You are on page 1of 72

NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant

NNP1-MS-TFP-001-A3

Detailed Work Program

and

Site Specific Environmental & Social


Management &
Monitoring Plan for Construction of CVC Plant

for

Nam Ngiep 1 Hydropower Project

Document No. : NNP1-MS-TFP-001-A3

OBAYASHI Corporation

Submitted By:

……………………………………….
Kazuhiko CHABAYASHI
Project Manager
Nam Ngiep Project Office

OBAYASHI CORPORATION Revision: A3


26thJanuary 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

CONTENT
Page
REVISION STATUS 3

PART 1: DETAILED WORKS PLAN (DWP) 4

1 GENERAL 5

2 REFERENCE 7
3 MATERIALS 7
3.1 Material to be used for foundation work 7
3.2 Materials for Mixing Concrete of CVC Plant Construction 7
4 EQUIPMENT AND MANPOWER 8
4.1.1 Equipment and Tool(For whole substructure works) 8
4.1.2 Equipment and Tool (For Installation CVC plant) 9
4.1.3 Equipment and Tool (For Operation CVC Plant) 9
4.2.1 The Manpower distribution for foundation work of CVC Plant 10
4.2.2 The Manpower Distribution for Installation work of CVC Plant 11
The Manpower distribution for production and ordinary concrete of CVC
4.2.3 11
Plant
4.3 Temporary Facilities 12
5 CONSTRUCTION PROCEDURE 13
5.1 Foundation Work 13
5.2 Assembly of Plant facilities 14
5.3 Test operation 14
5.4 Trial mix 15
5.5 Production and Maintenance 15
5.6 Disassembly of Plant Facilities 16
6 SAFETY CONTROL 16
7 QUALITY ASSURRANCE 18

PART 2: SITE SPECIFIC ENVIRONMENTAL & SOCIAL MANAGEMENT &


19
MONITORING PLAN (SS-ESMMP)- FOR CVC INSTALLATION

8 ENVIRONMENTAL & SOCIAL MANAGEMENT & MONITORING 20


8.1 Introduction 20
8.2 Environmental and Social Pre-construction 20
8.3 Sup-plan Detail for Tunnel Excavation- Environment 26
8.4 Sup-plan Detail for Tunnel Excavation- Social 27
8.5 Chance Find Procedures 29

OBAYASHI CORPORATION Page 1 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

9 APPENDIX 31
9.1 Layout of Facilities 31
9.2 Organization Chart. 31
9.3 Construction schedule for Installation and Operation Works of CVC Plant 31
9.4.1 Working Drawing for Installation Works of CVC Plant 31
9.4.2 Working Drawing for Foundation Works of CVC Plant 31
9.5 Emergency Action plan 31
9.6.1 Resource for Foundation and Installation Works of CVC Plant 31
9.6.2 Resource for Operation and Manpower of CVC Plant. 31
9.7 Inspection and test plan (ITP) 31
9.8.1 Calculation Sediment Pond and Drawing Inside CVC Plant. 31
9.8.2 Drawing for Turbid Water Treatment of Sediment Pond Inside CVC Plant 31
9.9 Map for Site Condition including Disposal Area 31
9.10 Sub-Plan for ESMMP-CP 31
9.11 Earthwork Plan for Excavation and Embankment of CVC Plant 31
9.12 Environmental Management Activity Table for CVC Plant 31
9.13 Summary Quantity of Foundation Works and Water Tank for CVC Plant 31
9.14 Concrete Production Schedule for CVC Plant 31
9.15 Test Result of Water, Cement, Aggregate for Foundation Works 31
9.16 Calculation Estimation of Materials for Stock Yard Capacity and Silo 31
9.17 Mobilization and Installation for Plant component 31
9.18 Surface Water Test Result 31
9.19 Time Diagram of Concrete Batching Plant (1.25m3/batch) 31
9.20 Schedule of fabrication, transportation and installation of 2 Batching Plant 31
9.21 List of spare part for equipment of Batching Plant 31

OBAYASHI CORPORATION Page 2 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

REVISION STATUS

Rev. No. Description Issue Date Remarks

A1 1st Submission for Owner’s Review 28th/July/2014

A2 2nd Submission for Owner’s Review 20th/August/2014

A3 3rd Submission for Owner’s Review 26th/Jan/2016

OBAYASHI CORPORATION Page 3 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

PART 1

DETAILED WORKS PROGRAM

(DWP)

OBAYASHI CORPORATION Page 4 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

1. GENERAL
This detailed works program focuses on the construction procedure for installation and
operation of ordinary concrete production facilities, (to describe with concision, “ordinary
concrete is described as “CVC” and “ordinary concrete production facilities” is described as
“CVC Plant”). The detailed works program for the earthwork of CVC plant has been already
submitted as the detailed works program for earth work of RCC Plant Yard (PCL NNP1-MS-
PY-001) separately.

This CVC Plant will be constructed in order to supply the ordinary concrete for the structural
works (i.e.. main dam internal structure, main dam powerhouse, re-regulation dam, dyke,
the structure and lining of diversion tunnel, upstream coffer dam, etc.) planed in this project.

Raw materials source to be used for CVC production such as water will be procured by
pumping up water from mountain at Disposal No.2 (quality of water had tested attached
Appendix 9.18), aggreagtes will be procured from Army Quarry (Paksan) until the start of
aggragate plant operation by dump tracks. After the aggregate plant operation, aggregates
will be transported from the aggregate plants by dump tracks.

The location of CVC Plant yard was selected on the basis of the following condition.
i. Near the Main Dam and Quarry
ii. The quantity of developed area is relatively small
iii. To ensure the necessary area including stockpile
iv. To ensure the strength of equipment foundation

CVC Plant yard is located including location of RCC Plant Yard at the vicinity of Road P1,
STA.7+180km with total average 1.9 Hectares and 6km away from the village of Ban Hat
Gniun and 3km with Ban Hatsaykham as shown in Fig.1.

The location of Ordinary Concrete plant is shown as Fig.1.

Fig.1 Location of CVC Plant

OBAYASHI CORPORATION Page 5 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

The plan layout for setting heavy equipment of CVC Plant Yard are shown in Fig.2

Fig.2 Plan Layout for CVC Plant Location.

The procurement schedule of CVC in this project is shown in Table 1.

Table 1. Procurement schedule of CVC in this Project


Item Volume Unit Remark
Design capacity of 2 batching
Volume concrete per hours 120 m3/ h
plant 60m3/h
Volume concrete per date 700 m3/ date Maximum volume per day
Volume concrete per
17,341 m3/ month Maximum volume per month
month

The maximum volume per month is 17,341m3 (Dec. 2016) and the maximum volume
per day is 700m3 (i.e., 17,341 m3 /26 day= 670 m3/day). If the average concrete
placing time is 12 hours, it is necessary to ensure the batching plant capacity more
than 120 m3/h (700m3/ 12h =58.3m3/h). In order to supply the planned quantity of

OBAYASHI CORPORATION Page 6 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

ordinary concrete as well as proposed maximum batching plant capacity shall be more
than 90m3/hr in Contract, we will install 2 numbers of batching plant with capacity is
60m3/h for parallel production or one of each batching plant standby.
2. REFERENCE

Referenced Specifications:
- Ordinary concrete : GS 2.1, TS 6

3. MATERIALS

3.1 Material to be used for Foundation Works

This CVC Plant is temporary, therefore, materials to be used are temporary use only.
The quantity of material to be used for foundation works depicted in table 2 and Appendix
9.4

Table 2.1 Material to be used

No. Description Use for Quantity Unit Location


Preparation for foundation
Excavated
1 work(M1,M2,M3,M4,M5,M6 2,742.53 m3 CVC Plant
(Rock and Soil)
and Ground beam)
Embankment Ramp for Wheel loader
2 925.12 m3 CVC Plant
(Rock and Soil) transport material (M6)
Open Ditch and Retaining
3 Stone 76.27 m3 CVC Plant
wall
Lean concrete Lean concrete for Foundation
4 32.2 m3 CVC Plant
10MPa and water tank
Structure
Structure concrete for
5 concrete 283.9 m3 CVC Plant
Foundation and water tank
25MPa
Reinforced concrete structure
6 Reinforcing Bar 22.5 Tons CVC Plant
for Foundation
*Excess Rock and soil Materials is disposed to Disposal Area No.2

3.2 Material sources

The material source to be used for foundation works are shown as follows
Table 2.2 – Material Source to be used for Concrete Foundation

Material Source Supplier

Coarse
Phamuang Quarry V & K Sole Co., LTD
Aggregate
Fine Aggregate River Sand (Nam San River) V & K Sole Co., LTD

Cement Lao Savannakhet Cement Plant Savannakhet Province

OBAYASHI CORPORATION Page 7 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

Water Surface Water at B.Thahua V & K Sole Co., LTD

Reinforcing bar Thailand and Laos VSI-Vientiane steel industry.

