You are on page 1of 12

APPENDIX 5

MS Number: 006
Revision No: 00

The Royal Commission of Jubail & Yanbu

Method Statement

SAUDI WITHCON CO. LTD.

CORROSION REPAIR AND PROTECTION WORKS

REPAIR AND REPLACEMENT OF ROAD ASPHALT


ALONG TAREEG 230 NEAR BRIDGE TAREEG 121

Method Statement No: 006


Issued by:

Rev.No. Date Description Prepared Checked Approved


REPAIR AND REPLACEMENT OF
ROAD ASPHALT ALONG T 230

Exhibit F, Quality Assurance Requirements Page 1 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

TABLE OF CONTENTS

1. TITLE.

2. SCOPE OF WORK
General description.
Plant and equipment.
Site planning & preparation
Work methodology.
Organisation, Responsibilities & Supervision.
Work Force.

3. HEALTH & SAFETY


Risk assessments
Risk Abatement
NDIA E S & H Contractor Requirements
Protective & Safety Equipment.
Contractual Requirements.
Information to personnel.
Emergency Procedures.
Permit Requirements.

4. ENVIRONMENTAL ISSUES
Environmental Impact assessment.
NDIA E S & H Contractor Requirements
Contractual Requirements.
Emergency Procedures.

5. QUALITY ASSURANCE
Contractual Requirements.
Critical works.
Inspection & Testing.
Follow up & Evaluation.

6. APPENDICES
1.) Plan Sequence – Drawing Attached

Exhibit F, Quality Assurance Requirements Page 2 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

1. TITLE
 REPAIR AND REPLACEMENT OF ROAD ASPHALT ALONG TAREEG
230 NEAR BRIDGE TAREEG 121

2. SCOPE OF WORK
General Description
 Repair and Replacement of Road Asphalt
Plant and Equipment
 List of Equipments:
1. Generator Set
2. JCB
3. Road Roller
4. Dump Truck
5. Water Truck
6. Plate Compactor
7. Cable Detector
8. Road Asphalt Cutter
 Permits to be attached:
1. Encroachment permit
2. Work permit
3. Transportation Permit

Site Planning & Preparation

Exhibit F, Quality Assurance Requirements Page 3 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

Encroachment permit shall be obtained first prior to start of activities on site. Once the
area is located and staking has been completed, hard barricades, jersey barriers and
safety poles will be installed to establish the perimeter of the work area to prevent and
protect the public from entering the worksite. The safety personnel shall coordinate
with the construction supervisor for the entry and positioning of heavy equipment,
establish danger zones and installation of warning signs. Prior to demolition and
excavation using JCB equipment and backhoe. Once the construction activities start
(removal of existing concrete culverts and disposing of removed materials and heavy
equipment set up, etc.) this isolation method shall be strongly employed throughout
the duration of the project.

Work Methodology
 Listed below is the activity in sequence of repair and replacement of road
asphalt

1. Encroachment and Works Permits shall be prepared. A flagman shall be


provided to guide moving equipment during construction activities.
2. Barricading the working area and install traffic sign and warning sign to
protect the public and approaching vehicles.
3. Once the site has been prepared, layout and road cutting will commence. A
cable detector will be used to determine the presence of underground utilities.
4. Commence manual excavation if underground cables or underground
infrastructure are present in the area. Temporary support and warning signs
will be installed. Breaking the existing road asphalt using JCB breaker, then
commence excavation using a JCB excavator to complete the works. A
spotter will be assigned to supervise equipment and care should be taken at
all times during equipment excavation.
5. Commence sub-grade preparation by doing watering and compaction using
plate compactor in order to meet the minimum required compaction density
which is 95%. Once the sub-grade has passed the compaction test then we
proceed with the next activity.
6. The granular base course shall be placed in two layers of equal thickness
and compacted to not less than 100% of maximum dry density. It shall be
sprayed with prime coating bituminous black coat . The vertical edges of the
existing asphalt concrete base course shall be hand brushed with tack coat.
7. The asphalt concrete base course shall be placed on the primed granular
base course and compacted to the specified density and smoothness.
8. The surface of the vertical edges of the existing asphalt concrete wearing
courses shall be hand brushed with tack coat.
9. The surface of the new asphalt concrete base course shall be sprayed with
tack coat.

