N°: WI-SSA-ENGTEC-001-E
WORK INSTRUCTION
VERIFICATION OF PROCESS ENGINEERING Rev.: 1 Date: 21/02/08
DOCUMENTS
Page: 1/13
WORK INSTRUCTION
WI-SSA-ENGTEC-001-E
Only the electronic version is updated, before any use the current version of this document shall be verified on the INTRANET network
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
REVISION RECORDING
Nota:
• This document cancels and replaces the Engineering Technical instruction TI P 102 Rev.A dated
July 2004.
• This document is in accordance with relevant conclusions of the “Engineering Integration Project”.
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
INDEX
2. REFERENCE DOCUMENTS......................................................................................................................4
3. DEFINITIONS .............................................................................................................................................4
4. ACTIVITIES DESCRIPTION.......................................................................................................................5
4.1 RESPONSIBILITIES ...............................................................................................................................5
4.1.1 Elaborator (E).......................................................................................................................5
4.1.2 Verifier (V) ............................................................................................................................5
4.1.3 Approver (A).........................................................................................................................5
4.2 GENERAL............................................................................................................................................6
4.3 ELABORATORS AND VERIFIERS ASSIGNMENTS – ENTITLEMENT...............................................................6
4.4 VERIFICATION PROCEDURE ..................................................................................................................7
4.4.1 Sequencing of the verification workflow...............................................................................7
4.4.2 Verification actions – verification sheets..............................................................................8
4.4.3 Filing of verification elements ............................................................................................10
4.5 P&ID VERIFICATION WORFLOW ..........................................................................................................12
4.5.1 Verification of the Process working copy ...........................................................................12
4.5.2 Elaboration of P&ID MASTER by PPS ..............................................................................12
4.5.3 Verification of P&ID MASTER by PPL or PSL ...................................................................12
4.5.4 Approval of P&ID MASTER by TM ....................................................................................12
5. FLOWCHART ...........................................................................................................................................13
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
This Work Instruction addresses the procedure to be followed to ensure the verification, within the
Process Department, of the documents elaborated by the process team during a project.
Objectives of this Work Instruction are to define:
• A verification process.
• The minimum verifications to be done, when and how to do them.
• The ways of classifying and filing all the documents, masters and other elements involved in the
elaboration and the verification process, for traceability purposes.
2. REFERENCE DOCUMENTS
3. DEFINITIONS
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
Original Copy for Verification A copy of an original dated document, which circulates for verification
and which must contain, at the end of the verification process, all the
mark-ups and handwritten signings and dates.
TM Technical Manager
4. ACTIVITIES DESCRIPTION
4.1 RESPONSIBILITIES
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
4.2 GENERAL
• Verification is not to be considered as a lack of trust against the author of a document: no one
is secure from any error (in design, calculation, or by omission). Also, verification is not to be
considered as a release of responsibility. It is not allowed to rely upon verification for tracking
and correcting errors.
• Setting a signature on a document attests that the action of verification (or of self-checking)
has been really done by the signer. Responsibility of the signer is directly engaged.
• Verification should not be considered as an action “a posteriori”. It should start as soon as the
elaboration process of a document begins and should go on during the elaboration itself of
the document up to its issue, by self-checking conducted by the Elaborator and by follow-up
by the Verifier on a regular and continuous manner.
• In order to comply with requirements of ISO 9001, verification should be done in writing, and
the actions to be implemented should be recorded, for traceability.
• Self-checking before the issue of the documents is systematic and then the verification
process should not be a source of extra consumption of hours. The earliest the detection and
the correction of errors and discrepancies are, the smallest the consequences will be. In the
same way, time will be saved if the Elaborator does not hesitate to request some information
or explanation when required rather than transmitting an incomplete or even incorrect
document.
• In the event of some doubt about a technical or contractual point, the Elaborator or the
Verifier should refer to their PPL or to the Department management.
• When it is a matter of urgency, it may happen that a document should be issued by the
process team before full verification. This situation is to be avoided, as far as possible but if it
is the case, then the document must be marked by the label “PRELIMINARY – NOT
CHECKED”.
• Colour code :
− Green is normally the colour used to materialize the verification (marking comments and
highlighting data or elements verified).
− Red is normally the colour used by the Elaborator to mark comments on the MASTER.
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
Key:
Xe, Xv : Process Engineers, Elaborators (Xe) or Verifiers (Xv)
SL : Process Section Lead, acting as Verifiers (SLv) or as Elaborators (SLe)
PPL : Project Process Leader
HOD : Head of Department
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
4.4.2.1 General
• At the beginning of the Process activities on a given project, the PPL should make
sure, that intervening parties (Elaborators and Verifiers) are well informed about the
existence and the localization of reference and basic technical documents such as
Technical Instructions, Procedures, Standards, Process Design Rules, etc… they
will have to follow during the development of the process engineering studies. Also,
software / simulation tools have to be used by entitled person from Process
Department.
• Providing the Elaborators with a document from a similar Plant, to be used as
analogy, may be of a useful help.
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
4.4.2.3 Verification
Level of Verification
The Verifier is not asked to strictly verify all the data which are specified on a
document.
The level of the verification has to be adapted according to the competency of the
Elaborator, to the experience on similar projects and to the nature of the document.
Verification actions
Verification actions are reported on the Verification Sheet (Refer to attachment A).
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
st
For the 1 issue of a Process document
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
4- Copy of the original document With label “revised as per Verifier With label “OK for issue”.
st
“1 issue” reworked as per comments”. Dated & signed.
Verifier comments. Dated & signed. Verification sheet completed.
5- Copy of the original
st Filed in the Master dossier, to be used
document “1 issue” with its
as Master for subsequent issue.
verification sheet
st
6- Original document “1
If no Project requirements, filed within
issue” with its original
the Process department.
verification sheet
4- Copy of the original document With label “revised as per Verifier With label “OK for issue”.
th
“n issue” reworked as per Verifier comments”. Dated & signed.
comments. Dated & signed. Verification sheet completed.
5- Copy of the original document
th Filed in the Master dossier, to be used
“n issue” with its verification
as Master for subsequent issue.
sheet
st
6- Original document “1 issue” If no Project requirements, filed within
with its original verification sheet the Process department.
): The data to be checked are let to the appreciation of the Verifier. For an extensive
(
report, the verification extent will be shown by a general statement (e.g. “conclusion
checked, in accordance with solution implemented on a similar project”).
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
5. FLOWCHART
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.
FORM-SSA-ENGTEC-001-E
This document is the property of the Company who will safeguard its rights according to the civil and penal provisions of the law.