*Note: The test result of Water, Cement, Aggregate as shown in Appendix 9.15

3.3 Materials for Mixing Concrete of Construction Work

After finish the foundation and installation work, CVC Plant will be constructed in
order to supply the ordinary concrete for the structural works (i.e.. main dam internal
structure, main dam powerhouse, re-regulation dam, dyke, the structure and lining of
diversion tunnel, upstream coffer dam, etc.) planed in this project. The materials to
be used in this construction work shown in table 3.

Table 3. Material to be used


No. Description Use for

1 Cement Mixing concrete for all construction

2 Admixture Mixing concrete for all construction

3 Fine Aggregate Mixing concrete for all construction

4 Coarse Aggregate Mixing concrete for all construction

4. EQUIPMENT AND MANPOWER

4.1.1 Equipment and tool (For whole Foundation Works)

Table 4. Major Equipment List for temporary foundation work

Item Equipment / Tool Capacity Nos. Purpose

1 Excavator 0.6~0.8 m3 1 Excavation

2 Dump Truck 15 ton 2 Disposal / Hauling

3 Mixer (mobile plant) 0.5m3~1m3 1 Mixing concrete


Embankment sub-base
4 Vibratory Roller 10 ton 1
Compaction
5 Bulldozer 13 ton 1 Spreading Material
Transport Water for Mixing
6 Water truck 6m3 1
concrete

OBAYASHI CORPORATION Page 8 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

4.1.2 Equipment and Tool (For Installation CVC plant)

Table 5. Major Equipment List for temporary installation work

Item Equipment / Tool Capacity Nos. Purpose

1 Crane 50 ton 1 Lifting Material

2 Crane 25 ton 1 Lifting Material

4.1.3 Equipment and Tool (For Operation CVC Plant)

Table 6. Major Equipment List

No. Equipment/ Tool Capacity Nos. Purpose

1 Batching Plant 1.25 m3/Batch 2 Mixing Concrete

2 Cement Silo 100Tons 6 Cement for Mixing

3 Admixture Tank 5000Liters 2 Admixture for Mixing of BP1

4 Admixture Tank 5000Liters 2 Admixture for Mixing of BP2

5 Water Tank 84 m3 1 Water for Mixing


Coarse Aggregate and Fine
6 Aggregate Bins 5 m3 8
Aggregate
7 Belt Conveyor (0.65 *23.5)m 2 Transportation of Materials

8 Belt Conveyor (0.65*23.5)m 2 Transportation of Materials

9 Generator 400KVA 1 Electric Supply

10 Air compressor 2.2kWA 2 Air Compressor for B/P

11 Truck Mixer 5 m3 8 Transportation Concrete

12 Dump Truck 16 Tons 8 Transportation Materials


Cleaning Sediment Pond and
13 Excavator 0.8 m3 1
Move Materials
Transportation materials to
14 Wheel Loader 3.5 m3&3.2m3 2
Aggregate Bins
Slump Testing
15 - 4 Checking Slump for Concrete
Equipment
16 Cylinder Sampling 150*300mm 200 Test Concrete samples
Compression Checking Compressive
17 2,000KN 1
machine Strength

OBAYASHI CORPORATION Page 9 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

18 Air Meter 7.92Liters 3 Checking Concrete Air Content


Checking Temperature
19 Thermometer - 8
Concrete, Material, Water
20 Cooler Machine - 2 Curing Samples

21 Laboratory Balance 5kg &150kg 2 Weighing material's


7Liters &
22 Dry Oven Machine 2 Drying Materials
150Liters

23 Sieving - 2 Material Test

24 Laboratory Mixer 70Liters 1 Trail Mix at Laboratory

Resource schedule is shown in Appendix 9.6 and Estimation of material stock capacity in
Appendix 9.16

4.2 Nominated Subcontractor and Manpower distribution

Nominated Subcontractor: V&K Concrete Sole Co., LTD


In general, the subcontractor will be nominated, concerning not only price/rate but
also following items, fully described below.
1) Technical competence
2) Financially stable
3) Administrative competence
4) Past project experience and reference
5) Ability to meet schedule
6) Quality and skill of work
7) Capacity(equipment, staff, worker) and organization
8) Ability to meet safety and environment requirements

And then, the evaluation for subcontractor will be done and recorded.
Manpower distribution for this work is planned as below.

4.2.1 The Manpower distribution for foundation work of CVC Plant

Table 7 – Manpower Distribution for Foundation Work of CVC Plant.


Planned
No. Title Duty
Number
1 Engineer 1 Site management

2 Foreman 1 Work management

3 Equipment Operator 5 Cut and Fill, compacted.

4 Common worker 4 Mix and Placing Concrete.

5 Chief Surveyor 1 Survey chief

OBAYASHI CORPORATION Page 10 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

6 Assistant Surveyor 1 Survey assistant

7 Mechanic 1 Maintenance of equipment

8 Driver 2 Transportation of materials (Aggregate)

Total 16

4.2.2 The Manpower Distribution for Installation work of CVC Plant

Table 8– Manpower Distribution for Installation CVC Plant.


Planned
No. Title Duty
Number
1 Engineer 1 Site management

2 Foreman 1 Work management

3 Equipment Operator 2 Lifting Equipment and Compacted

4 Skilled Worker 4 Setting, cutting and welding.

5 Chief Surveyor 1 Survey chief

6 Assistant Surveyor 1 Survey assistant

7 Mechanic 2 Maintenance of equipment

8 Electric Technical 1 Setting and Electrical connector System


Installation of electrical systems and
9 E&M Staff for Installation 5 operating systems, calibration and
calibration system weight materials
Total 18

4.2.3 The Manpower distribution for production and ordinary concrete of CVC Plant

Table 9. Manpower Distribution for CVC Plant Operation and Laboratory works
Planned
No. Manpower Duty
Number
1 Engineer 1 Production Manager

2 Laboratory Engineer 4 Supervised B/P for Quality Control

3 Materials Engineer 1 Test Sampling and Materials In Laboratory

4 Assistance Lab Engineer 5 B/P and Laboratory, Site Work

5 Operator 2 Production Concrete

OBAYASHI CORPORATION Page 11 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

6 Assistance Operator 2 Production Concrete

7 Safety Control 2 Helper to skilled worker and Security

8 Equipment Control 2 Maintenance of Equipment

9 Mechanic 2 Electrical equipment maintenance

10 Accountant 1 Data sheet and Payment

11 Transportation Team 3 Control Equipment and Driver

12 Mixer Truck Driver 8 Transportation Concrete

13 Dump Truck Driver 8 Transportation Materials


Cleaning Sediment Pond and Move
14 Operator 1
Materials
15 Operator 2 Transportation Materials for Aggregate Bins

16 Driver small Truck 3 sample collection

17 QC Workers 4 Laboratory Works

Total 51

4.3 Temporary Facilities

Table 10.Temporary Facilities


No Facilities Location

1 Contractor’s Camp STA.4+900Km (P1)

2 Worker’s Camp No.2 STA.6+120km (P1)

3 Disposal Area No.2 Left Bank of P1 Road STA.6+900km

Temporary Facility layout plan for CVC production work is shown in Appendix 9.1

OBAYASHI CORPORATION Page 12 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

5. CONSTRUCTION PROCEDURE

Construction procedure for earthwork of CVC Plant is shown in Fig. 3 below.

Fig.3 Construction Procedure for CVC Plant

CVC plant is located at the part of RCC Plant yard as shown in Fig.1. The earth work for
CVC Plant is finished before start installation work.

5.1 Foundation Work

After completion of the Plant Yard development, the foundation of each CVC Plant
facilities will be constructed. The drawing for foundation plant of each facilities is shown
in Appendix 9.4. The summary quantity of each foundation is shown in Appendix 9.13.

The design strength of lean concrete is more than 10N/mm2 and structure concrete is 25N/mm2.
The supply for foundation concrete will be used truck mixer/ Excavator.

