Professional Documents
Culture Documents
~ ., 1-
TABLE OF CONTENTS
1.0 SCOPE 4
2.0 SPECIFICATIONS, CODES, STANDARDS AND REGULATIONS 4
3.0 FABRICATION REQUIREMENTS OF PIPEWORK 5
3.1 General Requirements 5
3.1.1 Bends 6
3.1.2 GRE Piping Bonding 6
3.1.3 Fabrication Tolerance 7
3.1.4 Construction Marking 7
3.2 Welding 7
3.2.1 Welding Procedure Qualifications and Welder Qualifications 7
3.2.2 Welding Procedures and Processes 8
3.2.3 Filler Materials, Electrodes, Wire, and Flux 9
3.2.4 Fabrication and Welding Joint Preparation, Spacing and Alignment 10
3.2.5 Weld Contour and Finish 11
3.2.6 Butt Welds for Orifice Rums 11
3.2.7 Other Requirements 11
3.2.8 Heat Treatment 11
3.3 Non Destructive Testing (NDT) Requirements 12
3.3.1 General Requirements 12
3.3.2 Radiographic Tests 14
3.3.3 Acceptance Criteria 14
3.3.4 Ultrasonic Testing (UT) 14
3.3.5 Magnetic Particle Inspection (MPI) 14
3.3.6 Dye Penetrant Inspection (DPI) 15
3.3.7 Acceptance Criteria 15
3.3.8 NDE Operator Qualifications 16
3.3.9 Pressure Testing 16
4. INSTALLATION REQUiREMENTS 16
4.1 General 16
4.2 Piping Erection 17
4.3 Erection of Tie Ins to Equipment 18
4.4 Installation of Valves 18
4.5 Installation of Threaded Assemblies 19
4.6 Make Up of Flanged Assemblies 19
4.7 Insulating Flanges 20
4.8 Gaskets 20
4.9 Installation of Line Blinds, Spectacle Blinds and 20
5.0 INSPECTION AND TESTING REQUIREMENTS 21
5.1 Additional Quality Verification Inspections 21
5.1.1 General 21
5.1.2 Visual Inspection 21
5.1.3 Hardness Test 21
5.1.4 Radiographic Examination 22
5.1.5 Magnetic Particle Examination 22
5.1.6 Repairs for GRE Piping 22
5.1.7 Repairs 22
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 3 of 42
INSTALLATION AND TESTING
1.0 SCOPE
This Specification defines the minimum requirements for piping fabrication, erection
and installation and testing which shall be followed in the TGT Field Development
project.
Piping fabrication, welding, inspection, testing and heat-treating shall conform to this
Specification and ASME 831.3, 831.4 & 831.8 wherever applicable. The piping
includes pipe supports welded to the pipe.
Minimum spacing of circumferential welds between centre lines shall be minimum two
(2) pipe diameters or 6" whichever is less. In restricted circumstances minimum
spacing shall not be less than four (4) times the wall thickness or one inch (1")
whichever is the greater.
All metallic piping 1-1/2" and smaller for hydrocarbon service shall be butt welded.
Threaded and socket weld piping shall be restricted to non hydrocarbon piping
service. Other than flanged connections, only approved mechanical joints shall be
used. Threaded connections shall be gauge/checked, or chased after welding or heat
treatment. Seal welding of threaded connections is prohibited. If approved, seal
welding shall be accomplished in accordance with ASME 831.3.
Thermowells, caps and plugs on vents and drains, shall not be seal we.lded.
All small bore fitting branch welding shall be performed by Gas Tungsten Arc Welding
(GTAW).
Cleaning of the pipe after fabrication and heat treatment shall be performed externally
and internally to remove all loose scale, weld spatter, sand and other foreign matter.
All free issue materials shall be identified and stored separately in the Fabricator's
yard.
All pipe spools shall be tagged as indicated in the piping isometrics and shall be
tracked at all stages of fabrication, NOT, painting etc. to its exact location in the
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 6 of 42
INSTALLATION AND TESTING
fabrication yard. All pipe supports shall have a unique tag which is tracked at all
stages of fabrication and painting to its exact location in the fabrication yard.
Prefabricated pipe spools shall be cleaned, painted (if required) and preserved prior
to installation.
Internals of in-line valves and equipment that could be damaged due to heat transfer
shall be removed prior to welding and/or heat treatment.
3.1.1 Bends
Hot-formed pipe bends are acceptable with the following requirements; the pipe wall
thickness at the thinnest point after bending, less the corrosion allowance, shall not
be less than the calculated thickness required for the pressure and temperature; pipe
bends shall be free from cracks, wrinkles, and bulges after bending and heat
treatment; weld repair of cracks in pipe bends is not acceptable.
Bends made to a radius less than five times the outside pipe diameter shall be made
either above 590°C for carbon steel and 930°C for stainless steel, or shall require
heat treating. After hot bending, bends shall be cooled in still air.
Galvanised pipe shall not be bent, or welded. Such piping requiring bending or
welding shall be galvanised after fabrication.
Only 1.50 radius bends (elbows) shall be used, without prior Company approval.
Centre line radius of shop pipe bends shall be at least equal to three (3) times the
nominal pipe diameter. All pipe bends shall be accomplished in accordance with
ASME B31.3.
General
GRE piping and fittings shall be designed, fabricated and installed according to ASME
B31.3 code, except as stated elsewhere in this Specification. All pipe installation and
fabrication must be in strict accord with the pipe manufacturer's recommendations.
