check operation of louvers and operating linkage X
e. Check satisfactory operation of louvres and variable pitch
X
assembly
f. Start up fans and check vibrations, motor loading, and proper
X
operation of auto-varialbe fans
g. Conduction performance test X
2.4 Fired Heaters
b. execute all non operating prefiring checks in accordance with
X
the manufacturer's instructions
c. blow fuel lines, check them for cleanliness and connect
X
burner piping
d. check operation of registers and dampers and verify position
X
of indicators
e. check operation of air preheaters, blowers and soot blowers X
f. dry refractory during initial firing by following the manufacturer's
X
temperature cycles
g. conduct boil out, chemical cleaning and flushing operations, as
X
required dispose of wastes and cleaning media
h. obtain and charge liquid heat transfer media, if required X
i. conduct light off, drying, and purging operations X
j. After drying out, clean stack and duct, open manholes and
other openings inspection. Check operation of dampers. Close X
stack and duct after inspection
2.5 Pumps, Compressors, And Drivers
a. chemically clean any completed lube and seal oil when
X
specified. Dispose of wastes and cleaning media
b. charge the lube oil, seal oil, and oil cooling systems with
flushing oil and circulate for cleaning purposes. dispose of any X
flushing oil
c. install coupling between driven and driver machines X
d. charge the lube oil, seal oil, and oilcooling systems with the
X
operating oil recommended by the manufacturer
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 38/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
e. operate equipment and make vibration, trip, governor, and
safety device checks and any operating tests and adjustments, X
as required
2.5.1 Pumps
a. Set and cold align pumps and drivers X
b. Couple pumps to drivers X
c. Install temporary strainers X
d. Check that piston seal packaging followers, if any, are
X
correctly tightened
e. If discharge flow dampers are fitted(normally nitrogen filled
X
bladder type) check these are correctly charged and installed
f. Check pump gear box oil levels X
g. Run-in pump in recycle, check pump and motor operation and
X
do any required dowelling of the pump driver
h. Check oil for presence of chips after no load run X
i. Check gears, bearings and parts for signs of wear and damage X
j. Make final hot alignment check X
k. Run unit after start-up conduct performance test X
4.5.2. Gas Turbines, Compressors and Expanders
a. Install all piping and make piping corrections as required by
X
manufacturer's tolerances. Set and cold align unit
b. Clean chemically suction and interstage piping and lube/seal
X
oil piping
c. Disassemble above piping for cleanliness inspection as
X
required
d. Fill lube and seal oil system X
e. Carry out lube and seal oil systems flushing, circulate oil uit
X
test patches are clean
f. Drain lube and seal oil systems then refill with new oil, if
X
required
g. Run in driver(uncoupled) excepted for expanders X
h. Couple driver and driven unit X
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 39/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
i. Run in compressor in recycle on air or inert gas, if possible
X
and/or suitable, on gas after gas-in otherwise. Check operation
j. Check hot alignment X
k. Carry out comprehensive vibration tests X
l. Check equipment noise levels X
m. Run unit on stream X
n. Check plant noise levels X
o. Conduct performance tests X
2.5.3. Diesel Engines
a. Set and cold align units X
b. Clean lube oil piping X
c. Fill lube oil system X
d. Drain lube oil system then refill with new oil, if no required X
e. Test run Diesel engines and their accessories uncoupled X
f. Couple diesel engines to driven equipment X
g. Test run coupled unit verify all operating parameters X
h. Check alignment after operational test X
i. Carry out noise measurement tests X
j. Conduct performance test X
2.6 Tanks
a. after erection and installation, inspect any internals which
X
required field installation
c. conduct flushing operations, as required. dispose of wastes
X
and cleaning media
d. close after final inspection X
e. Install appurtenances X
f. Strap tank and issue record X
g. Organize independent calibraion of product tanks for custody
X
transfer where required by government regulations
2.7 Piping Systems
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 40/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
a. flush and drain system and install orifice plates. X
b. drain system, remove blinds and perform gross leak tests, as
X
required
c. check pipe hangers, supports, guides, expansion joints, and
other pipe specialties for the removal of all shipping and erection
X
stops and far the correctness of cold settings far the design
service.
