SAKA INDONESIA PANGKAH LIMITED

PIPING TEST PACKAGE CTR Ref.: UPD-GF-W3-CM-LT-7001

W3-0103-01 Date: 2 Juli 2020

Production Header Discipline: Piping

SAKA INDONESIA PANGKAH LIMITED


Contract No. 4600012838

PIPING TEST PACKAGE


W3-0103-01
Production Header

Date Description Issued by Checked by Approved by

2 Juli 2020 Issued For Review KL FS IHR


TOTAL E&P INDONESIE No.: SN12-20-050-002-E
SAKA INDONESIA PANGKAH Sisinubi
LIMITED Field Development Project

Phase 4
PIPING TEST PACKAGE CTR Ref.: UPD-GF-W3-CM-LT-7001

W3-0103-01 Project Date: 2 Juli 2020


Peciko 4 Offshore Facilities project
Production Header Discipline: Piping
Phase 4

Project
Peciko 4 Offshore Facilities project
PhaseOF
TABLE 4 CONTENTS
Phase 4
SECTION DOCUMENT QUANTITY OF SHEET
Project
Peciko 4 Offshore Facilities project
1 PIPING TEST PACK DATA SHEET AND LINE NUMBER

TABULATION OF REVISED DRAWINGS

MARKED-UP P&ID FOR TEST PACKAGE

2 DRAWING LIMIT OF SYSTEM/ SUBSYSTEM

ISOMETRIC SHOP DRAWING(S)

PIPE SUPPORT DRAWING(S)

TEST PACKAGE INDEX - CHECK LIST (C-LX-01)


3
QA/ QC DOCUMENTATION & TRACEABILITY RECORD

PIPEWORK BEFORE TEST PACK TESTS – CHECK LIST (C-LX-02A)


4
PIPEWORK LINE CHECK PUNCH LIST

PIPEWORK FLUSHING/ CLEANING – TEST SHEET (T–MX–05)

FLUSHING LAY OUT

5 PIPEWORK PRESSURE TEST – TEST SHEET (T–MX–03)

PIPING PRESSURE TEST LAY OUT

DRAINING AND DRYING

PIPEWORK AFTER TEST PACK TESTS - CHECK LIST (C-LX-02B)

6 GASKET STATUS & ACCEPTANCE SHEET

PIPEWORK REINSTATEMENT (CLX-01)


SAKA INDONESIA PANGKAH LIMITED

PIPING TEST PACKAGE CTR Ref.: UPD-GF-W3-CM-LT-7001

W3-0103-01 Date: 2 Juli 2020

Production Header Discipline: Piping

Data Sheet for Piping Test Pack W3-0103-01 Project : Zawtika Development Project Phase 1C

A Unit
B Secondary System
C Secondary System Name 01
D Subsystem No. 0101
E Subsystem Name Process Gas
F Test Pack Description Production Header
G Platform WHP-C

H Service Two Phases Fluids

I Piping Class B09B


J Design Pressure/Operating Pressure 138.Barg /
K Design Temperature/Operating Temperature 55ºC /
L
M Flushing Method Water Flushing Water Jet x N/A
N Barg 7
Initial Pressure for Flushing
O psig 102
P Flushing Medium Water x Air / Rapid Decompression
Q Flushing Temperature ºC AMB
R
S 207 Barg
Test Pressure
T 3001.5 psig N/A
U Test Medium x Water Air Air + Nitrogen
V Duration of Test 60 minute
W
X Item Description:
No. Line No. Iso Dwg No. Spool No. P&ID No. Pipe Support No.
SPS-C-3017-006, SPS-C-3017-
1 UPD-W3-10"-01015-B09B W3-10"-01015-B09B 1 of 1 ALL UPD-SM-W3-PR-DR-1005
005,SPS-C-3017-004, BR04

2 UPD-W3-10"-01016-B09B W3-10"-01016-B09B 1 of 1 1 UPD-SM-W3-PR-DR-1005/1007 NA

3 UPD-W3-2"-01021-B09B W3-2"-01021-B09B 1 of 1 ALL UPD-SM-W3-PR-DR-1005 FR12-300-460-B

4 UPD-W3-2"-01022-B09B W3-2"-01022-B09B 1 of 1 ALL UPD-SM-W3-PR-DR-1005 FR12-300-360-B

5 UPD-W3-6"-01004-B09B W3-6"-01004-B09B 1 of 1 ALL UPD-SM-W3-PR-DR-1005 NA

6 UPD-W3-6"-01006-B09B W3-6"-01006-B09B 1 of 1 ALL UPD-SM-W3-PR-DR-1005 NA

7 UPD-W3-6"-01008-B09B W3-6"-01008-B09B 1 of 1 ALL UPD-SM-W3-PR-DR-1005 NA


TOTAL E&P INDONESIE No.: SN12-20-050-002-E
SAKA INDONESIA PANGKAHSisinubi
LIMITEDField Development Project

Phase 4
PIPING TEST PACKAGE CTR Ref.: UPD-GF-W3-CM-LT-7001

W3-0103-01 Project Date: 2 Juli 2020


Peciko 4 Offshore Facilities project
Production Header
Phase 4 Discipline: Piping

Project
TABULATION
Peciko 4 Offshore OF REVISED
Facilities project DRAWINGS
Phase 4
Phase 4 Shop Drawing Rev. P&ID Drawing Rev.
No Drawing No Sheet No.
Project
0 1 2 3 4 5 0 1 2 3 4 5 6
1 W3-10"-01015-B09B Peciko 4 1Offshore
of 1 Facilities
x project
2 W3-10"-01016-B09B 1 of 1 x
3 W3-2"-01021-B09B 1 of 1 x
4 W3-2"-01022-B09B 1 of 1 x
5 W3-6"-01004-B09B 1 of 1 x
6 W3-6"-01006-B09B 1 of 1 x
7 W3-6"-01008-B09B 1 of 1 x
SAKA INDONESIA PANGKAH LIMITED
PRECOMMISSIONING CHECK LIST
PIPING & VESSEL
TEST PACKAGE INDEX

SYSTEM : 01 FORM : C-LX-01


SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids
TEST PACK NO : W3-0103-01 PLATFORM : WHP-C
SITE : ONSHORE OFFSHORE SHEET : 1 OF 1
LINE IDENTIFICATION :

PROCEDURE NO :

ACTIVITIES:

NDT CLEARANCE
REINSTATMENT
Flushing Hydro testing Draining & Drying Pickling

R R
S/SYSTEM LINE IDENTIFICATION ISO E PID E
V V

NA Not Applicable X Checked & not accepted  Checked & accepted

DATE NAME SIGNATURE

Carried out by

CONTRACTOR
Accepted by

COMPANY

COMMISSIONING

CERTIFYING AUTHORITY

FORM: C-LX-01 TEST PACKAGE INDEX SHEET 1 OF 1


SAKA INDONESIA PANGKAH LIMITED
PRECOMMISSIONING CHECK LIST
PIPING & VESSEL
PIPE WORK BEFORE TEST

SYSTEM : 01 FORM : C-LX-02A


SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids
TEST PACK NO : W3-0103-01 PLATFORM : WHP-C
SITE : ONSHORE OFFSHORE SHEET : 1 OF 1
LINE IDENTIFICATION :

PROCEDURE NO :

Remark/
ITEM CHECK LIST Y N
N/A

1 Check that all of the materiel conforms to the specifications

Check the installation of all pipe-supports are in accordance with the specifications and
2
drawings. Also that springs have shipping-stops fitted and that the piping sits on

3 Check the location of the pipe anchors.

4 Check the alignment of the pipe guides.

Check that the pipe flanges have been mounted square to each other. Also that the
5
bolting and gaskets are correct.