Bonded Joints
All materials used in the GRE joint system shall be compatible with the service and
the piping system and shall be applied in strict accordance with the pipe
manufacturer's recommended installation procedures. As a minimum, these
considerations shall include adhesives, resins, glass and curing agents; ambient
temperatures and weather conditions for pipe assembly; curing methods and times;
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 7 of 42
INSTALLATION AND TESTING
fitting up, joint preparations and assembly techniques; material handling and support;
and workmanship testing and inspection.
Tools recommended by the pipe manufacturer, especially those for pipe joint
preparation, must be used.
All pipefitters who fabricate GRE piping and fittings and flanges must be trained by
the pipe manufacturer and must be certified by the manufacturer within 1 year prior to
the pipefitting.
Fabricator shall certify all procedures by testing in accordance with ASME 831.3.
To facilitate erection, the appropriate pipe identification, consisting of the line number
and spool number, shall be legibly painted onto secondary coating surfaces of each
pipe spool in large block letters or hard stamped on metal tags firmly secured to the
spool if final coating has been applied to the finished spool. The paint shall not, in
itself, cause corrosion or affect final coating of the pipe or fittings to which it is applied.
Paint containing lead, zinc, copper or tin shall not be used.
In addition, each final made-up spool shall be identified with the line number and
spool number stamped with low stress dies on the edge of a flange. If the spool
contains no flanges, the information shall be stamped, or for stainless steel or non-
ferrous materials, vibro-etched on the bevel end of the pipework.
3.2 Welding
General
All welding procedures shall be as per ASME Section IX and shall be submitted to
Company for approval. Procedure qualifications shall be completed and submitted to
Company for Approval prior to starting fabrication.
All welding procedures shall be identified by number and shall be referenced on all
fabrication drawings. Details of welding procedures qualification tests, including test
results, shall be submitted to Company for review and approval prior to starting
fabrication. Company may choose to witness such qualification tests.
Welders and welding operators shall be qualified per ASME Section IX prior to
fabrication and records shall be made available to Company upon request.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 8 of 42
INSTALLATION AND TESTING
Cleaning shall be done in a manner that will not lead to contamination of the weld or
adjoining base metal. Cleanliness shall be maintained after completion of welding.
Stubs, rods, flux, slag and foreign material shall be removed from the equipment or
piping.
The welding procedure tests shall demonstrate that all details are satisfactory for
obtaining full penetration welds for the following types of joints:
For inert gas tungsten arc and inert gas metal arc process, the qualification record
shall include the composition and flow rate of inert gas backing when used.
The SAW procedure qualification test report shall show the name of the manufacturer
and the trade name of the wire and flux used to qualify the procedure.
For low temperature service DOC and below, procedure qualification for ferritic
materials shall include impact tests of both the weld metal and the heat affected
zones, even if the impact tests are not required on the base material.
The impact test shall be performed in accordance with ASME 831.3. The lateral
expansion shall be reported if required.
(a) General
Welds shall be made by one of the following processes:
Shielded metal arc (SMAW)
Gas tungsten arc (GTAW)
Gas metal arc (GMAW)
Submerged arc (SAW)
Welders and welding operators shall have been qualified within six (6) months prior to
the start of fabrication in accordance with B&PVC Section IX, Welding and Brazing
Qualifications. Qualification records shall be submitted to the Company for approval.
Backing rings shall not be used unless specifically approved by the Company.
Consumable inserts may be used if approved by the Company prior to fabrication.
The short-circuiting arc GMAW process may be used for root pass welding only. It
shall not be used on weldolets, reinforced nozzles and branch welds, couplings, slip-
on flanges, socket welds and other attachments. Wind velocities shall not exceed
8km/h in the weld area.
If low hydrogen SMAW electrodes are unsuitable for producing a weld of acceptable
quality, the GTAW process or cellulosic SMAW electrodes shall be used for root
passes on single welded butt joints.
An internal gas purge shall be used for the root pass and second layer of autogenous
and stainless steel welds.
No SAW passes shall be greater than 9.5mm thick and all SAW welding shall be
multi-pass.
The deposited filler metal shall match the nominal analyses and physical properties of
the base material when similar metals are welded. Alloyed welding material
(manganese and silicon) shall not be used. When metals of different nominal
analyses or physical properties are to be joined by welding, Fabricator is to supply to
Company the welding procedure for approval prior to fabrication.
Where impact testing is required, the filler metal for welds shall meet the same impact
test requirements as the base metal.
Exceptionally high strength welds or excessively alloyed welds are not acceptable.
Filler metal for welding similar materials shall be of the same nominal analysis as the
base metal.
Low carbon grades of austenitic stainless steels shall be joined with low carbon weld
metal of corresponding composition.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 10 of 42
INSTALLATION AND TESTING
In low temperature service, filler metal for welds shall meet the same impact test
requirements as the base metal. The composition of SAW weld wire shall match the
composition of the parent metal. Alloy agents added through the flux are not
acceptable.
Welding products shall be used within the limits recommended by the manufacturers.
For pressure containing welds, the following electrode classifications are not
acceptable:
E6012, E6013, E7014, E7020, E7024 and E8013-82.
Electrodes, filler wires and fluxes shall be kept clean, dry and properly stored
according to manufacturer's recommendation. Electrodes, filler wires or fluxes that
are damp, greasy or oxidized shall not be used.
Austenitic stainless steel weld deposits shall have a ferritic content of 3-10%. One
deposited weld metal sample shall be taken for every 30 linear meters of welding and
shall be checked for carbon, chromium, nickel, silicon, molybdenum, manganese and
niobium content. These analyses shall be used to determine the ferrite content by the
Schaeffler Diagram. When approved by the Company, the Ferritascope may be used
as an alternative method to verify ferrite content. Ferritascope must be used prior to
weld heat treatment.
