PROJECT TITLE:- North Gas Compression Pipeline Project

CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Procurement)


Total Open Closed Remarks Last Updated : 25-April -2020
Summary of Procurement INCRs Total
7 2 5
STANDARDS VIOLATED
TARGET DATE REVISED
Raised Closed COMPLETIO
S. No. NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE OF TARGET ACTION TAKEN STATUS
transmittal transmittal N DATE
COMPLETION DATE
DOC. REF. PARA NO.

Root Cause Analysis: As received latest MTO/MR Rev-C from


Engineering department, so based on that PO has been placed, as
It was observed that PO # PO-03-KSA04-PO-01-058 (Spectacle per latest MTO there was only quantity change, so we thought that
Plate) has been placed based on MR Rev-C. However, MR # CPP- MR approval is not require. Due to the urgency PO has been
PO Placed without Quality Plan CPP- 42306-PI-MR-0024 Rev-C is not yet approved from client. This MR forwarded to manufacture without PQCS verification.
MR approval , PO
1 CPP-NGCP-NCR-PROC-001 Procurement
submitted without
NGCP-QC-PLN- Clause: 6.2. is approved under Rev-B as of now. Jamaludeen 17-Jun-19 15-Jul-19 15-Jul-19 Correction Action: MR will be revised as per latest MTO and Tool Closed
PQCS Verification 0002 Moreover, PO-03-KSA04-01-058 has been issued without PQCS Box Meeting has been conducted for more awareness.
verification, which is a violation of Procurement Quality Plan CPP- Correction Action: MR will be revised as per latest MTO and Tool
NGCP-QC-PLN-0002 Clause: 6.2. Box Meeting has been conducted for more awareness.
General Reply: MR has been revised and got approved, based on
revised MR the PO also revised and acknowledged.

It was observed that PO#s 03-KSA04-PO-01-060 (Globe Valve), 03- Root Cause Analysis: PO has been placed due to urgent material
requirement to meet the delivery schedule.
PO Placed without KSA04-PO-01-043 (Copper Nickel Flanges) has been placed before Correction Action: PO date has been changed after the NOL
Schedule G , CPP- client approval (NOL). Which is a violation of Schedule G clause:
NOL , PO submitted NGCP-QC-PLN- clause: 11.2. , 20-Jul-19 received. Moreover, tool box meeting has been conducted for
2 CPP-NGCP-NCR-PROC-002 Procurement
without PQCS Clause: 6.2.
11.2. Jamaludeen 24-Jun-19 20-Jul-19
more awareness that without Client approval (NOL) PO cannot be Closed
Verification 0002 Moreover, PO#s-03-KSA04-01-060 & 03-KSA04-01-043 has been placed as per Sch G requirement.
issued without PQCS verification, which is a violation of
Procurement Quality Plan CPP-NGCP-QC-PLN-0002 Clause: 6.2. Corrective Action: PO cannot to be submit to Client without PO
review sheet signed by all parties.

Root Cause Analysis:


The rough forging used for A859 A Cl2 manufactured flanges is the
same as A707L5Cl3-4 (dual forging). For A707L5Cl3-4 Quenching
temperature of 980ºC is allowed.
During May-19, the temperature of Quenching for A707L5Cl3-4
was increased from 920ºC to 980ºC to reach the requirements of
Cl4, but it was not considered that A859 A Cl2 had the
NON- requirement of 870 to 940ºC.
SATISFACTORY HEAT TREATMENT surveillance items 3, 4, 7, 9, 11, 13, 17 (ASTM
A859 A Cl2) Correction Action:
because quenching NON-SATISFACTORY because quenching was done at 980ºC and All parts of A859 A Cl2 material included in PO 03-KSA04-PO-01-
was done at 980ºC 056 will be produced according the requirements of A859 A Cl2
ASTM A859 ASTM A859 Grade A according ASTM A859 Grade A class 2 should be within 870ºC and Javier Bravo- SAP
3 CPP-NGCP-NCR-PROC-003 Procurement and according
Grade A class 2 class 2 940ºC No. : 70016424 (TPI)
13-Sep-19 11-Oct-19 11-Oct-19 with Quenching temperature of 940ºC. Closed
ASTM A859 Grade Reference PO no. 03-KSA04-PO-01-056 Corrective Action:
A class 2 should be In the Heat treatment process, the Quenching temperature has
within 870ºC and Reference IL no. 107000156058
been changed to 940ºC to fulfill the requirements of A859 A Cl2
940ºC (870-940ºC).

Root Cause Analysis: Al Kaabi had received wrong plate from


supplier by mistake. Many plates from different manufactures
were lying in supplier yard and this mistake was happened during
loading from supplier QC as well lifter operator.
Correction Action: Al Kaabi had rejected the plate and issued
internal NCR# 46 to supplier and ask him to provide root cause,
Description of Non-conformance: During incoming material corrective and preventive action for same. New plate will replace
receiving inspection of plates which were procured for CPP the rejected plate and will arrive in Al Kaabi shop with next
project, it was noticed that offered plate 3mm x 1219mm x shipment material and will re-offer to CPP inspector.
2438mm, stenciling, marking and hard punching was missed on Preventive Action: Al Kaabi QC Manager had arranged meeting
plate and only (Made in China) was stenciled on plate; while MTC with all QCI and instruct them to do the inspection / MTCs review
Incoming material Reference PO no. Reference PO no.
receiving 03-KSA04-PO-01- 03-KSA04-PO-01- review for same plate; it was observed that provided MTC properly in order to avoid these problems in future. Closed NCR#
manufacture was (BHUSHAN Steel Ltd. Made in India). M. Adnan Riaz 46 is attached with this NCR.
inspection of Plate 072 072
4 CPP-NGCP-NCR-PROC-004 Procurement
MTC manufacture Reference IL no. Reference IL no.
Plate marking and provided MTC both were showing different 10-Oct-19 30-Oct-19 30-Oct-19 Implementation Status: Closed
& Plate stenciling 107000160020 107000160020 manufactures which is major non-conformance. Please refer Offered plate 3mm x 1219mm x 2438mm was rejected and
below picture of plates and attached MTC for your ready removed from CPP project. New plate will replace the rejected
both different. reference. plate. Hence NCR is closed now.
Reference PO no. 03-KSA04-PO-01-072
Reference IL no. 107000160020

Root Cause Analysis:


During the evaluation of valve data sheet, before issuing a NOI for gas
test, OMS personnel discovered the discrepancy in the definition of valve
service between “Wet sour service” and “Wet Sour Gas”. Considering
Gas testing of API 6D valves missing for PO line items: 001, 002, 003, the detailed definition of GAS we propose to TPI only those valves for
004, 005 witness the gas tested, even if for our internal procedure we carried out
04-SAMSS-048, 04-SAMSS-048, 5.1.2 04-SAMSS-048 gas test as per ARAMCO spec. 100% of valve.
5.1.2 API STD 598
paragraph API STD 598 5.1.2 High pressure steel valves in Class 900 and higher which are Preventive Action:
paragraph specified for gas service shall be subjected to a pneumatic high- 1. To avoid any misunderstand OMS will revise or ask to revise the valve
Gas testing of API 6D Reference PO no. Reference PO no. 03- pressure shell test per API STD 598 paragraph L. Magni (TPI) data sheet service to clearly mention GAS Service.
5 CPP-NGCP-NCR-PROC-005 Procurement valves missing for PO 03-KSA04-PO-01-
KSA04-PO-01-034 CO- 5.5. The holding time shall be a minimum of 5 minutes and no visible
3-Dec-19 30-Jan-19
2. Instruct all the personnel in charge to ARAMCO project to address in a OPEN
line items: 034 CO-02,
02, Reference IL no. leakage is allowed. proper way the gas test on all document for prompt understanding and
Reference IL no.
107000155521 usage.
107000155521
Reference PO no. 03-KSA04-PO-01-034 CO-02 Corrective Action:
Reference IL no. 107000155521 Based on ARAMCO specification requirement OMS will propose the gas
testing for the valve subject to this NCR to the TPIs involved for their
evaluation.

Root Cause Analysis:


Petronash offered receiving inspection of material at Petronash
Sub-vendor has prepared ITP as per IR022503 (Refer attachment 1)
Dammam fabrication shop.
which contains Review (R) for all stages but CPP has requested level ‘1’
It was found that Petronash Arabia procure material from M/S Officine
inspection in MR (refer attachment 2). Hence during ITP review this has
Santafede Italy as inspection level ‘ZERO” been overlooked by referring IR form and OMT (Order Management
approved SVL and As per the approved SVL for 9COM 6000000110, approved level of
approved SVL and Team) proceeded material shipment as per approved ITP without
SAEP-1151. SAEP-1151. inspection is level “ONE” for this 9COM. consulting with QC
Violation of Level of Reference PO no. It is a violation of Level of inspection against the approved SVL and
Reference PO no. 03- Arif Inamdar. (TPI) Preventive Action:
inspection as per the 03-KSA04-PO-01- SAEP-1151.
6 CPP-NGCP-NCR-PROC-006 Procurement approved SVL and 045.
KSA04-PO-01-045. 3-Dec-19 30-Dec-19 Sub-vendor ITP will be reviewed based on IR form and client OPEN
Reference IL no. Affected Material: requirement (MR)
SAEP-1151. Reference IL no. 1. 1” 900 Class SW-RTJ, Sch 160 SA350 LF6 Class 2 RTJ flange. Qty 280
107000156599. 107000156599. pcs heat # 4990. (MTC attached). Corrective Action:
Materials are available in Petronash Arabia facility. CPP can do final
2. FLG SWRTJ 1" 900# SCH40S B564UNS N08825 – 281 Quantity Ht#
555867 (MTC attached- Batch-80351). inspection at Petronash Arabia facility. Upon material acceptance and
release we will proceed further
3. FLG SWRTJ ½" 900# SCHXXS A350LF6 CL2 – 279 Quantity, Heat #
4990 (MTC attached - Batch-80473).

Page 1 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Procurement)


Total Open Closed Remarks Last Updated : 25-April -2020
Summary of Procurement INCRs Total
7 2 5
STANDARDS VIOLATED
TARGET DATE REVISED
Raised Closed COMPLETIO
S. No. NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE OF TARGET ACTION TAKEN STATUS
transmittal transmittal N DATE
COMPLETION DATE
DOC. REF. PARA NO.

Root Cause Analysis:


Valve serial number 53340017 - After dismantling and deep cleaning of
the valve components for PO item 4.01 we found one of the diaphragms
used for seal cover was damaged.
Description of Non-conformance: Valve serial number 51571095 - After dismantling and deep cleaning of
During hydrostatic shell pressure testing 2 valves leaked from the the valve components for PO item 4.01 we found one of the diaphragms
cover to body screwed joint. The valves that failed were from used for seal cover was damaged.
04-SAMSS-048 The assembly operators are fully trained in the build procedures,
separate production orders, the production orders had a quantity
Reference PO however in this instance visual inspection of the diaphragm was missed.
of 200 valves each. The valves that failed had been selected at
no. PO-03- No other diaphragm has been identified with the same damages.
Serck Audco random to form a 10% sample of each production order for Richard Branton
KSA04-PO-01-
192 CPP-NGCP-NCR-PROC-007 Procurement Hydrostatic Shell 9-Jan-00 witness inspection. Details of the valves that failed are as follows: 09-Dec-19 20-Jan-20 Preventive Action: OPEN
027
Test Failure Investigation on assembly procedure and components handling is been
Reference IL no.
PO item 4.01, 1” class 1500 plug valve, serial number 53340017, carried out.
107000155468
from production order 830253340 All assemblers have been assessed about the importance of both
PO item 4.01, 1” class 1500 plug valve, serial number 51571095, matters.
from production order 830251571
Corrective Action:
We are dismantling and reviewing the first two lots of valves offered for
inspection (400 items).
Following 04-SAMSS-048 we will increase the witness inspection to 100%
in these two batches.

Page 2 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root cause:Mishandled during loading and
transportation.
Correction Action: Subject two numbers of pipe coating
damaged to be repaired and to be
verified with holiday test for final acceptance by
During surveilliance it inspection.
was noticed that 2 nos During surveilliance it was noticed that 2 nos of pipes Corrective Action:
T-CPP-
CPP-NGCP-NCR-H-001 of pipes (FFCW203 and (FFCW203 and FFCX145) found coating damaged on Pipe loading / off loading crew has been instructed to
1 NA ARAMCO- Coating SAES-H-200 5.5.1 Mohammed Umair 01-Dec-18 01-Mar-19 05-Mar-19 04-Mar-19 Closed
EPM-INCR-6600001240 FFCX145) found the external surface of the pipes , which violates the take care of coating handling with more protection to the
02713
coating damaged on the requirements as on SAES-H-200 para 5.5.1 FBE coating.To prevent any future re-occurence CPP
external surface of informed SAPMT to notify coating vendor for re-
verification prior to dispatch/release any pip
es to site.
General Reply:
Please see attached signed and closed hard copy of
INCR H-001. This INCR can be close in EPM also.

Root cause:The pipes have no bevel protector provided


by the vendor, which was not part of the PO. VID and
PID acknowledged that the pipes are releasable based
on the sour gas service requirements. As a proactive
action, CPP provided temporary end bevel protectors to
avoid any damages and is working in quick basis to start
welding activities to avoid any potential risk on the
activities’ process.
During Material During Material Receiving Inspection of ARAMCO
Correction Action: CPP secured both ends of the pipes
Receiving Inspection of supplied line pipes (Line item # 3 of the collection
T-CPP- with plastic covers to prevent entry
CPP-NGCP-NCR-M-001 ARAMCO supplied line schedule- 8" x 0.375" Grade X65 pipes-581 each), it Mohammed
2 NA ARAMCO- Mechanical SAES-L-450 8.4 01-Dec-18 01-Mar-19 09-Jan-19 of dust, debris inside the pipe. Closed
EPM-INCR-6600001218 pipes (Line item # 3 of has been observed that all pipes are supplied without Umair
02714 Corrective Action: Based on CSD request response-
the collection schedule- Bevel end protectors. This is violation of SAES-L-450,
4042323432 & 4042338916, in relation
8" x 0.375" Grade para 8.4
with pipe end caps & bevel protectors (line pipe). End
cap only,
required for internally coated pipe. Bevel protectors not
required for
pipes purchased from in kingdom manufacturer as in
MS8444-09.
General Reply:Signed scanned copy of INCR is
uploaded to close this INCR.
During routine visit on DATE-15-Dec-18 at well Head
(HRDH-1170-919 & HRDH-1171) it was found that the
Contractor has changed the original Route of the Root cause:CPP Construction team submitted the
Pipeline without Prior Approval from Saudi Aramco PMT approval request for re-routing but due to site progress
onstruction (IFC)
or Proponent Representative which is a violation as per they continued without getting it approved.
T-CPP- drawings shall be
CPP-NGCP-NCR-CIV-001 SAES-L-450-Sec. 7.1.1” which states that “The pipeline Corrective: CPP construction team shall secure the
3 NA ARAMCO- Civil surveyed and staked by SAES-L-450 7.1.1 Hameed Ullah 16-Dec-18 16-Mar-19 26-Feb-19 Closed
EPM-INCR-6600001336 route as stipulated on the Issued for Construction (IFC) approval of re-routing from PMT
02712 the Construction
drawings shall be surveyed and staked by the or Proponent as required.
Contractor.
Construction Contractor. Changes to original routing Preventive Action: The subject re-route approved and
may be acceptable with prior approval by Saudi Aramco signed by SAPMT.
PMT and the Proponent Representative prior to
implementation in the form of Modified IFC Drawings.” Root cause:SAPMT to get root cause from coater and
provide accordingly.
During Material Receiving Inspection of ARAMCO
Correction Action:
supplied line pipes (Line item 2.1 of the collection
All misleading information's to be verified from
During Material schedule- 8" x 0.344" Grade X65 pipes-1652 each for
manufacturer MTC and sticker which is posted inside the
Receiving Inspection of the first delivery lot),
pipe and to be corrected accordingly with CPP QC
ARAMCO supplied line 1) 10 pipes have been observed pipe identification
T-CPP- signature.
CPP-NGCP-NCR-M-002 pipes (Line item 2.1 of marks not matching with Pipe documents. Mohammad
4 NA ARAMCO- Mechanical SAES-L-450 8.4 09-Jan-19 08-Apr-19 16-Feb-19 Corrective Action: Closed
EPM-INCR-6600001477 the collection schedule- 2) 3 pipes have been observed with overwriting Umair
02714 To prevent any future recurrence CPP informed SAPMT
8" x 0.344" Grade X65 information- which can mislead the traceability of the
to notify coating vendor for re-verification prior to
pipes-1652 each for the pipes.
dispatch/release any pipes
first delivery lot), This are violating the pipe identification marking
to site.To prevent any future recurrence CPP informed
requirements of 01-SAMSS-035, para 11 & API 5L Para
SAPMT to notify coating vendor for re-verification prior to
11.
dispatch/release any pipes
to site
Root cause: CPP Construction team proposed
After Getting Soil Sample Report for the Backfill inappropriate Material for selectfill.
Construction Team at
Material Proposed by the Construction Team at Borrow Correction Action:Backfill material stockpile have been
Borrow Pit number 01,
Pit number 01, Beside Wellhead 1117 was found failed cancelled and construction team
T-CPP- Beside Wellhead 1117
CPP-NGCP-NCR-CIV-002 the Gradation requirement of Select fill material and it is shall not use this material for backfilling.
5 NA ARAMCO- Civil was found failed the SAES-A-114 Sec. 6.1.2.1 Hameed Ullah 09-Jan-19 09-Apr-19 26-Feb-19 Closed
EPM-INCR-6600001331 Passing #200 sieve 53.5% which is a clear violation as Corrective Action: Construction team shall flat the
02712 Gradation requirement
per SAES-A-114-Sec. 6.1.2.1, which states that “The area.This stockpile is cancelled and construction will not
of Select fill material
amount of material passing the No. 200 sieve shall be use in future. The
and it is Passing
between 0-20% stockpile shall be spreaded out to the original condition.

During site visit at HRDH-1171 on Date-18-Jan-2019,


joint number (00-FW-017) Welder (CPP-W-008) it was
observed that the welding was ongoing with tent but
During site visit at door cover opened during welding as per attached
HRDH-1171 on Date- picture which is a standard violation as per SAES-W-
T-CPP- Root cause:Careless workmanship from the welders.
CPP-NGCP-NCR-W-001 18-Jan-2019, joint 012 Para 10.2.1 which states that Wind shields or tents Mohammad
6 NA ARAMCO- Welding SAES-W-012 Para 10.2.1 21-Jan-19 05-Feb-19 3/5/2019 02-Mar-19 Correction Action:Weld tent shall be closed from all Closed
EPM-INCR-6600001556 number (00-FW-017) shall be required when wind is strong enough to affect Sarfaraz
02717 sides during welding, especially when wind speed is high
Welder (CPP-W-008) it arc stability or when deemed necessary by Saudi
was observe Aramco Inspection.

Attachment-1 for picture of violation.


During daily routine Inspection at TCF-1, Welding area , Root Cause: Careless workmanship practice from the
it was observed that the welding was ongoing without welding crew supervisor.
adequate pipe supports as required in Saudi Aramco Correction Action: Delayed RT & MT shall be done to
During daily routine
CSD CRM-4042365859, (Approved for site welding with investigate any crack in the subject welds due to
Inspection at TCF-1,
T-CPP- Aramco CSD External line-up clamp with condition) Point-1, which improper supports.
CPP-NGCP-NCR-W-002 Welding area , it was
7 NA ARAMCO- Welding CRM- Point-1 states that Fit-up and welding activities will be Junaid Zafar 29-Jan-19 28-Feb-19 02-Mar-19 Corrective Action: Proper pipe supports and level Closed
EPM-INCR-6600001519 observed that the
02717 4042365859 performed by qualified welders on a stable, level ground ground shall be provided for further fit-up and welding
welding was ongoing
utilizing temporary pipe supports with a good activities.
without
workmanship practice. Reference weld numbers: TRL- General Reply:
1-DJ-09, TRL-1-DJ-10, TRL-1-DJ-11 & TRL-1-DJ-12. Signed scan copy of INCR-W-002 has been uploaded to
close this INCR.