OBAYASHI CORPORATION Page 13 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

5.2 Assembly of Plant facilities

The type of CVC plant will be transported from Viet Nam and made a unit in the factory.
The each facilities will be assembled by mobile crane. The procedure of assembly is
shown in Fig 4

Fig.4 Procedure for Installation Work of CVC Plant

5.3 Test operation

After the completion of assembly, test operation will be carried out. At the test operation, we
should confirm as follows:

i. Operation of each facility


ii. Movement and accuracy of instruments and scales
iii. Status of operation system and computer
iv. Printing record

Especially accuracy of each scales and load sell will be confirmed by loading test and should
be complied in accordance with Table 11 Batching and Mixing in Technical Specification of
Civil Works. And the proposed inspection and test plans (ITP) are as shown in the Table 12

OBAYASHI CORPORATION Page 14 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

Table 11. Test operation

Material Cement Water Admixture Aggregate

Admissible Error
1 1 3 3
In %
Volume or Volume or
Measured by Weight Weight
Weight Weight

5.4 Trial mix

After the CVC Plant finished installation work, plan for trial mix will be instructed for ordinary
concrete. The mix proportion will be proposed and submit the detail on trial mix plan
separately.

5.5 Production and Maintenance

The supply of CVC will be carried out in accordance with each construction schedule. These
schedule will be arranged daily, weekly and monthly. Supply schedule for concrete is shown in
Appendix 9.14
The CVC will be transported by truck mixer to each supply point. At the concrete placement,
the test on the fresh condition (Slump, temperature) will be carry out. At the same time, test
specimen for compressive strength will be made at the site.

The inspection of facilities should carried out in the commencement of daily opening and
monthly. And spare parts of plant will be stocked at the site.

OBAYASHI CORPORATION Page 15 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

5.6 Disassembly of Plant Facilities

After the completion of all CVC supply, each facilities CVC Plant will be disassembly. The
removal of each concrete foundation will be made a decision about that after disassembly it
with the Owner.

6. Safety control
Safety control for site works shall follow the latest Safety and Security Program
(Document No. NNP1-PRG-SSP-A3) enclosed with Contractor’s letter NNP1-PCL-
00044, dated 10th December 2013.

Especially for CVC Plant excavation works area and installation works for CVC Plant,
the following issues shall be concerned.

1) Accident by heavy equipment of Foundation works and Installation works

 For all staffs and workers, the safety training shall be carried out.
 Warning sign board will be arranged.
 Don’t approach the working radius of heavy equipment.
 High place works shall be wore the safety belt.
 All of staffs and worker should but on their safe shoes, helmet, goggles and leggings.

2) Accident by heavy equipment of Mobilization and Installation for Plant component

 The limited of truck lorry speed is less than 10km/h in site and 25km/h with outside.
 Signboard and instructions to download the driver and recognize dangerous problem.
 Watch man shall be arranged on the shoulder of area work for installation
 Plant component will be mobilized from Vietnam and transported by trailer (12m and
14m) that should be provided seatbelt for tight component during transportation.
 One small nylon piece or anything equivalent will be hanged on components which
are longer than trailer body length for safety alarm from afar view.

Fig. 5 – Transportation of CVC Plant Component by Trailer

 The plant component will be unloaded by tire crane or unit crane if crane capacity (25
tons) is safe enough, at Plant.

OBAYASHI CORPORATION Page 16 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

 Nobody is allowed to stand within working radius of crane arm except crane operator
and 2 workers for unloading.
 Crane operator must have license and available for checking whenever authority
party required.
 The calibration crane must be in valid.
 Two (02) ropes will be provided at two (02) edges of component for direction control
by two (02) workers during unloading.
 The crane’s swing speed is limited as slow enough to prevent any incident as well as
accident.

Fig. 6 – Unloading of CVC Plant component

 The installation must be conducted by experience man and carried out in day time only
 Nobody can enter installation area during setting up except relevant role man.

Fig.7 – Installation of CVC Plant component


The transportation, unloading and installation of CVC plant component are shown in detail drawing
in Appendix 9.17

OBAYASHI CORPORATION Page 17 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

3) Production and Transportation

 Before the start of mixing concrete warning bell shall be given to all personnel
working in batching plant to give warning and be aware of the operation plant
 The limited of dump truck speed is less than 10km/h in site and 25km/h with
outside.
 Signboard and instructions to download the driver and recognize dangerous
problem.
 For maintenance work such as clearing or tipping mixer, circuit breaker for shall
be off.

The safety control on site will be changed, revised and added every time in accordance with
the occurrence of a dangerous situation and/or the Owner’s comments.
Before commencement of work, safety training will be carried out to relevant staffs and
workers as follows. The emergency action plan is attached in Appendix 9.5.

4) Fire prevent
Each batching plant should have fire extinguisher when emergency happened.

7. QUALITY ASSURANCE
Quality Assurance shall be followed to the Quality Assurance Program (Document No.
NNP1-PRG-DrQAP-A3) enclosed with Contractor’s letter NNP1-PCL-00086, dated 16th
January 2014.

Basically, Quality Control works shall be conducted by the contractor whereby proper
implementation and inspection of this work shall be made to ensure that the quality is
maintained.

Material testing during construction will be performed by on-site laboratory as specified in


specifications. And the proposed Inspection and Test Plans (ITP) are as shown in the
Appendix 9.7.

OBAYASHI CORPORATION Page 18 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

PART 2
SITE SPECIFIC ENVIRONMENTAL & SOCIAL
MANAGEMENT & MONITORING PLAN
(SS-ESMMP)
For
CVC PLANT
INSTALLATION OF FACILITIES

OBAYASHI CORPORATION Page 19 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

8. SITE SPECIFIC ENVIRONMENTAL AND SOCIAL MANAGEMENT AND MONITORING PLAN

8.1 Introduction

This Site Specific Plan has been prepared to highlight environmental and social conditions
prior to the beginning of each construction activity and will be used as a tool to ensure the
particular activity follows the correct management and mitigation procedures. Sub-Plans will
be used to detail mitigation methods for each of the activities associated with the construction
or excavation works.

The CVC Plant will be used to produce conventional concrete for all civil works, from office
flooring and bridge foundations to the Main Dam construction. This Site Specific Plan will detail
construction of CVC Plant area and foundations along with installation of Plant facilities and
equipment, also described in Section 1 General, of the DWP.

Table 8.1 below shows the referential linkages of documents regarding environmental matters
in the NNP1 Project. The Owners (NNP1) documents use references and information from the
Concession Agreement. This SS ESMMP (Contractor) uses references and information from
Owners EIA/ESMMP and Owners ESMMP-CP.

Table 8.1 List of Main Documents and Approving Authority

Item Hierarchy of Documents Approving Authority


1 Concession Agreement GOL
2 NNP1 EIA/EMMP GOL
3 ESMMP-CP GOL
4 Contractors EMP NNP1
5 SS ESMMP NNP1

The Contractor documents are; Contractors EMP (Item 4) and SS ESMMP (Item5) which have
used applicable information extracted from the Owners documents which are Concession
Agreement (Item 1), NNP1 EIA/EMMP (Item 2) and ESMMP-CP (Item 3).

All obligations of the contractor are stated in the Civil Works Contract (CWC) which includes
Schedule 9 (Concession Agreement Pass Through Obligations) and is the only governing
document for the Contractor.

8.2 Environmental and Social Pre-Construction Description

Land and water use in the area

Previous land use in the area consisted mainly of shifting cultivation i.e., seasonal crops
including rice and corn, being farmed in the area. The area has since been cleared as part of
the earth and excavation works for the Plant Yard (CVC & RCC).
Sediment ponds, inside and outside of the CVC Plant will be installed to minimize sediment
loaded waste water from entering Nam Ngiep River.

Proximity to villages, cultural sites


The closest village to the project site is Ban Hatsaykham, approximately 3km and 6km with
Ban Hat Gniun to the west of no impacted is expected. No impacts are expected to cultural
sites such as temples or burial sites.