Weld bevel shall be made by machining, grinding or thermal cutting. The surface shall
be reasonably smooth and true. Materials that require preheat for welding shall be
preheated in the same manner for thermal cutting or gouging.
Surface to be welded shall be clean and free from paint, oil, dirt, scale, oxides, and
other material detrimental to welding.
Misalignment shall not be corrected by cold working (i.e. deformation beyond the yield
point) unless a subsequent Company approved heat treatment procedure is applied
prior to welding.
Weld beads shall be contoured to permit complete fusion at the sides of the bevel and
to minimize slag inclusions. Flux and slag shall be completely removed from weld
beads and from the surface of completed welds and adjoining base material. The flux
shall be removed in a manner that will not contaminate or overheat the weld or
adjoining base metal. Weld reinforcement and finish shall be as required by the
applicable code. Peening is not permitted.
When the design of an orifice run necessitates welds, these shall be ground smooth
and flush with the inside of the pipe. Pipe-tap connections where required, shall be
drilled through the pipe wall and be smooth inside.
No permanent backing rings shall be used. Consumable inserts are not classified as
backing rings, and thus may be used for all applications. Chemistry of the insert shall
match the base-metal chemistry.
GMAW welding process for other than root pass must be reviewed and approved by
Company.
Arc burns shall be removed by grinding or by cutting out a cylindrical section of pipe
and replacing with an undamaged spool. Grinding is permitted only if sufficient wall
thickness remains after grinding to sustain the pressure in the corroded condition.
The gap between the socket weld component and pipe end shall be approximately
1/16" to avoid "bottoming" which could result in excessive weld stress.
Minimum of 2 passes is required for all types of fillet welds on pressure containment
components, e.g. socket weld fittings.
All flange bolt holes shall straddle normal horizontal and vertical centre lines of the
pipe, except where connecting to equipment dictates otherwise.
Exposed machined and threaded surfaces shall be protected from oxidation during
heat treatment.
No welding shall be performed after heat treatment is completed.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 12 of 42
INSTALLATION AND TESTING
Minimum pre-heat temperatures for thermal cutting, welding, and tack welding shall
be as specified in ASME 831.3.
Surface Protection
Machined surfaces shall be protected by a suitable compound to prevent damage
from scaling during heat treatment.
Supports
During heat treatment, piping shall be properly supported in the furnace to minimize
warping and other distortion.
Preheating Temperature
The minimum pre-heat temperatures for thermal cutting, welding and tack welding
shall be as specified in ASME 831.3.
The process and materials for exothermic treatment shall be subject to approval by
the Company. The Vendor/Contractor shall demonstrate successful past experience
in using the materials on the specified size of pipe and wall thickness.
Castings shall be inspected as per ASME 831.3 and the listed standards therein.
For 100/0 NDE, progressive examination shall be applied according to ASME B31.3
341.3.4.
The interpass temperature shall be measured within the joint level. The minimum
interpass temperature shall not be less than the specified preheat temperature. The
maximum interpass temperature shall not exceed the highest of maximum qualified or
as stated below:
0
• 250 e for carbon steels;
0
• 150 e for stainless steels
• e
1000 Nickel base alloys, Duplex & Super Duplex Stainless Steels
The weld level of O-Iets shall be completely filled up to weld line on the O-Iets.
Smooth transition between the pipe and the O-Iets is required. Notches below the
weld line shall be avoided. Prior to welding, sufficient root gap shall be ensured.
First 2 welds by each welder shall be fully radiographed. Spot radiography shall then
be performed on a minimum of one shot on one weld in each 20 welds for each
welder on the following piping:
1) Water
2) Air
3) Atmospheric drain lines
The length of film for each weld shall be 250 mm (10") or half the pipe circumference
whichever is less.
1) The internal weld protrusion on lines subject to pigging operations shall not
exceed 1/16"
2) Orifice-flange butt welds shall be internally ground smooth and flush
3) Any other Company specified criteria e.g.- severe cyclic service criteria for
specific fluid service piping
Acceptance criteria for castings and welds shall be as stated in the engineering
design and ASME 831.3 as applicable for cyclic, sever cyclic or high pressure
service.
UT of welds shall be carried out in accordance with ASME 831.3 Section 344.6 and
ASME V article 5.
UT shall not be performed on thickness less that 12.5mm or where scanning surface
pipe diameters are less than ON 100.
On branches, weldolets and similar geometry's, scanning from the internal surface of
the branch shall be carried out wherever practical.
MPI shall be carried out in accordance with the requirements of ASME 831.3 or
ASTM E709.
The AC electromagnetic yoke technique shall be used with either black ink on white
background or UV fluorescent ink. Dry powders shall not be used.
Examination shall be carried out with the yoke both parallel and transverse to the axis
of the weld.
A.C Yokes shall be capable of lifting a carbon steel weight of 10 Ibs (4.5 kg).
The operator shall demonstrate the effectiveness of the technique being adopted on
any weldment by the use of a Penetrameter (e.g. Berthold, Setting 2/Burmah Castrol)
and portable field strength meters.
Visual! MPI : as per ASME B31.3, Table 341.3.2A Normal Service conditions.
UT
For all classes, all indications producing a response equal to or greater than 20%
DAC (14dB), shall be investigated.
All defects classified as liner defects, lack of fusion or lack of penetration shall be
rejected.
All indications producing a response greater than 50% DAC shall be reported.
Defects, other than linear defects, lack of fusion or lack of penetration producing
responses greater than 100% DAC shall be rejected if the linear dimensions exceed a
cumulative length of t in any length of 2t.
Single Point Reflectors (Indications, which show, pattern 1 behavior in both directions
as per BS 3923 Appendix L).
