5. To make sure the quality of upper and lower piling connections during the construction,
the work of welding and piling driving must be under the supervision of CONTRACTOR.
6. To improve the work of piling, the below methods shall be followed:
(1) The basis of ceasing driving shall adopt piling elevation control and piling penetration
control.
(2) To avoid adjacent piling floating when conduct the new driving work, the elevation
changes of finished pilings shall be monitored and recording.
(3) The total pilings must conduct integrity tests
(4) To avoid the problems of reprocessing and waste, it is recommended that piling test
shall be conducted immediately when the work of piling driving under the first tank foundation
has been finished for 28 days. Once the quality test of piling is satisfied, the rest work can
proceed.