Page 3 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
During routine inspection at HRDH-1171, joint # (02-
Root cause: Careless workmanship from the welders.
During routine FW-152) Welder (CPP-W-008) it was observed that
Correction: 100% RT will be performed for the joint 02-
inspection at HRDH- during welding portable electrode oven was open and
T-CPP- FW-152.
CPP-NGCP-NCR-W-003 1171, joint # (02-FW- temperature was below 65°C, which is a standard Mohammad
8 NA ARAMCO- Welding SAES-W-012 Appendix 1 31-Jan-19 28-Feb-19 02-Mar-19 Correcive Action: Closed
EPM-INCR-6600001542 152) Welder (CPP-W- violation as per W-012, Appendix 1, which state that Sarfaraz
02717 General Reply:
008) it was observed elec
Signed scan copy of INCR-W-003 has been uploaded to
that during welding trodesare continuously stored in a portable oven heated
close this INCR.
to 65°C minimum.

Root Cause Analysis: The material was transferred to


During daily site visit on
During daily site visit on date 12-Feb-2019 at Well pad site without screening.
date 12-Feb-2019 at
extension work for HRDH-1122 it was observed that the Correction Action: The subject 6th Layer shall be
Well pad extension
Material (General Fill) being spread for the 6th Layer removed and acceptable Sieved Materials shall be
T-CPP- work for HRDH-1122 it
CPP-NGCP-NCR-CIV-003 (Zone A and B) have over size Gravels more than placed.
9 NA ARAMCO- Civil was observed that the SAES-A-114 6.1.1. Hameed Ullah 12-Feb-19 12-May-19 24-Feb-19 Closed
EPM-INCR-6600001636 75mm which is a violation as per SAES-A-114, Sec. Corrective Action:
02712 Material (General Fill)
6.1.1. which states that “The maximum size of fill CPP Civil QC to monitor use of seive at site everytime
being spread for the 6th
materials shall be one-half (½) the lift thickness or before use.
Layer (Zone A and B)
75mm (3 inches), whichever is less.” General Reply:Implementation done. This INCR can be
have over size
close now in EPM.

During routine inspection at HRDH-1116, joint # (02-


During routine
FW-183) it was observed that the pipe was released
inspection at HRDH- Root Cause Analysis: Careless workmanship from
T-CPP- from site boom before the completion of hot pass which
CPP-NGCP-NCR-W-004 1116, joint # (02-FW- welding crew.
10 NA ARAMCO- Welding SAES-W-012 Para 10.7.3 is a standard violation as per W-012, Para 10.7.3, Mohammad Saif 17-Feb-19 17-Apr-19 31-Mar-19 Closed
EPM-INCR-6600001689 183) it was observed Correction Action: Joint 02-FW-183 shall be 100%
02717 which states that the hot pass shall be made while the
that the pipe was radiograph to ensure integrity/ soundness of joint.
pipe is fully supported by side boom.
released from site boom

Root Cause Analysis: Careless workmanship from


During routine inspection at HWYH-1134, joint # (00- welding crew
FW-50) it was observed that the pipe bevel was not Correction Action: Joint 00-FW-50, shall be 100%
properly cleaned prior to welding the weld joint. This radiograph to ensure integrity/ soundness of weld.
During routine
violates W-012, Para 10.3.1, which states that: Oil, Corrective Action:
inspection at HWYH-
T-CPP- moisture, rust, scale, sand, paint (except weldable Awareness Toolbox training will be provided to prevent
CPP-NGCP-NCR-W-005 1134, joint # (00-FW-
11 NA ARAMCO- Welding SAES-W-012 Para 10.3.1 primers for approved applications-refer to paragraph Umair Mukhtar 18-Feb-19 15-May-19 19-Mar-19 future Closed
EPM-INCR-6600001710 50) it was observed that
02717 7.4.7 for restrictions) metallic coatings (e.g., zinc), or recurrence, site QC to monitor closely to follow standard
the pipe bevel was not
other foreign matter shall be removed from the weld requirements
properly
surface and at least 25 mm of adjacent base metal prior General Reply:
to welding, including any such coatings on temporary Please close this INCR, Corrective action done and
attachments or supports. accepted, signed scan
copy uploaded.

Root Cause: Careless workmanship from welders.


Correction Action: Damaged area marked and will be
During routine During routine inspection at HRDH-1116, joint # (02- repaired and holiday tested before lowering and
inspection at HRDH- FW-183) it was observed that the pipe was released backfilling.
T-CPP-
CPP-NGCP-NCR-W-006 1116, joint # (02-FW- from site boom before the completion of hot pass which Corrective Action: Awareness toolbox training will be
12 NA ARAMCO- Welding SAES-W-012 Para 10.7.3 Junaid Zafar 20-Feb-19 18-May-19 13-May-19 Closed
EPM-INCR-6600001639 183) it was observed is a standard violation as per W-012, Para 10.7.3, conducted to prevent future
02717
that the pipe was which states that the hot pass shall be made while the recurrence, Site QC to monitor closely to follow standard
released from site boom pipe is fully supported by side boom. requirement
General Reply: Correction action implemented and
verified.

Root Cause Analysis: As per SAES- H-002, Para


5.1.12 For open cut excavation, APCS-113C can be
used over APCS-104A or APCS-104B.
Also, as per CPP-NGCP-CM-PRO-0009, Rev-01
approved procedure for APCS-113C Coating Application
Procedure for pipe Field Girth weld and Open Cut Road
During open cut Asphalt road crossing at km 3+577,
During open cut Asphalt Crossing APCS-113C (Canusa Wrapping) to be used as
HWYH-1134 flowline, it was observed that External FBE
road crossing at km an additional coating system or the crossing pipes.
T-CPP- coated Pipe surface is wrapped by APCS-113C
CPP-NGCP-NCR-H-002 3+577, HWYH-1134 Mohammad Correction Action: TQ-CPP-Q-0287 has been raised to
13 NA ARAMCO- Coating SAES- H-002 Para 5.1.12 (Canusa Wrapping) as an additional coating in place of 28-Feb-19 28-May-19 02-Apr-19 Closed
EPM-INCR-6600001836 flowline, it was Rizwan the designer to clarify Use of APCS-113C for pipes
02713 APCS-113A, which violates the requirements Project
observed that External under open cut road crossings.
IFC Painting/ Coating Schedule (TB-843596-001, Rev-
FBE General Reply:Based on the approved TQ-CPP-Q-0287
00).
statement "contractor is advised to
note that as per SAES-H-002 clause 5.1.12 for open cut
excav
ation APCS-113C can be used over APCS-104B" so
this INCR is considered
closed.

Root Cause Analysis: Construction team Failed to


comply the requirements of SAES- A-111Table 1
During daily site visit on date 04-Mar-2019 it was Correction Action: Site construction team shall propose
During daily site visit on
observed that the distance from the boundary of Borrow another area for borrow pit location to take sample
date 04-Mar-2019 it
T-CPP- Pit near Well pad HRDH-1145 to New Power line Pole Corrective Action: CPP site QC inspector will deliver a
CPP-NGCP-NCR-CIV-004 was observed that the
14 NA ARAMCO- Civil SAES-111 Table -1 Foundation is 60 meter which is a violation as per Hameed Ullah 04-Mar-19 04-May-19 28-Mar-19 quality toolbox to site Closed
EPM-INCR-6600001877 distance from the
02712 SAES-A-111 Table-1 which states that “The Minimum construction team to enhance the borrow pit location
boundary of Borrow Pit
Setback Distance from the Boundary of Borrow Pits construction requirements. Subsequently, CPP QC
near Well
shall be 100m from the Powerlines.” department will closely monitor to avoid re-occurrence.
Genaral Reply:Correction action done and verified.
Borrow pit violating the standard have been demolished.

Root Cause Analysis: Site construction team ignored


the standard requirements and
During daily site visit on instructions from site QC inspector.
Date 04-March-2019 it Construction team did not stop taking material from
was observed that the During daily site visit on Date 04-March-2019 it was borrow pit since the
distance from the observed that the distance from the boundry of Borrow construction of new light pole started.
T-CPP- boundry of Borrow pit pit near Wellpad RH-GK Hawiyah existing oil and Gas Correction Action: Site construction team shall propose
CPP-NGCP-NCR-CIV-005
15 NA ARAMCO- Civil near Wellpad RH-GK SAES-A-111 Table-1 sites is 60 meter which is Violation as per SAES-111 Aamir Solangi 04-Mar-19 04-Jun-19 28-Mar-19 another area for borrow pit location to take sample. Closed
EPM-INCR-6600001828
02712 Hawiyah existing oil Table -1 which states that “ minimum setback distance Corrective Action: CPP site QC inspector will deliver a
and Gas sites is 60 from the boundry of Borrow pits shall be 100meter from quality toolbox to site
meter which is Violation the existing oil and Gas sites.” construction team to enhance the borrow pit location
as per SAES-111 Table construction requi
-1 which rements. Subsequently, CPP QC department will closely
monitor to avoid
re-occurrence.

Page 4 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
During daily site visit on date 04-Mar-2019 it was
Root Cause Analysis: Construction team are ignoring
observed at all Hradh Area trenches
the procedure requirements and not following the QC
(1163,1170,1171,922,1116,1122,1117,1145,1162,1172)
inspector Instructions.
During daily site visit on that there is no proper station marks beside trenches for
T-CPP- MOS#(CPP- Correction Action: Provide station marks at every
CPP-NGCP-NCR-CIV-006 date 04-Mar-2019 it proper identification of chainage which is a violation as
16 NA ARAMCO- Civil NGCP-CM- Para-7.2 Hameed Ullah 04-Mar-19 01-May-19 01-May-19 200m. Closed
EPM-INCR-660001833 was observed at all per Approved MOS#(CPP-NGCP-CM-MS-
02712 MS-0003 Corrective Action: Implement the station marking as
Hradh Area trenches 0003-“Trenching and backfilling” Para-7.2) which states
per Approved Method of Statement Requirement for all
that ”Station marks shall be installed to the work site for
pipelines
identification of chainage at an interval of every
General Reply:
200meters”.

During routine surveillance on 06-MARCH-2019 of Well Root Cause Analysis: Site construction ignore the
Pad # HRDH-1035 & HRDH-1116 It was observed on requirements and instruction from the Site QC Inspector
site that the construction team have not maintained the Root Cause Analysis: Site construction ignore the
side slope as per 2:1 (horizontal to vertical) which is a requirements and instruction from the Site QC Inspector
It was observed on
clear violation of IFC drawing # ta-725661-sht-001-rev- Correction Action:
site that the
00 general notes and abbreviations section-6 note-12 Construction team will make the slope 2:1 (horizontal to
T-CPP- construction team have IFC drawing
CPP-NGCP-NCR-CIV-007 section-6 note- which states that the “side slope 2:1(horizotal to vertical) and will make it stabilized with 300mm marl.
17 NA ARAMCO- Civil not maintained the side # ta-725661- Talal Shabbir 06-Mar-19 06-Jun-19 12-Mar-19 Closed
EPM-INCR-660001854 12 vertical) shall be stabilized with 300mm thick marl, and Corrective Action: Construction will implement the
02712 slope as per 2:1 sht-001-rev-00
for height of embankment 3m and above shall be slope construction at all sites with proper survey
(horizontal to vertical)
provided with horizontal layers of geogrid and spacing markings to achieve the final & stabilized slope of 2:1
which is a clear
shall be as per vendor recommendation”. (horizontal to vertical). Strict surveillance will be done at
Initiated by: Talal Shabbir site to avoid further occurrence.
General Reply:Corrective action done and verified at
site by SAPID.Hence, this INCR is closed.

Root Cause Analysis: Careless workmanship of


On March 6, 2019, CPP On March 6, 2019, CPP QC Noticed an arc strike during
improper fixing of grounding clamp
QC Noticed an arc the welding activities of joint no. 00-FW-12 at 8" HWYH-
T-CPP- Correction Action: Grinding the defected area to
CPP-NGCP-NCR-W-007 strike during the 1070. This violates SAES-W-12, Para 10.10 which
18 NA ARAMCO- Welding SAES-W-12 Para 10.10 Imran Manzoor 06-Mar-19 06-Jun-19 18-Apr-19 remove the arc strike and apply PT test. Closed
EPM-INCR-6600001864 welding activities of states Arc strikes and other indications by careless
02717 Corrective Action: Proper fixing of grounding clamp
joint no. 00-FW-12 at 8" workmanship (Such as surface prosity, uneven weld
shall be provided for further fit-up
HWYH-1070. profiles and undercut) shall be removed by grinding
and welding activities.

Root Cause Analysis: : After welding of the string site


crew kept the pipe on berm support that’s are near to
excavated trench and string sliped from berm and fall
down in to the trench, poor workmanship to prevent the
During surveillance inspection at HRDH-1117 it was
pipe and negligence of the construction team to monitor
During surveillance observed that one string Joint number from FW-142 TO
regularly the condition of the string pipes.
inspection at HRDH- 233 dia 8” X 0.344” welded pipe string fall down in to
T-CPP- Correction Action: The pipe string shall be lift from the
CPP-NGCP-NCR-M-003 1117 it was observed the trench, which is violation of SAES-H-200 Sec # Mohammad
19 NA ARAMCO- Mechanical SAES-H-200 Sec # 5.2.1 10-Mar-19 10-Jun-19 28-Mar-19 trench and keep to a minimum of 150mm off the ground Closed
EPM-INCR-66000001879 that one string Joint 5.2.1 requirement. This standard requires the pipe Umair
02714 with a clear distance from the trench edges. Effected
number from FW-142 string shall be kept in suitable support 150mm off the
coating damage area shall be repair prior to backfill.
TO 233 ground at all times to protect the external FBE coating
Corrective Action: String support shall be in a good
from being damage.
shape with proper sand bags to avoid repeated violation.
General Reply:Corrective action implemented and
verified. Closed copy of INCR is uploaded in the
documents. Hence, this INCR can be closed.

Root Cause:Careless workmanship of keeping not


functioning equipment in work area.
Correction Action:Electrodes exposed to the
atmosphere for 1 hr. which less than the permitted time
n March 14, 2019, CPP
On March 14, 2019, CPP QC noticed calibrated period. So returned to a holding oven maintained at
QC noticed calibrated
T-CPP- portable electrode oven no.110F18 not functioning at 120°C. Remove not functioning portable oven from work
CPP-NGCP-NCR-W-008 portable electrode oven
20 NA ARAMCO- Welding SAES-W-012 Appendix 1 8”-HWYH-1076. This violates SAES-W-012, Appendix Imran Manzoor 14-Mar-19 14-Jun-19 28-Mar-19 area. Closed
EPM-INCR-6600001882 no.110F18 not
02717 1, which states: The electrodes shall be stored Corrective Action:Awareness toolbox training will be
functioning at 8”-
continuously in ovens at 120°C minimum. conducted to monitor the function of the equipment used
HWYH-1076
for storing, handling and conditioning of
welding consumables. Function of equipment will be
monitored daily by
welding foreman and verified by welding inspector.

On March 16, 2019, CPP QC noticed Improper cleaning Root Cause:Lack of standard requirement knowledge
On March 16, 2019,
during joint fit-up preparation at 8”-HWYH-1055 joint no. from the grinder side.
CPP QC noticed
T-CPP- 1-FW-133. This violates SAES-W-012, Para 10.3.1, Correction Action:Clean the joint and RT test shall be
CPP-NGCP-NCR-W-009 Improper cleaning
21 NA ARAMCO- Welding SAES-W-012 Para 10.3.1 which states: Oil, moisture, rust, scale, sand, paint or Umair Mukhtar 16-Mar-19 16-Apr-19 09-Apr-19 performed on the specified joint. Closed
EPM-INCR-6600002016 during joint fit-up
02717 other foreign matter shall be removed from the weld Corrective Action:Awareness toolbox training will be
preparation at 8”-
surface and at least 25 mm of adjacent base metal prior conducted for the welding team to be
HWYH-1055 joint no. 1-
to welding. familiar with joint preparation standard requirement.

Root Cause Analysis:The Survey Report based


During site Inspection on date 20-Mar-2019 it was found according to old Revision of drawing which is not
that at HRDH-1145 TO HRDH-1117(8”F/L) Centerline of rectified as per re-IFC drawings.
During site Inspection
Pipe Trench is not reflected on the provided Survey Correction Action: Conduct the Survey of Trench
T-CPP- on date 20-Mar-2019 it
CPP-NGCP-NCR-CIV-008 TA-843976-0F1- Report and not matching the Drawing as well which is a according to the Updated Revision of Drawing and
22 NA ARAMCO- Civil was found that at IFC Drawing Hameed Ullah 21-Mar-19 21-Apr-19 05-Apr-19 Closed
EPM-INCR-6600002086 Note#4 violation as Per IFC Drawing#TA-843976-0F1-Note#4 Provide survey report to conduct inspection again.
02712 HRDH-1145 TO HRDH-
Which states that” Construction Contractor need to Corrective Action:
1117(8”F/L)
follow the coordinates providing in this Alignment Verify the Centerline of Pipe according to Updated
sheet”. Revision of IFC Drawing prior to trench excavation.
General Reply:

Root Cause Analysis:Temporary Rubber Tires used to


support / store Welded String, settled down due to pipe
weight and touched Ground
Correction Action: All subject pipes to be lifted by
During surveillance
During surveillance inspection for Flowline HWYH-1134 placing proper support with a clear minimum gap of 6
inspection for Flowline
T-CPP- welded string- from KM 1+495 to km 0+525 (01-FW-123 inch (150mm) from ground. All coating damaged area
CPP-NGCP-NCR-H-003 HWYH-1134 welded
23 NA ARAMCO- Coating SAES-H-200 Para 5.2.1. to 00-FW-74)- some pipes are touching Ground marls N. Kishore 27-Mar-19 15-Apr-19 10-Apr-19 shall be marked for repair and holiday acceptance prior Closed
EPM-INCR-6600002136 string- from KM 1+495
02713 mixed with big stones. This is a violation of pipe to lowering.
to km 0+525 (01-FW-
handling and storage as per SAES-H-200, Para 5.2.1. Corrective Action:
123 to
To prevent any re occurrence Welding inspectors are
notified to monitor better support during welding.
Construction crews to be notified through Quality
Awareness Toolbox meeting.