6 Check that the pipework does not in any way load and stress the equipment it is serving.

Check that the flow direction of the valves and ckeck-valve is in the correct
7
sense/direction.

8 Check that there is a suitble access, both to operate and to maintain the valves.

9 Check the list of removed equipment


10 Check the Blind list
11 Check that all of the materiel to perform the test conforms to the procedure

NA Not Applicable X Checked & not accepted  Checked & accepted

REMARKS:

TOTAL
Produce
Record
Using
Inspect
Complete
The
Before
Fill
Lubricate
Hydrotest
Install
Test
Ensure
Check
Generally
Attatch
Leave
Fully
Bleed
Blank
NOTE:
Assemble
Connect
Grease
Fill
Lubricate
The
Install
Produce
Check
Ensure
Chech
Check
Lubricate
Generally
Ensure
and
the
brake
Hydraulic
Mud
Top
BOP
run
control
Hydraulic
centre
and
grease
the
and
off
the
all
and
that
for
hydraulic
diving
Grippers
between
flexible
Kill
inside
the
security
out
both
all
items
that
finger
connecting
the
all
correct
that
the
tank
the
bleed
blead
that
lubricate
to
aDrive,
and
flush
aThe
Standpipe
pipehandler
the
Control
Vendor
unused
the
flow
pipe
Drill
positioner
Manifold
instruments
Poorboy
components
downstream
Choke
Deadline
any
defects
rams
check
the
cooling
Top
pivot
security
integrity
installation
Mixing
manifold
all
Rotary
track
derrickman's
Grippers
Hydraulic
Drum
pressure
and
valve
interior
Manifold
accessibility
alignments
fluid
function
Drag
roller
fill
upper
defects
hydraulic
Mud
set
the
drum
installation
security
painting
check
correct
fluid
Screw
"tugger
all
the
sheave
outer
table
Unit
there
lines
that
brake
cooling
each
the
Grippers
all
these
the
Drag
the
all
sections
Panel
the
with
the
check
for
choke
the
hydraulic
components
equipment
system
manifold
cement
boards
mechanical
check
units
Chains
board
manifold
system
correct
systems
of
manifolds
Manifold
the
table
alignment
Derrick
valves
Cathead
interconnecting
bolts
hoses
installation
sheaves
flexible
Hook
large
small
Hydraulic
DisplacementtTanks
chains
hydraulic
install
Power
Drive
Top
project
silencer
crown
earthing
eathing
Manifold
of
the
expansion
heat
nameplate
Block
brake
Header
Shakers
hoses
alignment
ducting
items
guide
Crown
location
Mud
Derrick
hydraulic
flexible
equipment
Brake
handlers
Power
replaceable
pump
head
table
Rotary
skid
manifold
Anchor
and
of
Top
clevis
hold
Drum
location,
painting
Line
Hydraulic
control
hold-down
the
all
in
ends
Bucket
kit
sheaves
and
mechanism
Chains
service-loop
Skid
Anchor
assemblies.
stems
joint
cleanliness
must
centre
backlash.
marked-up
drive
the
are
Control
wraps
Poorboy
all
Control
instrument
the
Chains
control
aconnections
system
lines
provided
hydraulic
Conveyor
Hose
pipework
list
Package
all
list
the
Unit
enables
system
mounting
of
lines
grooves
installation
the
of
and
sheaves"
in
of
on
section
coolant
roughneck
transmitter
Drive
the
storage
visually
and
return
insulation
to
have
anchor
Drive
and
on
in
beams
onto
list
Manifold
Screw
list,
Jacks
jumper
Bucket
Derrick
grating
access
down
of
interface
and
is
Drum
Screw
cylinder
th
locks
into
rams
of
assembly
integrity
flexible
cooling
in
installed
Parking
to
draw-works
the
connections
rails
bolt
manifold
in
function
the
and
for
all
drives
installation
Cooling
are
the
accordance
is
in
Pack
pins
for
closed
all
unit
braket
termination
coincide
of
the
Unit
and
skid
project
bolts
the
for
in
supply
Shaker
Block
unit
Table
assembly
Box
in
and
that
expansion
level
section
with
are
integrity
the
in
is
hold-down
jumper
line
panel
the
have
bolts
and
of
connection
on
lines
complete
into
accordance
for
the
and
blocks
coupling
"C-GX-07"
control
security
between
in
accordance
(directly
kill
free
control
the
in
is
are
ref;
and
"C-GX-07"
in
connections.
hydraulic
of
lines
elevation
is
both
exhaust
are
the
accordance
issue
Station.
lines
top
been
hydraulic
with
the
Rams
installed
C-GX-07
accordance
hose
air
pipework
issue
mounted
located
and
square
Consul
supports
bolted
service
alignment
Hook
accordance
details
connections
instrument
damage.
with
drill
for
pipework
is
guide
hangs
the
on
Separator
Cathead
Derrick.
onto
alignment
to
provides
accordance
the
(typical
are
bolts
transmitters.
well
suitable
Rig
frovides
connection
Cathead
accordance
of
Draw-works.
for
are
bonding
secured
hydraulic
beams
bolts
Conveyor
in
securely
items
pre-charge
accordance
installation
and
have
mix
tank
manifold
the
pumps
doors
is
Conveyer
ensure
distance
the
system.
have
to
bonding
hoses.
ducting
for
lines
hydraulic
of
Control
drawings
greased
its
is
wear
are
have
lubricated
and
bonded
Drag
connected
lines
of
for
to
line
hydraulic
been
is
ensure
Drill
and
are
drive
position.
valves
the
assembly
Derrick.
system
water-lines,
C-GX-07
jumper
the
is
The
support
of
the
piping
accordance
correctly
free
manifold
DC.
mud
panel
Units
is
have
and
are
in
operator
where
hydraulic
drum
of
fully
Package
in
the
working
have
pipework
tightened
and
damage.
of
free
in
the
and
floor
have
for
is
hoses
potable
hydraulic
installed
free
in
Floor
between
rotate
the
adjoining
locate
station
damage.
for
correctly
greased
of;-
are
cabin
correctly
for
of
signes
over
small
atrolley
in
the
items
to
correctly
are
been
over
skid
also
from
the
are
place
package
to
all
hoses
system
in
been
can
the
of
with
Top
loop
at
to
with
the
bellows
plates
system
been
in
Pipe
have
one-
fully
as
units
kits
Floor
Chains
Rotary
rotation
small
defects
and
motors
for
diving
are
bolts
that
and
line
all
the
lines
check
place
is
of
for
to
been
)with
the
are
is
with
been
its
the
on
in
that
and
70%
hoses
pipe
has
the
for
been
as
and
to
from
in
for
unit
are
to
with
per
on
of
in
lines
with
for
the
on
for
has
the
in
has
it
the
in
kit,
are
the
in
be
its
is
in
of
all
to
it
as
is
in
DATE NAME SIGNATURE
FINA
is ELF
Punch
tightened
beams
greased
and
in
table
check
Ensure
tolerance
rotate.
fill
weld
connections.
fluid
on
damage
Rotary
handling
conveyor
connections
Skip
Cutting
hydraulic
flushed
piece
to
attached
valves
up
between
fluid.
pipework
with
shipped
manifold
from
the
Driller
security
been
have
free
parallel
located
complete
centre
structual
undamaged.
running
electrical
safety
Table.
eddy
package
necessary
correct
beams.
rams.
greased.
Handling
hoses
potable
its
drive
system
correctly
secure
board
installed
seal
Shaker
certain
applicable.
for
units.
corrosion;
vendors
comprised
support
project
manifold.
per
fittings.
accordance
against
within
supported
intended
drill
Drive
following
To
system.
water
diving
Derrick.
skid
installed.
have
the
Derrick
Skid
between
operational
Station
connections
(Punch
flushed-out
removed
accordance
Ensure
aligned
in
free
the
with
typically
located
correctly
accordance
comply
verify
accordance
the
to
bearing
and
be
Vendors
Derrick.
derrick.
Hydraulic
the
all
rig
link
project
hammer
security
BOP
tow
Vendors
correct
vendors
front
centre
run
that
complete.
structual
locking
the
fixed
HP.
from
hoses
Vendors
orientation
of
welded
D.C.
to
structual
the
floor
Positioners
as
correctly
flushed
been
edge
splatter,
the
is
current
and
been
the
all
mechanism.
where
list
assembly;
and
supported
are
AC.
clamps.
Drill
List.
line
Do
on
and
the
foreign
List.
floor.
Cabin
board,
Hydraulic
controls.
Table
that
rotate
are
position
skidding
lines
by-pass
spray
precharge
correctly
the
and
in
per
has
Transfer,
listed
to
that
water,
smoothly.
bars
and
brackets
structure.
sections
loose
and
of
etc.
pumps
free.
the
equipment
Vendors
requirements.
all
rig
the
to
is
welded
manifold.
Control
or
and
the
that
machine
damage
correctly.
on
Vendors
Draw-works
onto
installed.
is
installed
when
the
in
use
and
from
equipment
drives.
lines
Machine,
for
at
securely
power
lines.
correctly
fluid-power
their
between
to
not
the
flushed.
correctly
tested
with
closely
of
inhibitor.
is
correctly.
Drag
check
correctly
4hydraulic
of
the
installed,
blocks.
installed
where
structual
motors,
Vendors
P&ID.
type
the
it
supported
another
been
with
0.02"
Floor
tested
unit
position
Hook
and
of
with
requirements.
the
accord-ance
that
around
pins
its
between
thre
header
manifold
report
accordance
drawings.
schedule.
Schedule.
recommendations.
approved
unions
that
the
draw-works,
Poorboy
internal
between
package
and
Also
off
shown
flush
to
the
Check
requirements.
in
brake.
the
fully
bolted
unit
damage.
coupling.
control
centre
it's
bar
Manifold.
in
loose
is
of
the
above
that
check
and
correct
requirements.
by
Power
complete
skidding
with
fully
unit.
the
installed.
installed
pneumatic
with
debris.
the
between
the
