Paint of Approved Manufacturer, Checked for packed container 1
Date of expiry checked 2
Manufacturer's specification and approved procedure available 3 on the site Putty/Filler as Approved, Melamine as Approved 4 Procedures B Sanding by emery paper (180) 1 Sanding by emery paper (320) 2 Clean the surface of all loose particles 3 Apply wood filler & allowed to dry 1 to 2 hrs. 4 Remove excess filler by emery paper (320) 5
Apply approved natural wood sealer & allowed to dry 6 to 8 hrs 6
Scuff it with emery paper (320) & allowed to dry 6 to 8 hrs 7
Sealer 2nd coat applied (If Required) 8 Finish coat by spraying at pressure of 25 to 40 psi 9 Finish coats (2 nos.) applied with 2 to 3 hrs gaps 10 Surface dries 15 to 20 minutes & hard dries 24 to 48 hrs 11
Note 1: Sealer 1 to 2 coats as required
Note 2: Paint 2 to 3 coats as per manufacturer/site requirement