China Harbour Engineering Co.L.L.C.

CHECK LIST FOR CONCRETE BLINDING WORKS


SUBCONTRACTOR : HUNAN general contracting L.L.C CONTRACTOR: CHEC

SECTION OF WORK : CIVIL LACATION :

LEVEL : BELOW GROUND LEVEL

CHECKED BY DATE
STATGE ITEM
HGC CHEC DORSCH
Screed mix (C20/10 design approval.
PRELIMINARY
CHECKS Latest approved drawings used at site.
Method statement, QCP, ITP, Risk Assessment
approved.
Substrate surface is clean & free from oil, grease and
SURFACE any loose materials.
PREPARATION Floor area is prepared in bays of suitable sizes as per
the method statement & level guides are provided.
MEP SERVICES/ Check presence of MEP services / conduits are
BUILT-IN ITEMS installed and completed.
Concrete laid and compacted as detailed in approved
method statement.
LAYING OF
SCREED Check screed top level/ slope as per the architectural
finishes layout drawings and surface tolerances shall
within the limits.
Check top surface of screed finish as per the
FINISHING architectural floor finishes layout drawings.
Check control joints are provided where required by
specifications and as directed by COMPANY.
CONTROL
JOINTS Check control joints shall be 12 mm filled with filler
between each two panels. Size of the panels shall not
exceed 3m x 3m.

CURING AND Check floor screed as protected from any damages


until its final setting and cured for a minimum period
PROTECTION of 4 days.

FOR S/C QA/QC : FOR CONTRACTOR QA/QC : FOR DORSCH REP :

Name: Name: Name:

Sign: Sign: Sign:

Date : Date : Date :