Professional Documents
Culture Documents
MS Number: 006
Revision No: 00
Method Statement
TABLE OF CONTENTS
1. TITLE.
2. SCOPE OF WORK
General description.
Plant and equipment.
Site planning & preparation
Work methodology.
Organisation, Responsibilities & Supervision.
Work Force.
4. ENVIRONMENTAL ISSUES
Environmental Impact assessment.
NDIA E S & H Contractor Requirements
Contractual Requirements.
Emergency Procedures.
5. QUALITY ASSURANCE
Contractual Requirements.
Critical works.
Inspection & Testing.
Follow up & Evaluation.
6. APPENDICES
1.) Plan Sequence – Drawing Attached
1. TITLE
REPAIR AND REPLACEMENT OF ROAD ASPHALT ALONG TAREEG
230 NEAR BRIDGE TAREEG 121
2. SCOPE OF WORK
General Description
Repair and Replacement of Road Asphalt
Plant and Equipment
List of Equipments:
1. Generator Set
2. JCB
3. Road Roller
4. Dump Truck
5. Water Truck
6. Plate Compactor
7. Cable Detector
8. Road Asphalt Cutter
Permits to be attached:
1. Encroachment permit
2. Work permit
3. Transportation Permit
Encroachment permit shall be obtained first prior to start of activities on site. Once the
area is located and staking has been completed, hard barricades, jersey barriers and
safety poles will be installed to establish the perimeter of the work area to prevent and
protect the public from entering the worksite. The safety personnel shall coordinate
with the construction supervisor for the entry and positioning of heavy equipment,
establish danger zones and installation of warning signs. Prior to demolition and
excavation using JCB equipment and backhoe. Once the construction activities start
(removal of existing concrete culverts and disposing of removed materials and heavy
equipment set up, etc.) this isolation method shall be strongly employed throughout
the duration of the project.
Work Methodology
Listed below is the activity in sequence of repair and replacement of road
asphalt
10. The asphalt concrete wearing surface shall then be placed and compacted to
the specified density and smoothness.
11. The new wearing surface shall have the same texture and smoothness as the
existing surface. It shall be even with the existing surface and the elevation
over the center line of the trench shall be 5mm higher than the original
pavement.
12. The site shall be cleaned and excess material shall be disposed of a
designated area by the Royal Commission.
13. Road shall be restored back to the original condition.
1. Backfilling shall not commence until work has been inspected, tested and
approved by the Royal Commission.
2. Excavated materials shall be tested and approved by the Royal Commission
prior to use as backfill.
3. Field tests shall be carried out by an independent testing laboratory to
confirm compliance with the specifications.
4. Follow-up inspections for settlement shall be required. Should settlement
occur, the Contractor shall be responsible for the necessary repair to restore
the area to its original condition.
Site Cleaning
1. All surplus excavated material remaining after the backfilling operation shall
be removed from work site by the Contractor and disposed of as directed by
the Royal Commission.
2. The work site shall at all the times be kept neat, clean and free of waste
material or rubbish.
3. Following completion of all construction, the work site shall be cleaned of all
debris and leftover materials from excavation and construction operations.
Construction Manager – will be the one to plan and coordinate all the activity in
the site and he will be responsible for coordinating with other contractor working in
the area.
Safety Personnel – will be the one to establish all necessary warning signs and
barricades establish the high risk areas in coordination with the Construction
Manager and constantly monitor the activity in terms of safety to all the workers.
Furthermore he will give advice on current and forecasted safety issues and
concern.
Site Engineer - will be the one to implement the instruction of the Construction
Manager in the site, he will also directly supervise constantly the manpower and
equipment working in the area and implement all safety regulation and precaution
set by the safety personnel.
Quality Control Inspector – Will be the one to inspect and monitor the repaired
area before recommending to RC Engineer for inspection.
Supervisor – will be the one to supervise and assign the works as per schedule.
Carpenters – will be the one to install and remove the shuttering.
