Professional Documents
Culture Documents
METHOD STATEMENT:
RCC STRUICTURAL WORKS
Rev. Date
TABLE OF CONTENTS
1. SECTION: REFERENCES
GFC Drawings
Methodology while application should be available at site.
IS 456:2000 – Indian Standard Specification for Plain & Reinforced Concrete?
National Building Code of India (NBC 2005)
IS 383:1970 - Indian Standard Specification for Coarse and Fine Aggregates?
IS 2502 - Code of Practice for Bending & Fixing of Bars for Concrete Reinforcement
IS 1786:2008 - Indian Standard Specification for High Strength Deformed Steel, Bars and
Wires for Concrete
2. SCOPE OF WORK:
This Construction Work Procedure is applicable for execution of Concreting Works for the
Buildings as per approved GFC drawings.
This work procedure includes the following:
a. PCC
b. FOOTINGS
c. PLINTH BEAM & TIE BEAM
d. STARTER
e. COLUMNS
f. BEAMS & SLAB
3. SECTION: TOOL
Page | 1
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
4. WORK SEQUENCE:
Page | 2
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
5. CONSTRUCTION METHODOLOGY:
5.0.1 REINFORCEMENT:
MATERIAL :
Steel weighment should be done at site by the storekeeper by taking it to the nearest weigh bridge.
Stack steel 300 mm clear of ground on SSM walls.
Stack steel -Grade wise, consignment wise, diameter wise and length wise.
Protect stored steel from rusting, oil, grease and distortion.
Ensure Mill Certificate is delivered with each load.
Binding wire shall be 16-gauge soft annealed iron wire or 18 gauge GI annealed wire.
Collect the rings used for bundling rods in bags and store them.
Cut pieces/ scrap should be stored separately in an enclosed area (Scrap Yard).
If steel is going to be exposed to weather for a long time, give cement wash to protect it from
corrosion.
Surface rusting is good as it ensures proper bonding and should not be a cause of worry.
Steel is tested for its chemical and physical properties. Chemical tests checks for the Carbon, Sulphur
and Phosporous content, while the physical tests check the ultimate tensile strength, Elongation,
Bend and Rebend test.
Test frequency should be as per ISO procedure.
Page | 3
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
Mechanical splicing and welding of rods should be done only after proper details and instructions are
available from the structural consultant.
At time of concreting, reinforcement shall be free from mud, oil, grease, mortar dropping, mill scale or
other foreign matter.
Give spacer blocks of same grade of concrete.
Give spacers as per specifications. Generally 15mm for slab, 25mm for beam and 40mm for the footing is
provided. It depends on the maximum size of aggregate, the reinforcement size and the element
concreted or as per Drawings.
Proper end bearing of rods with required development length are the main points to check.
Chairs should be placed as last operation before concreting to avoid distortion of top rod due to traffic.
Check if dowels for columns, beams and slabs are given correctly and is of required minimum length.
For slab reinforcement, the structural consultant should check and certify each work before concreting.
Highlight areas of reinforcement congestion and get the bar arrangement revised to facilitate easy flow
of concrete all around.
Spacer bars shall maintain vertical distance between successive layers of bars.
Binding wire ends after tieing should be turned inside and should not stick out to the surface.
Work should be neat, correct as per drawing and specification. A separate engineer with prior experience
in reinforcement works is required to supervise works. Test frequency should be as per ISO procedure.
5.0.2 FORMWORK :
Form work shall be manufactured out of shuttering ply of required thickness or MS shuttering with backup
frame of MS or timber.
Formwork shall be manufactured according to the relevant specifications and shape / size of Beam & Slab
as per the drawings at the fabrication workshop established at site. Acrow Span, ISMC 100 & Hard Wood
Battens shall be used for bottom support. 12mm thick ply shall be used for slab shuttering and beam
shuttering
Formwork shall be so designed to support safely the worst combined effects of all loads within acceptable
dimensional tolerance and without causing bulging or deflection. Formwork should be:
Strong enough to bear the self-weight of formwork, wet concrete, reinforcement, and dynamic
effects of placing and compacting, construction traffic and wind load.
