Professional Documents
Culture Documents
METHODOLOGY
Embankment are the main part of the any earth work . They are widely used, e.g. as
embankment dams for reservoirs, as road, railway and airport runway
embankments in transportation but here we are discussing sequence wise working
methodology for the earthwork in embankment for highway work.
1. Scope of Work
2. Reference Documents.
3. Setting Out.
4. Selection of Material & Borrow areas.
5. Equipments.
6. Methods of Operation.
7. Quality Control.
8. Work Safety
9. Environmental Safety
The work shall consist of Construction of embankment with approved and specified
materials obtained from approved borrow areas or suitable material obtained from
roadway excavation and drain excavation and in accordance with clause 305 of
MORT&H specification.
2.0 Reference:
Reference Documents:
1. Ministry of Road Transport & Highway Specifications for Road & Bridges.5th
Revision
2. IRC SP-87
3. Technical Specification
4. Relevant contract drawings.
5. IS 2720 Codes
4.1 Material:
The material used in Embankment shall be soil, moorum, gravel, a mixture of these
or any other material approved by the Engineer. It shall be free from logs, stumps,
roots, rubbish & any other material detrimental to the stability of structure. The
material for embankment shall be obtained from the approved source with
preference to the material becoming available from nearby roadway excavation or
any other excavation under the contract. The material requirements shall be in
accordance with clause 305.2 of MORT&H.
Samples should be taken from the known borrow area & to be tested as per IS 2720
for the suitability in use in embankment as per project specification. On confirmation
of the suitability material the area shall be properly demarcated and satisfy the clause
305.2.2.2
5.0 Equipments:
The following equipments shall be carried out for the Embankment Construction. If
desired the contractor shall demonstrate the efficacy of the type of equipment to be
used, before commencement of work.
1. Hydraulic Excavator
2. Dozer
3. Dumper (Tipper Trucks)
4. Motor Grader
5. Soil Compactor
6. Water Tanker
7. Tractor Trolleys
8. Survey Kit / instrument
Subsequent layers shall be placed only after the finished layer has been tested as per
the clause 903.2.2 and accepted. The top levels of the embankment shall be checked
with reference to the longitudinal and cross profile of the road as per drawing to keep
the variation within tolerance limit as per table 900-1.
Different layers of embankment will be marked on pillars fixed outside the toe-line.
8.1 During construction of widening works, adequate safety and traffic signs shall be
installed adjacent to the road shoulders to protect the ongoing works as per location
specific safety plan.
8.2 For locations where the dumping of embankment materials by tippers are
performed from the road shoulder, a minimum of 2 flagmen with reflective vests and
holding a red flag each be deployed to control the traffic which may be affected by
the unloading operation.
8.5 The Safety Officer shall make frequent patrols along the highway to ensure that
the safety equipment and signs are operational at all time.
8.9 Trucks sometimes fall over a tip head because the driver backs over the edge or
the edge collapses under the weight of the truck. A protective berm or timber baulk
should be used. Alternatively, a signalman should be deployed in order to avoid this
possibility.
8.10 When excavating trenches, place the excavated material at least 600 mm clear
of the edge, where there is no danger of it falling back into or collapsing the side of
the trench.
9.Environmental Safety:
b.Vehicles tracks shall be kept moist to prevent flying of dust particles with the
vehicle movement.
Frequency as per
Serial No. Embarkment Reference code MoRT&H
1.1 Sand Content/Gradation test IS:2720(Part 4) 2 Tests/3000 m3
1.2 Atterberg’s limits IS:2720(Part 5) 2 Tests/3000 m3
1.3 Modified Protor Test IS:2720(Part 8) 2 Tests/3000 m3
1.4 Moisure Content IS:2720(Part 2) 2 Tests/3000 m3
1.5 Density of compacted Layer IS:2720(Part 28) 10 Tests/3000 m3
DETERMINATION OF DRY DENSITY OF
SOILS IN PLACE (SAND
REPLACEMENT METHOD)
Soil compaction is a artificial method in which expulsion of air from soil is done by
mechanical means thereby increasing the density of soil In construction.
It is important to know and control the soil density during compaction process. To
determine the proper soil compaction of embankment or subgrade in highway
project, several methods were developed. The most prominent method is Sand
Replacement method to check the relative density at site. In this article,we will
discuss in detail “how to perform sand replacement test at site”.
STANDARD USED
OBJECTIVE
To determine the in place dry density of natural or compacted fine and medium
grained soils by sand replacement method.
APPARATUS
PROCEDURE
1. Clean and dry, sand passing 1 mm sieve and retained on 600 microns sieve
approximately 5 to 6 kg for small pouring cylinder and 23 to 24 kg of sand for
large pouring cylinder.
2. Remove the cap of the pouring cylinder.
3. Weigh the empty pouring cylinder (W).
4. Close the shutter of the cone.
5. Fill the sand in to the pouring cylinder about 10 mm below from the top.
6. Determine the net weight of sand in the cylinder (W1).
7. Now place the pouring cylinder on a clean plane surface, open the shutter and
allow the sand to flow in to the cone.
8. Close the shutter when the flow stops.
9. Carefully collect and weigh (W2) the sand discharged from the pouring
cylinder.
10. Refill the pouring cylinder with sand such that the initial weight is W1.
11. Place the pouring cylinder on the top of the calibration cylinder concentrically.
12. Open the shutter and allow the sand to flow in to the calibrating cylinder.
13. Close the shutter when the flow stops or no further movement of sand takes
place in the cylinder.
14. Determine the weight (W3) of the pouring cylinder.
15. Repeat the above procedure for at least three times and determine the mean
values of W2 and W3.
16. Determine the volume (V) of the calibrating cylinder either by measuring the
dimensions
17. (Diameter and height) or by filling with water until the brim.
CALCULATIONS
WS =( W1 – W3 – W2) in grams
Volume of calibrating container = V in cc
𝑊𝑠
𝐵𝑢𝑙𝑘 𝑑𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑(𝛾𝑠 ) = 𝑔𝑚/𝑐𝑐
𝑉
1. Prepare a flat approximately 450 mm square area with the aid of a scraper
tool.
2. Place the metal tray just above the central hole on the prepared surface of the
soil to be tested.
3. Excavate the hole in the soil with a chisel & hammer using the hole in the tray
as a pattern to the depth of the layer to be tested.
4. Carefully collect the excavated soil from the hole and weigh (Ww).
5. Determine the water content (ω) of the excavated soil as per IS: 2720 (Part 2)
1973.
6. Fill the pouring cylinder to the constant weight (W1) i.e. weight equal to the
initial weight during calibration.
7. Remove the metal tray before the pouring cylinder is placed in position over
the excavated hole.
8. Place the cylinder such that the base of the cylinder covers the hole
concentrically.
9. Open the shutter and allow the sand to run out in to the hole.
10. Close the shutter of the pouring cylinder when no further movement of sand
takes place in the cylinder.
11. Remove the cylinder and determine the net weight of sand (W4).
CALCULATIONS
REPORT
Report the bulk density and dry density of soil to the nearest second decimal.
PRECAUTIONS
a. Care shall be taken to see that the test sand used is clean, dry and uniformly
graded.
b. Care shall be taken in excavating the hole to see that the hole is not
enlarged against the side of the hole, as this will result in lower densities.
c. Care shall be taken to see that the same initial weight of sand is taken during
calibration and during density measurement in the field.