Page 5 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis: Improper welder skills.
On March 21, 2019, On March 21, 2019, CPP QC noticed Welder W-050 Correction Action: The defected area will be grinded
CPP QC noticed started the adjacent weld beads from the same location and SAES-W-012 requirement for the welding of
T-CPP-
CPP-NGCP-NCR-W-010 Welder W-050 started Joint 00-FW-72 at 8”-HWYH-1076. This violates SAES- adjacent beads will be followed. RT and hardness test
24 NA ARAMCO- Welding SAES-W-012 Para 10.17 Imran Manzoor 21-Mar-19 21-May-19 21-May-19 Closed
EPM-INCR-6600002115 the adjacent weld W-012, Para 10.17, which states: Adjacent weld beads will be done for joint 00-FW-72.
02717
beads from the same shall be staggered and not started from the same Corrective Action: Awareness toolbox will be
location Joint 00 location. conducted to enhance welder skills and improve their
knowledge of the SAES-W-012 requirement

Root Cause Analysis: Lack of Awareness from welding


crew.
During routine During routine inspection at HWYH-1003, joint # (07- Correction Action: Joint 07-FW-605 & 07-FW-611,
inspection at HWYH- FW-605 & 07-FW-611) it was observed that welding shall be 100% radiograph to ensure integrity/ soundness
T-CPP-
CPP-NGCP-NCR-W-011 1003, joint # (07-FW- Item number is was continue without presence of QC welding of weld.
25 NA ARAMCO- Welding SATIP-W-012 Ruhul Amin 30-Mar-19 30-Apr-19 14-May-19 14-May-19 Closed
EPM-INCR-6600002114 605 & 07-FW-611) it 3.7 Inspector, This violates SATIP-W-012, Item number is Corrective Action: Awareness Toolbox training will be
02717
was observed that 3.7, which states that: Pre-Welding & Weld Joint Fit-up conducted to prevent future recurrence, Site QC to
welding was continue Inspection is hold point for contractor QC. monitor closely to follow standard requirement.
General Reply:
Correction Action implemented and verified

Page 6 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis: Construction team was
During daily site visit on date 31-Mar-2019 at RH-K1 transporting un-screened material from un-approved
Extension, it was observed that the Material (Select Fill) source.
During daily site visit on
being Dumped for the1st Layer have over size Gravels Correction Action: The subject 1st Layer shall be
T-CPP- date 31-Mar-2019 at
CPP-NGCP-NCR-CIV-009 more than 50mm which is a violation as per SAES-A- scarified in order to Remove over size material from it
26 NA ARAMCO- Civil RH-K1 Extension, it SAES-A-114 Sec. 6.1.2.1. Hameed Ullah 31-Mar-19 15-Apr-19 15-Apr-19 Closed
EPM-INCR-6600002149 114, Sec. 6.1.2.1. which states that “Select Fill or and CPP QC will verify before the compaction begin.
02712 was observed that the
‘Structural Fill’ shall be composed only of inorganic Corrective Action: Construction team shall take
Material (Select Fill)
material and shall have 100% passing the 5 cm (2 in) approved material from approved source before placing
sieve and from 0 to 20% passing the No. 200 sieve”. at site. Subsequently, CPP quality department will firmly
monitor the backfilling work.
During daily site visit on date 02-April-2019 at HRDH
902 (km 2+842), it was observed that the Flowline
Trench is Excavated within 3m Near to powerlines Root Cause Analysis: Construction Team Has
Support Structure which is a Violation as per SAES-B- Followed the Actual Centerline of Flowline without
During daily site visit on
064-Para-7.6.3 Which states That” Where pipeline and keeping Minimum Clearance from Existing Facilities.
T-CPP- date 02-April-2019 at
CPP-NGCP-NCR-CIV-010 overhead powerline corridors cross, the minimum Correction Action: Construction shall provide TQ
27 NA ARAMCO- Civil HRDH 902 (km 2+842), SAES-B-064 Para-7.6.3 Hameed Ullah 06-Apr-19 06-May-19 20-Jun-19 20-Jun-19 Closed
EPM-INCR-6600002160 horizontal separation between any pipeline and the Approved by SAPMT or Designer.
02712 it was observed that the
poles or support structures of overhead powerlines shall Corrective Action: Construction team shall Survey the
Flowline Trench is
be:(c) 4.5 m in producing areas for flowlines, trunklines, centerline of pipe and Notify to PMT if there is any
test lines, gas lift lines, gas injection lines, water Existing Facilities Prior To start Excavation.
injection, supply lines, and disposal lines with pipe
diameters of 24 inches and less.
Root Cause Analysis: Construction team followed the
During daily site visit on date 17-April-2019 at HRDH typical rocky area drawing and failed to maintain the
During daily site visit on 1160, it was observed that trench depth at km 3+028 to trench depth as per wadi area drawings.
date 17-April-2019 at 3+063 is 900mm which is not meeting the wadi area Correction Action: Construction team shall excavate
CPP-NGCP-NCR-CIV-011 HRDH 1160, it was crossing drawings TA-017571. The actual trench depth more at all wadi areas according to the Wadi Area Cross
28 Civil IFC drawings TA-017571-001 Hameed Ullah 17-Apr-19 17-Jul-19 17-Oct-19 Closed
EPM-INCR-6600002297 observed that trench provided at site clearly violates the Typical Wadi Area Section Drawing TA-017571.
depth at km 3+028 to Crossing Detail Drawing-TA-017571-001 “which shows Corrective Action: Construction team shall Review the
3+063 is that the total trench depth shall be Plan and Profile drawings before proceeding to
300mm+DIA+1200mm” Excavation and follow the detail Cross section drawings
for specific areas accordingly.

Root Cause Analysis: Construction team was


transporting un-screened material from the stockpile.
Correction Action: The subject 2ND Layer shall be
During daily site visit on date 11-APR-2019 at well pad
scarified in order to Remove over size material from it
During daily site visit on 996, it was observed that the Material (General fill)
and CPP QC will verify before the compaction begin.
date 11-APR-2019 at being dumped for the 2nd Layer have over size stones
T-CPP- Corrective Action: Construction team shall take
CPP-NGCP-NCR-CIV-012 well pad 996, it was & boulders more than 75mm which is a violation as per
29 NA ARAMCO- Civil SAES-A-114 6.1.1.1 Taseer Khan 11-Apr-19 30-Apr-19 25-Apr-19 screened material from approved source before placing Closed
EPM-INCR-6600002222 observed that the SAES-A-114, Sec. 6.1.1.1. which states that General
02712 at site. Subsequently, CPP quality department will firmly
Material (General fill) Fill Material shall consist of gravel, sand and/or marl.
monitor the backfilling work.
being dumped The maximum size of the fill material shall be one-half
General Reply:
the lift thickness or 75 mm (3 inches), whichever is less.
Corrective action completed and verified by SAPID. scan
copy of closed
INCR is uploaded. Hence, please close this INCR.

Root Cause Analysis:


During surveillance visit to the site- HRDH-1170,
Heavy rain this week.
HRDH-922, HRDH-1116 few locations, the lowered pipe
During surveillance visit Correction Action:
strings found submerged in the rain water – after the
T-CPP- to the site- HRDH-1170, Rain water shall be remove from the trench and from
CPP-NGCP-NCR-M-004 heavy rain this week. This resulted rain water staged Mohammad
30 NA ARAMCO- Mechanical HRDH-922, HRDH- SAES-L-450 Para 11.4 17-Apr-19 04-May-19 11-May-19 inside the strings (if there is) and all effected string Ends Closed
EPM-INCR-6600002316 inside the strings. This is a violation of SAES-L-450 Umair
02714 1116 few locations, the shall be capped Properly.
para 11.4 requirement. This standard requires the open
lowered pipe strings Corrective Action:
ends of pipeline strings shall be capped to prevent entry
Need to install proper end cap to avoid repeated
of debris, animals etc.
violation.

During site surveillance on date 21-Apr-19 at well head


HWYH-1100 F/L KM-4+000 it was observed that CPP
Root Cause Analysis: Careless workmanship and lack
During site surveillance installed the 60 Lbs. Magnesium anode and backfilled
of awareness/knowledge.
T-CPP- on date 21-Apr-19 at without saturated with water prior to, during and after
CPP-NGCP-NCR-E-001 Standard AA-036352, Mohammad Correction Action: Cathodic protection construction
31 NA ARAMCO- Electrical/CP well head HWYH-1100 backfilling. This is clear violation of standard drawing 22-Apr-19 07-May-19 06-May-19 Closed
EPM-INCR-6600002271 drawing Note #10 Amin team to comply the standard drawing AA-036352.
02716 F/L KM-4+000 it was AA-036352, Note #10. Which states that prepackaged
Corrective Action: QC tool box meeting for CP
observed that CPP anode to be thoroughly saturated with water prior to,
awareness to prevent recurrence.
during, and after backfilling “tamp backfill firmly around
the anode.

Root Cause Analysis: Construction team lowered the


pipe for TIE-IN Joint and didn’t provide Minimum Sand
Cover above the pipe.
During daily site visit on During daily site visit on date 21-April-2019 at HRDH Correction Action: Construction team shall excavate
date 21-April-2019 at 1063 sta.1+185 to 1+196 it was observed that the pipe under the pipe by manual excavation and remove
HRDH 1063 sta.1+185 string was lowered in the trench and the top of pipe is excess sand under the pipe string in order to provide
T-CPP-
CPP-NGCP-NCR-CIV-013 to 1+196 it was above the ground which is a violation as per SAES-L- proper sand cover over the pipe.
32 NA ARAMCO- Civil SAES-L-450 Sec. 14.9.3a Aqib Hussain 23-Apr-19 30-Jul-19 30-May-19 CLOSED
EPM-INCR-6600002335 observed that the pipe 450, Sec. 14.9.3a which states that” The minimum Corrective Action: CPP quality department will
02712
string was lowered in trench depth shall be such that the top of the pipe is enhance the site surveillance. Subsequently quality
the trench and the top below the original ground surface by 50mm in rippable department will firmly monitor the site activities to avoid
of pipe is above the or hard marl areas.” recurrence.
General Reply:Correction action implemented and
verified. Scan copy if closed INCR is uploaded. Hence,
please close this INCR.

Root Cause Analysis: Construction team was


transporting un-screened material to site moreover
construction did not follow the requirements of SAES-L-
450 Appendix D.
Correction Action: It was suggested by PID before to
During daily site visit on date 23-April-2019 at HRDH provide a manual screening tool at site to ensure
During daily site visit on 1063 sta.0+887 to 1+050 it was observed that the accumulated larger size stones are segregated
date 23-April-2019 at construction team dumped the sand having oversize accordingly. Construction team shall remove all the
T-CPP-
CPP-NGCP-NCR-CIV-014 HRDH 1063 sta.0+887 Appendix D, stones for backfilling of sand bedding and pipe covering oversize stones from the material at site and use the
33 NA ARAMCO- Civil SAES-L-450 Aqib Hussain 23-Apr-19 07-May-19 06-May-19 Closed
EPM-INCR-6600002406 to 1+050 it was note-4 at site which is clear violation of SAES-L-450 Appendix clean sand which is does not contain stones larger than
02712
observed that the D, note-4 which states that “Bedding material shall be 12mm.
construction sand or soil which will not damage the coating and shall Corrective Action: CPP quality inspector will deliver a
not contain stone larger than 12 mm (0.5 in.).” tool box meeting to enhance the awareness.
Subsequently quality department will firmly monitor the
site activities to avoid recurrence.
General Reply:
Corrective action done hence it is kindly requested to
please close this INCR.

During daily site visit on date 23-April-2019 it was


Root Cause Analysis: Construction team ignored the
observed at Haradh 619 (8” Flow line) trench there is no
During daily site visit on requirements as mentioned in approved method
proper station marks beside excavated trench for proper
date 23-April-2019 it statement.
T-CPP- identification of chainage which is a violation as per
CPP-NGCP-NCR-CIV-015 was observed at NGCP-CM- Correction Action: Provide station marks at every
34 NA ARAMCO- Civil Para-7.2 Approved MOS# (CPP-NGCP-CM-MS-0003- Hameed Ullah 23-Apr-19 01-Jul-19 18-Jun-19 Closed
EPM-INCR-6600002386 Haradh 619 (8” Flow MS-0003 200m.
02712 “Trenching and backfilling” Para-7.2) which states that”
line) trench there is no Corrective Action: Implement the station marking as
Station marks shall be installed to the work site for
proper per Approved Method of Statement Requirement for
identification of chainage at an interval of every
trenches.
200meters”.

Page 7 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

During site Surveillance on date 23-April-2019 at


HRDH-619 TO RH-CK(8”F/L) it was observed that the
Excavated Trench is not matching the Centerline of Root Cause Analysis: The Centerline of pipe was
Pipe as indicated on the IFC Drawing from Sta:2+992 to staked by the surveyor which was removed by the
During site Surveillance 3+000,3+070 to 3+150,3+250 to 3+262,2+254 to Equipment’s.
on date 23-April-2019 at 2+160,4+806 to 4+830 which is a violation as per Correction Action: Conduct the Survey for the
T-CPP-
CPP-NGCP-NCR-CIV-016 HRDH-619 TO RH- SAES-L-450 Sec. 7.1.1 which states that” The pipeline centerline of pipe again and staked it as per IFC
35 NA ARAMCO- Civil SAES-L-450 Sec. 7.1.1 Hameed Ullah 23-Apr-19 31-Jul-19 18-Jun-19 Closed
EPM-INCR-6600002425 CK(8”F/L) it was route as stipulated on the Issued for Construction (IFC) drawing.
02712
observed that the drawings shall be surveyed and staked by the Corrective Action:
Excavated Construction Contractor. Changes to original routing When Ever centerline of pipe marking for trench is
may be acceptable with prior approval by Saudi Aramco missing at site, it shall be informed to surveyor to provide
PMT and the Proponent Representative prior to centerline marking again in order to avoid double work.
implementation in the form of Modified IFC Drawings.”

During surveillance inspection at TCF-1 storage area, it


has been observed that, ARO and CANUSA materials Root Cause Analysis: Negligence of storekeeper.
kept Correction Action:
During surveillance
in container in controlled atmosphere but no Calibrated temperature gauge to be fixed as soon as
inspection at TCF-1
T-CPP- thermometer for monitoring the temperature is installed possible.
CPP-NGCP-NCR-H-004 storage area, it has
36 NA ARAMCO- Coating SAES-H-001 Para-6.2 for getting instant reading. Reading- which restricts to Bijoy C.R 24-Apr-19 07-May-19 29-Apr-19 Corrective Action: Closed
EPM-INCR-6600002350 been observed that,
02713 verify the requirement of SAES-H-001, Para-6.2: Toolbox meeting will be delivered to site construction
ARO and CANUSA
Coatings and thinners shall be stored in well-ventilated representative. Subsequently, CPP quality department
materials kept
buildings at storage temperatures as recommended in will firmly monitor to avoid recurrence.
the Manufacturer's data sheet.

Page 8 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis:
During surveillance visit to the site- HRDH-1171 &
Negligence of construction team.
HRDH-922, It has been observed that externally FBE
Correction Action:
coated pipes were been stored/strung on the heap of
During surveillance visit Re arrange the pipes to protect the External FBE
big and uneven stones and not stacked in a proper
to the site- HRDH-1171 coating. Effected coating damage area (If any) shall be
T-CPP- manner. It may lead to the external coating damage of
CPP-NGCP-NCR-M-005 & HRDH-922, It has Mohammad marked for repairing prior to lowering. Marl supports full
37 NA ARAMCO- Mechanical SAES-L-450 para 8.3 the pipes. Purpose of nylon string around the pipe was 24-Apr-19 09-May-19 29-Apr-19 Closed
EPM-INCR#6600002387 been observed that Umair of big stones to be corrected by sweet sand or sand
02714 failed due to the metal surface contacts each other.
externally FBE coated bags to protect the pipe coating which was contacted
This is a violation of SAES-L-450 para 8.3 requirement.
pipes with stones.
This standard requires the pipe stacking shall be made
Corrective Action:
in a manner, which will not damage the pipe or the
Quality toolbox meeting and QC monitoring while pipe
coating.
storage and rectify immediately.

Root Cause Analysis:


Lack of monitoring all sites by construction team.
Correction Action:
During surveillance visit to the site at HRDH-1171, It
During surveillance visit CPP to secure ends of the pipe string with durable
has been observed that welded string endcap in
to the site at HRDH- endcaps.
T-CPP- torn/open condition from KM-2.462 TO KM-2.678, KM-
CPP-NGCP-NCR-M-006 1171, It has been Corrective Action:
38 NA ARAMCO- Mechanical SAES-L-450 para 11.4 2.870 TO KM-3.201 & KM-3.237 TO KM-3.250. This is Masood Fareed 25-Apr-19 09-May-19 07-May-19 Closed
EPM-INCR#6600002357 observed that welded Quality awareness toolbox meeting and QC frequent
02714 a violation of SAES-L-450 para 11.4 requirement. This
string endcap in monitoring to avoid repeated violation.
standard requires open ends of pipeline strings shall be
torn/open General Reply:
capped to prevent entry of debris or animals and birds.
End caps been provided. Corrective action done hence,
this INCR can be
closed.A scan copy of closed INCR is uploaded.

Root Cause Analysis:


Clearing was not done completely because construction
personnel are on rush to proceed Compaction &
backfilling immediately to gain accomplishment.
Corrective Action:
Conduct clearing on the surface of area to receive
During site Surveillance During site Surveillance on 25-April-2019 at Wellhead
backfill until all visible trash is removed.
on 25-April-2019 at HRDH-1189 it was observed that the Area to received
Preventive Action:
T-CPP- Wellhead HRDH-1189 it fill was not cleaned properly from garbage. This is a
CPP-NGCP-NCR-CIV-017 Construction team informed to obey Saudi Aramco
39 NA ARAMCO- Civil was observed that the SAES-A-114 Sec. 6.2.1 clear violation to SAES-A-114. Sec. 6.2.1 which states Christian Valdez 25-Apr-19 30-Apr-19 28-Apr-19 Closed
EPM-INCR-6600002373 standard requirements even for rush work is not an
02712 Area to received fill was that: “Areas to receive fill, foundations, or pavement
excuse to violate the standards. Engineers and foreman
not cleaned properly shall be free of organic material, trash, or other
is informed that they are responsible to make sure that
from garbage. unsuitable material.”
the site is thoroughly cleaned before the backfilling
commence to avoid the same violation in the future.
General Reply:
Corrective action completed and verified by SAPID. scan
copy of closed
INCR is uploaded. Hence, please close this INCR.

Root Cause Analysis:


During surveillance visit to the site at HRDH-922, It has
Negligence of construction team.
T-CPP- During surveillance visit been observed that welded string line pipe not in the
CPP-NGCP-NCR-M-007 IFC alignment Mohammad Correction Action:
40 NA ARAMCO- Mechanical to the site at HRDH- TA-843609-003. drawing specified center. From KM-1+995 TO KM- 25-Apr-19 09-May-19 04-Apr-19 Closed
EPM-INCR#6600002354 drawing Umair Re arrange the pipeline as per drawing.
02714 922, It has 2.010. This is a violation of the IFC alignment drawing
Corrective Action:
TA-843609-003.
Close QC monitoring prior to start any welding activity.

Root Cause Analysis: Due to heavy sand storm the


slope erosion caused the collapse of sides of trench.
Correction Action: The CPP construction team shall
remove all the eroded material from subject station to an
During daily site visit on date 29-APR-2019 at HWYH
extent where clean sand is exposed. Furthermore, the
1088 at station 0+070 to 0+120, it was observed that
uring daily site visit on pipe shall be backfilled with clean sand after confirmation
due to heavy sandstorm side slope is eroded and fell
date 29-APR-2019 at of CPP QC inspector.
T-CPP- down on sides of pipe which contain stones larger size
CPP-NGCP-NCR-CIV-018 HWYH 1088 at station Corrective Action: CPP site QC shall deliver a quality
41 NA ARAMCO- Civil SAES-L-450 sec 14.9.3 than 12 mm. This non conformity as per the SAES-L- Taseer Khan 29-Apr-19 11-May-19 09-May-19 Closed
EPM-INCR-6600002447 0+070 to 0+120, it was tool box meeting to guide the site engineer and site
02712 450 sec 14.9.3 The pipe shall be embedded in clean
observed that due to foreman about the backfilling of top of pipe and follow
sand not less than 200 mm above the top of pipe in a
heavy the requirements of Saudi Aramco engineering
manner which shall not damage the coating. The sand
standards SAES-L-450.
shall not contain stones larger than 12 mm size.
General Reply:
Corrective action implemented and verified.Scan copy of
closed INCR is uploaded. Hence, please close this INCR

Root Cause Analysis:


1. Due to improper pipe handling.
On 30th April 2019 while doing Material Receiving
2. Due to lake of awareness.
On 30th April 2019 Inspection of pipes (10”x 0438” WT) at location HWYH-
Correction Action:
T-CPP- while doing Material 206, It was observed on Pipes we found some coating
CPP-NGCP-NCR-M-008 Lokanadham The coating damage area shall be marked properly and
42 NA ARAMCO- Mechanical Receiving Inspection of SAES-H-200 Para 5.1.1 damage and stones in between pipes. Hence it is clear 02-May-19 16-May-19 14-May-19 Closed
EPM-INCR#6600002432 Koyila effected area shall be repair prior to lowering.
02714 pipes (10”x 0438” WT) standard violation as per SAES-H-200, Para 5.1.1, The
Corrective Action:
at location HWYH-206, coated pipe shall be handled at all times in a manner
For awareness to the worker, so that it could be happen
that prevents damage to the pipe.
again, toolbox meeting shall be conducted.