Water tight to avoid grout loss
Easily removable without any damage and should be re-usable
It should be dimensionally accurate and give the desired finish to the contact surface.
Page | 4
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
Always use staging of MS tubes with timber runners. The staging should be placed on hard even surface.
If placed on ground compact it and use planks under the base plate to distribute load. Base plates should
not be placed on concrete blocks or bricks, which are likely to get crushed when wet.
Staging shall be true, rigid and thoroughly braced, shuttered and propped.
To achieve desired rigidity ample studs, braces, bolts, spacer blocks and stay wire to be given to avoid
distortion.
Check the shuttering work for vertical and horizontal alignment, level, surface cleanliness, water tightness,
and ability to withstand loads without distortion.
Before reusing the shutter for the next cycle of concreting, it shall be properly cleaned, buffed and
shuttering oil applied.
SCAFFOLDING: At the ground level, walk round the perimeter of the scaffold and check for
o Subsidence of the ground
o Cavities underneath sole plates
o Dislocation of base plates
Rectify with adjustable base plates or fill with concrete
Do not use Casarino poles / Bamboo as struts or supports.
GUARD RAILS & TOE BOARDS :
Both guardrails and toe boards should be fixed to the inside of the outer standards and remain in position
before decking is removed. Guardrails should be fitted at not less than 0.9m and not more than 1.15m
above the decking. Toe boards should be at least 150m high above the decking and the clear spacing
between the guardrails and the boards should not exceed 0.75m.
FORMWORK OIL
o The formwork oil basically serves the purpose of a separation medium. It acts as an intermediary that
avoids any damage to the concrete. It also helps keep the formwork clean and ensures easy
maintenance. The application of oil should be done with the help of foam or a similar soft medium and
should be applied within 48 hours prior to concreting.
o Machine oil or used oil is totally unsuitable and is unacceptable at any cost due to the chemical reaction
this type of oil has on concrete. Clefts created will have a telling effect on the external and internal
plastering, with the plastering tending to peel off.
o It is recommended to use formwork oil of a reliable manufacturer. There are also alternative sources
available that serve the purpose, which maybe an expensive proposition e.g., Natural oils such as
Rapeseed oil, Sunflower oil, etc.
All spans in excess of 5 metres for beams and slabs should be kept within a pre camber of 2mm per 1
metre. For cantilever, give a camber at the end of span of 4mm per 1 metre.
Page | 5
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
For balcony and other rib beams, duct beams support should be continuous for at least 3 floors.
Due to weather conditions if the concrete is not sufficiently hardened, the striking time to be extended
after discussing with the project in charge.
Obtain the 7th day cube test result before the removal of formwork.
After approval of founding level, the leveling course to be done. The size, shape and thickness of
the
Leveling course shall be as per approved drawing.
The grade of PCC concrete shall be as per approved GFC drawing and mix design.
The grade of concrete should be checked and ensured before unloading from transit mixer.
The leveling course concrete shall be poured directly by chute or by manually and compacted by
Wooden/aluminum straight edges to the required level.
After initial setting of PCC, curing shall be started by sprinkling with water.
Curing for PCC to be continued for minimum 7 days from date of concreting.
Page | 6
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
Page | 7
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
Page | 8
RCC STRUCTURES
METHOD STATEMENT OF GROUND DEVELOPMENT DOC. NO.: PSA/P7A/MS/003
REV NO: 0
Check and conform the formwork verticality immediately after concrete completion by plumb
bob.
6. SECTION: SAFETY
All workers should wear safety PPEs.
Proper working platform should be made.
Proper housekeeping should be ensured at the place of execution.
Scaffolding and its base shall be strong enough to withstand all loads which are likely to
come. (Dead and live and wind loads).
Proper inclined supports and handrail shall be provided in case of height of scaffoldings
More than 3m.
Not to be applied on damp/wet areas & areas subject to moisture restoration.
Documents to be maintained as per the relevant format, Checklist should be followed in flat
basis. All works shall be performed with Manufacturer’s Specifications.
Page | 9