Exhibit F, Quality Assurance Requirements Page 4 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

10. The asphalt concrete wearing surface shall then be placed and compacted to
the specified density and smoothness.
11. The new wearing surface shall have the same texture and smoothness as the
existing surface. It shall be even with the existing surface and the elevation
over the center line of the trench shall be 5mm higher than the original
pavement.
12. The site shall be cleaned and excess material shall be disposed of a
designated area by the Royal Commission.
13. Road shall be restored back to the original condition.

 Backfilling and Compaction

1. Backfilling shall not commence until work has been inspected, tested and
approved by the Royal Commission.
2. Excavated materials shall be tested and approved by the Royal Commission
prior to use as backfill.
3. Field tests shall be carried out by an independent testing laboratory to
confirm compliance with the specifications.
4. Follow-up inspections for settlement shall be required. Should settlement
occur, the Contractor shall be responsible for the necessary repair to restore
the area to its original condition.

 Site Cleaning

1. All surplus excavated material remaining after the backfilling operation shall
be removed from work site by the Contractor and disposed of as directed by
the Royal Commission.
2. The work site shall at all the times be kept neat, clean and free of waste
material or rubbish.
3. Following completion of all construction, the work site shall be cleaned of all
debris and leftover materials from excavation and construction operations.

Organisation, Responsibility & Supervision

Exhibit F, Quality Assurance Requirements Page 5 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

 Construction Manager – will be the one to plan and coordinate all the activity in
the site and he will be responsible for coordinating with other contractor working in
the area.
 Safety Personnel – will be the one to establish all necessary warning signs and
barricades establish the high risk areas in coordination with the Construction
Manager and constantly monitor the activity in terms of safety to all the workers.
Furthermore he will give advice on current and forecasted safety issues and
concern.
 Site Engineer - will be the one to implement the instruction of the Construction
Manager in the site, he will also directly supervise constantly the manpower and
equipment working in the area and implement all safety regulation and precaution
set by the safety personnel.
 Quality Control Inspector – Will be the one to inspect and monitor the repaired
area before recommending to RC Engineer for inspection.
 Supervisor – will be the one to supervise and assign the works as per schedule.
 Carpenters – will be the one to install and remove the shuttering.
 Mason – will be the one to perform the concrete works such as patching , surface
preparation and to install grouting.
 Technician – will be the one to do electrical work for temporary night lighting and
generators.

Work Force
 Listed below is the manual workforce:
1. Site Engineer = 1 6. Mason = 4
2. Supervisor = 1 7. Carpenters = 4
3. Technician = 1 8. Dump Truck Driver = 1
4. Flagman = 2 9. Water Truck Driver = 1
5. Skilled Helpers = 4

3. SAFETY AND HEALTH

Risk Assessment
 The following are the risk assessment for this activity:
1. Proximity of work in relation to public areas and passing vehicles.
2. Existing site conditions and damage to public areas.
3. Traffic accident due to no barricade and warning signage.
4. Equipment accident due to blind side and no spotter and soft soil condition.
5. Damage of underground cables or underground facilities and infrastructure.

Exhibit F, Quality Assurance Requirements Page 6 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

Risk Abatement
 Risk no.1: Excavation
1. All excavation and trenches shall be appropriately identified with signs,
warnings and barricades. If adjacent to roads or to general public access
these must conform to all relevant traffic regulations and also be adequately
lit at night.
2. Where vehicles are used for tipping materials into an excavation or trench,
well anchored stop-blocks must be used to prevent the vehicle overrunning
the edge 1.8 m from the edge. These must be placed at a sufficient distance
away from the edge to avoid the danger of it breaking away under the vehicle
weight.
3. Conventional timber-shore (shuttering) props may be supported by
mechanical (jack or acrows) or hydraulics.

 Risk no.2: Backfill


1. Prior to the start of backfilling, the excavation competent person shall confirm
that all utilities have been inspected, tested as required and adequately
protected.

 Risk no.3 : Proximity of work in relation to public areas


1. Barricade/Rope or safety pole will be installed around the work site to keep
public away from equipment and material. Barricade/Rope or safety pole shall
conform to road department requirements.
2. Cautionary signboards in Arabic and English languages will be posted along
work site.

 Risk no.4 : Existing site conditions and damage to public areas


1. To prevent damage on public areas at the work site, an existing condition site
survey (with pictures, station numbers) will be performed, submitted/ and
verified by the RC. Any existing damage will be reported in this survey.
2. Any damage on light poles, access pavements, landscaping or other
structures caused during construction work will be rectified by the contractor.
3. To ensure that no risk or hazard to the public as a result of ongoing
construction activities.