Root Cause Analysis: Construction team Ignored the


Standard Requirements.
During daily site visit on date 04-May-2019 at RH-GK
Correction Action: The subject 25th Layer shall be
Extension, it was observed that the Material (Select Fill)
scarified in order to Remove over size material from it
During daily site visit on being dumped for 25th Layer, which have over size
and CPP QC will verify before the compaction begin.
T-CPP- date 04-May-2019 at stones & boulders more than 50mm which is a violation
CPP-NGCP-NCR-CIV-019 Corrective Action: Construction team shall use the
43 NA ARAMCO- Civil RH-GK Extension, it SAES-A-114 Sec. 6.1.2.1. as per SAES-A-114, Sec. 6.1.2.1. which states that Hameed Ullah 04-May-19 07-May-19 07-May-19 Closed
EPM-INCR-6600002413 sieved & approved material from approved source before
02712 was observed that the “Select Fill or ‘Structural Fill’ shall be composed only of
placing at site. Subsequently, CPP quality department
Material (Select Fill) inorganic material and shall have 100% passing the 5
will firmly monitor the backfilling work.
cm (2 in) sieve and from 0 to 20% passing the No. 200
General Reply: Correction action implemeted and NCR
sieve”.
is closed. Scan copy of closed INCR is uploaded hence,
please close this INCR .

Root Cause Analysis: Careless workmanship from


On May 02, 2019, CPP QC noticed improper handling welding crew.
On May 02, 2019, CPP and storage of GTAW electrodes ER-70S-3 at HRDH- Correction Action: The contaminated rods are
T-CPP- QC noticed improper 902. The rods kept in wet place which violates SAES- discarded in the same time and not used for weld
CPP-NGCP-NCR-W-012
44 NA ARAMCO- Welding handling and storage of SAES-W-012 Appendix 2 W-012, Appendix 2, which states: All electrodes and Mohammad Saif 02-May-19 12-May-19 11-May-19 production. Closed
EPM-INCR-6600002362
02717 GTAW electrodes ER- wires shall be stored in sealed containers in a dry Corrective Action: Awareness toolbox will be
70S-3 at HRDH-902. environment. Any wires that have visible rusting or conducted to enhance welding crew performance and
contamination shall not be used and shall be discarded. improve their knowledge of handling and storing of
welding consumables as per SAES-W-012 requirement.

Page 9 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: Construction team did not follow


the requirements of SAES-L-450 SEC 14.5
Correction Action: The CPP construction team shall
During daily site visit on date 28-APR-2019 at HWYH
put the sand bags beneath the pipe on every 3 meter to
1134, it was observed that the CPP construction team
During daily site visit on avoid the unsupported length and CPP QC will verify it.
lowered the pipe in HWYH-1134 sta@ 3+009 to 3+ 030
date 28-APR-2019 at Corrective Action: CPP site QC shall deliver a quality
T-CPP- which have unsupported length more the 3 meter which
CPP-NGCP-NCR-CIV-020 HWYH 1134, it was tool box meeting to guide the site engineer and site
45 NA ARAMCO- Civil SAES-L-450 sec 14.5 is clear violation as per SAES-L-450 sec 14.5 prior to Taseer Khan 05-May-19 20-May-19 09-May-19 Closed
EPM-INCR-6600002495 observed that the CPP foreman about the unsupported length and follow the
02712 backfilling and during lowering the pipeline shall be
construction team requirements of Saudi Aramco engineering standards
supported inside the trench with a maximum allowable
lowered the SAES-L-450
unsupported length 3 meter (m) Any voids below the
General Reply:
pipe shall be carefully backfilled.
Corrective action implemented and verified.Scan copy of
closed INCR is uploaded. Hence, please close this INCR

On May 5, 2019 CPP QC observed during site Root Cause Analysis: Negligence and Lack of
On May 5, 2019 CPP
inspection at HWYH RH EJ 16” X 0.438” FBE coated awareness.
QC observed during
T-CPP- pipes are directly touching with the sand, This is clear Correction Action: Re arrange the pipes with proper
CPP-NGCP-NCR-M-009 site inspection at
46 NA ARAMCO- Mechanical SAES-L-450 para 8.3 violation of SAES-L-450 para 8.3, this standard requires Masood Fareed 05-May-19 20-May-19 19-May-19 support to protect the external FBE coating, mark any Closed
EPM-INCR#6600002452 HWYH RH EJ 16” X
02714 the pipe stacking shall be made in a manner which will coating damage for repairing before lowering.
0.438” FBE coated
not damage the pipe or the coating. The pipe joints shall Corrective Action: Close monitoring by QC, awareness
pipes are directly
not laid directly on the ground. tool box meeting.

Page 10 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis:


Separation pads or ropes fall down during transportation.
Correction Action:
On May 6, 2019, CPP QC observed during site
Separation pads shall be provided; twelve-meter (12 m)
On May 6, 2019, CPP inspection at HRDH RH GK 16” X 0.438” FBE coated
joints of pipe shall have at least 3 full encirclement
T-CPP- QC observed during pipes found without encirclement separation pads. This
CPP-NGCP-NCR-M-010 Mohammad separation pads.
47 NA ARAMCO- Mechanical site inspection at HRDH SAES-H-200 PARA 5.2.2 is clear violation of SAES-H-200 PARA 5.2.2, this 06-May-19 22-May-19 20-May-19 Closed
EPM-INCR#6600002527 Umair Corrective Action:
02714 RH GK 16” X 0.438” standard requires the FBE pipes shall not be stacked
Material coordinator make sure all the separation pads
FBE coated pipes found directly against each other at any time during storage or
prior to transportation and QC inspector to monitor
transportation.
during offloading. Coating damage area (If any) shall be
marked properly and effected area shall be repair prior to
lowering.

Root Cause Analysis: Construction team carrying the


During routine site surveillance on 7th may at RH-CJ it unscreened material from stockpile and did not follow the
During routine site was found that construction team started backfilling of requirements of SAES-A-114.
surveillance on 7th may RH-CJ 1ST layer ( Zone C) with a material which Correction Action: Construction team shall remove all
T-CPP-
CPP-NGCP-NCR-CIV-021 at RH-CJ it was found contains over size stones. This is a clear violation of the oversize stones from site and CPP QC will verify
48 NA ARAMCO- Civil SAES-A-114 sec 6.1.2.1 Aamir Solangi 07-May-19 20-May-19 20-May-19 Closed
EPM-INCR-6600002545 that construction team SAES-A-114-sec 6.1.2.1 which states that “Select Fill or before the compaction begin.
02712
started backfilling of ‘Structural Fill’ shall be composed only of inorganic Corrective Action: Construction shall take the screened
RH-CJ material and shall have 100% passing the 5 cm (2 in) material from approved stockpile before placing it at site
sieve and from 0 to 20% passing the No. 200 sieve more over CPP QC will firmly monitor the backfilling
work.

During site Surveillance on date 09-MAY-2019 at Root Cause Analysis: The Centerline of pipe was
HRDH-GGM TO RH-CK(10”F/L) it was observed that staked by surveyor, but Construction did not provide
the Excavated Trench is not matching the Centerline of continuous white marking for excavation of Trench.
Pipe as indicated on the IFC Drawing from Correction Action: Construction team shall provide the
Sta:0+511,567,839,984,1070,1196,1297,1396,1849,211 approved redline drawings from SAPMT as per trench
During site Surveillance
1,2186,2244,2313 and Various which is a violation as excavated at site.
T-CPP- on date 09-MAY-2019
CPP-NGCP-NCR-CIV-022 per SAES-L-450,Sec. 7.1.1 which states that” The Corrective Action:
49 NA ARAMCO- Civil at HRDH-GGM TO RH- SAES-L-450 Sec. 7.1.1 Hameed Ullah 13-May-19 13-Jun-19 11-Jun-19 Closed
EPM-INCR-6600002569 pipeline route as stipulated on the Issued for When Ever centerline of pipe marking for trench is
02712 CK(10”F/L) it was
Construction (IFC) drawings shall be surveyed and missing at site, it shall be informed to surveyor to provide
observed that the
staked by the Construction Contractor. Changes to centerline marking again in order to avoid double work.
original routing may be acceptable with prior approval Provide continue white marking for centerline of trench
by Saudi Aramco PMT and the Proponent and surveyor has to checked on daily basis in order to
Representative prior to implementation in the form of avoid rework.
Modified IFC Drawings.”

Root Cause Analysis: Construction team was


During daily site visit on date 13-May-2019 at Hawiyah transporting unapproved un-screened material from the
well pad RH-GK, it was observed that the Material stockpile.
During daily site visit on
(General fill) being dumped for the 6th Layer Zone-D Correction Action: The subject 6th Layer shall be
date 13-May-2019 at
T-CPP- have unapproved over size stones & boulders more scarified in order to Remove unapproved over size
CPP-NGCP-NCR-CIV-023 Hawiyah well pad RH-
50 NA ARAMCO- Civil SAES-A-114 Sec. 6.1.1.1. than 75mm which is a violation as per SAES-A-114, Taseer Khan 13-May-19 13-Jun-19 13-Jun-19 material from it and CPP QC will verify before the Closed
EPM-INCR-6600002534 GK, it was observed
02712 Sec. 6.1.1.1. which states that General Fill Material compaction begin.
that the Material
shall consist of gravel, sand and/or marl. The maximum Corrective Action: Construction team shall take
(General fill)
size of the fill material shall be one-half the lift thickness screened material from approved source before placing
or 75 mm (3 inches), whichever is less. at site. Subsequently, CPP quality department will firmly
monitor the backfilling work.

Root Cause Analysis:


Due to Ignorance of construction crew, some sand
padding areas are missed to place polyethylene
protective sheets and because of that reason, Pipe
touched the ground.
Correction Action:
During site surveillance at HWYH-1055 welded string
All the sand padding areas of subjected pipes has to be
During site surveillance Km 0+781 to Km 1+806, It has been observed that
placed proper Polyethylene sheeting under temporary
at HWYH-1055 welded some of the pipes are touching ground at sand padding
T-CPP- Aimon Iqbal tire supports and the areas shall be holiday tested and
CPP-NGCP-NCR-H-005 string Km 0+781 to Km area due to absence of polyethylene sheeting. This is
51 NA ARAMCO- Coating SAES-H-200 Para 5.2.1 Sharif 15-May-19 30-May-19 30-Jun-19 clearly marked for any damage occurred, and shall be Closed
EPM-INCR-6600002588 1+806, It has been clearly a violation of SAES-H-200, Para 5.2.1 which
02713 repaired before Lowering.
observed that some of stated that “Coated pipe shall be placed at-least 150
Corrective Action:
the mm off the ground on either rock free sand berms
A tool box meeting has to be given to Civil Construction
covered with polyethylene sheeting.
crew on the importance of Saudi Aramco Engineering
Standards and project requirements to prevent re-
occurrence of such issues.
General Reply:Correction action implemented and
verified. Scan copy of closed INCR is uploaded. Hence,
please close this INCR.

Root Cause Analysis: Careless workmanship and lack


During site surveillance on date 27 Apr-19 it was of awareness/knowledge.
observed that HWYH-WH # 1071 F/L KM-1+083 CPP Correction Action:
During site surveillance
installed 60 Lbs. Magnesium anode and does not CPP Cathodic protection Construction team to comply
on date 27 Apr-19 it
CPP-NGCP-NCR-E-002 T-CPP- comply with the minimum distance requirements which the standard drawing AA-036352, Note-2.
was observed that Standard Muhammad
52 EPM-INCR-6600002435 NA ARAMCO- Electrical/CP AA-036352 is only 300mm from pipe to anode. This is clear 28-Apr-19 13-May-19 06-May-19 Corrective Action: Closed
HWYH-WH # 1071 F/L drawing Amin
02716 violation of standard drawing AA-036352, Note-2. A quality tool box meeting will be delivered to site
KM-1+083 CPP
Which states that the distance from pipeline to be construction team in order to increase the quality
installed 60 Lbs.
600mm MIN. Multiple anodes to be installed on 1500 awareness. Subsequently, quality department will
minimum center. enhance the site surveillance to avoid recurrence.

During site visit at HWYH-1036 on Date-20-May-2019,


Root Cause Analysis: Careless workmanship from the
joint number (03-FW-305) Welder (CPP-W-059) it was
welders.
During site visit at observed that the welding was ongoing with tent but
Correction Action: 100% Radiography shall be done of
HWYH-1036 on Date- door was opened during welding as per attached picture
T-CPP- joint number 03-FW-305 to ensure soundness of
CPP-NGCP-NCR-W-013 20-May-2019, joint which is a standard violation as per SAES-W-012 Para
53 NA ARAMCO- Welding SAES-W-012 Para 10.2.1 Imran Manzoor 20-May-19 10-Jun-19 01-Jun-19 welding. Closed
EPM-INCR-6600002631 number (03-FW-305) 10.2.1 which states that Wind shields or tents shall be
02717 Corrective Action: Weld tent shall be closed from all
Welder (CPP-W-059) it required when wind is strong enough to affect arc
sides during welding, especially when wind speed is
was observed stability or when deemed necessary by Saudi Aramco
high. Site QC to monitor closely for standard compliance
Inspection.
especially for strong windy days.

Page 11 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: Construction team followed the


typical rocky area drawing and failed to maintain the
trench depth as per wadi area drawings. Another reason
is that Construction Team is waiting for New Revision of
Drawings in which wadi area will be Eliminated from IFC
During daily site visit on date 25-MAY-2019 at HRDH drawings.
1164, it was observed that trench depth at km 0+380 Correction Action: Construction team shall excavate
During daily site visit on
TO 0+676,1+085 TO 1+292,4+399 TO 4+696 is 1m more at all wadi areas according to the Wadi Area Cross
date 25-MAY-2019 at
CPP-NGCP-NCR-CIV-024 which is not meeting the wadi area crossing drawings. Section Drawing TA-017571 Or Provide New Revision of
54 Civil HRDH 1164, it was IFC drawings TA-017571-001 Hameed Ullah 25-May-19 17-Jul-19 17-Oct-19 Closed
EPM-INCR-6600002775 The actual trench depth provided at site clearly violates Drawings in which wadi area is Eliminated from the
observed that trench
the Typical Wadi Area Crossing Detail Drawing-TA- drawings.
depth at km 0+380 TO
017571-001 “which shows that the total trench depth Corrective Action: Construction team shall Review the
shall be 300mm+DIA+1200mm” Plan and Profile drawings before proceeding to
Excavation and follow the detail Cross section drawings
for specific areas accordingly. Other than that
Construction team shall communicate with PMT or
Designer prior to beginning Trench excavation in order to
Avoid misconceptions in such areas.

On May 26, 2019, CPP QC noticed 86 joints welded


with wrong thickness at 8″-HRDH-1164 and 8″-HRDH-
1160, The actual thickness is 0.344″ which violates the
IFC DWG requirement 0.375″Details:
1- 8″-HRDH-1164
• 6 Joints from 4.772 to 4.833 KM – Joints 04-FW-384 Root Cause Analysis: Construction and QC inspectors
To 04-FW-389. missed the IFC DWG requirement.
On May 26, 2019, CPP
• 28 Joints from 5.462 KM to 5.637 KM – Joints 05-FW- Mohamed Correction Action: TQ will be submitted to engineering
QC noticed 86 joints
440 To 05-FW-467. Othman to “USE AS IS” either the welded string will be cut to
CPP-NGCP-NCR-W-014 welded with wrong
55 Welding IFC DWG IFC DWG 2- 8″-HRDH-1160 26-May-19 26-Jul-19 17-Sep-19 proper length and adjust in other line location. Closed
EPM-INCR-6600002769 thickness at 8″-HRDH-
• 7 Joints from 1.957 to 2.053 KM – Joints 01-FW-137 Corrective Action: Warning letter will be issued for
1164 and 8″-HRDH-
To 01-FW-143. responsible person and awareness Toolbox training will
1160,
• 3 joints from 2.001 to 2.026 KM – Joints 01-FW-157 be conducted to prevent future recurrence, Site QC to
To 01-FW-159. monitor closely to follow IFC DWG requirement.
• 21 Joints from 2.135 to 2.382 KM – Joints 01-FW-168
To 02-FW-188.
• 21 Joints from 2.722 to 2.969 KM – Joints 02-FW-216
To 02-FW-236

Page 12 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: Construction unloaded the FBE


rebar temporary in storage yard and planned to transport
it to pre-cast yard that’s why poor planning from
construction team as there was no Proper Care and
padding for FBE Coated Rebar was provided before
During Routine Visit on date 27-MAY-2019 at CPP
arrival of rebar in storage yard. Hence FBE coated rebar
During Routine Visit on Storage Yard located at TCF- 1 it was observed that the
unloaded directly on ground.
date 27-MAY-2019 at FBE coated rebar (16mm and 10mm) for pipe support Faisal Atta
T-CPP- Correction Action: Construction team shall provide
CPP-NGCP-NCR-CIV-025 CPP Storage Yard 09-SAMSS- foundations PS-01,02,04,05 & 06 was placed directly on
56 NA ARAMCO- Civil Sec. III.B 27-May-19 10-Jun-19 16-Jun-19 Ribs or appropriate padding which can keep the FBE Closed
EPM-INCR-6600002762 located at TCF- 1 it was 106 the ground which is a violation as per 09-SAMSS-106-
02712 Rebars off the Ground.
observed that the FBE Sec. III.B Which states that” Coated steel reinforcing
Corrective Action:
coated bars shall be stored off the ground on protective
Material storage responsible personnel shall make
cribbing. (ASTM A775/A 775-07b, Sec. 15.3)”
enough arrangements for proper storage and
preservation of material prior to delivery or at least arrival
of material. CPP quality department will keep monitoring
the material storage and preservation to improve its
quality.

Root Cause Analysis: Careless workmanship from


On May 28, 2019, CPP QC noticed after root pass
welding crew.
On May 28, 2019, CPP cpmpletion the pipe was laid on the pads without Mohamed
Correction Action: Joint 05-FW-421 shall be 100%
T-CPP- QC noticed after root completing hot pass at HRDH-1171 F/L joint # (05-FW- Sarfaraz
CPP-NGCP-NCR-W-015 radiograph to ensure integrity/ soundness of joint.
57 NA ARAMCO- Welding pass cpmpletion the SAES-W-012 Para 10.7.3 421) Welder (CPP-W-090) which is a standard violation 29-May-19 19-Jun-19 19-Jun-19 Closed
EPM-INCR-6600002818 Corrective Action: Awareness toolbox training will be
02717 pipe was laid on the as per SAES-W-012 (Para 10.7.3) which states that
conducted to prevent future
pads without “The hot pass shall be made while the pipe is still fully
recurrence, Site QC to monitor closely to follow standard
supported by the Side boom tractor or supports”.
requirement.

