Professional Documents
Culture Documents
إلطرق
,Construction, Completion and Maintenance of Roads, Overpasses
Storm-Water Drainage, Sewer and other Services for Jahra Road
.Services for Jahra Road
Table of content
No Description Page No
1 Introduction. 3
2 Approval of sources 3
3 Inspection outside the site 3
4 Approval based on the producer certificate 3
5 Refusal of materials 3
6 Resources 3
1
6.1 Personnel 3
6.2 Equipment 4
7 Quality control and supervision of concrete materials 5
7.1 Inspection of aggregates 5
7.2 Preparations of Aggregate Samples for Testing 5
7.3 Physical and Chemical properties of aggregate 5
7.4 Quality control requirements for cement 7
7.5 Quality control requirements for admixtures 8
8 Quality control requirements for concrete 9
8.1 Initial tests on concrete 9
8.2 Determination of water content of coarse and fine aggregate 9
8.3 Checking of mix proportions 9
8.4 Checking of workability at Batch plant 10
8.5 Tests on concrete during execution 10
8.6 Concrete workability at casting site 10
8.7 Concrete temperatures 10
8.8 Concrete cube sample 10
8.9 Cube marking: 10
8.10 Concrete cube transportation: 10
8.11 Curing of concrete cube samples: 10
8.12 Crushing test of concrete cube 11
9 Concrete Fabrication: 11
9.1 Operating Instruction: 11
9.2 Batch Plant Operation 11
9.3 Mix temperature 11
9.4 Batch Plant Maintenance 12
9.5 Concrete transporting0 12
9.6 Return to Batch Plant and maintenance 12
10 Checking 12
10.1 Check before mixing concrete: 12
10.2 Check during mixing concrete 12
10.3 Check after mixing concrete 12
Appendix No 1 14
Appendix No 2 18
1. Introduction
This Method statement is prepared to define the outlines procedure for obtaining good results in
concrete works, quality control, mixing and Transporting as mentioned in technical specification of the
.project
2. Approval of sources
1. MPW representative shall approve the suggested sources of materials. A.C shall, and then submit
MSF, draw contracts with producers or suppliers of materials.
2. The approval of materials shall be supported by MSF see appendix, supplier's certificates, test results
for the material at main and site laboratories and delivery terms.
3. A.C shall remain responsible for the quality of the supplied materials from the approved sources or
from other sources which may be approved during the course of the work.
5. Refusal of materials
1. A material shall not be used if it does not conform to the standard specifications or project
specifications.
2. Such material shall be disposed of or at least be kept away from the approved consignments.
3. MPW representative shall obtain confirmation regarding the material's fault which leads to its refusal
from the site engineer or quality control Engineer.
6. Resources:
6.1- Personnel:
Personnel staff of laboratory, fabrication and transportation of freshly batches concrete involves, per
Batch Plant and per shift as shown in the following tables
6.1.1 Batch Plant Staff
Description Number Description Number
Batch Plant Engineer. 2 Labors 15
Batch Plant Foreman. 3 Electrical 3
Batch Plant Operator. 3 Truck mixer Operators 85
Mechanical 3 Loader operator 3
Senior Engineer 1 -
Engineer 3 2
Chemist 2 -
Foreman 2 3
Labor 6 3
6-2 Equipment:
Laboratory Equipment:
Laboratory Equipment as mentioned in clause No 1001.03 of the technical specification of the project.
6-2-2 Batch Plant Equipment
3
N Number of batch plant company
Description National Kuaiti Kuaiti
o Industries manager Germany
1 Computerize Batch Plant. 2 2 2
2 Washing sand Plant. 1
3 Silos capacity. 600 ton 600 500
4 Silos number. 4 6 5
5 Ice plant capacity. 1 1 -
6 Chilling tank capacity m3/hour 75 60 40
7 Loaders. 4 4 3
8 Truck mixers numbers. 85 30 30
9 Truck mixers capacity. 750 300 300
10 Mobile concrete pump (36 meter length) 4 - -
11 Mobile concrete pump (42 meter length) 4 2 3
12 Mobile concrete pump (52 meter length) - 1 -
13 Stationary concrete pump (250 meter length) 1 - 1
1. Inspection and testing of aggregates shall start before stoking aggregates in-site.
2. Aggregates samples shall not be approved until they meet the requirements of project's specifications
(type and quality).