d. check pipe hangers, supports, guides, and pipe specialties for
X X
hot settings and make minor adjustments, as necessary
e. install permanent filter elements, as required X X
f. verify, to the extent required by the contractor, that specified
X
valve packing has been provided in valves installed in the plant
g. install car seals on valves, where necessary and check and
record the positions of all car-sealed valves; paint or identify X X
valves, as required
h. correct support, vibration, and thermal expansion problems
X
detected during commissioning
i. retorque all hot and cold service bolting during commissioning
X X
and start-up, as required
j. Carry out preliminary cleaning and hydrostatic testing of piping X
k. Alleviate any excess piping stresses that may be imposed on
X
pipes, compressores or pump flanges
l. Provide and install all temporary strainers, blinds and blanks X
m. Check packing and packing materials and lubrication of
X
valves : repack and lubricate if necessary
n. Supply and install line identification tags and signs, stencil
X
lines for identification
o. Install safty valves or temporart spool pieces during
X
construction
p. Remove as necessary and transport all safty valves to and
X
from test facilities
q. Test, set and tag all safty valves, then carry out safety valves
X
final installation
r. Carry out piping water or air flushing operations X
s. Perform chemical cleaning were applicable X
t. Fill in hydraulic unit and network with appropriate oil X
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 41/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
u. Perform drying out where applicable X
v. Carry out leak testing X
w. Carry out innerting X
x. Provide list and location of all blinds intalled X
y. Define, provide and install temporary blanks required for start
X
up
z. Install corrosion probes X
a'. Carry out oil and gas-in X
b'. Perform hot or cold bolting of piping and equipment during
X
initial plant start up
c'. Check spring hangers, pipe anchors and guides in hot
X
position
d'. Remove temporary strainers(normally after start-up) X
2.8 Electrical Power And Lighting Systems
a. perform trials and adjustments on all switchgear, motor control
X
equipment, and generators
b. test and set switchgear and circuit breaker relays for proper
X
coordination
c. obtain local inspector's approval, where required X
d. energize all substations with approval of the owner after
X
completion of all tests
e. check phase sequence, polarity, and motor rotation X
f. check installation of emergency power and lighting systems,
X
including light intensity
g. Perform preliminary tests with equipment de-energized,
including :
- Insulation resistance measurements
X
- Di-electric strength tests
- Loops and circuits continuity tests
- Earthing resistance measurements
h. Fill in transformers with oil X
i. Carry out breakdown test of oil samples X
j. Energize and test control power system X
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 42/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
k. Perform all functional tests, including :
- Adjstment and testing of protective devices
X
- Chec-out and adjustment of electrical instruments
- Operation of safety devices
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 43/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
i. isolate or remove, if necessary, inline components such as
X
control valves, positive displacement meters, and turbine
j. flushing operations and reinstall them on the completion of
X
these operations
k. install any sealing fluids, as required X
l. fully pressurize and energize the transmitting and control signal
system(s) by opening process connections at primary sensors
and final regulators and by making control mode settings for X
automatic operation of equipment as the process unit is charged
and brought on stream
m. Remove in-line intruments before hydralic test(except control
X
valves)
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 44/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
b. check operation of air preheaters, dampers, soot blowers, and
X
other equipment for proper positioning and travel
c. dry refractory during initial firing by following the
X
manufacturer’s temperature cycles
d. purge, flush, and drain steam mains, as necessary X
e. obtain and charge treated water for boil out and initial
X
operation, as required
f. commission auxiliaries as detailed elsewhere under the
X
appropriate equipment type
g. conduct boil out, chemical cleaning, and flushing operations,
X
as required. dispose of wastes and cleaning media
h. conduct initial light off, making the associated checks and
X
adjustments
i. conduct all operating tests and obtain the required
X
certification
j. recheck and set pressure relief valves X
2.11 Water Treatment Plants
a. inspect for completeness and correctness of installations and
X
make any non operating checks that may be required
b. provide and install the initial charge of ion-exchange resins
X
and inert bed material
c. provide all water treatment chemicals except the initial charge
X
of ion- exchange resins
d. make the necessary operating tests and adjustments to water
X
treatment systems
e. purify potable water systems X
2.12 Water Systems (cooling towers, fire water systems,
and river water systems)
a. inspect for completeness and correctness of installations and
X
make any non operating checks that may be required
b. clean the cooling tower basin and install screens in the suction
X
pit before water circulation
c. flush, drain, and clean the cooling tower basins X
d. clean intake screens X
e. adjust cooling tower fans to obtain specified tip clearance and X
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 45/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
test
f. operate fire pumps to check performance of systems X
g. head up reservoirs vessels tanks, and other water system
equipment, as required, fill with water, check for leaks, and flush X
to clean
h. Provide insurance company inspection of the fire systems, as
X
required
i. obtain and install all required fire fighting chemicals and
portable equipment, such as hoses, fire extinguishers, and X
related equipment
2.13 Waste Disposal
a. inspect facilities for completeness and correctness of
installation and make any non operating checks to ensure their X
conformance to specifications
b. operate all equipment and supply all chemicals and agents
X
related to waste treatment
2.14 Buildings And Accessories
a. check installation of buildings and accessories. including all
heating, ventilating, and air conditioning equipment, to ensure X
their completeness and conformance to specifications
b. as required, obtain certification that all plumbing, electrical, fire
protection. elevator, and special materials handling installations X
comply with local government regulations
c. operate heating, ventilating, and air conditioning units and
X
make all performance
2.15 Miscellaneous Equipment (agitators, mixers, rotary
filters, weigh scales, and materials handling equipment)
a. fully assemble rotary filters except for final filter media (cloth,
X
precoat, or screen)
b. install all final filter media X
c. level and calibrate weigh scales with the assistance of the
manufacturer's representative and set tare weights wherever X
possible
d. manually check materials handling equipment for freedom and
X
direction of movement
e. check clearances on materials handling equipment X
f. make all final adjustments during run-in and conduct any
X
required performance tests
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 46/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
g. as required, obtain certification that all lifting and materials
handling installations and other items of equipment comply with X
government regulations
2.16 Living Quarters Equipment
a. Check condition of equipment quality of installation and
cmpliance with Project drawings, manufacturer's instructions, X
safety rules and specifications and good practice.