For any testing frequency less than 100%> e.g. 1 in 10, the stated frequency shall be
applied on a per system basis, or a representative sampling method.
If at any time examination or NOE carried out in accordance with this specification
reveals the presence of cracking in a welded joint including HAZ, the applicable
welding procedure shall be withdrawn until such time as the cause has been
established and appropriate modifications made to the procedure.
All NOE shall be carried out after any applicable post weld heat treatment, and 48
hours minimum after welding.
4. INSTALLATION REQUIREMENTS
4.1 General
The following documents and any other relevant documents related to piping material
and equipment shall be reviewed before starting of the installation at site:
Material certificates
NOT certificates
Shop fabrication inspection reports
Installation, operating and maintenance instructions
Safety data on equipment and contained materials
Number, type, size, bore, body material, pressure and temperature ratings
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 17 of 42
INSTALLATION AND TESTING
Pipe shall be free of all internal loose rust, scale, soil and debris before assembly.
Every precaution shall be taken during erection to prevent foreign matter from
entering the piping system. Protective covers shall not be removed until final
assembly is imminent.
Chains shall not be used for handling pipe spools, valves or associated piping
attachments. Only certified rope or webbed slings shall be used.
All piping shall be installed in accordance with approved Company drawings. The
Vendor /Contractor shall provide adequate break-out points for removal of pipe
sections in socket weld construction, even though such break-out are not shown on
the piping drawings.
Cold springing or forcing of piping for the purpose of joint make up is not permitted
unless approved by the Company.
For GRE piping the pipe manufacturer, Contractor and Company shall review and
approve all piping layouts for suitability of piping flexibility and support. All types of
supports shall be in accordance with pipe manufacturer's recommendation.
Where it is necessary for the pipe to move about the support, suitable slip pads shall
be provided to prevent wear.
For the site run piping system the Contractor shall submit to Company for approval
suitable sketch plan showing proposed pipe run, pipe support locations and pipe
support types proposed.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 18 of 42
INSTALLATION AND TESTING
Piping shall be erected and supported in a manner that will not put undue strain on
equipment such as compressors, engines, pumps, vessels and heat exchangers. The
following procedure shall be observed:
After the equipment has been set the pipe shall be connected to the
equipment without making any tight connections to flanges.
Flat face flanges and full-face gaskets shall only be used on piping
connecting to equipment with flat face flanges.
Flanges shall be checked to ensure that no strain is placed on the
equipment. If the pipe is not in correct alignment it shall be realigned. The
correction in alignment shall not be made while the pipe is connected to the
equipment. Heating of piping to correct misalignment shall not be permitted.
The following procedure shall also be applied for the alignment of flanges to rotating
equipment:
Spring loaded type check valves must be installed with the pin in vertical position
when flow is horizontal.
Ball valves with socket weld type, the need for disassembly or other requirements to
prevent seat damage shall be investigated.
All valves, including control or shut off valves, shall be installed in the correct
orientation for flow. Where incorrect installation has taken place the valve shall be
removed, inspected and correctly positioned at the Vendor/Contractor's expense.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 19 of 42
INSTALLATION AND TESTING
Threads shall be clean cut with no burrs or stripping and thread shall be per ASME
B1.20.1 tapered. Ends shall be reamed to remove burrs. Immediately before erecting
piping, pipe and fitting threads shall be thoroughly cleaned of cuttings, dirt, oil, or
other foreign matter. The male threads shall be coated with thread sealant and the
piping made up sufficiently for the threads to seize. Thread sealant such as three
bond sealant and thread locker shall be used.
Bolt tensioning equipment shall be used for bolts of diameter 1-1/2" and larger. Bolt
tensioning shall be used for hot oil service for all sizes of bolts irrespective of rating.
Gaskets once taken out from a made-up assembly shall not be reused.
Before installation of new gasket, the old gasket shall be completely removed and the
flange facings shall be thoroughly cleaned.
Insulation
Where specified, piping, valves and associated equipment and fittings shall be
insulated in accordance with Specification for Insulation, S0442-GPS-L-XXX-SP-
0006.
4.8 Gaskets
The Vendor/Contractor shall ensure that the correct gasket material and thickness, as
specified in the Specification for Piping and Valve Materials, S0442-GPS-L-XXX-SP-
0001 and on piping drawings, is used.
Care shall be taken to ensure that the gasket and mating flanges are clean, true and
free from defects.
The Vendor/Contractor shall ensure that the correct bolting material and grade is
used as specified in the Specification for Specification for Piping and Valve Materials,
S0442-GPS-L-XXX-SP-0001 and on piping drawings.
All carbon steel bolting shall be Hot Dip Spun Galvanized.
All bolting shall move freely through the flange bolt holes.
The Vendor/Contractor shall be responsible for all bolt torque requirements and their
applications. All actual bolt torque values shall be measured for every bolt 1%"
diameter and larger in piping 600lb flange rating and above and submitted to the
Company for approval.
The stud bolts for flange joints pressure class 600 and above, which are subject to
tightening, hydrostatic test, dismantling and retightening, may be reused. Stud bolts,
which have been hydro-tensioned, shall not be reused. This is provided that the bolt
stress during hydrostatic test does not exceed 80% of yield stress and the threads
have not been damaged. Hydro-tensioned bolts shall be replaced.
As an alternative, the Company prefers that temporary test bolting are used for
hydrostatic testing and replaced with bolting specified in the piping material
specification after successful completion of the hydrostatic test.
Hydraulic bolt tensioning systems, approved by the Company shall be used on bolts
of 11/2" diameter and larger. Bolts for hydraulic tensioning shall be supplied with one
additional bolt dia length longer than standard. The extra length shall protrude on one
side of the flange only and shall be protected.