Vendors
correct
handrails
pilot
and
the
correct
board
of
mounted
accordance
required.
control
finger
These
clear
and
Drill
the
Chain
of
per
tested
rust
to
manifold.
they
water
are
beams.
have
and
Drill
they
the
to
clean
Rotary
that
are
installed
correctly
both
the
requirements.
Unit.
schedule.
supplies
system.
Rotary
and
requirements
or
unit.
/is
necessary
appropriate
as
the
requirements.
all
drill
camera.
can
the
Check
in
that
with
transmission
torqued
and
mud
on
gasket
Also
the
0.03")
Installation
relative
That's
units
pump,
the
provides
tighten
spaced
valves,
from
box
Ensure
are
the
method
same
installed.
on
that
drawing.
project
leg)
installed
to
and
defects.
left
security
requirement.
that
equipment
supports.
Vendor's
specifications.
project
intergrated
lines
per
on
approved
specifications
installation.
its
installed
and
Vendor.
debris.
Vendors
service
accordance
level
rams
Pack.
flushed
manifold.
the
lines
they
of
rotate
Floor,
and
brake
the
Separator
are
Vendors
is
conveyor
and
exhaust
its
been
Floor
internally
rotate.
procedures.
c/l.
boards
are
to
the
desired
table
in
of
assemblies.
position
Vendors
fully
floor
position.
BOP
drawings
the
itbeams
tight.
Check
vendors
valve
sumps.
the
and
levelled
the
with
manifold
and
reqirements.
the
square
Also
foreign
with
Table.
in
the
that
are
it
Table.
screw
Control
with
on
other
condition.
are
the
Cathead,
that
accordance
project
Also
free
is
debrit.
plane
and
driller's
the
between
to
material
and
power
between
as
the
are
cooling
shakers.
level.
that
as
between
installed.
is
vendors
to
the
It
from
holding-down
tees
top
also
drawing
Rig
installed
with
procedure.
equipment
hydraulic
freely.
that
of
clearance
hoses
in
drawings
procedures.
level
the
project
as
wire-locked.
beams.
mud
torqued.
fully
and
Also
correctly
say
Stacks
loops.
all
in
it's
manifold.
they
of
per
service
rig
comes
adequately
prior
ie;
as
per
the
and
draw-works
system.
that
schedule.
all
are
and
install
hydraulic
driller
to
properly
the
system
as
the
bolts
closed
location
rig-up
drawings.
gaining
that
defects.
they
per
acceptable
of
to
and
position
and
are
as
Floor.
lines
unit
and
can
the
that
per
schedule.
debrit.
If
vertically
and
the
skidding
that
rotate.
the
square
bolt
with
and
the
project
to
per
correct
Station,
return
square
ensure
and
are
be
torqued
Derrick
Ensure
the
check
all
control
centre
that
are
the
fan
it
to
project
is
the
and
the
and
insure
level.
the
during
that
have
are
move
from
the
and
is
in
the
free
and
rig
is
of
the
line
and &
manufacturers
been
wire-locking
air
insructions
floor.
torqued
Rotary
system.
Check
Grippers
layout
Drum
ie;
flow
screw
mechanism
freely
connections.
conveyors,
position.
Screw
mentioned
accepted
complete
the
thay
cabin.
procedures.
square
chokes,
shim
accordance
NOTE:
lines
project
connecting
entry
not
installation
specifications.
bolts
panel
lubrication
(pump/motor
gripper
Control
they
Hydraulic
correctly
30%
value.
that
fully
adequate
and
tolerances
aligned
roughneck
have
Also
Derrick
handwheels
package
ensure
lube
P&ID.
installed.
externally.
fittings
"Drill
Ensure
between
requirements.
drilling
supported.
the
condition.
Rotary
fast-line
test
Vendors
line
loops,
via
from
hydraulic
structual
are
layout
up.
with
and
of
correct
monkey
interface
load.
lines
shipping
projecr
Derrick.
then
the
correctly
drawings.
are
procedure.
the
of
level
have
are
oil
line
between
installed
Glycol
project
this
have
torqued.
the
been
until
defects.
into
and
flights
between
Floor
drawing.
Conveyors
that
junction
to
the
requirements.
Flush
they
Table
the
procedures.
layout
gripper
that
and
which
Poorboy
jack
secure.
to
operations.
buffer
Carriedpivot
P&ID.
system
vent
Panel,
have
Station
fully
Note:
use
level
the
sheave
lines
instructions.
project
/has
requirements
run
length
section.
comply
Also
with
to
been
board
fluid
the
Rams
Rig
within
Cat-head,
the
drive
been
height
leveled.
and
(high
Rotary
in
and
layout.
Grippers
the
schedule.
with
of
rotates
are
prior
are
junctionboxes,
Layout".
and
All
the
also
Manifold
jacks
brackets
procedure
alignment
line.
is
are
and
been
installed,
control
the
Cylinder
been
system
outtorqued
hydraulic
exhaust
the
as
drawing.
and
Vendors
are
all
hammer
chambers
tightening
Floor
DO
free
the
Hydraulic
unit.
jack.
the
fully
done
parallel
power
that
boxes
pumps
free
tested
(in
Derrick.
the
and
is
couplings
level
function
procedures.
project
ducting
and
aSeparator
per
bolted
above
to
bytest
of
platforms,
with
secure.
instruments,
It
tested
fixed
and
+/-
Table
and
supported
suitable
guide
on
correctly
Hydraulic
skip
NOT
lower
freely.
blown
from
drillers
NOTE:
the
connection
must
it
valves
The
to
the
can
free
Vendors
The
flushed
distribution
and
panel
the
is
these
are
the
)is
etc.
duct.
as
0.25°
to
for
and
the
structual
rotate.
should
tested
on
and
recommendation.
for
lug
hydraulic
checks
and
functional.
positioners
together
heading.
board
brake
centred
P&ID.
and
freely
Hydraulic
system
start
wheel
and
recommended.
damage.
temperature)
the
from
that
rig
removed.
and
procedures.
mate
Draw-works
check
Power
through
the
both
shims
flushed.
the
are
flushing.
corrosion
assembly
should
cabin)
unions
is
lines
cable
Before
vertical
installed
access
Skip
is
flushed.
out.
The
correctly
erosion
unit,
&
drawings
the
also
upper
following:-
control
above
be
aligned.
Drillers
defects.
to
locked
and
are
traverse
units.
the
function.
that
valves.
flushed
Ensure
correctly.
comp-
and
Pack
using
in
The
be
finally
motor
loops
Mud
rig
and
level.
with
not
the
for
made.
choke
item
align
Power
ways,
the
to
open
the
that
and
and
and
be
the or
8
centralised
air.
control
pump
unit
manifold.
etc.
there
installed
the
Positioners.
attachment
flushing
accordance
during
requirements
spools.
with
that
tested
valves
isprovided
handrails,
system.
drill
clamps.
Gipper
Bucket,
Refer
inhibitor
carriage
hammer
lines
Cabin.
rises
thestarted
side
into
Rig full
mechanism
skip
crown.
Also
all
have
Floor
position
floor
of
the
hydraulic
have
isunless
to
and
the
the
NOTE:
manifold
Jacks
length
sufficient
Ensure
positioners.
Ensure
flanges
should
assemblies.
the
lugg
in
to
the
that
by
been
Also
datum.
pipe
distribution
test.
been
lines
the
Derrick.
greasing
to
the
with
correct
For
project
same
the
Vendor
the
via
and
the
type
of
choke
tested
retracted
pumps
they
supports,service
new
rotates
that
be
that
flushed
rail
Vendor
have
on
accumulators
the
the
are
hydraulic
project
movement.
the
rating
Refere
unions.
inPh.
the
tolerances
the
have
correct
system
the
project
Check
P&ID
locking
beam.
tested
should
consul.
Ensure
and
accordance
Locking
been
(manifold.
freely.
Poorboy
lines
can
in
flushing
to
position.
as
pipework.
been
to
flushed-out.
accordance
level
flushed.
to
and
choke
lines
that
type
is
be
the
clamps.
that
have
ensure
ie.
in
Clamps.
have
refer
flushed
air
invited
flushed
these
Derrick
loops
the
section
ring
place.
have
of
check
the
with
Check
and
been
the
been
toalland
toof
been
out.
charged.
The
and
that
lines
project
specifications.
gaskets
the
manifolds
run
Derrrick.
cable
tested
Vendors
Ensure
Drill
system
with
transmission
AC.
thatmanifold.
the
tested
the
Comply
required
all
motor
the
have
flushed
Line
are
rack
and
procedure.
pneu-matic
is
that
lines
must
flow
project
drawings.
complete.
square
or
been
to
Spool,
flushed.
supports
driven
all
with
have
the
line
lines
through.
be
standard
NOTE:
lines
tested
used.
requirements.
standard
to
does
the
)been
isComply
and
the
and
that
are
instandard
new
and
for
not
drill-
accordance
hydraulic
tested
accumulator
flushed
they
re-quired
this
rest
flushed
andwith
floor
conform
and
operation
on
demanded
correct
Top
and
the
lines
the
and
flushed
towith
inthe
the
in
tois
CONTRACTOR
in
to
onshore
Header
standard
type
aCheck
with
tested
Drive
the
banks
tobulkhead
"onshore
be
the
centre
requirements
ring
the
found
Parking
in
standard
for
against
Box.
"flushing
Vendors
required
accordance
demanded
gaskets
back-up
ofterminal
in
flushing
thethe
demanded
set-back
of
must
drawings.
in
onshore
of
accepted
fluid
in
the
plate
the
of
with
drilling
the
bedrilling
project.
power.
onshore
area.
at
used.
the
"onshore
in
guide,
procedures.
the
hydraulic
the
standard
hydraulic
edge
"onshore of
systems".
"flushing
systems"
flushing
the
re-quired
The
"flushing
skid.
Rig of Floor
and
Plate
of
in
ofhydraulic
the
drilling
cleaning
Distributuon
position
onshore,"flushing
drilling hydraulic
systems".
ofto hydraulic
airbeManifold.
anddetermined
systems".
hydraulic
of
Accepted by