 Risk no.5 : Lighting at night

Exhibit F, Quality Assurance Requirements Page 7 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

1. Safety cone or safety pole with string of light bulbs. Temporary lighting strings
shall consist of non-conductive lamp sockets and connections permanently
molded to the conductor insulation.
2. Temporary electrical power shall not be “tapped” off from any part of a
permanent electrical wiring system of a building or structure.

Environmental Safety & Health Contractor Requirements


 Section II series 15 ( Personal Protective Equipment)

Protective & Safety Equipment


 The following are the list of Personal Protective Equipment:
1. Hard hat, to be worn at all times
2. Safety shoes, to be worn all times
3. Safety gloves, to be worn all times
4. Safety goggles, for workers around working equipment
5. High visibility vest, especially for workers around machinery, to be worn all
times
6. Ear plugs
7. Mask

Contractual Requirements
 SECTION II – 200 SERIES (15: Personal Protective Equipment):

15.1 Personal Protective Equipment shall be considered only as a “last resort of


defence” against potential risks and hazards. Where so ever possible hazards
and risk are to be addressed and reduced by other means.
15.2 based upon the findings of 3.1.3 Section 1 and 11 above the contractor shall
ensure that adequate stock of Personal Protective Equipment are readily either
available on site or issued to personnel. PPE shall be considered as consumable
items.
15.3 All PPE utilised shall be manufactured to a recognized international
acceptable standards.

Information to Personnel

 All the manual workers that will be working in the site will be informed and
reminded by conducting morning tool box meeting in order to continuously
remind them of the existing safety risk and it will be handled by the designated
site supervisor and sometimes with the presence of the safety personnel.
Exhibit F, Quality Assurance Requirements Page 8 of 11 Contract No.560-C33
Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

Emergency Procedures
 The following are the safety procedure that will be implemented in case of
accident:
1. In case of traffic accident or person hit by the equipment notify immediately
the police and emergency crew do not engage in moving the person who are
injured.
2. Emergency contact numbers including Police, Ambulance and Industrial
Security will be prominently posted on bulletin board.
3. First Aid box will be readily available on site.

Permit requirements
 The following are the required permit before implementing the activity:
1. Encroachment permit
2. Work permit
3. Road Open Cut permit

4. ENVIRONMENTAL ISSUES
Environmental Impact Assessment
 One possible risk to the environment is oil spillage may be due to equipment
breakdown. If and when this will happen immediately contained the area of
contamination then remove the contaminated soil. In order to avoid this incident
proper maintenance procedure for the equipment shall be implemented.
 Other possible risk to environment is garbage and debris accumulated thru-out
the construction activity, for this matter collection bin shall be used and proper
disposal and housekeeping shall be done.

5. QUALITY ASSURANCE
Contractual Requirements
 The quality assurance requirements based on our contract specifications are the
following:
1. Prior to the construction activity RC Engineer shall inspect the area to verify
the area of the repair.
2. RC Engineer shall inspect the approved materials which will be incorporated
into works.
3. RC engineers shall inspect hold point release (HPR) and witness points as
per ITP.

Exhibit F, Quality Assurance Requirements Page 9 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

Critical Works

 The possible critical work for this activity is the cutting of road, excavation and
placement of new aphalt along the roadways for it require a lot of heavy
equipment activities as well as hazards to the public and vehicle users.

Inspection & Testing


 Restoration of Grade and Elevation
 Placement of New Wearing Surface Asphalt
 Excavation and Backfilling

Follow up & Evaluation


 We intend to follow up and evaluate our performance by constantly implementing
strict quality control as this is the most critical activity that can affect our progress
and constantly monitoring it and implement measures to expedite this activity.
The crewing system shall be monitored constantly in order to meet the required
volume installed and any delays shall be recorded and evaluated in order to
implement measures and improvements to augment the productivity.

6. APPENDICES

1.) Plan Sequence – Drawing Attached

Exhibit F, Quality Assurance Requirements Page 10 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

CONFIRMATION OF INSTRUCTIONS
TO OPERATIVES

Those names listed below confirm receipt of the method statement and have had the
contents explained to them/understand it and are aware of the site ES&H requirements.
Name Employer Date Signature

Exhibit F, Quality Assurance Requirements Page 11 of 11 Contract No.560-C33


Appendix 5 Rev 0
APPENDIX 5
MS Number: 006
Revision No: 00

Note to contractor supervisor – Any significant change from this method statement
requires it to be revised and resubmitted to OBI before work can
commence.

Exhibit F, Quality Assurance Requirements Page 12 of 11 Contract No.560-C33


Appendix 5 Rev 0

You might also like