Blind Flanges
The number of line blinds required for pressure testing of piping system shall be
determined by the Vendor/Contractor. These line blinds shall not be shown on the
P&IDs.
5.1.1 General
The extent of welding inspection and hydrostatic testing shall be in accordance with
ASME B31.3 and the following requirements.
All welds shall be visually inspected after the root pass and after the work is
completed. The fabricator shall visually inspect weld preparation, fit-up and weld
assemblies during all phases of fabrication. Correction shall be made in the weld
preparation to ensure that sound welds can be achieved by welding process used.
Cracks and undercutting or any evidence of poor workmanship shall result in the
rejection of the weld. Weld quality based on visual examination shall otherwise meet
the requirement of ASME B31.3. Branch welds and reinforcing pad welds shall merge
smoothly with the surface of the pipe.
Notches or undercutting are not acceptable. Sharp corners of reinforcing pads shall
be removed.
A final visual inspection shall be carried out of all the piping and pipe supports for
integrity of installation.
A check on protective coating shall be carried out.
A P&ID line walk with a yellow line of the P&ID shall be carried out jointly by the
process engineer and piping supervisor.
A punch list shall be prepared of any repair or rework that will need to be carried out
before hydrotest and before leak testing and before final acceptance of piping.
No hydrotest or leak test may be carried out if punchlist items are outstanding which
affect the validity of such testing or where clearing the punchlist would call into
question the validity of such testing.
All locally heat treated welds in carbon steel pipe shall be hardness tested as outlined
below.
Final hardness of deposited weld metal in carbon steel shall not exceed 200
Brinell. At least 5% of all welds shall be hardness tested with a Telebrineller
portable hardness tester or Company approved alternate (one test per weld and
at least one weld per spool). Should any weld metal deposit have a rejected
hardness, additional hardness shall be made at Vendor's/Contractor's expense,
until the extent of unacceptable weld metal is established.
All unacceptable weld metal shall be reheat treated or replaced, and then retested
at Vendor's/Contractor's expense.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 22 of 42
INSTALLATION AND TESTING
Defective joints shall be repaired by cutting out the defective joint and bonding in a
new coupling. On a case-by-case basis the piping fabricator may submit a wrap repair
procedure for Company approval. In general these procedures shall meet the pipe
manufacturer's recommendations.
5.1.7 Repairs
Material such as gaskets and bolting that are damaged during tests shall be replaced.
Any welded joint that is defective shall be repaired with the procedures specified in
B&PVC Section IX, and shall be heat-treated after the repair. The treating method
shall be approved by the Company if approval is originally required. Repair shall be
re-examined by the original method to determine if the welds are free from defects.
Repaired joints shall be retested.
Repairs of defects in the root and filler beads shall require Company approval. Before
repairs are made, defects shall be entirely removed by grinding or oxygen gouging to
the clean metal. All slags and scales shall be removed by power brushing.
Preheating of an area with a defect shall be in accordance with the original preheat
requirements for the materials and type of weld. After repair of the weld, the entire
circumference shall be radiographed again.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 23 of 42
INSTALLATION AND TESTING
External undercut shall be repaired by grinding off the weld cap in the undercut
location and recapping the location.
Arc burn defect shall be ground smooth provided that the depth of the defect does not
exceed 8% of the nominal wall thickness. Arc burn defects with a depth greater than
8% but less than 33%> of the nominal wall thickness shall be repaired by welding. The
defect shall be thoroughly removed by grinding. The cavity shall be welded and
ground smooth. The weld shall be preheated in accordance with the original preheat
requirements for the materials and type of weld. All repair procedures shall be
approved by the Company.
Laminations, split ends or other defects in the pipe shall be brought to the attention of
the Company and shall be cropped, repaired or removed from the pipe as per
approved procedure.
No weld containing cracks, regardless of size and location, is acceptable. Cracked
welds shall be cut and removed.
Welding which is accidentally quenched e.g. rain or washdown shall be cut out.
7.0 FLUSHING
7.1 General
Prior to commencing any flushing, Contractor or Vendor shall verify with Company
Representative that all required post weld heat treatment (PWHT), non-destructive
testing (NOT) such as radiography, ultrasonic, etc., has been completed in
accordance with this specification. Upon verification of the above requirements, the
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 24 of 42
INSTALLATION AND TESTING
Relngress of Contaminants
If it is determined that for any reason that there is a risk that the flushing is no longer
valid due to sloppy housekeeping practices or carelessly leaving the system open all
flushing and if applicable chemical cleaning shall be repeated. Exceptions to this rigid
rule are at the sole discretion of Company.
8.1 General
Hydrostatic pressure testing of piping systems shall be in accordance with ASME
831.3 (latest edition). Piping test pressures shall be given on the Line List S0442-
GPS-P-H01-LL-0001.
For piping system with pressure rating greater than ASME Class 600, Contractor and
Vendor shall submit bolt torquing / tensioning procedures prior to conducting
hydrostatic testing.
Prior to commencing any pressure test, Contractor or Vendor shall verify with the
Company Representative that completed NOT & PWHT Traceability Summary Report
was sighted and verified. The report form shall be approved by Company. Upon
review of the Summary Report the Company Representative shall authorize the
Contractor or Vendor to proceed with the pressure testing.
Contractor or Vendor shall hydrostatically test piping, vessels and equipment for
which he has fabrication or assembly responsibility. Pipe spools shall be hydrostatic
tested prior to installations. Hydrostatic testing may be performed for completed
systems or for individual components of the system, as approved by the Company.