COMPANY
systems".
on
lines".
drilling
site. hydraulic systems"

COMMISSIONING

CERTIFYING AUTHORITY
FORM: C-LX-02A PIPEWORK BEFORE TEST PACK TESTS SHEET 1 OF 1
PRECOMMISSIONING CHECK LIST
PIPING & VESSEL
NDE CLEARENCE

0
Test Pack : W3-0103-01 FORM : T-MX-07 - NDT CLEARENCE
Production Header

TASK NUMBER : TASK LOCATION :


ESTIMATED TIME (MH) : EXPENDED TIME (MH) :
PUNCH LIST ITEMS : Subsystem: 0101

ACTIVITIES:

NDT CLEARANCE
REINSTATMENT
Flushing Hydro testing Draining & Drying Pickling

R R
S/SYSTEM LINE IDENTIFICATION ISO E PID E
V V

DATE NAME SIGNATURE


Carried out by
CONTRACTOR
Accepted by

COMPANY
COMMISSIONING
Accepted by
CERTIFYING AUTHORITY
SAKA INDONESIA PANGKAH LIMITED
PIPING & VESSEL
PRECOMMISSIONING ENTRY FORM

PIPEWORK LINE CHECK PUNCH LIST


SYSTEM : 01 FORM : PIPEWORK LINE CHECK PUNCH LIST

SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids


TEST PACK NO : W3-0103-01 PLATFORM : WHP-C
SITE : : ONSHORE OFFSHORE SHEET : 1 OF 1
LINE IDENTIFICATION :

PROCEDURE NO :

CLEARANCE
BY COMPANY REPRESENTATIVE
ITEM ISOMETRIC DRAWING PRIO-
DESCRIPTION
NO. NO. RITY
SIGNATURE DATE

1 W3-10"-01015-B09B

2 W3-10"-01016-B09B

3 W3-2"-01021-B09B

4 W3-2"-01022-B09B

5 W3-6"-01004-B09B

6 W3-6"-01006-B09B

7 W3-6"-01008-B09B

DATE NAME SIGNATURE

Carried out by

CONTRACTOR
Accepted by

COMPANY

COMMISSIONING

CERTIFYING AUTHORITY

NOTE: PRIORITY 1 : Item shall be cleared prior to pressure test


PRIORITY 2 : Item can be cleared after pressure test
SAKA INDONESIA PANGKAH LIMITED
PRECOMMISSIONING TEST SHEET
PIPING & VESSEL
PIPE WORK FLUSHING / CLEANING

SYSTEM : 01 FORM : T-MX-05


SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids
TEST PACK NO: W3-0103-01 PLATFORM : WHP-C
SITE : SHEET : 1 OF 1
LINE IDENTIFICATION :

PROCEDURE NO :

TEST PREPARATION
Weight control (for gas line supports): NO YES
Water quality Inhibitor: NO YES
Filtration: NO YES
Water disposal: NO YES
Equipment removed: NO YES Conformity PID's* NO YES
REQUEST TO FLUSH DATE: WITNESSING: NO YES
PERMISSION TO FLUSH NAME DATE