b. Pressurize water Pipes(hot and cold) and test taps, sinks,
X
toilets, Showers
c. Energize specific(kichen) electrical appliances and check
X
functions with reference to electrical procedures
d. Leak test Fresh Water Maker system X
e. Energize and test run unit X
f. Verify conformity to specifications of the water quality X
g. Conduct performance test X
2.17 Fire Fighting Equipment
a. Check storage locations of all extinguishers X
b. Function test CO2/Halan skids without actual release X
c. Carry out operational test of deluge System, Hydrants and
X
Monitors.
d. Carry out specific tests as required by local Authorities X
2.18 Telephones
a. Check condition of equipment, quality of installation, and
compliance with Project drawings, manufacturer instructions, X
safty rules, specifications and good practice
b. Check especially that EX equipment has been installed in
X
classified area
c. energize and carry out equipment functional tests X
d. Test actual operation of all equipment X
2.19 Public Address
a. Check condition of equipment, quality of installation, and
compliance with Project drawings, manufacturer instructions, X
safty rules, specifications and good practice
b. Energize and carry out PA loops functional tests X
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 47/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
c. Test actual operation of loudspeakers and flushing beacons,
including check and adjustment of operational features on field X
such as : range/coverage, visibility, etc.
2.20 Radios
a. Check condition of equipment, quality of installation, and
compliance with Project drawings, manufacturer instructions, X
safty rules, specifications and good practice
b. Check condition of antennas, feeders, radio transceivers and
X
associated equipment
c. Energize and carry out one in-station test per radio equipment X
d. Test radio systems operation X
2.21 Meteorological Equipment
a. Check condition of equipment, quality of installation, and
compliance with Project drawings, manufacturer instructions, X
safty rules, specifications and good practice
b. Carry out the calibration of sensors X
c. Energize and test the operation of each loop X
d. Test the system test processing X
e. Test logging equipment X
2.22 Telemetry(MTU & RTU's)
a. Check condition of equipment, quality of installation, and
compliance with Project drawings, manufacturer instructions, X
safty rules, specifications and good practice
b. Energize and test data transmission X
c. Carry out instrument inerface tests X
2.23 CCTV systems
a. Check condition of equipment, quality of installation, and
compliance with Project drawings, manufacturer instructions, X
safty rules, specifications and good practice
b. Check free operation of cameras and pan-and-tilt equipment X
c. Energize and check proper functioning of equipment X
d. Test system test, scanning, sequencing, etc X
2.24 HVAC Equipment
PRECOMMISSIONING &
COMMISSIONING Execution Plan
PROJ. 2171
DOC. NO. : IONE-AA00-PE-CM-0001
KARBALA REFINERY PROJECT Rev. 0 Page 48/48
Ref. FEED DOC. No. : 2342-AA00-JSM-901
pre-commissioning
Commissioning
start-up
a. Check condition of equipment quality of installation and
cmpliance with Project drawings, manufacturer's instructions, X
safety rules and specifications and good practice.
b. Check alignment of motors/fans and drivers X
c. Check that tension on drivers is correct X
d. Check that fans and motors rotate manually and run freely X
e. Check that anti0vibration mountings are correctly installed X
f. Check that sealing compound of fire dampers is installed
X
correctly
g. Check that linkage and blades of dampers operate correctly
X
and freely
h. Check that dampers actuators operate correctly X
i. Check that airflow direction in pre-heaters is correct X
j. Carry out ductwork leak tests X
k. Energize and run unit. Test sequences and interlocks. Check
X
vibrations
l. Carry out airflow and balacing tests X
m. Control and adjust rooms temperature and pressurization X
n. Conduct Performance Test X