Root Cause Analysis: Construction team did not follow


the requirements of Schedule Q and failed to re-calibrate
the equipment due to workload.
Correction Action: The subject total station shall be
During routine site surveillance on May 29th at well pad
sent to lab for re-calibration. As a replacement, any other
RH-CJ it was found that construction team using
uring routine site total station shall be used with a valid calibration
expired calibration total station model no SET550X
surveillance on May certificate.
T-CPP- SERIAL NO 102939. This is a clear violation as
CPP-NGCP-NCR-CIV-026 29th at well pad RH-CJ attachment IV Corrective Action: Construction shall follow the
58 NA ARAMCO- Civil Schedule Q Schedule Q attachment IV para no 7.1. Which states Aamir Solangi 29-May-19 15-Jun-19 14-Jun-19 Closed
EPM-INCR-6600002811 it was found that para no 7.1 requirement of Schedule Q attachment IV para no 7.1
02712 that “The CONTRACTOR shall identify, maintain,
construction team using and any equipment used at site shall be included in the
control, adjust, and calibrate all tools, gauges,
expired calibration monitoring log.
instruments and other measuring and testing devices
To select row, press SPACEBAR
used for controlling quality”.
General reply:orrective action implemented and INCR
closed. Please find the scan copy
of INCR uploaded.

Root Cause Analysis:


Negligence and lack of awareness.
On May 30, 2019 CPP QC observed during pipe
On May 30, 2019 CPP Correction Action:
inspection at TCF-1 yard, FBE coated pipes 8” & 16”
QC observed during Re arrange the pipes with proper support to protect the
T-CPP- pipes are directly touching with the sand, This is clear
CPP-NGCP-NCR-M-011 pipe inspection at TCF- Muhammad external FBE coating, mark any coating damage for
59 NA ARAMCO- Mechanical SAES-L-450 para 8.3 violation of SAES-L-450 para 8.3, this standard requires 30-May-19 13-Jun-19 12-Jun-19 Closed
EPM-INCR#6600002819 1 yard, FBE coated Saleem repairing before lowering
02714 the pipe stacking shall be made in a manner which will
pipes 8” & 16” pipes are Corrective Action:
not damage the pipe or the coating. The pipe joints shall
directly Close monitoring by QC, Awareness tool box meeting.
not laid directly on the ground.
General Reply:Corrective action implemented and NCR
is closed. Scan copy of closed INCR is uploaded.

During site surveillance on 30- May-19 HRDH-WH #


Root Cause Analysis:Using the prolonged and
611 (F/L KM-1+000) it was noticed that, Thermite weld
damaged cad weld mold.
slag have more sharp edges and we conducted the
Correction Action:
During site surveillance strength test by lightly tapping top of the weld with one-
Replace physically damaged cad weld mold and use
on 30- May-19 HRDH- pound hammer and it the weld point failed. This is clear
CPP-NGCP-NCR-E-003 T-CPP- new mold by prepared new pipe surface 75mm from the
WH # 611 (F/L KM- Standard AA-036381, violation of standard drawing AA-036381, Note-4, Muhammad
60 EPM-INCR-6600002836 NA ARAMCO- Electrical/CP 01-Jun-19 15-Jun-19 13-Jun-19 original attempt. Closed
1+000) it was noticed drawing Note-4 Which states that test strength of connection by lightly Amin
02716 Corrective Action:
that, Thermite weld slag tapping top of the weld with one-pound hammer if weld
Contractor be ensure that prior to use cad meld mold in
have fails and must be repeated, a new pipe surface must be
good condition and shall not exceed the cad weld
prepared at least 75mm from the original weld attempt.
connections limit as per the manufacturer instruction.
More than one weld attempt on the same spot shall not
be permitted.

On May 29, 2019, CPP QC noticed welder no CPP-W-


109 at HRDH-AK-RH TR/L joint # (03-FW-279) got one
repair from one of his initial production welds, as a
tracer welded he welded 3 joints in place of 2 (joint # Root Cause Analysis:misunderstanding of SEAP-324
(03-FW-279).Welding of any additional joint before requirement from welding crew.
clearing the tracer welds (2 joints) is a standard Correction Action:Welder stopped until final RT result
T-CPP- Improper weld tracer of
CPP-NGCP-NCR-W-016 violation as per SAES-W-012 (Para 6.1.8) which states of IP joints and Joint 03-FW-279 shall be 100%
61 NA ARAMCO- Welding initial production joints SAES-W-012 Para 6.1.8 Irshad Ahmed 30-May-19 19-Jun-19 17-Jun-19 Closed
EPM-INCR-6600002752 that “The first three (3) production butt welds made by radiograph to ensure integrity/ soundness of joint.
02717 at HRDH-AK-RH TR/L
each new welder, regardless of welding process, shall Corrective Action:Awareness toolbox training will be
be 100% examined by the applicable NDE method. conducted to prevent future recurrence, Site QC to
NDE acceptance shall be as specified by the applicable monitor closely to follow standard requirement.
Code. Decision path for evaluation of the first three (3)
production welds is illustrated in Appendix III.”.

Root Cause Analysis:Careless workmanship from


On May 29, 2019, CPP QC noticed during routine
welding crew.
surveillance that the pipe end was open during welding
Correction Action:End cap has been fixed and joint 00-
T-CPP- Improper shielding root and hot pass at HRDH-1128 joint # (00-FW-060)
CPP-NGCP-NCR-W-017 FW-060 will be covered by 100 % RT.
62 NA ARAMCO- Welding during welding at SAES-W-012 Para 10.2.3 which is a standard violation as per SAES-W-012 (Para Mohammad Saif 01-Jun-19 25-Jun-19 17-Jun-19 Closed
EPM-INCR-6600002867 Corrective Action:Awareness toolbox training will be
02717 HRDH-1128 10.2.3) which states that “Contamination from the
conducted to prevent future
environment, such as wind-blown sand, shall be
recurrence, Site QC to monitor closely to follow standard
prevented by the use of adequate shielding.
requirement

On June 12, 2019, CPP QC noticed during routine


surveillance that the pipe coating was damaged with Root Cause Analysis: Pipe hit with side boom during
side boom during shifting at 24’’-HWGCP-1-T/L SWEET lifting. Correction Action: Touch up will be done for
T-CPP-
CPP-NGCP-NCR-W-018 Pipe coating damage Joint # (T/L-DJ-11) which is a standard violation as per damage area and will be verified by holiday test.
63 NA ARAMCO- Welding SAES-W-012 (Para 10.15 Junaid Zafar 12-Jun-19 12-Jul-19 10-Jul-19 Closed
EPM-INCR--6600002986 during lifting SAES-W-012 (Para 10.15) which states that “coated Corrective
02717
and clad or overlaid surface shall be protected from the Action: Awareness toolbox will be conducted to care
welding arc, associated weld spatter, and damage from material coating during handling and lifting
ground clamps or other associated equipment”.

On June 13, 2019 CPP QC observed during inspection


at HRDH-902 lowered string Between joints FW-154
and FW-155 at location of KM 1+990 the coated pipe
T-CPP- Root Cause Analysis: Due to sand storm and high wind
CPP-NGCP-NCR-M-012 Coated pipe directly directly exposed after backfilling. This is clear violation Muhammad
64 NA ARAMCO- Mechanical SAES-L-450 Para 14.9.3 13-Jun-19 12-Jul-19 06-Jul-19 the pipe sand cover had blown away from the subject Closed
EPM-INCR#6600002907 exposed of SAES-L-450 para 14.9.3, this standard requires the Umair
02714 location.
pipe shall be embedded in clean sand not less than 200
above the top of pipe in a manner which shall not
damage the coating.

Page 13 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis: No Borrow Pit has been sampled
During daily site visit on date 15-06-2019 at HRDH or submitted for testing of Marl Capping material.
1170, it was observed that Berm Construction is Correction Action: Material used for
Unapproved Marl
T-CPP- ongoing for 8” F/L but Marl material which construction berm and capping construction shall be sampled and
CPP-NGCP-NCR-CIV-027 Material used for berm
65 NA ARAMCO- Civil SAES-L-450 is using for Capping is not approved. Which is a clear Hameedullah 15-Jun-19 27-Jun-19 27-Jun-19 tested by third party. This material shall pass the marl Closed
EPM-INCR#6600002957 construction and
02712 violation as per SAES-L-450-Sec. 14.10.3 which states classifications.
Capping at HRDH-1170
that “The entire dike shall be stabilized with marl of 152 Corrective Action: Construction team shall sample the
mm minimum depth.” material for testing prior to use it on site in order to avoid
any re-work.

On June 13, 2019, CPP QC noticed during routine


surveillance that the welder left electrodes in the quiver
Root Cause Analysis: Power of electrode oven switch
during lunch time and power was switch off, the
off during lunch time.
temperature was below 65°C and the exposure time
T-CPP- Welding electrodes
CPP-NGCP-NCR-W-019 exceed 2hr at 8" HRDH-1153 F/L which is a standard
66 NA ARAMCO- Welding exceed exposure time SAES-W-012 Appendix 1 Yavar Shadab 13-Jun-19 30-Jun-19 06-Jul-19 Corrective Action: Awareness toolbox will be Closed
EPM-INCR-6600003005 violation as per SAES-W-012 (Appendix 1) which states
02717 @ 8" HRDH-1153 F/L conducted to avoid power switching off if the ovens filled
that “The exposure times may be doubled (to 4 hours
by electrodes. Correction Action: The
and 1 hour, respectively) if the electrodes are
affected electrodes are discarded.
continuously stored in a portable electrode oven heated
to 65°C minimum”.

On Jun 12, 2019, CPP QC noticed an arc strike during


the welding activities of joint no. 03-FW-252 at 16" Root Cause Analysis: Improper fixing of grounding
HWYH CK-RH TR/L. This violates SAES-W-012, 10.10, clamp Correction Action: Grinding the
T-CPP- Improper fixing of which states: Arc strikes, gouges, and other indications defected area to remove the arc strike and apply PT test.
CPP-NGCP-NCR-W-020 SAES-W-012,
67 NA ARAMCO- Welding grounding clamp @ 16" Para 10.10 of careless workmanship (such as surface porosity, Abdul Raheem 12-Jun-19 12-Jul-19 06-Jul-19 Closed
EPM-INCR-6600003015 10.10
02717 HWYH CK-RH TR/L uneven weld profiles, and undercut) shall be removed Corrective Action: Proper fixing of grounding clamp
by grinding. and replacing the clamp material by same pipe material
shall be provided for further fit-up and welding activities.

On Jun 12, 2019, CPP QC noticed The pipe bevel was


Root Cause Analysis: Careless workmanship from
not properly cleaned prior to welding the weld joint 01-
welding crew.
FW-98 at 8” HRDH-1195 F/L. This violates SAES-W-
Correction Action:
T-CPP- Improper joint cleaning 012, 10.3.1, which states: Oil, moisture, rust, scale,
CPP-NGCP-NCR-W-021 Joint 01-FW-098, shall be 100% radiograph to ensure
68 NA ARAMCO- Welding prior to welding @ 8" SAES-W-012 Para 10.3.1 sand, paint metallic coatings (e.g., zinc), or other foreign Mohammed Saif 12-Jun-19 12-Jul-19 07-Jul-19 Closed
EPM-INCR-6600003025 integrity/ soundness of weld.
02717 HRDH-1195 F/L matter shall be removed from the weld surface and at
Corrective Action: Awareness Toolbox training
least 25 mm of adjacent base metal prior to welding,
will be conducted to prevent future recurrence, Site QC
including any such coatings on temporary attachments
to monitor closely to follow standard requirement.
or supports.

On Jun 12, 2019, CPP QC noticed the pipe bevel was Root Cause Analysis: Careless workmanship from
not properly cleaned prior to welding the weld joint 06- welding crew.
FW-531 at 8'' HRDH 1171 F/L. This violates SAES-W-
T-CPP- Improper joint cleaning 012, 10.3.1, which states: Oil, moisture, rust, scale, Correction Action: Joint 06-FW-0531, shall be 100%
CPP-NGCP-NCR-W-022 Mohammed
69 NA ARAMCO- Welding prior to welding @ 8'' SAES-W-012 Para 10.3.1 sand, paint metallic coatings (e.g., zinc), or other foreign 12-Jun-19 12-Jul-19 13-Jun-19 13-Jun-19 radiograph to ensure integrity/ soundness of weld. Closed
EPM-INCR-6600002968 Sarfaraz
02717 HRDH 1171 F/L matter shall be removed from the weld surface and at Corrective Action: Awareness Toolbox
least 25 mm of adjacent base metal prior to welding, training will be conducted to prevent future recurrence,
including any such coatings on temporary attachments Site QC to monitor closely to follow standard
or supports. requirement.

Root Cause Analysis:


Welded pipe sting settled down due to weight and
touched to the marl pad. Smaller rubber sheets keeping
On May 30, 2019 CPP QC observed during site
stones as a pipe stopper is carelessness from site
inspection at HRDH RH-CK, FBE coated 16” pipes are
foreman. Correction
string without rock-free sand, This is clear violation of
CPP-NGCP-NCR-M-013 T-CPP- Action:
Sting pipes laid without SAES-H-200 para 5.3, this standard requires the Muhammad
70 EPM # INCR- NA ARAMCO- Mechanical SAES-H-200 Para 5.3, 16-Jun-19 30-Jun-19 30-Jun-19 1) Remove stone from marl padding. Closed
rock-free sand Externally coated line pipe strung along the right-of-way Umair
6600003006 02714 2) Use longer rubber sheets.
shall be supported on rock-free sand, sand bags, rubber
3) Use wood pieces as a stopper.
tires, or similar compressible material to prevent coating
Corrective Action:
damage
Quality awareness toolbox meeting and QC frequent
monitoring to avoid repeated violation.

During site surveillance on date 23 Jun-19 it was


Root Cause Analysis:Careless workmanship and lack
observed at the location of HRDH-WH # 902 F/L KM-
of awareness/knowledge.
3+400 CPP Construction installed the 60 Lbs.
Correction Action:
Magnesium anode which is not compliance with the
During site surveillance CPP Cathodic protection Construction team complete
CPP-NGCP-NCR-E-004 minimum requirements of backfilling and saturation of
T-CPP- on date 23 Jun-19 it the backfilling of magnesium anode and saturate with
EPM-INCR-6600003088 Standard AA-036352, Magnesium anode. This is clear violation with reference Muhammad
71 NA ARAMCO- Electrical/CP was observed at the 25-Jun-19 10-Jul-19 13-Jun-19 water during and after backfilling within the ACD. Closed
drawing Note-10 to standard drawing AA-036352, Note-10. Which is Amin
02716 location of HRDH-WH # Corrective Action:
clearly stated that the prepackaged anode thoroughly
902 F/L KM-3+400 CPP A quality tool box meeting will be delivered to site
saturated prior to, during and after backfilling. TAMP
construction team in order to increase the quality
backfill firmly around the anode.
awareness. Subsequently, quality department will
enhance the site surveillance to avoid recurrence.

Page 14 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis: Welder failed to comply
Correction Action: QC inspector
immediately instruct welder CPP-W-063 and other crew
On Jun 15, 2019, CPP QC noticed Welder W-063 welders to avoid recurrence. The defected area will be
Adjacent weld beads started the adjacent weld beads from the same location grinded and SAES-W-012 requirement for the welding of
T-CPP-
CPP-NGCP-NCR-W-023 started from the same Joint 00-FW-36 at 16" HWYH GK-RH TR/L. This adjacent beads will be followed. RT and hardness test
72 NA ARAMCO- Welding SAES-W-012 Para 10.17 Imran Manzoor 15-Jun-19 15-Jul-19 07-Jul-19 Closed
EPM-INCR-6600002991 location @ 16" HWYH violates SAES-W-012, Para 10.17, which states: will be done for joint 00-FW-36. Corrective Action:
02717
GK-RH TR/L. Adjacent weld beads shall be staggered and not started Awareness toolbox will be conducted to enhance welder
from the same location. skills and improve their knowledge of the SAES-W-012
requirement.

Root Cause Analysis: welder’s tendency to open the


tent door to avoid heat during high temperature weather
On Jun 18, 2019, CPP QC noticed that the welding
condition. Correction Action: wind shelter shall be
shelter was open during welding at HRDH-922 joint #
closed during welding and joint 00-FW-267T will be
T-CPP- Improper shielding (00-FW-267T) which is a standard violation as per
CPP-NGCP-NCR-W-024 Mohammed covered by 100 % RT Corrective Action:
73 NA ARAMCO- Welding during welding at SAES-W-012 Para 10.2.3 SAES-W-012 (Para 10.2.3) which states that 18-Jun-19 10-Jul-19 10-Jul-19 Closed
EPM-INCR-6600002984 Farhan Awareness toolbox training will be conducted to prevent
02717 HRDH-922 “Contamination from the environment, such as wind-
future
blown sand, shall be prevented by the use of adequate
recurrence, Site QC to monitor closely to follow standard
shielding”.
requirement.

Root Cause Analysis: pipe has been lifted by side


boom during tack welding
Correction Action:
The defected cracked tack weld has been removed by
On Jun 16, 2019, CPP QC noticed the tack weld had
grinding and new tack weld made before welding the
crack after fit-up completed at 16" HRDH AK-RH TR/L
joint. 100% MT & RT to be done for joint 01-FW-091 to
Joint 01-FW-091 This violates SAES-W-012, Para
T-CPP- verify weld soundness.
CPP-NGCP-NCR-W-025 Tack Weld cracked @ 10.9.4 which states: Tack welds that are to be
74 NA ARAMCO- Welding SAES-W-012 Para 10.9.4 Irshad Ahmed 16-Jun-19 10-Jul-19 10-Jul-19 Correction Action: The defected Closed
EPM-INCR-6600003055 16" HRDH AK-RH TR/L incorporated into the final weld shall be thoroughly
02717 cracked tack weld has been removed by grinding and
cleaned, prepared at each end, and inspected for
new tack weld made before welding the joint. 100% MT
cracks. Any crack shall be removed and another tack
& RT to be done for joint 01-FW-091 to verify weld
weld shall be made before welding the joint.
soundness.
Corrective Action: Awareness toolbox will be
conducted to enhance welding crew skills and improve
their knowledge of the SAES-W-012 requirement
On Jun 18, 2019, CPP QC noticed an arc strike during Root Cause Analysis: Improper condition and fixing of
the welding activities of joint no. 03-FW-263 at 8”- grounding clamp
T-CPP- HWYH-1023. This violates SAES-W-012, 10.10, which Correction Action: Grinding
CPP-NGCP-NCR-W-026 Arc strike at @ HWYH-
75 NA ARAMCO- Welding SAES-W-012 Para 10.10, states: Arc strikes, gouges, and other indications of ABDUL AJEEZE 18-Jun-19 10-Jul-19 07-Jul-19 the defected area to remove the arc strike and apply PT Closed
EPM-INCR-6600003043 1023
02717 careless workmanship (such as surface porosity, test, ground clamp to be fixed. Corrective
uneven weld profiles, and undercut) shall be removed Action: Proper fixing of grounding clamp shall be
by grinding. provided for further fit-up and welding activities.
Root Cause Analysis: Construction team is ignoring the
standard requirements of Borrow Pit.
Correction Action: Barricade the
During daily site visit on date 26-June-2019 at HRDH- Designated Borrow Pit area and provide safe access for
Borrow Pit#17 Near HRDH-1151 Well pad it was IN and OUT to avoid safety hazards
T-CPP- observed that there is no Barrier controlling access for
CPP-NGCP-NCR-CIV-028 Borrow Pit#17, Near
76 NA ARAMCO- Civil SAES-A-111 Sec-6.6 the Designated pit area which is a violation as per Hameedullah 26-Jun-19 15-Jul-19 08-Jul-19 Corrective Action: Closed
EPM-INCR#6600003106 HRDH-1151
02712 SAES-A-111-Sec-6.6 which states that “A pit shall have A toolbox meeting will be delivered to enhance the
a barrier controlling access and such barriers shall be awareness for borrow pit requirements to avoid any
clearly visible to prevent safety hazards to the public safety and quality issues. Subsequently, CPP quality
department will firmly monitor the site to avoid
recurrence

Root Cause Analysis: Construction Team just dumped


During daily site visit on date 25-06-2019 at HRDH the sand to cover the pipe only rather than provide a
1177, it was observed that the sand pad for the top of shaped and enough sand cover.
the pipe is not in proper shape which did not maintain Correction Action:
T-CPP- No Proper Sand Pad
CPP-NGCP-NCR-CIV-029 the required 200mm sand cover over the pipe top which Construction team shall make the proper shape of sand
77 NA ARAMCO- Civil Over the pipe at HRDH- SAES-L-450 Sec. 14.10.3e Aqib Hussain 26-Jun-19 17-Jul-19 17-Jul-19 Closed
EPM-INCR#6600003034 is a violation as per “SAES-L-450-Sec. 14.10.3e. A pad cover in order to fulfill the standard requirements and to
02712 1177
of selected bedding material shall be placed under and proper 200mm thick pad all around the pipe.
around the pipe to provide a minimum cover of 200 mm Corrective Action: A quality toolbox meeting will be
above the pipe.” delivered to site construction foreman in order to have
full understanding of sand padding as per SAES-L-450.