However, if individual components are hydrostatically tested, the Contractor or
Vendor shall flush the completed assembly prior to the system service test. Should
Contractor or Vendor desire to hydrostatically test through Company furnished
equipment, he may do so with written approval of Company Representative. When
hydrostatically testing through Company furnished equipment, Contractor or Vendor
shall exercise due caution to protect any instrumentation associated with the
Company furnished equipment.
Vents shall be open during water filling so that air is vented prior to applying pressure
to the system.
Following completion of pressurization of the system, the pump shall be completely
disconnected from the subject piping system.
Testing shall not be done against closed valves. If it is impractical to test through a
valve, that valve shall be isolated by blinds or disconnected from the piping system.
The pressure for each section tested shall be contained by suitably placed spectacle
blinds, spades, skillets, blank insert chokes, blind flanges or other means of positive
closure. Contractor or Vendor shall supply calculations to Company verifying the
thickness and material specification of blinds to be used for isolation during
hydrostatic tests. Test pressure connections shall be on the upstream side of check
valves. In no case shall flappers, pistons, discs, etc. be removed from check valves in
order to facilitate flushing and/or hydrostatic testing. Thermowells shall be included in
hydrostatic tests.
A minimum of two (2) pressure gauges shall be used for pressure tests. One shall be
a pressure-temperature recorder (Foxboro 24-hour chart or equal) with a range
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 26 of 42
INSTALLATION AND TESTING
suitable for recording the test pressure. The bulb of the temperature pen shall be
supplied with adequate capillary to allow attachment to the pipe. The full scale of the
other pressure gauge shall be 1.5 to 3 times of the test pressure. At the start of each
test, the pressure gauges shall be tested hydraulically utilizing a master gauge. This
.master gauge shall not be exposed to any hydrostatic testing. The pressure gauges
shall be deadweight tested after every 5 tests, regardless of test duration.
The master gauge calibration shall be carried out every six months and witnessed by
Company's representative to start the pressure tests, pressure shall be increased
step by step at 250/0, 500/0, 750/0, and 100% of the test pressure. Leaks shall be
checked between each step. The hydrostatic tests shall be held at 1000/0 of the test
pressure for a minimum of one (1) hour or beyond, for a period required to complete
full visual inspection of the test sections to the satisfaction of the Company
Representative. Fire water piping shall be hydrostatically pressure tested in
accordance with NFPA 13 for 2 hours. Readings shall be taken from the temperature
and pressure gauges at fifteen-minute intervals during the test, and recorded on the
Company approved form. During the test, the test medium may be subject to thermal
expansion. Contractor or Vendor shall take proper precautions to avoid excessive
pressure. Pressure bleeds back to test pressure shall be witnessed by a Company
Representative and noted on the test record. When practicable, piping or equipment
under test shall be shielded from direct sunlight.
All joints, including welds, are to be left uninsulated, unpainted, and exposed during
the test. Only tests with ending pressure equal to or above the test pressure will be
accepted. Contractor or Vendor should schedule tests for that portion of the day when
thermal contraction will not result in ending pressure lower than the starting pressure.
Before decreasing the pressure, the piping shall be examined for deformation and all
joints and connections shall be examined for leaks.
Vents shall be open during water draining so that air is filled to prevent pulling a
vacuum in the system.
Pressure tests on each major section of piping shall be carried out with all pressure
relief valves removed and their respective nozzles or connections blinded off or
plugged. The pressure relief valves will themselves be tested to their respective set
point pressures, by the Contractor or Vendor, in a separate test. Tests of pressure
relief valves are to be witnessed and approved by the Company's Representative.
Upon completion of piping or vessel hydrostatic test, pressure relief valves shall be
reinstalled in each system.
Systems below design pressures of 7 Barg may be soap bubble tested.
Short pipe spools, which must be removed to permit installation of test blinds, shall be
tested separately. Where piping being tested extends beyond the scope of its module
then the pipe shall be left long blanked and tested. After testing the pipe shall be left
long, and the hydrotest blind shall remain for preservation purposes.
The following piping and equipment shall be excluded or isolated from hydrostatic
testing:
• Up to 1 wk No chemical required
• 1 wk - 1 month SEA TR Oil Services: Corrtreat-650 OR 300 ppm
Jetco Chemicals: Jet Cor-471 200 ppm
• 1-24 months SEA TR Oil Services: Corrtreat-650 OR 300 ppm
Jetco Chemicals: Jet Cor-471 250 ppm
If seawater is used for hydrostatic testing, the following steps shall be taken:
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 29 of 42
INSTALLATION AND TESTING
Isolation of all austenitic and duplex stainless steel piping (including all components
such as valves, fittings, etc.) and connected equipment from contact with the
seawater.
Complete removal of saltwater from the system after testing including flushing with
potable water and then drying with air.
Oxygen removal and bacteria control treatment rates shall be as follows or Company
approved equal:
Water used to test piping or vessels fabricated from or containing parts (including clad
or overlay) of austenitic stainless steel, duplex stainless steel, ferritic stainless or high
nickel alloy shall be free from undissolved solids and meet the following chloride
limits:
If the vessel or piping metal temperature never exceeds 65 deg C during
commissioning, operation or non-operation, water containing up to 50 ppm
chlorides may be used for the hydrostatic test.
If the vessel or piping metal temperature exceeds 65 deg C during
commissioning, operation or non-operation, and the vessel is flushed with
condensate or demineralised water immediately after testing, water
containing up to 50 ppm chlorides may be used for pressure test.
When flushing with demineralised water it is essential to ensure that all
surfaces previously wetted during the pressure test are flushed. All residual
water shall be completely removed.
If the vessel or piping metal temperature exceeds 65 deg C during
commissioning, operation or non-operation, but the water can be fully
drained and completely removed immediately after testing, e.g., by mopping
up, water containing up to 50 ppm chlorides may be used for hydrostatic
testing.