OBAYASHI CORPORATION Page 20 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

ENVIRONMENTAL ASSESSMENT CHECKLIST – FOR PRE CONSTRUCTION

Site Location Along road P1 STA. 7+180, near temporary bridge


GPS Coordination Refer to Map, Appendix 9.9
Photo See attach
Date 19th August 2014
Estimated Area 1.9ha
Prepared By Santi Sayakoummane
Checked By Mr Miyanohara
Site Description Installation works of CVC Plant equipment and facilities
Project Sitting
YES NO N/A Description
UXO clearance for entire Project area
Will the site require UXO
X completed during initial survey by
clearance?
NNP1.
Is there surface water located in Nam Ngiep is in close proximity to the
X
close proximity to the site? CVC Plant. Approx 150m away.
Is there a village or community Closest Village is Ban Hatsaykham,
located in close proximity to the X approx. 3km away and over 6km from
site? Ban Hat Gniun west of site.
Is the site located in a vegetated Site has been previously cleared during
X
area? earthworks and excavation phase.
Is the site located in agricultural
X
land?
No confirmed PCR on site, but
Are there any PCR sites in the previously discovered PCR near
X
area? temporary bridge had been removed
following Chance Find Procedures.
Is there an existing access road to Main entrance is a long road P1
X
the site? STA.7+180.
Can the site be viewed from public
X
viewpoints?
The CVC Plant is within the Plant Yard
Is the site located within an
X compound which also includes the RCC
existing Construction Area?
Plant.
Will the site development require
the construction of a sub-camp, Will have: site office, workshop, parking
X
office and storage? (if yes, provide area and laboratory
a list)

Other Comments:

OBAYASHI CORPORATION Page 21 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

Environmental Impacts
Likelihood Mitigation measure to be
N/A
(Likely/Unlikely) Implemented
Will the site development result in
increased dust generation at near- Unlikely No nearby Village
by villages?

Will the site development result in


increased noise generation at near- Unlikely No nearby Village
by villages?

Sediment traps will be installed


Will the site development result in to reduce excess topsoil run-off
Likely
surface water contamination? during construction and heavy
rain.

Will site development result in


Unlikely
changes to drainage patterns?

Will the site result in erosion? Unlikely


Site has already been cleared in
Will vegetation clearing be
Unlikely preparation for installation
required?
works.
Will the site be setting up All hazardous materials to be
hazardous components? (storage, Likely stored and labelled correctly. In
workshop…etc.) bunded areas
Will be collected and disposed
Will the site generate waste? Likely
of at waste disposal site no.2

Site closure plan:

No site closure plan is available at this time, one will be provided towards the end of the Plant
closure date.

Can site development proceed? YES NO N/A Description


X

OBAYASHI CORPORATION Page 22 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

Image 1: Site of proposed CVC Plant. With road T5 in the foreground

Image 2: Looking up closer at the CVC Plant site from road T5, arrow indicates location of
sedimentation pond.

OBAYASHI CORPORATION Page 23 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

Image 3: Sedimentation Pond as indicated in Image 2, will mainly collect water from outside of the
CVC Plant.

OBAYASHI CORPORATION Page 24 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

Table 8.2 below identifies the relevant list of Sub Plans required for the construction activities being
undertaken in the CVC Plant area. The Sub Plans were selected after a review of the following:

 Detailed Works Program


 Pre-Construction assessment (as per Environmental Checklist attached)
 NNP1 EIA, ESMMP and ESMMP CP Access Road

Table 8.2 relevant Sub Plans for Construction of CVC Plant

Sub-Plan Item Environmental Social


SP01 Erosion and Dust Control X
SP02 Water Availability and Pollution Control X -
SP03 Emission and Dust Control X
SP04 Noise and Vibration X
SP05 Waste Management X
SP06 Hazardous Material Management X
SP07 Vegetation Clearing X -
SP08 Landscaping and Re-vegetation - -
SP09 Protected Area management - -
SP10 Biodiversity Management - -
SP11 Soil Disposal X
SP12 Quarry and Construction Layout - -
SP13 Unexploded Ordinance (UXO) Survey and Disposal X -
SP14 Construction of Work Camps - -
SP15 Traffic and Access X
SP16 Training Awareness X
SP17 Project Personal Health Program X
SP18 Public Safety X
SP19 Damage to Property and Facilities - -
SP20 Emergency Preparedness X
SP21 Cultural Resource X

Detailed descriptions of Sub Plan content and guiding objectives are found in the relevant sections
relating to NNP1 Environmental and Social Management and Monitoring Plan. See Contractors
EMMP-CP Appendix 2.1 “Sub-Plan for Civil Works”
An Environmental Management Activity Table with monitoring method and frequency, for
construction of the CVC Plant can be referred to in Appendix 9.12 of the DWP.

OBAYASHI CORPORATION Page 25 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

8.3 Environmental Management and Mitigation

SP01) Erosion and Sediment Control

The control of erosion and sedimentation will be conducted by drainage ditches,


sediment ponds and closed water treatment facilities.
Mitigation measure for erosion and sedimentation control of slope will include:

- A sediment pond within the plant site will be used to collect run-off from
construction activities. Appendix 9.1 shows location of sediment ponds.
- Open ditches will run along the outside of the CVC Plant and collect in a
sediment pond (See Appendix 9.1)
- Material stockpiles within the Plant will be contained within a bunded area to
reduce run-off during rain periods.

Weekly inspection are conducted as part of the Contractors Environmental, Health and
Safety procedures, and these will include inspections of sediment ponds. Any
maintenance such as clearing of sediment will be at the inspector’s discretion, with
frequency of clearing increased during heavy rain periods.

SP02: Water Availability and Pollution Control

- Sediment ponds will be installed within the CVC Plant Yard to collect surface run-off
- An additional Sediment pond/waste water treatment pond, will treat waste water from
washing down cement trucks and recycled for use within the plant, it will not be
discharged outside of the plant.
- The “stock pile” shown in Appendix 9.1 is actually a de-watering station, used to
remove water from sludge collected in the waste water treatment pond.
- Recycled water may be reused as dust suppression within the plant yard or access
roads
- Proper waste collection of construction waste, such as oil rags, used oil containers, oil
filters and any hazardous materials will be crucial. Disposal will be through authorized
waste management companies.
- Septic tanks will be installed along with toilets

See Appendix 9.1 for details regarding location drainage systems, and septic systems.

SP03) Emission and Dust Control

Water spraying vehicle will be provided in active construction sites as necessary.


During dry periods water spraying trucks will water the road periodically. All vehicles,
while parked on site, will be required to have their engines turned off.
All workers will be required to wear the correct PPE such as eye and respiratory
protection.

SP05) Waste Management


- Burning of non-hazardous waste will be minimized by recycling and reusing waste
where possible and ensuring waste is delivered to designated waste disposal
sites.
- Installation of toilets including septic tank and domestic waste water treatment.

OBAYASHI CORPORATION Page 26 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

- A sufficient number of waste collection bins will be made available at the


construction site.
- Treated waste water shall be released into Nam Ngiep River.
- Appendix 9.1 shows for location of septic tanks, toilets, sediment ponds and
drainage systems.

SP06) Hazardous Material Management

- All fuels/oils and other hazardous materials will be stored in correctly constructed
storage facilities to prevent spillage or un-authorized use i.e., raised concrete
floor, bund, roof or sunshade, oil weir or trap.
- All hazardous materials to be correctly labeled.
- Hazardous materials and chemicals used in the construction work shall be stored
with Material Safety Data Sheets (MSDS).
- Discharge of any contaminated water into the environment shall be prohibited.
- Prior to the operation of the CVC Plant, the Contractor shall install a wastewater
treatment system that: have the capacity to treat wastewater to a quality
compliant with relevant standards (refer to Appendix 9.8 and Appendix 9.10 of the
ESMMP-CP) and are designed appropriately for site conditions. For example,
settling and retention ponds with sufficient specifications/capacity for treatment of
wastewater, e.g., from washing of equipment such as mixer drums, mixer trucks
and chutes being in contact with storm water.

SP07: Vegetation Clearing

- All vegetation clearing has already been completed as part of the Detailed Work
Program for Earth Works of Plant Yard.

SP11) Spoil Disposal

Spoil disposal within the plant yard refers to sludge that is removed from the
sediment ponds or drainage ditches. After de-watering, dry spoil will be
transported to Disposal site No.2.

8.4 Sub-Plan detail for Construction of CVC Plant - Social

SP04) Noise and Vibration

The distance from the CVC Construction site to the closest Village, Ban Hatsaykam is
over 3km away and over 6km from Ban Hat Gniun. There is no influence of noise and
vibration.
Excessive noise cannot be avoided during construction of plant facilities; all workers will
be required to wear PPE, such as ear plugs if noise levels exceed 80dBA. Other PPE
such as safety glasses and breathing masks must also be worn if necessary.

SP13: Unexploded Ordinance (UXO) Survey and Disposal

OBAYASHI CORPORATION Page 27 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

UXO clearance has been carried out within the CVC Plant site by NNP1 before the
beginning of any construction activities.

SP15) Traffic and access

Traffic speed regulation devices, such as speed bumps, and signage will be installed at
sensitive locations including in the vicinity of villages, construction camps and at busy
intersections on the approach to the CVC Construction work area. Regular monitoring
of traffic conditions will be conducted as part of the weekly Environmental, Health and
Safety inspection. In case that explosive material will be transported, the permission by
relevant authorities shall be obtained.