Root Cause Analysis: Construction Team did not follow


the centerline of the pipe and failed to maintain the
During daily site visit on date 26-06-2019 at HRDH standard width of berm.
1170, it was observed that Berm Construction is Correction Action: Construction team shall follow the
ongoing for 8” F/L at Station-KM-0+300 to KM-0+500 centerline of the pipe and after preparation of berm
Centerline of pipe for
T-CPP- but it is not exactly following the centerline (Top of Pipe) surveyor shall verify the centerline and width of berm
CPP-NGCP-NCR-CIV-030 berm Construction is
78 NA ARAMCO- Civil SAES-L-450 Sec. 14.10 of the pipe which is a clear violation as per SAES-L- Hameedullah 26-Jun-19 30-Jul-19 27-Jul-19 while berm inspection will be conducted. Closed
EPM-INCR#6600003092 not followed at HRDH-
02712 450-Sec. 14.10.3g which states that “The width of the Corrective Action: A toolbox meeting will be conducted
1170
flat top of the dike berm shall be at least twice the pipe to deliver the requirements for construction berm and
diameter along the overall minimum cover above the Construction team will use the stakes over the sand
top of the pipe.” cover to specify the centerline of pipe and berm
construction shall be then started in order to avoid
double work.

During daily site visit on date 25-June-2019 at HRDH-


Root Cause Analysis: The material was transferred to
Remote Header -GK Extension Work it was observed
site without screening
that Inappropriate Material being spread for the 30th
Correction Action: The
Layer (Zone A Part-1) which has over size Gravels up
T-CPP- subject 30th Layer shall be removed, and acceptable
CPP-NGCP-NCR-CIV-031 Backfill at RH-GK to 300mm which is a violation as per SAES-A-114-Sec.
79 NA ARAMCO- Civil SAES-A-114 Sec. 6.1.2.1 Hameedullah 26-Jun-19 15-Jul-19 01-Jul-19 Sieved Materials shall be placed. Corrective Closed
EPM-INCR#6600003014 HRDH 6.1.2.1. which states that “The amount of material
02712 Action:
passing the 50mm sieve shall be 100% for Select Fill
All the backfilling material shall be stocked through
Material.”
proper screening prior to dumping and spreading at site.

Page 15 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis:


Clearing was not done completely because construction
personnel are on rush to proceed Compaction &
backfilling immediately to gain accomplishment
Correction Action:
During site Surveillance on 26-June-2019 at Hawiyah
Conduct clearing on the surface of area to receive
Remote Header CJ zone F & G it was observed that the
backfill until all visible trash is removed.
Trash/garbage found on Area to received fill was not cleaned properly from
CPP-NGCP-NCR-CIV-032 Corrective Action:
80 Civil HRDH-1189 to received SAES-A-114. Sec. 6.2.1 garbage. This is a clear violation to SAES-A-114. Sec. Aamir Solangi 26-Jun-19 01-Jul-19 01-Jul-19 Closed
EPM-INCR#6600003126 Construction team informed to obey Saudi Aramco
backfill material. 6.2.1 which states that: “Areas to receive fill,
standard requirements even for rush work is not an
foundations, or pavement shall be free of organic
excuse to violate the standards. Engineers and foreman
material, trash, or other unsuitable material.”
is informed that they are responsible to make sure that
the site is thoroughly cleaned before the backfilling
commence to avoid the same violation in the future.

Root Cause Analysis:


During offloading of pipes from truck, construction
On June 26, 2019 CPP QC observed during site loaded 3 pipes at one time,Negligence and lack of
inspection at HWYH-1023 (10''X0.438'') pipes FBE awareness by construction team.
coating damaged due to improper lifting, This is clear Correction
CPP-NGCP-NCR-M-014 T-CPP- violation of SAES-H-200 para 5.1.1, This standard Action:
FBE. Coating damage K.LOKANADHA
81 NA ARAMCO- Mechanical SAES-H-200 para 5.1.1 requires the coated pipe shall be handled at all times in 26-Jun-19 10-Jul-19 07-Jul-19 The coating damage area shall be marked properly and Closed
due to improper liftin M
EPM-INCR#6600003091 02714 a manner that prevents damage to the pipe walls, effected area shall be repair prior to lowering.
beveled ends, and to the applied coatings. Corrective Action:
Quality awareness toolbox meeting and QC frequent
monitoring to avoid repeated violation.

Root Cause Analysis:


During transporting the cladded pipe plywood cap could
have removed from the pipe ends.
On June 26, 2019 at TCF1 Yard.During surveillance of Correction Action:
T-CPP- QC observed that 8” cladded pipe stored without end New Plywood cap shall be installed in both side of the
CPP-NGCP-NCR-M-015 Cladded pipe stored 01-SAMSS- Muhammed
82 NA ARAMCO- Mechanical para 12.4.2 cap this is the clear violation of 01-SAMSS-048 para 26-Jun-19 10-Jul-19 08-Jul-19 pipe ends and it shall be firmly attached to the pipe. Closed
EPM-INCR-6600003097 without end cap. 048 Saleem
02714 12.4.2 which states that pipe ends shall be protected by Corrective Action:
caps in order to prevent built up of moisture in the pipe. A tool box meeting shall be delivered to ware house
team in order to avoid any re-occurrence of such issue.

Root Cause Analysis:


Unavailability of space and lack of awareness contractor
On June 27, 2019 at TCF1 ware house during
have not been maintained a quarantine area.
surveillance QC observed that contractor shall not
maintained any quarantine area for rejected materials in
Correction Action:
the warehouse. This is the clear violation of contractor
T-CPP- Dedicated quarantine area will be provided and sign
CPP-NGCP-NCR-M-016 Quarantine area not material handling, storage and preservation procedure Muhammed
83 NA ARAMCO- Mechanical para 6.4. 27-Jun-19 11-Jul-19 08-Jul-19 board shall be placed. Closed
EPM-INCR-6600003156 maintained para 6.4. which states that any materials found to be Saleem
02714
non-conforming shall be quarantined in the dedicated
Corrective Action:
area.
Tool box meeting will be conducted and will be explained
to ware house employees about the material storage
and preservation.

Root Cause Analysis: During stringing the pipes were


slipped from the sand berm
Correction Action:
On June 27, 2019 at Hawiyah-1071 area of KM 0+300
Those pipes will be lifted and supported on the rock-free
T-CPP- during inspection QC Found that three qty of 8” pipes
CPP-NGCP-NCR-M-017 Coated pipe strung on K.LOKANADHA sand berm. Holiday test shall be done prior to lowering.
84 NA ARAMCO- Mechanical SAES-H-200 Para 5.3 were strung on the ground this is a clear violation of 27-Jun-19 11-Jul-19 08-Jul-19 Closed
EPM-INCR-6600003119 the ground M Corrective Action:
02714 SAES-H-200 Para 5.3 which states that externally
Tool box meeting shall be conducted to construction
coated line pipe along the right-of-way shall
team in order to avoid any re-occurrence of such issues.

During fabrication shop surveillance on dated 26-June-


2019 it was observed that, the construction team was
Root Cause Analysis: Careless workmanship and lack
tightening the ground bolts with torque wrench whose
of awareness/knowledge.
calibration is expired. This is a clear violation of
Correction Action:
Schedule Q, Attachment IV, Paragraph 7.1 which states
Torque wrench need to be calibrated and torquing of
that; The CONTRACTOR shall identify, maintain,
CPP-NGCP-NCR-E-005 T-CPP- bolts need to be conducted again.
Torque Wrench Q, Attachment control, adjust, and calibrate all tools, gauges, Mohammad
85 EPM-INCR-6600003166 NA ARAMCO- Electrical/CP Paragraph 7.1 26-Jun-19 27-Jul-19 22-Jul-19 Corrective Action: Closed
Calibration Expired IV instruments and other measuring and testing devices Moizuddin
02716 A quality tool box meeting will be delivered to site
used for controlling quality. Calibration shall be
construction team in order to increase the quality
performed at established periods as specified in the
awareness. Subsequently, quality department will
most stringent of COMPANY standards, other
enhance the site surveillanceduring
Root cause:Mishandled to avoid recurrence.
loading and
applicable standards, or manufacturer
recommendations; if no standards apply, the calibration transportation.
cycle shall not exceed six months. Correction Action: Subject two numbers of pipe coating
damaged to be repaired and to be
During daily site visit on date 26-JUNE-2019 at HWYH
verified with holiday test for final acceptance by
1100, it was observed that the CPP construction team
inspection.
lowered the pipe in HWYH-1100 sta@ 1+944 to 1+954
Corrective Action:
T-CPP- which have unsupported length more the 3 meter which
CPP-NGCP-NCR-CIV-033 Pipe loading / off loading crew has been instructed to
86 ARAMCO- Civil Civil SAEP-1160 sec 14.5 is clear violation as per SAES-L-450 sec 14.5 prior to Taseer khan 14-Jul-19 11-Jul-19 Closed
EPM-INCR-6600003152 take care of coating handling with more protection to the
02712 backfilling and during lowering the pipeline shall be
FBE coating.To prevent any future re-occurence CPP
supported inside the trench with a maximum allowable
informed SAPMT to notify coating vendor for re-
unsupported length 3 meter (m) Any voids below the
verification prior to dispatch/release any pip
Duringpipe
siteshall be carefully
surveillance backfilled.
on June 27, 2019 @ esCarelessness
to site.
Root Cause Analysis: of site surveyor
HWYH/RH-CK, it is observed that SURVEY BENCH General Reply:
and foreman.
MARKS PLACE Please see attached signed and closed hard copy of
CPP-NGCP-NCR-CIV-
WITHOUT BARRICADE, this is a clear violation to INCR H-001. This INCR can be closeBench
in EPM also.to
EPM-34 INCR- T-CPP- Correction Action: Barricade Survey Marks
Survey Bench Mark not Aramco Standard as per SAES-A-114 PARA 5.5.4.5.
87 6600003123 NA ARAMCO- Civil SAES-A-114 Farncis 18-Jul-19 14-Jul-19 23-Jul-19 avoid any damage & to maintain its original location. Closed
properly protected “All reference points, bench marks, monuments, etc.,
02712 Corrective Action:
shall be carefully maintained during excavation,
Construction team will be guided by a quality tool box
backfilling, compaction & earthwork”.
meeting how to ensure all bench marks shall be
protected.

Page 16 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: Careless workmanship from the


MT Technician.
During site visit at HWYH-GK-RH on Date-26-June-
2019, joint number (01-FW-86 to 01-FW-103, 01-FW- Correction Action: All the joints (01-FW-86 to 01-FW-
147 to 01-FW-165, 02-FW-166, 167 & 169 and 02-FW- 103, 01-FW-147 to 01-FW-165, 02-FW-166, 167 & 169
CPP-NGCP-NCR-W-27, T-CPP- 198 to 02-FW-201) it was observed that MT Technician and 02-FW-198 to 02-FW-201) shall be cleaned as per
Post cleaning not done
88 EPM # NA ARAMCO- Welding SAEP-1144 Mr. Yub K Kammu (SOGEC) performed MT without Imran 25-Jul-19 20-Jul-19 SAEP-1144, Para-9. Closed
after performing of MT
6600003118 02717 post cleaning which violates SAEP-1144, Para-9, which
states that The examination area shall be cleaned after Corrective Action: Awareness Toolbox training will be
inspection with solvent to remove any excess residues conducted to prevent future recurrence, Site QC to
from the MT examination process. monitor closely to follow standard requirement.

Root Cause Analysis: Careless workmanship from the


welders.
During site visit at HWYH-934 on Date-26-June-2019,
Correction Action: 100% Radiography shall be done of
joint number (04-FW-414) Welder (CPP-W-134) it was
joint number 04-FW-414 to ensure soundness of
observed that the welding was ongoing without proper
CPP-NGCP-NCR-W-28, T-CPP- Inadequate wind welding.
wind shielding as per attached picture which is a Muhammad
89 EPM # NA ARAMCO- Welding protection during SAES-W-012 25-Jul-19 21-Jul-19 Closed
standard violation as per SAES-W-012 Para 10.2.1 Shahbazudain
6600003132 02717 welding Corrective Action: Weld tent shall be closed from all
which states that Wind shields or tents shall be required
sides during welding, especially when wind speed is
when wind is strong enough to affect arc stability or
high. Site QC to monitor closely for standard compliance
when deemed necessary by Saudi Aramco Inspectio
especially for strong windy days.

Root Cause Analysis: Careless workmanship from the


During site visit at HWYH-934 on Date-27-June-2019, welders.
joint number (05-FW-429) Welder (CPP-W-044) it was
observed that the welding was ongoing and Arc strike Correction Action: Arc strike shall be removed by
CPP-NGCP-NCR-W-29, T-CPP- found on base metal near weld joint as per attached grinding and PT or MT will be performed.
Arc strike not removed Muhammad
90 EPM # NA ARAMCO- Welding SAES-W-012 picture which is a standard violation as per SAES-W- 20-Jul-19 20-Jul-19 Closed
during welding Shahbazudain
6600003141 02717 012 Para 10.10 Arc strikes, gouges, and other Corrective Action: Awareness Tool box shall be
indications of careless workmanship (such as surface conducted and Site QC to monitor closely for standard
porosity, uneven weld profiles, and undercut) shall be compliance.
removed by grinding.

On Jun 26, 2019, CPP QC noticed an arc strike during Root Cause Analysis: Improper condition and fixing of
the welding activities of joint no. 01-FW-104 at 8”- grounding clamp
T-CPP- HRDH-1165. This violates SAES-W-012, 10.10, which Correction Action: Grinding the defected area to
CPP-NGCP-NCR-W-030 Arc strike at @ HRDH-
91 NA ARAMCO- Welding SAES-W-012 states: Arc strikes, gouges, and other indications of Rajesh Kumar 15-Jul-19 07-Jul-19 remove the arc strike and apply PT test, ground clamp to Closed
EPM-INCR-6600003072 1165
02717 careless workmanship (such as surface porosity, be fixed.
uneven weld profiles, and undercut) shall be removed Corrective Action: Proper fixing of grounding clamp
by grinding. shall be provided for further fit-up and welding activities

Root Cause Analysis: Root pass welder went to


On Jun 26, 2019, CPP QC noticed during routine smoking shelter and hot pass welder not wait until
inspection that the welder starts the hot pass before completion of root pass. Correction Action:
other welder finish his root pass during welding at 16" Visual inspection done by welding inspector and no sign
CPP-NGCP-NCR-W-031 T-CPP- Improper welding
HRDH CK-RH TR/L joint # (01-FW-120) which is a for welding distortion. 100% RT to be done for joint 01-
92 EPM-INCR-6600003102 NA ARAMCO- Welding sequence @ 16" HRDH SAES-W-012 Irshad Ahmed 15-Jul-19 14-Jul-19 Closed
standard violation as per SAES-W-012 (Para 10.7.2) FW-091 to verify weld soundness.
02717 CK-RH TR/
which states that “The second or hot pass shall be Corrective Action:
added as soon as possible after the completion of the Awareness toolbox will be conducted to enhance
root pass”. welding crew skills and improve their knowledge of the
SAES-W-012 requirement.
On June 25, 2019, CPP QC noticed during routine
surveillance that the welder left electrodes in the quiver
during lunch time and power was switch off, the Root Cause Analysis: Power of electrode oven switch
temperature was below 65°C and the exposure time off during lunch time.
CPP-NGCP-NCR-W-032 T-CPP- Welding electrodes
exceed 4hr at 8" HRDH-922 F/L which is a standard Muhammad Correction Action: The affected electrodes are
93 EPM-INCR-6600003121 NA ARAMCO- Welding exceed exposure time SAES-W-012 15-Jul-19 12-Jul-19 Closed
violation as per SAES-W-012 (Appendix 1) which states Farhan discarded. Corrective Action: Awareness
02717 @ 8" HRDH-922 F/L
that “The exposure times may be doubled (to 4 hours toolbox will be conducted to avoid power switching off if
and 1 hour, respectively) if the electrodes are the ovens filled by electrodes.
continuously stored in a portable electrode oven heated
to 65°C minimum

Root Cause Analysis: Radiographic Work Permit


(RWP) for NDT Provider SOGEC, expired 24th June
During review of weld summery on Dated 27-June- 2019. RWP renewal request not approved by OID- due
2019, it was found that 03 joints (03-FW-265, 266 & to some issue with SOGEC in their different project. So,
267T) RT Backlog from HRDH-922 and 04 joints (02- they could not complete CPP daily NDT request.
T-CPP- RT Backlog found in
CPP-NGCP-NCR-W-33 FW-187, 188T, 207A & 212) from HRDH-1116 which Muhammad Correction Action: CPP immediately arranged AIS
94 NA ARAMCO- Welding HRDH-922 & HRDH- SAEP-1160 12-Jul-19 11-Jul-19 Closed
EPM-INCR-6600003103 violates SAEP-1160, Para-6.4, which state that RT Farhan NDT- another NDT service providers’ additional NDT
02717 1116.
Backlog shall be considered as an accumulation of crew in the Weekend (28th and 29th 2019) and cleared
uncompleted work that has already been requested all subject backlog welds.
within one week’s productio Corrective Action: CPP is arranging to mobilize the
third NDT service provider (NDTCCS) to handle any
such emergency situation in future.

During inspection at HRDH-WH# 1177 (TA-843575- Root Cause Analysis:


Sheet No:002-Rev-0F1, and -003- Rev-00), It was Construction failed to measure the dew point and steel
observed that, repair touch up painting was carried out temperature prior to start the coating activity.
without monitoring the weather (Steel temperature, Dew
points and Relative humidity) , It is found out that at 16 Correction Action:
CPP-NGCP-NCR-H-007 T-CPP- Touch up painting locations without notification and monitoring of weather Current patch coating will be removed and new repair
95 EPM-INCR- NA ARAMCO- Coating carried out without SAES-H-002V condition. Subjected joint numbers and locations Bijoy C.R 30-Jun-19 30-Jun-19 coating will be performed. Closed
6600003011 02713 monitoring weather respectively FW# 44 to FW# 123 (KM-0+623 to KM-
1+584).This is a clear violation of SAES-H-002V, Corrective Action:
Para.9.2 and 9.3 which states that control of dew point A tool box meeting will be conducted to construction
is important to prevent moisture condensation on the team in order to avoid any re-occurrence of such issues.
steel pipe substrate during the application of the coating
system.