If the vessel or piping metal temperature exceeds 65 deg C during
commissioning, operation or non-operation, and proper drainage is not
possible, the recommended practice is to utilize water containing less than 1
ppm chlorides, i.e., condensate or demineralised water.
Instrument air lines and utility air lines shall be tested with compressed air
(maximum dewpoint of -29°C).
Lube oil and seal oil lines shall be tested with oil as approved by Company.
Short pipe spools, which must be removed to permit installation of test
blinds, shall be tested separately. Where piping being tested extends
beyond the scope of its module then the pipe shall be left long blanked and
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 30 of 42
INSTALLATION AND TESTING
tested. After testing the pipe shall be left long, and the hydrotest blind shall
remain for preservation purposes.
Alternative I:
Only where design pressure < 10 Barg on non toxic and non flammable utility service
All hook-up spool closure welds and any minor change/additional welds shall be NOE
tested at design conditions in accordance with ASME B31.3 Para. 345.1 and visually
inspected. But NOE shall not be less than requirement stated earlier in this
specification.
Alternative II:
All hook-up spool closure welds and any minor change/additional welds shall be
subject to 100 % radiography and 1000/0 MPI or dye penetrant as applicable to
material.
Where due to hook up or the likes completion of service tests onshore is not possible
then limited overlapping service tests shall be carried out offshore such that the entire
system has been subject to a service test prior to being placed in operation.
During the service test, the isolation valves for relief valves shall be closed and relief
valves removed. Where relief valves are equipped with isolation and vent/calibration
valves then the relief valve may be maintained in its position with the isolation valves
closed and the vent / calibration valves opened. After the service test of that portion of
the system containing the isolation valves and prior to depressurizing the test fluid the
relief valve shall be installed.
The test pressure shall be lowered to ninety percent (90°!cJ) of the relief valve and/or
rupture disc set point pressure, the vent / calibration valve closed and the block valve
opened. The purpose of this procedure is to check the connection between the block
valve and relief valve.
All temporary positive closures such as plugs, blinds, spectacles, spades, and skillets
which may have been used during hydrostatic testing, shall be removed and all piping
joints shall be made up as they would be during normal operation of functional
systems.
Any used gaskets from prior tests shall be replaced.
On liquid systems the test fluid will be water, whilst on process gas the test fluid shall
be nitrogen, and on mixed systems gas over water may be used to limit the volume of
Nitrogen's used.
For water systems the filling and venting procedures shall be the same as for
hydrostatic tests. Pressure shall be brought to system design pressure and held for
30 minutes. All connections which were not made prior to hydrostatic tests shall be
checked for leaks and tightened as necessary. During service test, every valve in the
system shall be tested by being closed and used to hold the test pressure for a period
of time necessary to determine whether each valve is in turn positively shutting off
and holding pressure. Packing shall be replaced in equipment, such as valves, when
leaks cannot be stopped by normal tightening of packing glands. Valve seat leaking
shall be determined by monitoring levels and pressures and by listening for leaks
across the seat with an ultrasonic leak detector.
When Contractor is testing systems on completed platforms, only one complete
system at a time shall be tested for safety reasons and to prevent structural failures (if
this is a risk). During testing, Contractor shall take suitable precautions to prevent
building up excessive pressures in adjacent equipment not included in the test, such
as opening vent valves in the adjacent systems, etc.
In the event that a piping system contains a piece of skidded equipment that has
already been nitrogen leak and service tested by the Vendor, the Contractor shall
carry out service testing again in the yard.
1. Prior to testing Contractor shall submit to Company three (3) sets of Piping
and Instrument Diagrams colour coded to depict individual test limits and
their corresponding test pressure. In general, these limits shall follow ASME
pressure classification.
2. All valves shall be leak tested and shall be clearly labeled on these
diagrams with an identification number. A Valve Test Schedule shall be
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 32 of 42
INSTALLATION AND TESTING
12. Joints which cannot be service tested as above shall be witnessed make up
and shall be hydro tightened.
For low pressure utilities Contractor may propose to carry out an instrument air
service test subject to Company approval.
Open drain service testing shall be a liquid full test only.
11.0 RETESTING
Should piping failure occur during testing, the Contractor or Vendor shall locate the
failure. Contractor or Vendor shall at his expense repair all defects resulting from
inferior workmanship or defective materials furnished by the Contractor or Vendor.
After repairs have been made, the Contractor or Vendor shall retest until a successful
test is obtained to the satisfaction of the Company's Representative.
13.1 General
Specific equipment requires connected piping to be chemically cleaned prior to
commissioning, in order to prevent undesirable foreign matter entering the equipment.
Any requirement for chemical cleaning shall be listed in the project Line List.
Flushing
All piping shall be flushed.
Chemical Cleaning
Chemical cleaning shall be carried out in accordance with section 13.3 on carbon
steel piping in the following systems:
All compressor suction lines and recycle lines between the suction scrubber
and the compressor suction nozzle
All compressor discharge lines up to the first discharge block valve
All compressor recycle lines upstream of the recycle control valve
All expander inlet lines between the inlet scrubber and the expander inlet
nozzle
All metering piping and inlet piping to metering skids
Fuel gas distribution piping after the main fuel gas filter coalescers
Seal gas systems after the main filter coalescers
Hot Oil system piping
Hydraulic Oil system piping
Lubrication and Seal Oil systems piping
Inert Gas distribution piping to compressors, and hot oil systems
Video Inspection
All condensate pump suction lines between the pump suction vessel/tank
and the pump suction nozzle
All hydrocarbon pump discharge lines up to the first discharge block valve
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 35 of 42
INSTALLATION AND TESTING
All compressor suction lines between the suction scrubber and the
compressor suction nozzle
All compressor discharge lines up to the first discharge block valve (only if
the control valve is prone to blockage due to small ports)
• All compressor recycle lines upstream of the recycle control valve (only if the
control valve is prone to blockage due to small ports)
All expander inlet lines between the inlet scrubber and the expander inlet
nozzle
• All metering piping and inlet piping to metering skids
All piping between the filter coalescers and the C02 removal membranes
Fuel gas distribution piping after the main fuel gas filter coalescers
Seal gas systems after the main filter coalescers
• Diesel distribution piping after the filter coalescer
Hot Oil system piping
• Hydraulic Oil system piping
Lubrication and Seal Oil systems piping
• Inert Gas distribution piping to compressors, and hot oil systems from the
last filter
Grit Blasting
Compressor suction lines.