SP16) Training and Awareness

 The New Employee Indoctrination Training is executed for all new employees prior
to commencement of the works. In this training, the Contractor staff have
explained the site regulation/rule, site situation and safety & environmental
issue. The content can be referred to the site regulation in the Contractor letter
NNP1-PCL-00050, dated 13th December 2013.
 All workers have to complete the environmental training programs. A register of this
training is kept and can be given to NNP1 on request.
 The monthly safety mass meeting will be carried out regularly and the instruction for
safety and the environment impact will be mentioned in this meeting.
 Weekly meetings are also conducted to bring further awareness to environmental
health and safety issues in the CVC Construction area.

SP17) Project Personnel Health Program

 Regarding the content of Section 6, Part 1 of the DWP, the tool box meeting will be
carried out weekly and before commencement of any new works.
 Health Awareness Training has been be carried out for all personnel in the monthly
mass meeting.
 First aid kits will be made available by the Sub-Contractor in charge of construction
activities.
 First aid kits should be located in the temporary site office.
 The register for each item above can be provided to NNP1 on request.

SP18) Public Safety

 Barriers shall be installed to keep visitors and workers away from hazardous areas.
 Signage shall be installed around the outside of the construction site to warn and
direct traffic and visitors.
 Strictly impose speed limits on construction vehicles along residential areas and
where other sensitive receptors such as schools, hospitals, and other populated
areas are located.
 Limiting construction vehicle speeds to appropriate levels (typically 25 km per hour)
to reduce accident potential, and securing all construction vehicles and equipment

OBAYASHI CORPORATION Page 28 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

during non-working periods to prevent unauthorized access or use (e.g. through use
of a fenced and locked staging site and/or security guards).

SP20) Emergency Preparedness

 Referring to the emergency action plan in Appendix 9.4, the emergency response
procedures, emergency contact numbers and communication and reporting
procedures will be clearly displayed and each staff always carry it.
 First aid kits will be prepared at each site accordingly.
 Hazardous materials will be stored in the permitted area only and according to the
instruction by the authorities,
 Facilities and equipment for firefighting shall be prepared.

SP21) Cultural Resource

According to the EIA document, a preliminary survey of the Project Area was
conducted by the Lao PDR Department of Museums and Archaeology (DMA) in
October of 2007. In September 2013 local villagers informed NNP1 of Buddha images
located in caves near the NNP1 Temporary Bridge site (near CVC Plant). On the 30th
November 2013 the images were successfully relocated to the local Temple at Ban Hat
Gniun. The relocation was complemented by traditional Buddhist ceremonies, which
involved Lao department and authorities including; Head of Hat Gnuin Village,
Representative from NNP1, Representative from Bolikhamxay Province, and
Representative from Bolikhan District and RMU.

If the Contractor is to find any new physical or cultural resources during CVC Plant
construction, the Contractor shall stop the works and inform the Owner immediately
and follow the Chance Find Procedures (below).

8.5 Chance Find Procedures

Objectives of Chance Find Procedures are to; (a) minimize impacts to resources from
all NNP1 related activities and (b) to ensure that any artifacts uncovered are
appropriately recorded, documented and reported to the appropriate line agencies.

If any fossil or cultural item of significance is found the Contractor will promptly give
notice to the owner. This follows the guidelines stated in the Civil Works Contract
“CWC” Clause 4.25 regarding Fossil and Artifacts. The Contractor will work with Owner
to ensure safe removal of the artifacts, as directed by the Owner who will implement
Chance Finds Procedures with a variation order.

Chance Find Procedures mentioned in the Contractors EMMP-CP Sub-Plan, Appendix


2.1 Sub-Plan for Civil Works, “21: Cultural Resources” also states the following steps
will be implemented in the event that previously unidentified artifacts are identified:

(i) The contractor shall immediately cease operations on road section where
artifacts/archaeological finds are unearthed and immediately inform NNP1 Site
Manager.

OBAYASHI CORPORATION Page 29 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

(ii) The Owner will consult the Head of Village and Culture and Tourism
Administration Office to obtain advice regarding the next steps.
The contractor to recommence work only after the Culture and Tourism Office has
provided official notification accordingly.

OBAYASHI CORPORATION Page 30 Revision: A3


26th January 2016
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for Construction of CVC Plant
NNP1-MS-TFP-001-A3

9. Appendix

9.1 Layout of Facilities


9.2 Organization Chart
9.3 Construction Schedule for Installation and Operation Works of CVC Plant.
9.4.1 Working Drawing for Installation Works of CVC Plant.
9.4.2 Working Drawing for Foundation Works of CVC Plant
9.5 Emergency Action Plan.
9.6.1 Resource for Foundation and Installation Works of CVC Plant
9.6.2 Resource for Operation and Manpower of CVC Plant
9.7 Inspection and Test Plan
9.8.1 Calculation of Sediment Pond and Drawing Inside CVC Plant.
9.8.2 The Drawing for Turbid Water Treatment of Sediment Pond Inside CVC Plant
9.9 Map for Site Condition including Disposal Area
9.10 Sub-plan for ESMMP-CP
9.11 Earthwork Plan for Excavation and Embankment of CVC Plant
9.12 Environmental Management Activity Table for CVC Plant
9.13 Summary Quantity of Foundation Work and Water Tank for CVC Plant
9.14 Concrete Production Schedule for CVC Plant.
9.15 Test Result of Water, Cement, Aggregate for Foundation Works
9.16 Calculation Estimation of Materials for Stock Yard Capacity and Silo
9.17 Mobilization and Installation for Plant component
9.18 Surface Water Test Result
9.19 Time Diagram of Concrete Batching Plant (1.25m3/batch)
9.20 Schedule of fabrication, transportation and installation of 2 Batching Plant
9.21 List of spare part for equipment of Batching Plant

OBAYASHI CORPORATION Page 31 Revision: A3


26th January 2016
Attachment Comments for 2nd submission of Construction of CVC Plant

Item Page Section & Title The Owner Comments on 1st Reply comment and due The Owner Comments on 2nd Reply comment and due date
No submission date for completion by submission for completion by Obayashi
Obayashi (2nd submission) (3rd submission)
1 6 1. General Table 1  Please explant how to - According to Appendix - But please clearly described - We calculate the workable
calculate volume concrete 9.14 the maximum how to set 26 day/ month in day for each month in basis
per date of 700 m3/day casting concrete a the DWP. We understand it on stastics recorded rainfall
and necessary design month is 17,341m3, so will be the number of data near the site provided
capacity of B/P of 120 we have calculated working day for concrete from you. Therefore,
m3.hr in more detail in 17,341m3/26days ~ work in December. 26days workable is on
the Detailed Works 700m3/day. December.
Program (DWP). - We will install 2 B/P - According to the Contractor - Amended in the DWP (page
with capacity 60m3/h, proposal attached with the 7)
so we can use for Contract, the maximum
parallel or 1B/P standby. batching plant capacity to be
Refer to table 1 ensure by the Contractor
shall be more than 90m3/hr.
Please mention that in DWP
- Please explain why the - Based on time diagram of
Contractor can ensure concrete batching plant
production of concrete more 1.25m3/batch, mixing time
than 90m3/hr by proposed for 1 cycle is 75s (time for
batching plant (2 x material discharge to
1.25m3/batch) based on mixer, mixing in the drum
time diagram of concrete and concrete discharge to
batching plant. truck mixer). Therefore
productivity of batching in
1hr is [1.25/75s of 1 batch x
1hr x 2 plants = 120m3/h],
these capacity satisfy with
the maximum requirement
(90m3/hr.). See attached
Appendix 9.19 – Time
diagram