DATA
FLUSHING MEDIUM: FLUSHING FLOW: FLUSHING MEDIUM T°:
FLUSH DATE: FLUSH DURATION: WITNESSING BY:
REMARKS
* Excepted removed equipments, pipework installation is conform to the specification & PID's ,

NOTE:
1. ADDITION SHEET FOR TEST PACKAGE INDEX

DATE NAME SIGNATURE

Carried out by

CONTRACTOR
Accepted by

COMPANY

COMMISSIONING

CERTIFYING AUTHORITY

FORM: T-MX-05 PIPEWORK CHEMICAL FLUSHING/ CLEANING SHEET 1 OF 1


SAKA INDONESIA PANGKAH LIMITED
PRECOMMISSIONING TEST SHEET
PIPING & VESSEL
PIPEWORK PRESSURE TEST

SYSTEM : 01 FORM : T-MX-03


SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids
TEST PACK NO : W3-0103-01 PLATFORM : WHP-C
SITE : ONSHORE OFFSHORE SHEET : 1 OF 1
LINE IDENTIFICATION :

PROCEDURE NO :

TEST PREPARATION
Weight control (for gas line supports): NO YES
Water quality Inhibitor: NO YES
Filtration: NO YES
Equipment removed: NO YES Conformity PID's* NO YES
REQUEST TO PRESSURE TEST DATE: WITNESSING: NO YES
PERMISSION TO TEST NAME DATE
DATA
DESIGN PRESSURE: TEST PRESSURE: TEST MEDIUM

CALIBRATION CERTIFICATE: BLIND LIST


TEST RESULTS
TEST DATE: TEST DURATION: WITNESSING BY:
TEST PRESS-START: TEST PRESS- FINISH: TEST MEDIUM TEMP:

REMARKS
* Excepted removed equipments, pipework installation is conform to the specification & PID's ,

NOTE:
1. ADDITION SHEET FOR TEST PACKAGE INDEX
2. PRESSURE TEST RECORD SHEET

DATE NAME SIGNATURE

Carried out by

CONTRACTOR
Accepted by

COMPANY

COMMISSIONING

CERTIFYING AUTHORITY
FORM: T-MX-03 PIPEWORK PRESURE TEST SHEET 1 OF 1
SAKA INDONESIA PANGKAH LIMITED
PRECOMMISSIONING CHECK LIST
PIPING & VESSEL
PIPEWORK AFTER TEST

SYSTEM : 01 FORM : C-LX-02B


SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids
TEST PACK NO : W3-0103-01 PLATFORM : WHP-C
SITE : ONSHORE OFFSHORE SHEET : 1 OF 1
LINE IDENTIFICATION :

PROCEDURE NO :

Remark/
ITEM CHECK LIST Y N
N/A

1 Check that the pipework and equipment are drained as per procedure
Check that the pipework and equipment (re)installation conforms to the
2
specifications, drawings and to the P&ID's
Check that new gasket have been installed after pipework and equipment
3
reinstallation
Check that the pipework, valves, check valves are undamaged. Also check the
4
ancillaries and any other components.
5 After the (re)installation of a valve check that it operates freely.
Check that the flow direction of the valves and ckeck-valve is in the correct
6
sense/direction.
Check that the valves have been correctly lubricated and that they have the correct
7
spindle packing
8 Check that all the bolts and fasteners are suitably lubricated.
Check that after pre-commissioning is finished that the painting of piping systems
9
and of the equipment is "touched up" to conform to the specifications
Check for the correct tagging, labelling and colour coding of pipework and
10
equipment.
11 Produce a set of marked-up drawings in accordance with the installation.
12 Produce a defects list for issue in the Punch List.