Gas re-injection lines.
Prior to chemical cleaning the piping shall be flushed.
Any internal coating other than initial preservation oil shall also be removed prior to
chemical cleaning.
The systems to be chemical cleaned shall have high and low point vents and drains.
These shall be marked on chemical cleaning Isometrics.
Precautions to be taken to prevent the ingress of chemical cleaning fluids into
equipment shall form part of the procedures to be submitted by the Contractor for
approval.
The chemical cleaning procedure shall describe a method using only one volume
chemical cleaning fluid per system (i.e. the same volume to be used for all steps
mentioned below), adding the required amount and type of chemicals required in
order to carry-out the following steps:-
1) Degreasing
2) Descaling
3) Neutralisation
4) Passivation
When above steps are completed a second volume of fresh water shall wash out
remaining chemical fluid.
For systems where microscopic test samples are required for cleanliness verification,
i.e. compressor suction lines, lube oil lines and instrument air lines: ISO-standard
4406 shall be used for defining the solid contaminate quantities in the flushing
medium. The upper and lower limits for the number of particles which will be
permitted for the various systems are specified in Appendix C.
Finally the system shall be dried and preserved.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 36 of 42
INSTALLATION AND TESTING
13.3.1 Degreasing
Degreasing shall be achieved by the addition of suitable degreasing agents based on
emulsifiers and/or detergents compatible with the chemical cleaning, neutralization,
and passivation mediums.
Whenever protective coatings of preservatives are present on the internal surface, the
chemical cleaning fluid shall be formulated in the manner as to dissolve and remove
such contaminants.
For certain types of coatings/preservatives a two stage cleaning method may be used
if required. However, the method and procedures shall be subject to the Principal's
acceptance before application.
13.3.3 Neutralisation
The chemical cleaning fluid shall be neutralised with the compatible type of alkali
(Caustic Soda, Hydrazine, Sodium Bicarbonate or Ammonia) to a pH range of 8.5-10
depending on the type of chelant used.
13.3.4 Passivation
The chemical cleaning solution shall be cooled to between 45-55°C (depending on
the type of passivating agent used), and the pre-calculated quantity of passivator
(nitrite, phosphate or peroxides) based on the level of iron concentration added.
This solution shall be circulated in the system for minimum of one (1) hour depending
on the type of passivator and temperature.
GLOBAL PROCESS SYSTEMS PTE LTD Document No. : S0442-GPS-L-XXX-SP-0005
Revision :0
SPECIFICATION FOR PIPING FABRICATION Page : 37 of 42
INSTALLATION AND TESTING
All blanked ends, including vents, drains, instrument taps etc. shall be opened long
enough to flush out all entrapped chemicals.
Rinsing shall continue for at least ten (10) minutes after the pH of the effluent water
equals the pH of the feed water.
13.3.6 Drying
Drying shall be performed immediately after completion of final water flushing.
13.3.7 Inspection
A visual inspection of internal piping surfaces by videotape, shall be performed to
ensure that piping surfaces are free from all traces of contamination and liquid.
13.4.1 General
The cleaning operation follows to a great extent the same procedure as for chemical
cleaning of carbon steel piping, except for the following:
Cleaning agent shall be Nitric Acid. Alternatives in accordance with ASTM A380 may
be proposed.
Note: Neutralisation not required
Note: Passivation not required
Temperature shall not exceed 55°C at any time
13.4.5 Drying
Drying shall be done as per carbon steel.
13.4.6 Inspection
This shall be as per carbon steel piping.
13.5.1 General
Hydraulic oil, lube oil and seal oil systems shall be hot oil flushed to ensure the
internal piping surfaces are free from all traces of contamination.
If chemical cleaning is specified, this must be carried-out prior to hot oil flushing. The
Contractor shall develop detailed hot oil flushing procedures which shall be adjusted
to suit each type of system. Hot oil flushing on vendor packages shall in general
follow the above sequence. However, the Vendors recommended procedures and
cleanliness standard shall be submitted for approval by the Principal.
15.0 WARRANTY
The engineering Contractor shall have final and total responsibility for the fabrication
and installation of the piping as described in this Specification.
The warranty for the works shall be in accordance with the requirements of the Terms
and Conditions accompanying the Purchase Order / Contract.
RECORDS
APPENDICES
APPENDIX-1
FLANGE
t.
NOTE 1
SECTiON . ED
Notes:
1. Tolerances on dimensions, which do not include pipe segments, are to be
based on ASME standards for fittings or flanges involved, otherwise tolerance
is3mm.
2. Rotation of flanges from the indicated position measured as shown 2mm
maximum.
3. Alignment of facings or ends shall not deviate from the indicated position
measured across any diameter more than 2mm per 300mm.
4. End preparation for weld shall not deviate from the indicated position by more
than 1mm across the diameter. For inert gas weld joints or 3mm for other
joints.