P ag e 1|6
Attachment Comments for 2nd submission of Construction of CVC Plant

3 1. General  Please explain a - Flow of concrete But, according to clarifications


procedure of concrete production in the CVC to the Contractor, we are
production in the CVC plant including informed that water will be
plant including procurement materials procured by pumping up
procurement of concrete such as aggregate, water from wells to be
material such as sand, fine cement, water, installed inside the CVC plant
and coarse aggregate, admixture we will yard (location of the well has
water using necessary propose more detail in not been decided yet) and
figure and/or drawings in the concrete trial mix aggregate will be procured
detail in the DWP. plant submission outside until the start of
Ex. aggregate plant operation by
How will concrete aggregate dump trucks. After the
be transported to the CVC aggregate plant operation,
Plant? How will water be aggregates will be transported
supplied to the CVC Plant from the aggregate plants by
dump trucks.
The information above, which Amended in the DWP (page
is fundamental information for 5)
design of CVC plant, shall be
described in the DWP.
4 1. General Fig.2  Two sediment ponds are - Inside CVC Plant: The water quality of the Noted
described in the plant Sediment pond No.2 sewage sedimentation shall be
layout. Please explain the with dimension monitored, recorded and
purpose of each sediment 16*12*4m for gathering informed to the Owner during
pond, how to drain water drain water by inside the plant operation. As results
to each sediment pond, open ditch, Sediment of the water monitoring, the
and what kind of water pond No.1 Sewage Contractor shall consider and
will be treated in sediment sedimentation for taken addition
pond in detail gathering turbid water countermeasures when
from washing and from required.
dewatering stock soil
- Outside CVC Plant,
sediment pond No.3
with dimension
38*18*4m to discharge
P ag e 2|6
Attachment Comments for 2nd submission of Construction of CVC Plant

flow quantity from


sediment pond No.2 by
outside open ditch and
discharge to River.
(Refer to Appendix 9.1
and 9.8)
7 8 4.1.3  Please explain why the - We have used 2 B/P Please see the Owner's Please see the reply in Item
Equipment and Tool contractor consider that with 1.25mb/batch, comments on the Contractor’s No.1
Table 6 two (2) batching plant capacity is 60m3/h. It is reply regarding Item No.1
with 1.25m3/ batch will be enough to produce
enough to produce maximum volume of
expected maximum concrete 700m3/day
volume of the concrete in
detail.
9 4.1.3  Please explain how to - We have revised in But, there is no explanation on Water will pump up from
Equipment and Tool decide the necessary Appendix 9.16. how to decide the capacity mountain at Disposal No.2 to
Table 6 capacity and number of Calculation for materials 84m3 of water tank. Please tank 8mx8mx3m, and then
equipment such as cement at stock yard explain it in the DWP treatment by chiller system
silo, admixture tank, water to get cold water (tank 84m3)
tank, aggregate bin, etc. for mixing concrete. This
in the DWP. Please attach process is continuous.
the related calculation Therefore, tank capacity
sheet as an appendix with 84m3 satisfied requirement.
the DWP
11 5.1 Foundation  The relevant description of - We have revised Please clearly mentioned We will order concrete
Work foundation works is not concrete class in table 2, where concrete for the 14N/mm2 and 25N/mm2
enough. Explain it in more base on drawing of CVC foundation shall be procured from CMC Batching Plant
detail. plant. from by truck mixer (Paksan) during construction
 Where will concrete with - The quantity of each foundation works.
14N/mm2 and 25N/mm2 foundation has
be placed? Please explain mentioned in drawing
it in the drawings attached NNP1-DW-OC-CVC-
with the DWP 01001~01027

P ag e 3|6
Attachment Comments for 2nd submission of Construction of CVC Plant

12 5.2 Assembly of  Please attach the detailed - Assembly of plant Please attach schedule of Please see attached the
Plant facilities plan on the assembly on facilities has submitted fabrication, transportation Appendix 9.20 – Schedule of
the CVC Plant facilities to in drawing NNP1-DW- and installation for 2 batching fabrication, transportation
the DWP as an appendix OC-CVC-01001~01027 plants as an appendix of the and installation of Batching
DWP. The Owner requests the Plant
Contractor to provide further
information on assembly
procedure
13 5.3 Test Operation  Please submit the detailed - We have revised as Table 12 seems to be an The test operation for CVC
inspection and test plans show in Table 12 of inspection and test plan for Plant have submitted
for test operation of each section 5.3 - Test CVC plant during the plan separately with DWP NNP1-
facilities of the CVC Plant Operation operation (not for test MS-TFP-001A-A4 on 5 March
separately. The operation of CVC plant). 2015
information in this clause The inspection and test plan
and Appendix 9.7 is not for test operation of CVC plant
enough. shall be submitted separately
with checklist to be used for
inspection and test.
15 5.5 Production and  Please submit a detailed - We have revised in But, the inspection and test The inspection and test plan
Maintenance plan on inspection and Appendix 9.7 plan to check functions of CVC to check function of CVC
test for quality control of plant is described in Appendix plant have submitted
concrete and stable 9.7. Table 12 shows the test separately with DWP NNP1-
operation of the CVC Plant items and test frequencies for MS-TFP-001A-A4 on 5 March
during operation period CVC plant during the plan 2015
separately. The operation. Information is not
information in this clause enough (detailed check item,
is not enough. test methods and each
 Items to be inspected and inspection criterion are not
tested and their inspection described)
criterion shall be The inspection and test plan
described in the detailed (quality control plan) for
plan above. quality control of CVC during
 The necessary spare part the plan operation shall be The spare part of CVC Plant
to be stocked at the site submitted separately together have attached in Appendix
and a number of them with check lists to be used for
P ag e 4|6
Attachment Comments for 2nd submission of Construction of CVC Plant

shall be described in the the quality control (Refer to 9.21 – List of Spare Part for
DWP. Clause 6.7 batching and CVC Batching Plant
mixing of Technical
Specification of CWC)
17 7. Quality control  As mentioned in the - We have revised in But, the conformity for each We have revised in Appendix
comments on Clause 5.5, Appendix 9.7 test described in Appendix 9.7 9.7
the detailed quality shall be changed subject to
control plan for ordinary final decision of the mixture
concrete to be procured at design of CVC
the CVC Plant shall be As for test and inspection for
submitted separately. It concrete produced at CVC
shall be prepared plant, test items listed in
considering the Appendix 9.7 are slump,
requirement of Section 6 concrete temperature and
“Ordinary Concrete” of compressive strength of CVC.
Technical Specification For quality control of the CVC
attached with CWC at the site, unit weight of CVC
and air content also shall be
tested during plant operation
period regularly
19 Appendix 9.4  A gradient of the mixer - Revised for feeding belt Actual transportation Noted
Working Drawing feeding belt conveyor is conveyor is width condition shall be checked at
designed to be 22.5 650mm, that size enough the test operation of CVC
degree, which seem a little for transportation plant.
bit steeper than usual. material and in the belt
Therefore, please consider make steep two side by
necessary roller of belt conveyor. So
countermeasures to that concrete material
prevent concrete can’t falling down and
materials to be dropping down
transported by the
conveyor from falling
down and dropping down
from the conveyors, and
describe them in the DWP
P ag e 5|6
Attachment Comments for 2nd submission of Construction of CVC Plant

 If aggregate hopper will be - Revised in Appendix 9.4 No revision is found in NNP1- We have revised drawing
used based on size of – Working drawing for WD-OC-CVC-01002 of NNP1-WD-OC-CVC-01002 of
aggregates, please show CVC Plant Appendix 9.4 Appendix 9.4
them in the drawing and
at the site.
Shop drawing for each
equipment and facilities listed
in the table in NNP1-WD-OC-
CVC-01002 shall be included in
Appendix 9.4 to the Owner for
reference
20 Appendix 9.7  Please describe more - We have revised in DWP Refer to Owner’s comments Please see the reply in Item
Inspection and test detailed information on table 12 of section 5.3 – on the Contractor’s reply No.13
plan how to test and inspect Test Operation regarding Item No.13.
each facilities of the CVC
Plant in this Appendix
21 Appendix 9.8  Please explain what kind - We will use Sulfuric acid Please discuss this matter Noted
Calculation of of materials will be used (H2 SO4) for turbid prior to the plant operation.
sediment pond and for treatment of turbid water and reduce pH in
drawing inside CVC water to collected in the the water
plant sediment pond in the DWP

P ag e 6|6
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.1
Layout of Facilities

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.2
Organization Chart

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.3
Construction Schedule for Installation and Operation Works

of CVC Plant

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.4
Working Drawing for Foundation and Installation Works of

CVC Plant (Revised)

Only Aggregate Hopper

OBAYASHI COPRORATION Revision: A3


MARKING DRAWING AND CLASSIFICATION FOR HOPPER OF COARSE AGGREGATE AND SAND AT CVC PLANT

14000

2500 3250

1300
2500
2500
6780

4500
12000

1750
1250 2400 1250
41370

36000

2500 3000 3000 2500 1280


5400

8000

16400

4500
6780

2500
2500 3250

14000

14000 1700 19365


39880

1300
2500
LEFT SIDE RIGHT SIDE 12000

1750
Aggregate 12.5x25mm River Sand
Aggregate 5x12.5mm Crush Sand 1280 2500 3000 3000 2500

Crush Sand Aggregate 5x12.5mm

River Sand Aggregate 12.5x25mm

REVISION
DESCRIPTION DATE TITLE NAME DATE
No.
NAM NGIEP 1 HYDRO POWER PROJECT
OWNER: NAM NGIEP 1 POWER COMPANY A3 3rd SUBMISSION Jan, 2016 DESIGNED Mr.Loc

DRAWN Mr.Kiet Jan, 2016 TITLE


HOPPER OF COARSE AGGREGATE AND SAND
CHECKED Mr.Miyanohara Jan, 2016

CONTRACTOR: OBAYASHI CORPORATION ISSUED Mr.Miyanohara Jan, 2016 SCALE: DRAWING NO. REV
A3: NNP1-WD-OC-CVC-LA-01002-1 A3
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.5
Emergency Action Plan.