NA Not Applicable X Checked & not accepted  Checked & accepted

REMARKS:
TOTAL
Produce
Lubricate
Install
Check
Ensure
Record
Using
Inspect
Complete
The
Before
Fill
Hydrotest
Test
Generally
Attatch
Leave
Fully
Bleed
Blank
NOTE:
Assemble
Connect
Grease
Produce
The
Fill
Install
Check
Ensure
Lubricate
Chech
Check
Lubricate
Generally
Ensure
and
the
brake
Hydraulic
Mud
Top
BOP
run
centre
control
Hydraulic
and
grease
the
and
off
all
the
that
for
flexible
Kill
hydraulic
diving
Grippers
and
between
security
out
inside
the
both
that
all
items
finger
connecting
the
all
that
correct
the
tank
the
bleed
blead
that
lubricate
to
aDrive,
and
aflush
The
Standpipe
pipehandler
the
Control
Vendor
unused
the
Deadline
flow
defects
pipe
Drill
positioner
Manifold
instruments
Poorboy
components
downstream
Choke
any
rams
cooling
Top
check
security
installation
the
pivot
integrity
Mixing
manifold
Rotary
track
derrickman's
Grippers
Hydraulic
Drum
pressure
all
and
valve
interior
fill
Manifold
accessibility
alignments
fluid
function
Drag
roller
hydraulic
Mud
set
upper
defects
the
drum
installation
security
painting
check
correct
fluid
Screw
all
"tugger
the
sheave
outer
table
Unit
there
lines
that
brake
the
cooling
each
Grippers
all
these
the
Drag
sections
all
the
Panel
the
with
the
check
for
choke
the
equipment
hydraulic
components
system
manifold
cement
mechanical
check
boards
board
units
Chains
manifold
system
correct
systems
of
manifolds
Manifold
the
alignment
table
Derrick
valves
Cathead
bolts
interconnecting
hoses
installation
sheaves
install
flexible
Hook
large
small
Hydraulic
hydraulic
DisplacementtTanks
chains
Drive
Power
Top
expansion
heat
nameplate
Block
brake
Header
Shakers
of
the
project
silencer
crown
earthing
eathing
Manifold
hoses
alignment
flexible
equipment
Brake
ducting
items
guide
Crown
location
Mud
Derrick
hydraulic
handlers
Power
table
Rotary
skid
pump
replaceable
head
manifold
Anchor
and
of
Top
clevis
hold
painting
location,
Drum
Line
control
hold-down
Hydraulic
the
all
in
Bucket
ends
kit
and
sheaves
mechanism
Chains
service-loop
Skid
Anchor
stems
assemblies.
must
centre
joint
cleanliness
marked-up
backlash.
drive
the
are
Control
wraps
Poorboy
all
Control
instrument
the
Chains
control
aconnections
system
lines
hydraulic
provided
Conveyor
Hose
pipework
list
Package
all
the
list
Unit
system
mounting
enables
of
lines
grooves
installation
the
of
and
sheaves"
of
in
on
section
transmitter
roughneck
coolant
Drive
storage
of
the
visually
and
return
insulation
to
anchor
have
Drive
and
beams
on
in
onto
list
Manifold
Screw
Jacks
list,
jumper
Bucket
Derrick
grating
access
down
of
interface
and
is
Drum
Screw
cylinder
th
locks
into
rams
integrity
assembly
cooling
flexible
of
Parking
in
installed
to
draw-works
connections
the
rails
bolt
in
manifold
function
and
for
all
drives
the
installation
Cooling
are
accordance
is
Pack
in
pins
all
for
closed
unit
termination
braket
coincide
of
the
Unit
all
and
skid
project
bolts
for
in
Shaker
supply
Block
unit
the
Table
assembly
Box
in
and
that
expansion
level
with
section
are
integrity
the
in
is
jumper
panel
line
hold-down
the
have
bolts
and
connection
of
on
lines
complete
into
accordance
for
the
and
blocks
"C-GX-07"
control
coupling
security
between
in
accordance
(directly
kill
free
control
is
the
in
are
ref;
and
"C-GX-07"
connections.
hydraulic
in
of
elevation
lines
is
both
exhaust
are
the
accordance
issue
Station.
top
lines
been
hydraulic
with
Rams
the
installed
accordance
C-GX-07
air
pipework
hose
mounted
issue
located
and
Consul
square
supports
service
bolted
alignment
Hook
accordance
details
connections
instrument
with
damage.
drill
for
pipework
is
guide
hangs
the
Separator
on
Cathead
Derrick.
onto
alignment
to
provides
accordance
the
(typical
are
bolts
transmitters.
well
suitable
Rig
frovides
connection
accordance
Draw-works.
of
Cathead
are
for
bolts
hydraulic
beams
secured
bonding
Conveyor
in
securely
and
accordance
installation
pre-charge
have
items
for
mix
tank
the
manifold
pumps
doors
is
Conveyer
ensure
distance
the
system.
have
to
bonding
hoses.
ducting
for
drawings
hydraulic
lines
its
of
greased
Control
is
wear
are
have
and
lubricated
bonded
of
Drag
connected
lines
line
for
to
hydraulic
is
been
ensure
Drill
and
are
drive
position.
valves
the
assembly
Derrick.
system
water-lines,
C-GX-07
jumper
is
the
The
support
of
the
piping
accordance
correctly
free
manifold
DC.
mud
panel
Units
is
have
and
where
are
in
operator
Package
drum
hydraulic
of
fully
in
working
the
have
pipework
tightened
and
damage.
in
free
of
the
and
floor
have
for
hoses
is
potable
installed
free
Floor
hydraulic
in
between
rotate
the
adjoining
locate
station
damage.
correctly
for
greased
of;-
are
cabin
correctly
for
of
signes
over
small
atrolley
the
in
items
are
to
correctly
been
over
skid
also
from
the
are
place
package
to
all
hoses
system
in
been
the
can
loop
of
Top
with
at
to
with
the
bellows
plates
system
been
in
Pipe
have
one-
as
fully
units
kits
Floor
Rotary
Chains
rotation
small
defects
and
motors
diving
are
for
bolts
that
and
line
all
the
lines
check
place
is
of
for
to
been
)with
the
are
with
is
been
its
that
in
on
and
hoses
70%
pipe
has
the
for
been
as
and
to
from
in
for
unit
are
to
per
with
on
of
in
lines
with
for
the
on
for
has
the
in
has
it
the
in
kit,
are
the
in
its
be
is
of
in
all
to
it
as
is
in
DATE NAME SIGNATURE
FINA
withELF
Punch
tightened
and
in
table
Ensure
rotate.
weld
on
connections
Rotary
the
handling
between
is
beams
greased
check
tolerance
fill
connections.
fluid
damage
conveyor
Skip
Cutting
hydraulic
flushed
piece
to
attached
valves
up
fluid.
pipework
shipped
manifold
from
Driller
security
been
have
free
parallel
located
complete
centre
structual
undamaged.
running
electrical
safety
Table.
eddy
package
necessary
correct
beams.
rams.
greased.
Handling
hoses
potable
its
drive
system
correctly
secure
board
installed
seal
Shaker
certain
applicable.
for
units.
corrosion;
vendors
comprised
support
project
manifold.
per
fittings.
accordance
against
within
intended
following
To
the
system.
water
Derrick.
installed.
have
Skid
operational
connections
supported
drill
Drive
diving
skid
Derrick
between
Station
(Punch
flushed-out
removed
accordance
Ensure
aligned
in
free
the
with
typically
located
correctly
accordance
comply
verify
the
accordance
to
bearing
and
be
derrick.
Vendors
Derrick.
Hydraulic
the
all
link
security
rig
project
hammer
BOP
tow
Vendors
front
centre
correct
vendors
run
that
complete.
structual
locking
the
orientation
fixed
HP.
from
hoses
Vendors
of
D.C.
welded
the
to
structual
floor
Positioners
as
correctly
flushed
been
edge
splatter,
the
is
current
been
and
the
all
mechanism.
where
list
assembly;
and
supported
are
AC.
Drill
clamps.
List.
line
Do
and
on
the
foreign
List.
floor.
Cabin
controls.
board,
Hydraulic
that
Table
rotate
are
position
skidding
lines
by-pass
spray
precharge
correctly
the
and
in
per
has
Transfer,
listed
to
that
smoothly.
water,
bars
and
brackets
structure.
sections
loose
and
of
free.
etc.
the
pumps
equipment
Vendors
requirements.
all
rig
the
to
is
welded
manifold.
Control
or
and
the
machine
that
damage
correctly.
on
Vendors
Draw-works
onto
installed.
is
installed
in
use
the
when
and
from
equipment
drives.
lines
Machine,
at
for
securely
lines.
power
correctly
fluid-power
their
between
not
to
the
closely
with
flushed.
correctly
tested
of
inhibitor.
is
Drag
correctly.
check
correctly
4of
the
hydraulic
blocks.
installed,
installed
where
structual
motors,
Vendors
P&ID.
type
the
another
it
supported
been
with
0.02"
Floor
the
position
tested
unit
Hook
of
and
with
requirements.
accord-ance
the
that
between
around
pins
its
thre
header
manifold
recommendations.
approved
schedule.
report
accordance
drawings.
Schedule.
unions
that
the
draw-works,
Poorboy
internal
between
package
and
Also
flush
to
off
shown
the
Check
requirements.
in
brake.
fully
bolted
unit
damage.
coupling.
it's
control
centre
bar
Manifold.
loose
in
of
is
the
above
and
that
check
correct
Power
requirements.
by
complete
skidding
with
fully
unit.
the
installed.
installed
pneumatic
with
debris.
the
between
the
Vendors
correct
pilot
handrails
and
the
correct
board
of
accordance
mounted