3. During the course of the work, unloading and use of an aggregate delivery to the site shall not be
allowed until visual inspection or simple in-situ testing indicates that the aggregate consignment is
identical to the approved sample.
No Property SL
NOTE 5- The base fineness modulus should be determined from previous tests, or if no previous tests exist,
from the average of the fineness modulus values for the first ten samples (or all preceding samples if less than
ten) on the order. The proportioning of a concrete mixture may be dependent on the base fineness modulus of
the fine aggregate to be used. Therefore, when it appears that the base fineness modulus is considerably
.different from the value used in the concrete mixture, a suitable adjustment in the mixture may be necessary
7.4Quality requirements for cement
1. The resident engineer shall not allow storing cement in-site until the lot was found to conform to the
project's specifications.
2. The engineer may approve the lot based on the producer's certificate or he may test a sample in the
field laboratory or an approved external laboratory.
Notices:
A see Note.
B The expressing of chemical limitations by means of calculated assumed compounds does not necessarily mean
that the oxides are actually of entirely present as such compounds.
C= CaO S= SiO2, A= Al2O3 F= Fe2O3
C
this limit applies when moderate heat of hydration is required and the limit for heat of hydration in
table 2A is not specified.
D This limit may be specified when the cement is to be used in concrete with aggregates that may be
deleteriously reactive.
Age A B C D E F G
1
day --- --- --- --- --- 140 125
days 3 110 90 125 110 125 125 125
days 7 110 90 100 110 110 115 115
28 days 110 90 100 110 110 110 110
months 6 100 90 90 100 100 100 100
year 1 100 90 90 100 100 100 100
1. *The compressive flexural strength of the concrete containing the admixture under test at any test
age shall be not less than 90per cent of that attained at any previous test age.
2. The objective of this limit is to require that the compressive or flexural strength of the concrete
containing the admixture under test shall not decrease with age
Age A B C D E F G
days 3 100 90 110 100 110 110 110
days 7 100 90 100 100 100 100 100
days 28 100 90 90 100 100 100 100
Property A B C D E F G
Per cent of control 135 135 135 135 135 135 135
Increase over control 0.01 0.01 0.01 0.01 0.01 0.01 0.01
**RDF minimum
80 80 80 80 80 80 80
1. * Alternative requirements, per cent of control limit applies when length change of control is 0.030per
cent or greater; increase over control limit applies when length change of control is less than 0.030per
cent
2. ** This requirements is applicable only when the admixtures is to be used in air-entrained concrete
which be used concrete which may be exposed to freezing and thawing while wet
8
8. Quality control requirements for concrete
8.1 Initial tests on concrete
1. Before starting the execution of concrete works, whether the concrete is mixed in-site or ready mixed,
tests shall be conducted on the concrete in its fresh and hardened states.
2. Commencing the production of concrete shall not be allowed until the mix requirements are achieved.
3. If such requirements are not met, the person responsible for the mix shall be notified in order to make
necessary adjustments to the mix proportions.
4. This cycle shall be repeated until the confirmatory mix in its final state is found to satisfy the
requirements for both fresh and hardened states.
1. The laboratory Engineer gives the operator checks and adjusts the water content of aggregate
before starting mixing.
2. The laboratory Engineer checks the concrete mix design before starting mixing.
3. Central mixed concrete is mixed completely in a stationary mixer and then transferred by the truck
mixers.
4. The mixing time should be measured for the time all ingredients are in the mixers and should be
based upon the ability of the mixer to produce through the batch and from batch to batch.
5. Delivery bill will be issued for each truck.
10. Checking
Checking is performed by the operator of the Batch Plant and mechanical Eng.
Appendix No 1
1. Concreting Follow up
2. Crushing strength of Concrete cube
3. Average cube compressive strength kg/cm2
4. Quality control manual / testing program.
12
Arab contractors
Osman ahmed Osman
Concreting Follow up
13
Arab Contractors
Site laboratory
Description
Name Signature
AC
Consultant
14
Average cube compressive strength kg/cm2
No Date C7d C28d No Date C7d C28d
16