Mason – will be the one to perform the concrete works such as patching , surface
preparation and to install grouting.
Technician – will be the one to do electrical work for temporary night lighting and
generators.
Work Force
Listed below is the manual workforce:
1. Site Engineer = 1 6. Mason = 4
2. Supervisor = 1 7. Carpenters = 4
3. Technician = 1 8. Dump Truck Driver = 1
4. Flagman = 2 9. Water Truck Driver = 1
5. Skilled Helpers = 4
Risk Assessment
The following are the risk assessment for this activity:
1. Proximity of work in relation to public areas and passing vehicles.
2. Existing site conditions and damage to public areas.
3. Traffic accident due to no barricade and warning signage.
4. Equipment accident due to blind side and no spotter and soft soil condition.
5. Damage of underground cables or underground facilities and infrastructure.
Risk Abatement
Risk no.1: Excavation
1. All excavation and trenches shall be appropriately identified with signs,
warnings and barricades. If adjacent to roads or to general public access
these must conform to all relevant traffic regulations and also be adequately
lit at night.
2. Where vehicles are used for tipping materials into an excavation or trench,
well anchored stop-blocks must be used to prevent the vehicle overrunning
the edge 1.8 m from the edge. These must be placed at a sufficient distance
away from the edge to avoid the danger of it breaking away under the vehicle
weight.
3. Conventional timber-shore (shuttering) props may be supported by
mechanical (jack or acrows) or hydraulics.
1. Safety cone or safety pole with string of light bulbs. Temporary lighting strings
shall consist of non-conductive lamp sockets and connections permanently
molded to the conductor insulation.
2. Temporary electrical power shall not be “tapped” off from any part of a
permanent electrical wiring system of a building or structure.
Contractual Requirements
SECTION II – 200 SERIES (15: Personal Protective Equipment):
Information to Personnel
All the manual workers that will be working in the site will be informed and
reminded by conducting morning tool box meeting in order to continuously
remind them of the existing safety risk and it will be handled by the designated
site supervisor and sometimes with the presence of the safety personnel.
Exhibit F, Quality Assurance Requirements Page 8 of 11 Contract No.560-C33
Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00
Emergency Procedures
The following are the safety procedure that will be implemented in case of
accident:
1. In case of traffic accident or person hit by the equipment notify immediately
the police and emergency crew do not engage in moving the person who are
injured.
2. Emergency contact numbers including Police, Ambulance and Industrial
Security will be prominently posted on bulletin board.
3. First Aid box will be readily available on site.
Permit requirements
The following are the required permit before implementing the activity:
1. Encroachment permit
2. Work permit
3. Road Open Cut permit
4. ENVIRONMENTAL ISSUES
Environmental Impact Assessment
One possible risk to the environment is oil spillage may be due to equipment
breakdown. If and when this will happen immediately contained the area of
contamination then remove the contaminated soil. In order to avoid this incident
proper maintenance procedure for the equipment shall be implemented.
Other possible risk to environment is garbage and debris accumulated thru-out
the construction activity, for this matter collection bin shall be used and proper
disposal and housekeeping shall be done.
5. QUALITY ASSURANCE
Contractual Requirements
The quality assurance requirements based on our contract specifications are the
following:
1. Prior to the construction activity RC Engineer shall inspect the area to verify
the area of the repair.
2. RC Engineer shall inspect the approved materials which will be incorporated
into works.
3. RC engineers shall inspect hold point release (HPR) and witness points as
per ITP.
Critical Works
The possible critical work for this activity is the cutting of road, excavation and
placement of new aphalt along the roadways for it require a lot of heavy
equipment activities as well as hazards to the public and vehicle users.
6. APPENDICES
CONFIRMATION OF INSTRUCTIONS
TO OPERATIVES
Those names listed below confirm receipt of the method statement and have had the
contents explained to them/understand it and are aware of the site ES&H requirements.
Name Employer Date Signature
Note to contractor supervisor – Any significant change from this method statement
requires it to be revised and resubmitted to OBI before work can
commence.