Page 17 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: The earth moving equipment-


excavator bucket touched the wrapping and damaged
the coating. This is careless behavior from the operator.
Correction Action:
As per standard requirement- based on the size of the
On 29-June- 2019, It is observed during site inspection
damaged area, the whole wrapping shall be removed,
at HRDH WH#1086 APCS -113C coated joint FW#132
APCS-113C COATED remove any possible debris and reapply Canusa
T-CPP- (Km-1+702, Drawing Number:-TA-843625- Sheet
CPP-NGCP-NCR-H-008 GIRTH WELD wrapping (APCS-113C) with approved Coating
97 NA ARAMCO- Coating SAES-H-002V No#003, Rev;0F1) found damage on the Girth Weld Bijoy C.R 10-Jul-19 10-Jul-19 Closed
EPM-INCR-6600003142 WRAPPING FOUND applicator, In presence of approved Crew Supervisor
02713 Canusa Wrapping, Damage only limited to the wrapping
DAMAG and Approved Qc Inspector. Holiday test will be the final
portion- pipe material is safe. This is a violation of
acceptance.
SAES-H-002V PARA 8.2
Corrective Action:
Quality awareness toolbox arranged to discuss the care
Root
of FBE Cause Analysis:
coated pipes and During liftingcoatings.
girth weld accidentally
Sideslipped
boom
off from
and sand filled
Excavator bag. This
operators’ is mishandling
are included in the of pipe.
meeting.
Correction Action:
As per standard requirement- based on the size of the
Before Lowering, During Holiday testing of Flowline damaged area, patches of wrapid bond shall be sized to
welded string HRDH 1086, Km 0+873 (Reference RFI open window scale 50mm addition on all side and shall
Before Lowering, Dated 29-June- 2019, EPM # 1400130762, be pressed in to ensure good adhesion to the substrate.
During Holiday testing 1400130821,1400130791) slipped off from the sand remove any possible debris and reapply Canusa
T-CPP-
CPP-NGCP-NCR-H-009 of Flowline welded bag support, and portion of APCS-113C Canusa wrapping (APCS-113C) with approved Coating
98 NA ARAMCO- Coating APCS-113C Bijoy C.R 15-Jul-19 13-Jul-19 Closed
EPM-INCR-6600003184 string HRDH 1086, Km Wrapping damaged at FW#064. applicator and SAPID notification. Holiday test will be the
02713
0+873 (Reference RFI Reference Drawing Number: -TA-843625- Sheet final acceptance.
Dated 29- No#002, Rev;0F2. Corrective Action:
This is a violation of SAES-H-002V PARA.8. Quality awareness toolbox arranged to discuss the care
of FBE coated pipes and girth weld coatings. Side boom
Root Causeand
operators Analysis: Construction
Rigger are included increw missed to
the meeting.
follow the manufacturer
Operators and Riggersdata are sheet.
reminded Data
to sheet
handlealso
FBEnot
mentioned maximum application
coated pipes temperature.
with more care.
Correction Action:
While daily monitoring the temperature, it has been
Manufacturer shall be contacted to specify or
observed that substrate temperature is reaching up to
recommend the maximum mixing and application
While daily monitoring 60°C and above now a days. As per data sheet of
temperature. One confirmation letter required from
T-CPP- the temperature, it has CANUSA-CPS High Build Epoxy HBE-HT data sheet,
CPP-NGCP-NCR-H-010 Manufacturer to close this violation.
99 NA ARAMCO- Coating been observed that the ideal mixing and application temperature is between Bijoy C.R 15-Jul-19 13-Jul-19 Closed
EPM -INCR-6600003217 Corrective Action:
02713 substrate temperature 20°C to 40°C. These patch compound using for Repair
CPP QC, Crew Supervisor and Coating Crew in charge
is reaching up to 60°C touch up painting over FBE coated pipe. This is
to read, follow the manufacturer data sheet, approved
violating the requirements of manufacturer
procedure and standard requirements and raise any
recommendation.
concern before starting any new activity. One QC
Awareness meeting shall be conducted to discuss this
issue.

Root Cause Analysis: Radiographic Work Permit


(RWP) for NDT Provider SOGEC, expired 24th June
During site visit at HWYH-GK-RH on Date-29-JUNE-
2019. RWP renewal request not approved by OID- due
2019 24’’-HWGCP-1-T/L SWEET (T/L-DJ-54) & 24’’-
to some issue with SOGEC in their different project. So,
HWYH-GGM-TR/L-2 (TRL-2-DJ-19,TRL-2-DJ-60) at
they could not complete CPP daily NDT request.
T-CPP- TCF-1 (PIPE YARD it was observed that MT Technician
CPP-NGCP-NCR-W-34 Correction Action: CPP immediately arranged AIS
100 NA ARAMCO- Welding Broken wind shied SAES-W-012 Para10.2.1 (SOGEC) performed MT without post cleaning which Irshad Ahmed 20-Jul-19 21-Jul-19 Closed
EPM-INCR-600003215 NDT- another NDT service providers’ additional NDT
02717 violates SAEP-1144, Para-9, which states that The
crew in the Weekend (28th and 29th 2019) and cleared
examination area shall be cleaned after inspection with
all subject backlog welds.
solvent to remove any excess residues from the MT
Corrective Action: CPP is arranging to mobilize the
examination process.
third NDT service provider (NDTCCS) to handle any
such emergency situation in future.

Root Cause Analysis: Careless workmanship from the


MT Technician.
During site visit at HWYH-GK-RH on Date-29-JUNE-
Correction Action: All the joints 24’’-HWGCP-1-T/L
2019 24’’-HWGCP-1-T/L SWEET (T/L-DJ-54) & 24’’-
SWEET (T/L-DJ-54) & 24’’-HWYH-GGM-TR/L-2 (TRL-2-
HWYH-GGM-TR/L-2 (TRL-2-DJ-19,TRL-2-DJ-60) at
DJ-19, TRL-2-DJ-60) shall be cleaned as per SAEP-
T-CPP- TCF-1 (PIPE YARD it was observed that MT Technician
CPP-NGCP-NCR-W-35 Post cleaning not done violates 1144, Para-9.
101 NA ARAMCO- Welding (SOGEC) performed MT without post cleaning which Junaid Zafar 20-Jul-19 18-Jul-19 Closed
EPM-INCR-6600003183 after performing of MT SAEP-1144 Corrective Action: Awareness Toolbox training will be
02717 violates SAEP-1144, Para-9, which states that The
conducted to prevent future recurrence, Site QC to
examination area shall be cleaned after inspection with
monitor closely to follow standard requirement.
solvent to remove any excess residues from the MT
examination process.
Corrective Action:Corrective Action And implemented
this INCR Closed

Root Cause Analysis: Negligence of Construction team


and failed to fulfil the Mandatory requirements.
During site Surveillance on July 2nd 2019 at HRDH-
Correction Action: Construction Team will send the
1151 Well pad, it was found that Construction team
Auto Level Machine for Calibration and in the meantime
were using expired calibration Auto Level Machine
CPP-NGCP-NCR-CIV-035 any calibrated auto level shall be used..
T-CPP- Expired Calibrated Serial#674695 Model-AC-2s. This is a clear violation as
EPM-INCR-6600003233 Corrective Action:
102 NA ARAMCO- Civil Survey Machine at Model-AC-2s Schedule Q attachment IV para no 7.1. Which states Hameedullah 17-Jul-19 18-Jul-19 Closed
Construction team will send Equipment and tools for
02712 HRDH-1151 that “The CONTRACTOR shall identify, maintain,
calibration before its expiry and shall update their
control, adjust, and calibrate all tools, gauges,
equipment’s Log accordingly. A quality toolbox meeting
instruments and other measuring and testing devices
will be delivered to site construction team to enhance the
used for controlling quality”
awareness.

Page 18 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: Negligence of Construction team


and Ignoring the standard requirements due to rush the
progress.Correction Action: Construction Team will
During Internal Inspection of Stockpile-01 at Borrow Pit-
clean all the bushes, trash and soft material from the top
26 near HRDH-RHCK on July 3rd 2019 it was found
and will provide sieve to place graded material for
CPP-NGCP-NCR-CIV-036 that Construction team offered Ungraded, unplaced,
T-CPP- stockpile of select fill material.
EPM-INCR-6600003237 Ungraded and unplaced freeze and bushes mixed material for Laboratory
103 NA ARAMCO- Civil SAES-A-114 Hameedullah 17-Jul-19 15-Jul-19 Corrective Action: Closed
material for stockpile Testing which is a clear violation as per SAES-A-114-
02712 Construction team shall full fil the standard requirements
Sec-6.1 which states that” Stockpiles shall be placed,
for borrow pit and stockpile and shall place well graded
graded and shaped for proper drainage. Stockpile of
material for stockpile. Construction team will also clean
cohesive soil shall be protected from freezing”
the trashes and any kind of grass/bushes prior to
preparing stockpiling

Root Cause Analysis: Negligence of construction team


for rushing the progress.
Correction Action: Barricade the Designated Borrow Pit
During daily site visit on date 03-July-2019 at HRDH-
area and provide safe access for IN and OUT to avoid
Borrow Pit#26 Near HRDH-RH-CK it was observed that
safety hazards.
T-CPP- No Barrier Controlling there is no Barrier controlling access for the Designated
CPP-NGCP-NCR-CIV-037 Corrective Action:
104 NA ARAMCO- Civil access for Borrow Pit- SAES-A-111 Borrow pit area which is a violation as per SAES-A-111- Hameedullah 20-Jul-19 19-Jul-19 Closed
EPM-INCR-6600003238 A toolbox meeting will be delivered to enhance the
02712 26, Near HRDH-RH-CK Sec-6.6 which states that “A pit shall have a barrier
awareness for borrow pit requirements to avoid any
controlling access and such barriers shall be clearly
safety and quality issues. Subsequently, CPP quality
visible to prevent safety hazards to the public.
department will firmly monitor the site to avoid
recurrence

On dated 2 July 2019 during surveillance at HRDH-922


it was observed that FW#231 & Fw#233 were ruptured
which is clear violation of SAES-H-002V para. 1.1 which
states that Wrapid Bond system is a wraparound
corrosion protective Visco-Elastic coating system for
new construction or rehabilitation of existing pipeline
coatings. The system may be used for below grade
Root Cause Analysis:
subsea steel pipeline operating at temperature up to
Lack of knowledge about Saudi Aramco Standards,
CPP-NGCP-NCR-H-011 T-CPP- 75°C. the wrapid bond system consists of 2 major
APCS-113C coated Work procedure and poor workmanship from
105 EPM-INCR-6600003250 NA ARAMCO- Coating SAES-H-002V components: Awais Khan 18-Jul-19 15-Jul-19 Closed
joints damage construction concern persons.
02713 a) The first layer (inner) wrapid bond is a modified and
reinforced Visco Elastic adhesive applied onto a
Correction Action:
polyethylene carrier film that facilitates wrapping directly
to substrate thus creating an impermeable barrier to
water & air.
b) The second layer (outer) wrapid or Wrapid Coat XL
range is a tough PVC or FRP tape designed as an outer
wrap for the VE inner wrap for mechanical protection

Upon routine RFI site visit at HRDH-TCF-1 yard dated


03-July-19, it has been observed that the safety
pressure relief valve with serial No A072514 attached Root Cause Analysis: Poor observation from
with the compressor (SN: B4-6C27934) has been construction department prior to getting the equipment to
Calibration expired which is a standard violation as per site.
Schedule “Q” attachment 4 para 7.1 which states that Correction Action:
contractor shall include procedures for the control of The above mentioned safety pressure relief valve has
T-CPP- Calibration Expiry of
CPP-NGCP-NCR-H-012 Q” attachment Inspection, measuring and testing equipment. The been sent for Third party calibration prior to use in site.
106 NA ARAMCO- Coating Safety pressure Relief Rajendra Salian 20-Jul-19 20-Jul-19 Closed
EPM-INCR-6600003295 4 contractor shall identify, maintain, control, adjust and Corrective Action: Tool box meeting shall be delivered
02713 Valve
calibrate all tools, gauges, instruments and other to construction dept and calibration monitoring log shall
measuring and testing devices used for controlling be monitored by inspector.
quality. Calibration shall be performed at established
periods as per company standards or manufacturing
recommendations, if no standards apply the calibration
cycle shall not exceed six months.

On dated 06 July 2019 during site surveillance at Root Cause Analysis:


HWYH-1136 flow line welded string from Joint# Fw-14 Rubber tires used to support welded string which were
to Fw-61, It was observed that some of the APCS 104B not placed correctly between pad area and pipes and
(FBE) coated pipes laid on inappropriate supports and some of the tires settled down due to pipe weight and
thus touching ground marl mixed with stones, which unable to protect pipe from touching the ground.
may lead to FBE coating damage and it is a clear Correction Action:
violation of pipe handling and storage as per SAES-H- Effected pipes shall be lifted by placing proper support
CPP-NGCP-NCR-H-013 T-CPP-
Coated pipes laid on 200, Para 5.2.1 which stated that: with a minimum gap of 150mm off the ground. All area
107 EPM-INCR-6600003261 NA ARAMCO- Coating SAES-H-200 Amion Iqbal 21-Jul-19 20-Jul-19 Closed
inappropriate supports. During storage, the coated pipes shall be placed at shall be holiday tested and repair according to approved
02713
least, 150 mm off the ground on either rock-free sand repairing procedure prior to lowering.
berm covered with polyethylene sheeting or on padded Corrective Action:
skids spaced and leveled so that the pipes are Tool box meeting shall have arranged for construction
supported without damaging the coating. All possible crew on importance of Saudi ARAMCO Engineering
efforts shall be exerted to prevent direct contact of the Standards and Requirements.
coated pipes with the ground or ground moisture.

During site surveillance at HRDH-WH# 1162 (TA-


843974- Sheet No:003-Rev-0F1,KM 1+440), It has
Root Cause Analysis: Lack of planning from execution
been observed that, Canusa CPS (APCS-113C) which
team
has been girth weld coated (FW Joint# 110,111 & 112)
Correction Action: The existing coating need to be
on Date: 25-April-2019, has not been buried for more
removed from the joints and wrapped with new coating
than 10 weeks from the maximum exposure period of 4
material with proper surface Preparation as per
T-CPP- Coated pipe exposed to weeks, which is the standard violation as per CANUSA
CPP-NGCP-NCR-H-014 approved APCS 113C coating application procedure.
108 NA ARAMCO- Coating direct sunlight above Canusa CPS – CPS procedure Doc# CPP-NGCP-CM-PRO-0009, Rajendra Salian 21-Jul-19 21-Jul-19 Closed
EPM-INCR-6600003251 Corrective Action:
02713 the exposure duration. content No-12. Which states that, as per canusa
Construction has been strictly advised to follow the
clarification, visco elastic Wrapid Bond product applied
Saudi Aramco Engg Standard to prevent repeated
on girth weld filed joints, can be kept exposed to direct
violation.
sunlight for up to 4 weeks in the middle East ambient
temperatures without any protection needed against UV
exposure.

Page 19 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: Careless workmanship and lack


of awareness/knowledge.
During the site surveillance of the fabrication shop on Correction Action:
dated 03-July-2019 it has been observed that the Cables need to be isolated from the terminals and
construction team terminated and energized the perform IR test in compliance with the standard
installed power cables prior to checking the continuity requirements prior to be placing in service.
Energization of Installed
CPP-NGCP-NCR-E-006 T-CPP- and insulation resistance test which is non-compliance Corrective Action:
Cables without Mohammad
109 EPM-INCR-6600003299 NA ARAMCO- Electrical/CP SAES-P-104 the standard requirements as per SAES-P-104 Para 03-Aug-19 23-Jul-19 The electrical site supervisor is strictly instructed not to Closed
Insulation Resistance Moizuddin
02716 13.1 which clearly stated that the “Low voltage (600, violate the standard requirements. A quality tool box
Test.
450/750, or 600/1000 V rated) cables, including splices meeting will be delivered to site construction team in
to existing cables, shall be 1000 V DC megger tested order to increase the quality awareness. Subsequently,
after installation and prior to placing in service (during quality department will enhance the site surveillance to
commissioning).” avoid recurrence.

Page 20 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
During daily site visit on date 07-JULY-2019 at HWYH Root Cause Analysis: Construction team did not follow
1078, it was observed that the CPP construction team the requirements of SAES-L-450 SEC 14.5
lowered the pipe in HWYH-1078 which have Correction Action: The CPP construction team shall
T-CPP- unsupported length more the 3 meter which is clear put the sand bags beneath the pipe on every 3 meter to
CPP-NGCP-NCR-CIV-038 Unsupported length at
110 NA ARAMCO- Civil SAES-L-450 violation as per SAES-L-450 sec 14.5 Prior to backfilling Aqib Hussain 14-Jul-19 22-Jul-19 avoid the unsupported length and CPP QC will verify it. Closed
EPM-INCR-6600003305 HWYH-1078
02712 and during lowering the pipeline shall be supported Corrective Action: A quality
inside the trench with a maximum allowable toolbox meeting will be delivered to site construction
unsupported length 3 meter (m) Any voids below the foreman in order to have full understanding of sand
pipe shall be carefully backfilled. padding as per SAES-L-450.

Root Cause Analysis: Sand pads damaged due to


personnel movements.
During site inspection on date 07-07-2019 at HWYH Correction Action: Construction team will make the
CPP-NGCP-NCR-CIV-039 1078, it was observed that the sand provided at sta. proper shape of sand pads in order to fulfill the standard
T-CPP-
EPM-INCR-6600003262 No Proper Sand Pad 2+805 to 2+955 was not maintained properly which is requirements and sand pads shall be placed at
111 NA ARAMCO- Civil SAES-L-450 Aqib Hussain 14-Jul-19 22-Jul-19 Closed
HWYH-1078 violation as per “SAES-L-450-Sec. 14.10.3e. sand pads approximately every 9 m to support the pipe
02712
or sand bags shall be placed at approximately every 9
m to support the pipe 100 mm off the prepared bottom.” Corrective Action: A quality toolbox meeting will be
delivered to site construction foreman in order to have
full understanding of sand padding as per SAES-L-450.

Root Cause Analysis: PVC conduit is stored inside


During surveillance at CPP warehouse NGCP TCF1 it
warehouse not directly under sunlight. Due to ongoing
was observed that PVC pipe is not preserved properly
activities in warehouse is covered by dust & dirt.
with dust & dirt on it. As per SAES-T-911
Correction Action: Warehouse Supervisor is informed
Telecommunication Conduit System Design 5.1.5
CPP-NGCP-NCR-T-001 T-CPP- to clean PVC conduits & cover PVC conduit with
Handling and Storage Handling and Storage of Conduit Materials: Handling
112 EPM-INCR- 6600003345 NA ARAMCO- Telecom SAES-T-911 Asad Saeed 13-Aug-19 27-Jul-19 tarpaulin to avoid dust & dirt on & inside PVC conduit. CLOSED
of Conduit Materials and Storage of NEMA TC 8 conduits and NEMA TC 9
02715 Preventive
accessories shall be according to the manufacturers’
Action:
direction or NEMA TCB2, User’s Manual. 5.1.5.2 a)
All conduits & accessories must be covered with
Clean the conduit surface, so that it is free from oil,
tarpaulin in future.
grease, dirt, etc.

Root Cause Analysis: The material was transferred to


During routine site surveillance on 10th July at RH-CJ it site without screening.
was found that construction team started backfilling of Correction Action: Construction team shall remove all
RH-CJ 4th layer (Zone B and D) with a material which the oversize stones from site and CPP QC will verify
CPP-NGCP-NCR-CIV-040 T-CPP- Inappropriate Material
contains over size stones. This is a clear violation of before the compaction begin.
113 EPM-INCR-6600003336 NA ARAMCO- CIVIL Used for Backfill at RH- SAES-A-114 Aamir Solangi 25-Jul-19 25-Jul-19 Closed
SAES-A-114-sec 6.1.2.1 which states that “Select Fill or Corrective Action:
02712 CJ ( Zone B and D)
‘Structural Fill’ shall be composed only of inorganic Construction shall take the screened material from
material and shall have 100% passing the 5 cm (2 in) approved stockpile before placing it at site more over
sieve and from 0 to 20% passing the No. 200 sieve CPP QC will firmly monitor the backfilling work.