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.6
Resource for Foundation, Installation Works, Operation and

Manpower of CVC Plant

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.7
Inspection and Test Plan (ITP)

(Revised)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT OBAYASHI CORPORATION
Inspection Test Plant

INSPECTION AND TEST PLANS FOR CONCRETE

Spec.Section Testing Items Description (Properties to be tested) Test Method Specification Conformity Frequency Test
Section 6 Portland Cement Chemical ASTM C114 ASTM C150 ASTM C150 Table 1&2 By mill cetificate & per 1 source
Material Cl 6.18.1(2) Physical ASTM C185 ASTM C150 Table 3&4 By mill cetificate & per 1 month
Cl 6.18.2(2) Alkalis content <0.6% Per 1 source
Particles passing mesh No.325 ≥ 80%
False set ≥ 50%
Admixture Specific gravity at 25oC (g/ml) Manufacture ASTM C494 Manufacture's specification By mill cetificate for every delivery
Cl 6.18.1 (5) pH index at 25oC
Cl 6.18.2 (5) Solid content (%)
Viscosity at 25oC (cps)
Water Chloride as Cl-, (ppm) ASTM C114 ASTM C1602 1,000 max Per one source
Cl 6.18.1 (6) Sulfate as SO4, (ppm) ASTM C1603 3,000 max
Cl 6.18.2 (7) Alkalies as (Na2O + 0.658 K2O), (ppm) 600 max
Total solids by mass, (ppm) 50,000 max
Fine Aggregate Grading ASTM C136, AASHTO T27 ASTM C33 ASTMC33 Each 500 m3 or twice a week
Cl 6.18.1 (3) Finer than 75μm ASTM C117, AASHTO T11 ASTM C33 <5.0%
F.M. for Natural Sand ASTM C136, AASHTO T27 ASTM C33 2.30 < F.M. < 3.10
Moisture content ASTM C128 Every day
Lighter than S.G. 2.0(Coal & Lignite) ASTM C123 ASTM C33 <1.0% Once before operation and
Clay Lumps & Friable Particle ASTM C142, AASHTO T112 ASTM C33 <3.0% where location has been changed
Soundness w/Na2SO4 or ASTM C88, AASHTO T104 ASTM C33 <10%
Organic Impulities ATSM C40, AASHTO T21 ASTM C33 Colour clear than Standard
Specific Gravity (SSD, OD) ASTM C128, AASHTO T84
Water Absorption ASTM C128, AASHTO T84
Coarse Alkali-aggregate reaction ASTM C289 ASTM C33 ASTMC33, X1.3 Guide line Before design mix
Aggregate Grading ASTM C136, AASHTO T27 ASTM C33 ASTMC33 Each 500 m3 or twice a week
Cl 6.18.1 (3) Finer than 75μm ASTM C117, AASHTO T11 ASTM C33 <1%
Moisture content ASTM C127 Every day
Lighter than S.G. 2.0(Coal & Lignite) ASTM C123 ASTM C33 <0.5% Once before operation and
Chert (less than 2.4spgr SSD) ASTM C123 ASTM C33 <5.0% where location has been changed
Clay Lumps & Friable Particle ASTM C142, AASHTO T112 ASTM C33 <5.0%
Sum of clay lumps, friable particle and chert ASTM C123 ASTM C33 <7.0%
Los Angels Abrasion ASTM C131, C535, AASHTO T96 ASTM C33 <50% (500 Revolutions)
Soundness w/Na2SO4 or ASTM C88, AASHTO T104 ASTM C33 <12%
Flakiness Index BS 812-105.1&2 BS882 <40
Specific Gravity (SSD) ASTM C127, AASHTO T85
Water Absorption ASTM C127, AASHTO T85
Concrete Mix Design Slump ASTM C143 Class 18, 21, 24Mpa 8 + 2.5cm & 12 ± 4.0cm Once before operation
Cl 6.6(2) Concrete Temperature Thermometer ACI -318 ≤ 32 °C
Air Content ASTM C231 ASTM C138 3% ≤ A ≤ 6% Not less than once test for each 100m3
Compressive Strength ASTM C39 ASTM C94 Cylinder mould 7, 28Days Every class or day of concreting
No individual strength <15% Not less than once test for each 100m3
of 28days strength
Concrete Production ASTM C94 Accordance with ST6.7 1time/batch, automatically recorded

1 of 1 August/2014
NAM NGIEP 1 HYDROPOWER PROJECT OBAYASHI CORPORATION
Quality Management Plan

INSPECTION AND TEST PLANS FOR BATCHING PLANT

Spec.Section Testing Items Description (Properties to be tested) Test Method Specification Conformity Frequency
Batching Plant Admissible error Weighing Scale ASTM C94
Cl 6.7.6 Cement / Fly ash Measured by weight %
Water %
Admixture %
Aggregate %

1 of 1 August/2014
NAM NGIEP 1 HYDROPOWER PROJECT OBAYASHI CORPORATION
Shotcrete Quality Control Plan

INSPECTION AND TEST PLANS FOR SHOTCRETE

Spec.Section Testing Items Description (Properties to be tested) Test Method Specification Conformity Frequency Test
Section 3.5 Welded wire fabric Yield strength ASTM A370 ASTM A185, A82 ≥ 485 Mpa By mill cetificate for every delivery
Wire Mesh mesh Tensile strength ≥ 550 Mpa
CL.3.5.1

Section 3.4 Portland Cement Chemical ASTM C114 ASTM C150 ASTM C150 Table 1&2 By mill cetificate & per 1 source
Material for Cl.3.4.2 Physical ASTM C185, ASTM C150 Table 3&4 By mill cetificate & per 1 month
Shotcrete Alkalis content <0.6% Per 1 source
Particles passing mesh No.325 ≥ 80%
False set ≥ 50%
o
Admixture Specific gravity at 25 C (g/ml) Manufacture ASTM C494 Manufacture's specification By mill cetificate for every delivery
Cl.3.4.2 pH index at 25oC
Solid content (%)
Viscosity at 25oC (cps)
Water Chloride as Cl-, (ppm) ASTM C114 ASTM C1602 1,000 max Per one source
Cl.3.4.2 Sulfate as SO4, (ppm) ASTM C1603 3,000 max
Alkalies as (Na2O + 0.658 K2O), (ppm) 600 max
Total solids by mass, (ppm) 50,000 max
Fine Aggregate Grading ASTM C136, AASHTO T27 ASTM C33 ASTMC33 Each 500 m3 or twice a week
Cl.3.4.2 Finer than 75μm ASTM C117, AASHTO T11 ASTM C33 <5.0%
F.M. for Natural Sand ASTM C136, AASHTO T27 ASTM C33 2.30 < F.M. < 3.10
Moisture content ASTM C128 Every day
Lighter than S.G. 2.0(Coal & Lignite) ASTM C123 ASTM C33 <1.0% Once before operation and
Clay Lumps & Friable Particle ASTM C142, AASHTO T112 ASTM C33 <3.0% where location has been changed
Soundness w/Na2SO4 or ASTM C88, AASHTO T104 ASTM C33 <10%
Organic Impulities ATSM C40, AASHTO T21 ASTM C33 Colour clear than Standard
Specific Gravity (SSD, OD) ASTM C128, AASHTO T84
Water Absorption ASTM C128, AASHTO T84
Coarse Aggregate Alkali-aggregate reaction ASTM C289 ASTM C33 ASTMC33, X1.3 Guide line Before design mix
Cl.3.4.2 Grading ASTM C136, AASHTO T27 ASTM C33 ASTMC33 Each 500 m3 or twice a week
Finer than 75μm ASTM C117, AASHTO T11 ASTM C33 <1%
Moisture content ASTM C127 Every day
Lighter than S.G. 2.0(Coal & Lignite) ASTM C123 ASTM C33 <0.5% Once before operation and
Chert (less than 2.4spgr SSD) ASTM C123 ASTM C33 <5.0% where location has been changed
Clay Lumps & Friable Particle ASTM C142, AASHTO T112 ASTM C33 <5.0%
Sum of clay lumps, friable particle and chert ASTM C123 ASTM C33 <7.0%
Los Angels Abrasion ASTM C131, C535, AASHTO T96ASTM C33 <50% (500 Revolutions)
Soundness w/Na2SO4 or ASTM C88, AASHTO T104 ASTM C33 <12%
Flakiness Index BS 812-105.1&2 BS882 <40