required.
control
finger
These
clear
and
Drill
the
Chain
of
per
tested
rust
to
manifold.
they
water
are
beams.
and
have
Drill
the
they
Rotary
to
clean
that
are
installed
correctly
both
the
schedule.
Unit.
requirements.
system.
supplies
Rotary
requirements
and
or
unit.
/is
as
necessary
appropriate
the
requirements.
all
drill
camera.
can
the
Check
in
with
that
transmission
torqued
and
mud
on
gasket
Also
the
0.03")
relative
Installation
That's
units
pump,
the
tighten
provides
valves,
spaced
box
from
Ensure
are
the
method
same
installed.
on
that
drawing.
project
to
leg)
installed
and
defects.
security
left
requirement.
that
equipment
supports.
Vendor's
lines
intergrated
specifications.
project
per
on
specifications
installation.
approved
its
installed
and
Vendor.
debris.
Vendors
service
accordance
level
Pack.
rams
flushed
manifold.
the
lines
they
of
Floor,
rotate
and
the
brake
Separator
Vendors
are
is
conveyor
exhaust
and
its
been
Floor
internally
rotate.
procedures.
c/l.
are
boards
the
to
desired
of
table
in
position
Vendors
assemblies.
fully
floor
position.
drawings
BOP
the
itbeams
tight.
Check
valve
vendors
the
sumps.
and
levelled
the
with
manifold
and
reqirements.
the
square
Also
foreign
with
Table.
in
the
that
are
it
Table.
with
Control
screw
on
other
condition.
are
the
Cathead,
that
project
accordance
Also
is
free
debrit.
plane
and
driller's
the
between
to
material
and
power
as
between
the
are
cooling
shakers.
level.
as
that
between
installed.
is
vendors
to
the
It
from
holding-down
top
tees
also
drawing
Rig
installed
with
procedure.
equipment
hydraulic
freely.
that
of
clearance
hoses
in
project
level
drawings
procedures.
the
wire-locked.
as
mud
torqued.
beams.
fully
and
Also
correctly
say
Stacks
loops.
in
all
it's
manifold.
they
per
of
rig
service
comes
adequately
prior
ie;
as
per
the
and
draw-works
system.
that
schedule.
all
are
and
install
hydraulic
driller
the
properly
to
system
the
as
bolts
closed
rig-up
location
drawings.
gaining
that
defects.
they
acceptable
per
of
to
and
position
and
are
Floor.
as
lines
unit
and
that
can
the
per
schedule.
debrit.
If
vertically
and
the
skidding
that
the
rotate.
square
bolt
with
the
and
project
to
per
correct
Station,
return
square
ensure
and
are
be
torqued
Derrick
the
Ensure
check
all
control
centre
that
are
fan
the
it
to
project
is
the
and
the
and
insure
level.
the
during
that
have
are
move
from
the
and
is
and
in
the
free
and
rig
is
of
the
line
and &
flow
manufacturers
wire-locking
insructions
floor.
Rotary
Check
layout
Drum
ie;
been
air
torqued
system.
Grippers
screw
mechanism
freely
connections.
conveyors,
position.
Screw
mentioned
accepted
complete
the
thay
cabin.
procedures.
square
chokes,
shim
accordance
NOTE:
lines
connecting
project
entry
not
installation
specifications.
bolts
panel
lubrication
(pump/motor
gripper
Control
they
Hydraulic
correctly
30%
value.
that
fully
adequate
and
tolerances
aligned
roughneck
have
Also
Derrick
handwheels
package
ensure
lube
P&ID.
installed.
externally.
fittings
"Drill
Ensure
between
requirements.
drilling
supported.
the
condition.
test
Vendors
line
from
structual
Rotary
fast-line
loops,
via
hydraulic
are
layout
up.
with
and
of
correct
monkey
interface
load.
lines
shipping
projecr
Derrick.
then
drawings.
the
correctly
are
procedure.
the
of
level
have
oil
are
line
between
installed
Glycol
project
this
have
the
torqued.
been
until
defects.
into
and
flights
between
Floor
drawing.
Conveyors
that
junction
to
the
requirements.
Flush
they
Table
procedures.
layout
gripper
that
and
which
Poorboy
jack
Carriedsecure.
operations.
to
buffer
pivot
system
P&ID.
vent
Panel,
have
Station
fully
Note:
use
level
the
instructions.
sheave
lines
project
/has
requirements
run
length
section.
comply
Also
with
to
been
board
the
fluid
Rig
Rams
within
Cat-head,
the
drive
been
height
leveled.
and
(high
Rotary
in
Grippers
and
layout.
the
schedule.
with
of
rotates
are
prior
junctionboxes,
Layout".
and
All
Manifold
also
the
jacks
brackets
procedure
alignment
is
line.
are
and
control
been
installed,
the
Cylinder
outbeen
system
exhaust
torqued
hydraulic
the
as
drawing.
Vendors
and
are
all
hammer
tightening
Floor
chambers
DO
free
the
Hydraulic
unit.
jack.
the
fully
done
parallel
power
that
boxes
pumps
free
tested
(in
the
Derrick.
and
is
couplings
level
function
procedures.
ducting
project
and
aSeparator
per
bolted
above
to
bytest
platforms,
of
with
secure.
instruments,
It
tested
fixed
and
+/-
Table
and
supported
suitable
correctly
guide
on
Hydraulic
skip
NOT
lower
freely.
blown
from
drillers
NOTE:
the
it
connection
must
valves
The
to
the
can
free
Vendors
distribution
The
flushed
and
panel
the
is
these
are
the
)is
etc.
duct.
as
0.25°
to
and
for
the
structual
rotate.
should
on
and
tested
recommendation.
for
lug
hydraulic
checks
and
functional.
positioners
together
heading.
board
brake
centred
P&ID.
and
freely
Hydraulic
system
start
wheel
temperature)
and
damage.
recommended.
the
from
that
rig
removed.
and
procedures.
mate
Draw-works
check
Power
through
the
both
shims
flushed.
are
the
corrosion
flushing.
assembly
should
cabin)
is
unions
lines
cable
Before
vertical
installed
access
Skip
is
flushed.
out.
The
correctly
erosion
unit,
&
the
drawings
also
upper
following:-
control
above
be
Drillers
aligned.
defects.
to
locked
and
are
traverse
units.
the
function.
that
valves.
flushed
Ensure
correctly.
comp-
and
Pack
using
in
The
be
finally
motor
loops
Mud
rig
and
level.
with
not
the
for
made.
choke
item
align
Power
ways,
the
to
open
the
that
and
and
and
be
the or
8
centralised
control
the
manifold.
etc.
there
air.
pump
unit
installed
Positioners.
attachment
flushing
accordance
during
requirements
spools.
with
that
tested
valves
isprovided
handrails,
system.
drill
clamps.
Gipper
Bucket,
Refer
inhibitor
carriage
hammer
lines
Cabin.
rises
Rig
thestarted
side
into full
mechanism
skip
crown.
Also
all
have
Floor
position
floor
of
the
hydraulic
have
isunless
to
and
the
the
NOTE:
manifold
length
the
Jacks
sufficient
Ensure
positioners.
Ensure
flanges
should
assemblies.
the
lugg
in
to
the
that
by
been
Also
datum.
pipe
distribution
test.
been
lines
the
greasing
Derrick.
to
the
with
correct
For
project
same
the
the
Vendor
via
and
the
type
of
choke
tested
retracted
they
pumps
supports,service
new
rotates
that
be
flushed
that
rail
Vendor
have
on
accumulators
the
the
are
hydraulic
project
movement.
the
rating
Refere
unions.
inPh.
the
tolerances
the
have
correct
system
the
project
Check
P&ID
locking
beam.
tested
should
consul.
Ensure
accordance
and
Locking
been
(manifold.
freely.
Poorboy
lines
can
in
flushing
to
position.
as
pipework.
been
to
flushed-out.
accordance
level
flushed.
to
and
choke
lines
that
type
is
be
the
clamps.
that
have
ensure
ie.
in
Clamps.
have
refer
flushed
air
invited
flushed
these
Derrick
loops
the
section
ring
place.
have
of
check
the
with
Check
and
been
the
been
toalland
toof
out.
and
that
been
charged.
The
lines
project
specifications.
gaskets
the
manifolds
run
Derrrick.
cable
tested
Vendors
Ensure
Drill
system
with
transmission
AC.
thatmanifold.
the
tested
the
Comply
required
CONTRACTORall
motor
the
have
flushed
Line
are
rack
and
procedure.
pneu-matic
is
that
lines
must
flow
project
drawings.
complete.
square
or
to
been
Spool,
flushed.
supports
driven
all
with
have
line
the
lines
through.
be
standard
NOTE:
lines
tested
used.
requirements.
standard
to
does
the
)been
isComply
and
the
and
that
are
instandard
new
and
for
not
drill-
accordance
hydraulic
tested
accumulator
flushed
they
re-quired
this
rest
flushed
andwith
floor
conform
and
operation
on
demanded
correct
Top
and
the
lines
the
and
flushed
towith
inthe
the
in
tois
in
onshore
Header
to
standard
type
aCheck
with
tested
Drive
the
banks
tobulkhead
"onshore
be
the
centre
requirements
ring
the
found
Parking
standard
in
for
against
Box.
"flushing
Vendors
required
accordance
demanded
gaskets
back-up
ofterminal
in
flushing
thethe
demanded
set-back
of
must
drawings.
in
onshore
of
accepted
fluid
in
the
plate
the
of
drilling
with the
bedrilling
project.
power.
onshore
area.
at
used.
the
"onshore
in
guide,
procedures.
the
hydraulic
the
standard
hydraulic
edge
onshore
" of
Accepted by

