Professional Documents
Culture Documents
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any
part of this document may be disclosed to others or reproduced, stored in a retrieval system, or
transmitted in any form by any means (electronic, mechanical, reprographic recording or otherwise)
without prior written consent of the owner.
Design Integrity Review Procedure Version 1.0
Signed :....................................................
David McMullan
CFDH Process Engineering
The following is a brief summary of the 4 most recent revisions to this document. Details of
all revisions prior to these are held on file by the issuing department.
CONTENTS
1. Introduction...........................................................................................................................2
1.1 Background.......................................................................................................................2
1.2 Purpose..............................................................................................................................2
1.3 Distribution/Target Audience...........................................................................................2
1.4 Structure of This Document..............................................................................................2
1. Introduction
1.1 Background
In June 1993 a very serious incident occurred in Marmul whereby a control valve
released high pressure gas into the drain system which resulted in a gas cloud
being released into the gas turbine housing and over-pressure of the flare system.
In response to this incident, comprehensive integrity reviews of the Yibal production
facilities and of various production facilities were carried out which revealed a
number of design, safety and operational deficiencies. These deficiencies are
principally attributed to additions and modifications to the facilities made in response
to changes in field development.
In the course of the Yibal integrity reviews, it was also identified that some integrity-
related documentation did not exist or was out of date. It was recognised that
similar deficiencies were likely to exist elsewhere, and therefore a comprehensive
integrity review of all remaining production facilities was carried out.
A Design Integrity Review (DIR) review process was set-up and is now in the
execution phase.
1.2 Purpose
The purpose of this procedure is to document the DIR process carried-out in the
past and to define the procedure for future design reviews. It is a PDO control
document, under the Project Engineering Code of Practice (Ref. 1).
This procedure targets the engineers in each of the Product Flow Asset Teams
(PFATs) responsible for the implementation of the DIR process and for maintaining
the design integrity of their facilities.
The document is divided in two sections; the first section describes the DIR process
and the second describes the maintenance of design integrity.
The scope of this procedure is limited to the design integrity review process of
surface facilities. It excludes the design integrity review of off-plot pipelines and
electrical infrastructures. This procedure also excludes the steps required to ensure
design integrity in the design, procurement and construction phases of new surface
facilities.
1. Prepare and/or update (as-build) the key design integrity documents (specified
below).
Step 1 delivers for all surface facilities a set of as-built Process Engineering Flow
Schemes (PEFS), a Safeguarding Memoranda including Cause & Effect diagrams,
Hazardous Area drawings and a Flare/Blowdown Study.
Step 2 delivers a HAZOP Report which lists and categorises all the station
deficiencies as identified during the station HAZOP.
Step 4, delivers Asset Development Plan (ADP), which covers the agreed scope of
work, the costs, project execution strategy and schedule.
The DIRs resulting from the 1993 incident are scheduled to be completed by the
end of 1999 and is monitored by the Design Integrity Performance Indicator (DIPI),
which is reported by each PFAT on a monthly basis. The DIPI is defined in
Composite Integrity Performance Indicator Compilation Procedure (Ref. 3) and
summarised below.
DIPI-1 is the aggregate score for the completion of as-building and preparing the
key
documents.
DIPI-2 is the aggregate score for completing the reviews.
DIPI-3 is the aggregate score for screening all action lists.
DIPI-4 is the score for completing the Asset Development Plan’s per station.
DIPI-5 is the score for implementing the modifications in accordance with the ADP.
The HAZOP step, however, shall be replaced by the Process Hazard Review (PHR)
method described in EP95-0300, Shell Hazard and Effect Management Manual,
since the latter method achieves the same results much faster. The PHR is an
‘expert review’ led by an experienced leader, containing design engineers but
heavily weighted towards plant operators and maintenance staff. The review
primarily focuses on potential causes of ‘loss of containment’. The study progresses
through the plant looking at each major equipment item, applying a leader’s
checklist of causes of loss of containment. The current design and operation of the
plant is assessed and a critical examination made of the revision history to identify
any causes of release resulting from changes to the design and operation of the
equipment item since commissioning. The team also reviews any hazards arising
from variations (due to the age of the plant) from current design or operating
standards. The PHR delivers a report including identified deficiencies and proposed
actions.
The responsibility for the design integrity review of the surface facilities lies with the
Engineering Team Leader of the relevant Asset. This responsibility is delegated to
individual engineers by setting yearly tasks and targets. The surface facilities
include all production stations, pumping stations and gathering stations.
Specification None
Guidelines None
Abbreviation Description