1 of 2 Oct/2014
NAM NGIEP 1 HYDROPOWER PROJECT OBAYASHI CORPORATION
Shotcrete Quality Control Plan

INSPECTION AND TEST PLANS FOR SHOTCRETE

Spec.Section Testing Items Description (Properties to be tested) Test Method Specification Conformity Frequency Test
Specific Gravity (SSD) ASTM C127, AASHTO T85
Water Absorption ASTM C127, AASHTO T85
Section 3.4&4.5 Quality control Compressive Strength 7Days, 28Days ASTM C42, C39 Quality control ≥ 25 Mpa for slope protection Each 40m3 for a test panel
Shotcrete Cl.3.4.5 ASTM C1140 ≥ 18 Mpa for Linning Diversion
Cl.4.5.2 ASTM C1116 Tunnel

2 of 2 Oct/2014
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.8
Calculation of Sewage Sedimentation, Sediment Pond

(Inside/ outside) of CVC Plant.

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.9
Map for Site Condition including Disposal Area

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.10
Sub-plan for ESMMP-CP

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.11
Earthwork Plan for Excavation and Embankment of CVC

Plant

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.12
Environmental Management Activity Table for CVC Plant

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.13
Summary Quantity of Each Foundation Work for CVC Plant

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.14
Concrete Production Schedule for CVC Plant.

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.15
Test Result of Water, Cement, Aggregates

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.16
Calculation Estimation of Material Stock Capacity

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.17
Mobilization and Installation for Plant Component

(No change)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.18
Surface/Ground Water Test Results

(Additional)

OBAYASHI COPRORATION Revision: A3


NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.19

Time Diagram of Concrete Batching Plant

1.25m3/batch

(Additional)

OBAYASHI COPRORATION Revision: A3


APPENDIX 9.19 - TIME DIAGRAM OF CONCRETE BATCHING PLANT (1.25m3/batch)
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.20

Schedule of Fabrication, Transportation and


Installation 2 BP

(Additional)

OBAYASHI COPRORATION Revision: A3


Appendix 9.20
NAM NGIEP 1 HYDROPOWER PROJECT DWP & SS-ESMMP for construction of CVC Plant
NNP1-MS-TFP-001-A3

Appendix 9.21

List of Spare Part for Batching Plant

(Additional)

OBAYASHI COPRORATION Revision: A3


Appendix 9.21 LIST OF SPARE PART FOR EQUIPMENT OF BATCHING PLANT

No. Equipment Part Number Quantity Photo Remark

Electric devices arrived Used Remain

Input: 220VAC
10VDC Voltage source Output: 10VDC - 1A
1 Set 1 1.0
Manufacturer: CLE - Vietnam

Input: 220VAC
24VDC voltage Source Output: 24VDC - 5A
2 Set 1 1.0
Manufacturer: Omron - Japan

Source: 24VDC
Voltage Amplifie
3 Input: 0-20mV Output 0-10VDC Set 2 2.0
Manufacturer: CLE-Vietnam

Source: 24VDC
4 Module 231 Analog Input: 04 Pcs 1 1.0
Manufacturer: SIEMEN-GE

Source: 220VAC
Contractor + TR 85A-
Working current: 85A
5 220VAC Set 2 2.0
Manfacturer: LS-Korea

Source: 220VAC
Contractor + TR 40A-
Working current: 40A
6 220VAC Set 2 2.0
Manfacturer: LS-Korea

Source: 220VAC
Contractor + TR 32A-
Working current: 32A
7 220VAC Set 2 2.0
Manfacturer: LS-Korea

Source: 220VAC
Contractor + TR 22A-
Working current: 22A
8 220VAC Set 2 2.0
Manfacturer: LS-Korea

Source: 220VAC
Contractor + TR 9A-380VAC Working current: 9A
9 Set 2 2.0
Manfacturer: LS-Korea

Vmax:250 VAC
Switch D25
10 Imax: 5A Pcs 2 2.0
Manufacturer: Sungho-Korea

Vmax:250 VAC
Button(Red)
11 Imax: 5A Pcs 2 2.0
Manufacturer: Sungho-Korea

Vmax:250 VAC
Button(Blue)
12 Imax: 5A Pcs 4 4.0
Manufacturer: Sungho-Korea

1
Vmax:250 VAC
Emergency Stop Button
13 Imax: 5A Pcs 1 1.0
Manufacturer: Sungho-Korea

Vmax:250 VAC
Time Relay
14 Imax: 5A Pcs 2 2.0
Manufacturer: Sungho-Korea

Vmax: 24 VAC
Buffer Relay 24V-5A
15 Imax: 5A Pcs 5 5.0
Manufacturer: Sungho-Korea

Vmax: 24 VAC
Buffer Relay 24V-10A
16 Imax: 10A Pcs 5 5.0
Manufacturer: Sungho-Korea

Selenoid Valve coil Source: 220VAC


17 Pcs 3 3.0
Manufacturer: Paker-Korea

Pressure Relay (Air


18 Compress) Manufacturer: Paker-Korea Pcs 1 1.0

Contactor HYP-18RNAF
Source: 24 VAC
19 (Control Gate of Mixer) Pcs 4 4.0
Manufacturer:Hanyoung-Korea

CLD-A54
(Control gate of discharge Source: 24 VAC
20 Pcs 4 4.0
Cement,Water,aggregate) Manufacturer: Paker-Korea

Flowmeter Source: 24VAC


21 Pcs 1 1.0
Manufacturer: CIE- Vietnam

Loadcell for feeding hopper


22 Manufacturer: Flintec Pcs 1 1.0

Twin Mixer (Wearing Part)


-

1 Wear Plate Pcs 32 32.0

2 Wear Plate 2 Pcs 16 16.0

2
3 Wear Plate 3 Pcs 4 4.0

4 Wear Plate 3MIR Pcs 4 4.0

5 Trough Wear Pcs 80 80.0

6 Dischagre Door Cover Pcs 2 2.0

7 Socker Bolt set 192 192.0

Twin Mixer (Blade)


-

Sets of cutting concrete


1 mixing mortar 1850/1250L Set 2 2.0
including bolt and nut

Twin Mixer (Seal and


-
Bearing)

Weigh belt Conveyor -

1 Belt Pcs 1 1.0

2 Carrier roller D89*250 Pcs 25 10.0 15.0

3 Return roller D89*750 Pcs 15 1.0 14.0

Feeding Belt Conveyor -

3
1 Belt Pcs 1 1.0

2 Carrier roller D89*250 Pcs 0 -

3 Return roller D89*750 Pcs 0 -

Other -

1 Rubber hose for cement bin D250*300 Pcs 8 8.0

Not yet
2 Motor for air compressure 3,7 KW Pcs 1 1.0
arrive

Air nipple for conection air


3 Ø08,10,12,16 mm -
pipe

8 Pcs 15 15.0 Recheck price

10 Pcs 15 15.0

16 Pcs 15 15.0

selenoid valve for discharge


4 Pcs 2 2.0
door of mixer

Seal of Cylinder for


5 GDC 125*200 Set 4 4.0 ?
Discharge gate of mixer

Selenoid Valve for


6 Discharge and Weighing 520S-8 Pcs 2 2.0
hopper

4
Selenoid Valve for Weighing
7 530C-10 Pcs 1 1.0
Hopper's Sand

Cylinder for Feeding


8 GDC 80*350 Set 4 4.0 ?
Hopper

Cylinder for Discharge of


9 Weighing Hopper's water 50-H200 Pcs 2 2.0
and Cement

10 The belt for Mixer Motor Pcs 12 12.0 ?

Dischagre Water pump 5KW/ 3P/ 380V Pcs 1 1.0

Bolt & nut M20*120 set 32 32.0

Bolt & nut M20*80 set 40 40.0

Nut M20 pcs 72 72.0

Cooling Chiller -

Source: 220VAC
Contractor + S-N85A-
Working current: 85A
220VAC Pcs 2 2.0
Manfacturer: Mitsubishi
( Khởi động từ)

Source: 220VAC
Contractor + S-N95-220VAC Working current: 105A
Pcs 4 4.0
( Khởi động từ) Manfacturer: Mitsubishi

You might also like