COMPANY
systems".
systems"
"flushing
flushing
the
re-quired
The
"flushing
skid.
Rig of Floor
and
Plate
of
in
ofhydraulic
the
drilling
cleaning
Distributuon
position
onshore,"flushing
drilling hydraulic
systems".
ofto hydraulic
airbeManifold.
and
determined
systems".
hydraulic
of
systems".
on
lines".
drilling
site. hydraulic systems"
COMMISSIONING

CERTIFYING AUTHORITY
FORM: C-LX-02B PIPEWORK AFTER TEST PACK TESTS SHEET 1 OF 1
SAKA INDONESIA PANGKAH LIMITED
PRECOMMISSIONING TEST SHEET
PIPING & VESSEL
DRAINING AND DRYING

FORM : TMX16 - DRAINING AND DRYING

TASK NUMBER : TASK LOCATION :


ESTIMATED TIME (MH) : EXPENDED TIME (MH) :
PUNCH LIST ITEM : Subsystem : 0101

ACTIVITY
DRAINING YES NO
BLOWING WITH AIR YES NO
DRYING METHOD: AIR VACUUM NITROGEN
DEW POINT VALUE:
PIPEWORK INDEX
VELOCITY
LINE SIZE N° SPOOL N° ISO N° REV. P&ID N° TEST DRG N°
M/S

REMARKS

DATE NAME SIGNATURE

Carried out by

CONTRACTOR
Accepted by

COMPANY

COMMISSIONING

CERTIFYING
AUTHORITY
FORM: TMX16 - DRAINING AND DRYING SHEET 1 OF 1
SAKA INDONESIA PANGKAH LIMITED
PIPING & VESSEL
PRECOMMISSIONING TEST SHEET
GASKET STATUS & ACCEPTANCE SHEET
SYSTEM : 01 FORM : GASKET STATUS & ACCEPTANCE SHEET
SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids
TEST PACK NO : W3-0103-01 PLATFORM : WHP-C
SITE : : ONSHORE OFFSHORE SHEET : 1 OF 1
LINE IDENTIFICATION :

PROCEDURE NO :

GASKET INDEX
PERMANENT GASKET
GASKET EQUIPMENT NO. ACCEPTANCE BY
NO. GASKET TYPE STATUS
NO. (ISOMETRIC NO. FOR PIPING) COMPANY REP.
SIGNATURE DATE

Gasket 900# RTJ OCTOGONAL RING TYPE Permanent


1 F1 W3-10"-01015-B09B
R53
Temporary

Gasket 1500# RTJ OCTOGONAL RING TYPE Permanent


2 F2 W3-10"-01015-B09B
R16
Temporary

Gasket 1500# RTJ OCTOGONAL RING TYPE Permanent


3 F3 W3-10"-01015-B09B
R14
Temporary

Gasket 900# RTJ OCTOGONAL RING TYPE Permanent


4 F4 W3-10"-01015-B09B
R53
Temporary

Gasket 900# RTJ OCTOGONAL RING TYPE Permanent


5 F1 W3-10"-01016-B09B
R53
Temporary

Gasket 900# RTJ OCTOGONAL RING TYPE Permanent


6 F2 W3-10"-01016-B09B
R53
Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
7 F1 W3-2"-01021-B09B
R24 Temporary

Gasket 1500# RTJ OCTOGONAL RING TYPE Permanent


8 F2 W3-2"-01021-B09B
R24
Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
9 F3 W3-2"-01021-B09B
R24 Temporary
Gasket 1500# RTJ OCTOGONAL RING TYPE Permanent
Temporary
10 F4 W3-2"-01021-B09B
R24
Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
11 F5 W3-2"-01021-B09B
R24 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
12 F6 W3-2"-01021-B09B
R24 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
13 F7 W3-2"-01021-B09B
R24 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
14 F8 W3-2"-01021-B09B
R14 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
15 F1 W3-2"-01022-B09B
R24 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
16 F2 W3-2"-01022-B09B
R24 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
17 F3 W3-2"-01022-B09B
R24 Temporary
SAKA INDONESIA PANGKAH LIMITED
PIPING & VESSEL
PRECOMMISSIONING TEST SHEET
GASKET STATUS & ACCEPTANCE SHEET
SYSTEM : 01 FORM : GASKET STATUS & ACCEPTANCE SHEET
SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids
TEST PACK NO : W3-0103-01 PLATFORM : WHP-C

SITE : : ONSHORE OFFSHORE SHEET : 1 OF 1

LINE IDENTIFICATION :

PROCEDURE NO :

GASKET INDEX

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
18 F4 W3-2"-01022-B09B
R24 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
19 F5 W3-2"-01022-B09B
R24 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
20 F6 W3-2"-01022-B09B
R14 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
21 F1 W3-10"-01015-B09B
R45 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
22 F2 W3-10"-01015-B09B
R45 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
23 F3 W3-10"-01015-B09B
R45 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
24 F4 W3-10"-01015-B09B
R45 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
25 F5 W3-10"-01015-B09B
R14 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
26 F1 W3-6"-01006-B09B
R45 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
27 F2 W3-6"-01006-B09B
R45 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
28 F3 W3-6"-01006-B09B
R45 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
29 F4 W3-6"-01006-B09B
R45 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
30 F5 W3-6"-01006-B09B
R14 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
31 F1 W3-6"-01008-B09B
R45 Temporary

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
32 F2 W3-6"-01008-B09B
R45 Temporary

Gasket 900# RTJ OCTOGONAL RING TYPE Permanent


33 F3 W3-6"-01008-B09B
R45 Temporary
SAKA INDONESIA PANGKAH LIMITED
PIPING & VESSEL
PRECOMMISSIONING TEST SHEET

GASKET STATUS & ACCEPTANCE SHEET


SYSTEM : 01 FORM : GASKET STATUS & ACCEPTANCE SHEET

SUBSYSTEM : 0101 LINE SERVICE : Two Phases Fluids

TEST PACK NO : W3-0103-01 PLATFORM : WHP-C

SITE : : ONSHORE OFFSHORE SHEET : 1 OF 1

LINE IDENTIFICATION :

PROCEDURE NO :

GASKET INDEX

Permanent
Gasket 900# RTJ OCTOGONAL RING TYPE
34 F4 W3-6"-01008-B09B
R45 Temporary

Permanent
Gasket 1500# RTJ OCTOGONAL RING TYPE
35 F5 W3-6"-01008-B09B
R14 Temporary

We hereby confirm that all gaskets above have been installed and checked and classified as either temporary or permanent.
Any temporary gasket shall be replaced by permanent one during reinstatement as per specification. Only permanent gaskets to be
accepted by COMPANY.
DATE NAME POSITION SIGNATURE

INSTALLED BY

CONTRACTOR
ACCEPTED BY

COMPANY

COMMISSIONING

CERTIFYING AUTHORITY

FORM: GASKET STATUS AND ACCEPTANCE SHEET


PIPING & VESSEL
PRECOMMISSIONING ENTRY FORM

PIPEWORK REINSTATEMENT PUNCH LIST

PROJECT : SAKA INDONESIA PANGKAH LIMITED


JOB NO. : 19087
SUBSYSTEM : 0101 SHEET : 1 OF 1
TEST PACK NO. : W3-0103-01
CLEARANCE
ITEM ISOMETRIC DRAWING BY COMPANY REPRESENTATIVE
DESCRIPTION TYPE
NO. NO.
SIGNATURE DATE

CARRIED-OUT BY CONTRACTOR COMPANY

NAME

POSITION

SIGNATURE

DATE
NOTE: TYPE A: Item considered as block point for commissioning activity of the sub-system
TYPE B: Item considered as block point for start-up activity of the sub-system
TYPE C: Item not considered as block point for start up activity