Root Cause Analysis:


Separation pads or ropes fall down during transportation
Correction Action:
Separation pads shall be provided; twelve-meter (12 m)
On July 17, 2019, CPP QC observed during site
On July 17, 2019, CPP joints of pipe shall have at least 3 full encirclement
inspection at HWYH RH DK 16” X 0.562” FBE coated
QC observed during separation pads.
CPP-NGCP-NCR-M-018 T-CPP- pipes found without encirclement separation pads. This
site inspection at Muhammad Corrective Action:
114 EPM # INCR- NA ARAMCO- Mechanical SAES-H-200 is clear violation of SAES-H-200 PARA 5.2.2, this 31-Jul-19 28-Jul-19 Closed
HWYH RH DK 16” X Umair Material coordinator make sure all the separation pads
6600003354 02714 standard requires the FBE coated pipes shall not be
0.562” FBE coated prior to transportation and QC inspector to monitor
stacked directly against each other at any time during
pipes found during offloading. Coating damage area (If any) shall be
storage or transportation.
marked properly and effected area shall be repair prior to
lowering.

Root Cause Analysis: Construction team was


During daily site visit on date 17-July-2019 at HWYH-
transporting un-approved material to the site from un
RH-CK it was observed that the construction team
approved source.
dumped the material for the 2nd Layer of zone 2 in
Correction Action: The subject 2ND Layer of zone 2
which the construction team placed the unapproved
T-CPP- all the unapproved material shall be removed from site
CPP-NGCP-NCR-CIV-041 Material placed from material from un approved source which is clear
115 NA ARAMCO- Civil SAES-A-114 Taseer Khan 15-Aug-19 22-Jul-19 and replace it with approved material from approved Closed
EPM-INCR-6600003384 unapproved source violation as per SAES-A-114, Sec. 6.1 “All sources of
02712 stockpile and approved borrow pit.CPP QC will verify
supply shall be approved by Saudi Aramco. Stockpiles
before the compaction begin. Corrective Action:
shall be placed, graded, and shaped for proper
Construction team shall take all the material from
During Storage
drainage. site surveillance at HWYH-1136-F/L
or stockpiling of material shall(TA-
not be
Root cause:Mishandled
approved during loading
sources. Subsequently, and
CPP quality
445826) Km-3+055
permitted onto aKm-3+840,
completedJoint# 03-Fw-306 to
subgrade”
transportation.
department will firmly monitor the backfilling work.
03-Fw-310 It was observed that APCS 104B (FBE)
Correction Action: Subject two numbers of pipe coating
coated pipe string has been dislodged from Pipe
damaged to be repaired and to be
supports and laid on the ground due to thermal
verified with holiday test for final acceptance by
expansion and contraction, which may lead to FBE
inspection.
coating damage. It is a violation of pipe handling and
Corrective Action:
CPP-NGCP-NCR-H-015 T-CPP- storage as per SAES-H-200, Para 5.2.1 which stated
Pipe loading / off loading crew has been instructed to
116 EPM# INCR- 6600003367 ARAMCO- Coating Coating SAES-H-200 Para 5.2.1 that: 27-Jul-19 25-Jul-19 Closed
take care of coating handling with more protection to the
02713 During storage the coated pipes shall be placed at least
FBE coating.To prevent any future re-occurence CPP
150 mm off the ground on either rock-free sand berm
informed SAPMT to notify coating vendor for re-
covered with polyethylene sheeting or on padded skids
verification prior to dispatch/release any pip
spaced and leveled so that the pipes are supported
es to site.
without damaging the coating. All possible efforts shall
General Reply:
be
Onexerted
dated 14 toJuly
prevent
2019direct contact
during of the coated
site inspection pipes
at HRDH- Please see attached signed and closed hard copy of
with the No.TA-843609
922 for Drawing ground or ground moisture
near the joints INCR H-001. This INCR can be close in EPM also.
FW# 246,247,248,284 & 296 it was observed that touch
up repair for External FBE Coating (APCS-104)
CPP- NGCP-NCR-H-016 T-CPP- Root Cause Analysis: Poor workmanship from
Repair touchup for performed in bad weather so sand were contaminated
117 EPM# INCR- 6600003556 NA ARAMCO- Coating APCS-104 Para 5.8. 14-Jul-19 29-Jul-19 29-Jul-19 construction concern persons and lack of knowledge of Closed
External FBE Coating. and accumulated on the joints due to high wind speed
02713 Saudi Aramco Engineering Standard.
which is a violation as per approved procedure(CPP-
NGCP-CM-PRO-0012_1) of para 5.8. Wind is strong
enough to blow sand, salt spray, or other foreign matter
onto the surface being coated.

Root Cause Analysis: Negligence of Construction team


and ignoring the Saudi Aramco Standard Requirements.
During Site surveillance on date 29-July-2019 at (8”F/L Correction Action: Construction team shall excavate
HRDH-1171)Station-2+851 Pipe Curve it was found that the edge of the trench where the pipe is near and where
CPP-NGCP-NCR-CIV-042 the Sand Cover from Edge of the Pipe was not enough the Sand cover is less then 300mm from each side of
Insufficient sand cover
EPM-INCR- 6600003641 and centerline of the pipe was disturbed which is a clear pipe.
118 CIVIL from the side Edge of SAES-L-450 Sec. 14.9.3b Hameedullah 29-Jul-19 15-Sep-19 12-Sep-19 Closed
violation as per SAES-L-450-Sec. 14.9.3b which states Corrective Action:
pipeline in trench
that “The minimum width of the bottom of the trench in Construction Team shall excavate the trench wider than
rock areas shall be 600 mm wider than the pipe. The the Normal (Straight) Trench at every Curve of the
pipe shall be centered in the trench.” pipelines.Toolbox Meeting will be conducted regarding
this matter.

Page 21 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis: Lack of monitoring/ awareness of


lowered pipe.
Correction Action:
During site surveillance on 30- july-19 HRDH-WH # Contractor has to installed the 60LBS galvanic anode
1178 (F/L KM0+239 TO 0+491) it was noticed that, immediately in order to avoid the corrosion of pipe
CPP-NGCP-NCR-E-007 T-CPP- No Galvanic Anode Pipeline was buried one month ago., but still galvanic Preventive Action:
119 EPM # INCR- 6600003586 NA ARAMCO- Electrical/CP installation in the SAES-X-400 para 6.7, anode not yet installed and it will cause the corrosion of 30-Jul-19 15-Aug-19 14-Aug-19 The electrical site supervisor is strictly instructed not to CLOSED
02716 Burried Pipeline buried pipe. This is clear violation of standard SAES-X- violate the standard requirements. A quality tool box
400 para 6.7, which states that the temporary catholic meeting will be delivered to site construction team in
protection shall be provide within 30 days of burial. order to increase the quality awareness. Subsequently,
quality department will enhance the site surveillance to
avoid recurrence.

During the site surveillance on date 30 July-19 it was


Root Cause Analysis: Careless workmanship and lack
observed at the location of HWYH-WH # 1134 F/L KM-
of awareness/knowledge.
3+567 found that the open cut road crossing CPP
Correction Action:
Construction department damage the 60 Lbs.
CPP Cathodic protection Construction team install the
T-CPP- 60 Lbs.MG anode Magnesium anode during the trench excavation so
CPP-NGCP-NCR-E-008 new anode and protect the pipeline within the ACD.
120 NA ARAMCO- Electrical/CP damage during Trench SAES-X-400 para 6.7 pipeline is no more protected at these location KM- 30-Jul-19 15-Aug-19 14-Aug-19 CLOSED
EPM-INCR- 6600003640 Corrective Action:
02716 excavation 3+567 T0 KM-5+00.Moreover it will the cause the
The Cathodic site supervisor is strictly instructed to
corrosion of buried pipe which is clearly violation with
excavation crew and show him the anode locations
reference to standard SAES-X-400 para 6.7, which
before start of excavation.
states that the temporary cathodic protection shall be
provide within 30 days of burial.

During site surveillance on July 20, 2019 @ HWYH/RH-


CK, it is observed that Borrow pit #23/Stock Pile #2
Is without IDENTIFICATION & TRACEABILITY. This is Root Cause Analysis: Lack of Knowledge of
a clear violation to Schedule Q PARA 4.4.2. “Contractor Construction team about Material Identification &
shall implement an identification procedure for all Preservation.
CPP-NGCP-NCR-CIV-043 Materials, parts & components monuments, including Correction Action: Identification tags/sign board will be
T-CPP-
EPM-INCR-6600003522 Identification and partially fabricated assemblies. Identification of an item place in Borrow pit/stock pile Area.
121 NA ARAMCO- CIVIL Schedule Q PARA 4.4.2. Farancis 20-Jul-19 10-Aug-19 04-Aug-19 CLOSED
Traceability shall be addressed either by using tags, stamps, color Corrective
02712
coding, stencils or labels, & Para 4.4.3, Traceability Action: Construction team will be guided regarding
shall be maintained on Equipment, materials, parts & proper Material Identification & Preservation, &
components, as specified in COMPANY standards & Traceability will be maintained as per Company
Manufacturer’s specification. Standard.

Root Cause Analysis: Negligence of Construction team


and ignoring the Saudi Aramco Standard Requirements.
Correction Action: Construction team shall excavate
During Site surveillance on date 29-July-2019 at (8”F/L
the edge of the trench where the pipe is near and where
HRDH-1171)Station-2+851 Pipe Curve it was found that
the Sand cover is less then 300mm from each side of
CPP-NGCP-NCR-CIV-044 the Sand Cover from Edge of the Pipe was not enough
Insufficient sand cover pipe.
EPM-INCR- 6600003641 and centerline of the pipe was disturbed which is a clear
122 CIVIL from the side Edge of SAES-L-450 Sec. 14.9. 29-Jul-19 15-Sep-19 14-Sep-19 Corrective Action: Closed
violation as per SAES-L-450-Sec. 14.9.3b which states
pipeline in trench Construction Team shall excavate the trench wider than
that “The minimum width of the bottom of the trench in
the Normal (Straight) Trench at every Curve of the
rock areas shall be 600 mm wider than the pipe. The
pipelines.Toolbox Meeting will be conducted regarding
pipe shall be centered in the trench.”
this matter.

During Site surveillance on date 30-July-2019 at (8” F/L


HRDH-1171) Station-2+900 it was found that there is no
Root Cause Analysis: Negligence of Construction team
sand bedding under the pipe and it is directly In Contact
CPP-NGCP-NCR-CIV-045 and ignoring the Saudi Aramco Standard Requirements.
No Sand Bedding with the Bottom of trench which is a violation as per
EPM-INCR-6600003653 Correction Action: Construction team shall lift the pipe
Under the Pipe at SAES-L-450-Sec. 14.9.3c which states that” Selected
123 Civil SAES-L-450 Sec. 14.9.3c 30-Jul-19 15-Sep-19 12-Sep-19 and Provide sand bedding under the pipe. Closed
HRDH-1171 STA- bedding material shall be placed in the bottom of the
Corrective Action:
2+900 trench and made level. The bedding material shall be
Toolbox Meeting will be conducted regarding this matter.
clean sand or soil and shall not contain stones larger
than 12 mm size that would cause damage to the pipe
or pipe coating.

Page 22 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis: Negligence of Construction
Team and Ignoring the standard requirements.
Correction Action:
During routine site surveillance at well pad RH-EK zone Construction Team shall remove the excess material
Placement of Layer B, it was found that Construction Team has Placed 1st from the top and shall provide marking for layer
CPP-NGCP-NCR-CIV-046
thickness more than layer of 90cm which is a clear violation as per SAES-A- thickness inside pad area. Qc has to verify the thickness
124 EPM-INCR-6600003590 Civil SAES-A-114 Sec-6.3.3.2 Aamir Solangi 31-Jul-19 15-Aug-19 19-Aug-19 CLOSED
200mm at HWYH-RH- 114-Sec-6.3.3.2 Which states that “Selectfill Material of layer together with surveyor.
EK shall be placed in lifts of 200mm Maximum in loose Corrective Action:
Depth Construction shall provide marking for each layer
thickness to avoid excess of material. QC to monitor
each layer placement and tool Box Meeting shall be
conducted.

Root Cause Analysis: Negligence of Third Party (AL-


During internal inspection on date 30-July-2019 at CPP- OSAIMI) and not having enough approved technicians to
Precast Yard-2 HRDH it was found that the Third Party accommodate Client requirements.
Technician Assigned for the Concrete sampling and Correction Action: Provide Approved and Competent
testing was not Technically Competent which is a Technician at site to execute the job with in the Aramco
T-CPP-
CPP-NGCP-NCR-CIV-047 Incompetent Technician violation as per Schedule Q,Attachment-1,Sec-5.5 standards and CTTA card shall be available all the time
125 NA ARAMCO- Civil Schedule Q Sec-5.5 Sufiyan Ali 31-Jul-19 08-Aug-19 05-Aug-19 CLOSED
EPM-INCR-6600003667 from 3rd Party which states that “CONTRACTOR, subcontractors and with them to allow for work according to the Client
02712
third party agency Quality personnel assigned to the requirements. Corrective Action:
WORK shall meet the minimum qualification Third Party (Al Osaimi) shall increase their technicians
requirements of Attachment I of this Schedule “Q”, and according to the Contractor need and shall have
must be technically competent to perform their duties.” Minimum Qualification Requirement as per Schedule Q.

On July 18, 2019, CPP QC observed during site Root Cause Analysis:
inspection at KM 0+638 HRDH-1170 8”X0.344” pipes Constriction activity performed without informing to
and cable found backfill without verifying the clearance quality department.
from existing pipeline and cable to the new pipeline. Correction Action:
PIPELINE AND CABLE This is clear violation of SATIP-450-04 item No # 3.14 Verified subjected crossing locations before finalizing
CPP-NGCP-NCR-M-019 T-CPP-
CROSSING and SAES-L-410 PARA 13.4.2, this standard requires berms
126 EPM # INCR- NA ARAMCO- Mechanical SATIP-450-04 PARA 13.4.2 M Umair 18-Jul-19 07-Aug-19 05-Aug-19 CLOSED
CLEARANCE the buried pipelines crossing each other shall have a THIS INCR IS ESCALATED TO LBE
6600003363 02714
VERIFICATION. minimum clearance of 0.6 M (2 ft) and shall be Corrective Action:
increased as achievable. For telecommunication cable, Awareness toolbox, early information and RFI for
the minimum vertical distance between the bottom of verification.
any pipe and the top of the concrete encased conduit
bank shall be 1 M. SAES-T-928 PARA 6.7.1-A.

While opening vendor packing box for visual inspection


of ball valve 16” ball valve class # 600 (SERIAL #
98177, Tag # H92-HWYH GGM-MOV-0169) at TCF-1
ware house 04THAug, 2019 1” GATE VALVE CL # 800
(SERIAL # 99595 -Vent valve) is found with bent stem,
gland.
This is a Violation of:
1) SAEP-35 Para 5.1 which states “Appropriate care Root Cause Analysis: To be provided by Company/
and consideration shall be taken to prevent any damage Valve vendor.
to the valve assembly during handling and Correction Action: CPP
CPP-NGCP-NCR-M-020 T-CPP- BALL VALVE 16”
transportation”. reported SAPMT/SAPID Representative- for further
127 EPM # 6600003679 ARAMCO- Mechanical CLASS # 600 Found SAEP-35 Para 5.1 Irshad Alam 08-Aug-19 06-Nov-19 05-Nov-19 CLOSED
2) Approved Procedure from Project Quality Plan (CPP- action.
02714 Damage
NGCP-QC-PRO-0010, rev-02) for ‘Material Handling,
Storage and Preservation Procedure’, Para 6.3.2 states
‘Upon receiving the material, it is the responsibility of
the Material Controller to ensure all item have receiving
in accordance with the P.O. delivery note and relevant
document, any overage shortage, physical damage
noted at that time shall be documented ESD report, and
intimated to the Project Manager, Procurement
Department and QA/QC Dept.

On Aug 03, 2019, CPP QC noticed during post weld


inspection that excessive capping (Reinforcement) of Root Cause Analysis: Due to welder negligence. As he
the weld joint in certain points (3.3mm). at 8”-HWYH- was in hurry to complete Joint welding.
CPP-NGCP-NCR-W-036 Excessive 1074 F/L joint 04-FW-340 Welder W-104. This violates Correction Action: Excessive capping will be ground.
128 EPM- 6600003666 Welding Reinforcement @ 8”- API 1104 Para 7.8.2 the wps-15 rev.00. it has clearly mentioned that max Varun O.S 03-Aug-19 23-Aug-19 22-Aug-19 Corrective Action: Awareness toolbox will be Closed
HWYH-1074 F/L weld capping height is (0.8 –1.6mm) and API 1104 Para conducted to follow the WPS requirement.
7.8.2 “At no point shall the crown surface fall below the Corrective Action:Corrective Action And implemented
outside surface of the pipe, nor should it be raised this INCR Closed
above the parent metal by more than 1/16 in. (1.6 mm)”

On Aug 04, 2019, CPP QC noticed during routine Root Cause Analysis: Welding crew didn’t have
inspection at 10”-HWYH-1093 F/L that welding crew not sufficient material to cover the open areas of wind shield.
provided proper wind shield during welding on weld joint Correction Action: RT will be done on joint number 03-
03-FW-258 at KM 03+103, it is clear volition of SAES- FW-258 for ensuring the soundness of the joint.
CPP-NGCP-NCR-W-037 Improper wind shield W-12, paragraph 10.2.1 “Wind shields or tents shall be Corrective Action: Sufficient
129 EPM- 6600003689 Welding during Welding @ 10”- SAES-W-12 paragraph 10.2.1 required when the wind is strong enough to affect arc Asish 04-Aug-19 24-Aug-19 22-Aug-19 material will be provided and inspection of wind shield Closed
HWYH-1093 F/L stability or shielding gas coverage or when deemed will be done before welding by welding foreman and
necessary by Saudi Aramco Inspection. GTAW, welding inspector
GMAW, or gas-shielded FCAW shall not be used for Corrective Action:Corrective
field or yard fabrication unless adequate windshields Action And implemented this INCR Closed
are used

On Aug 22, 2019, CPP QC noticed during routine


inspection at 8”-HWYH-1003 F/L it was observed that
Root Cause Analysis: Poor Workmanship and lack of
GTAW Filler Wire placed on the ground during Welding
knowledge
Improper consumable of joint 01-FW-155 which may contaminated by dust, it
CPP-NGCP-NCR-W-038 .Correction Action: RT will be done on joint number 01-
130 Welding handling @ 8”-HWYH- SAES-W-12 Appendix 2 is clear volition of SAES-W-12, Appendix 2 “All Sanjeeva 22-Aug-19 21-Sep-19 25-Sep-19 Closed
EPM- 6600003754 FW-155 for ensuring the soundness of the joint.
1003 F/L electrodes and wires shall be stored in sealed
Corrective Action: Awareness toolbox will be
containers in a dry environment. Any wires that have
conducted to avoid repeating such performance.
visible rusting or contamination shall not be used and
shall be discarded”.

Root Cause Analysis: Contractor construction crew


failed to provide the suitable supports for external
On dated 27 August 2019 during site inspection at
coated pipe which strung along the right of way.
HRDH-AK-RH Between the joints FW 117 and FW-235
Correction Action:
it was observed that coating damaged on several
Holiday testing and repair will be performed all the
CPP-NGCP-NCR-H-017 Coating damaged on locations this is the standard violation against SAES-H-
131 Coating SAES-H-200 Para 5.3 31-Aug-19 11-Sep-19 05-Sep-19 coating damaged area prior to lowering into the trench. Closed
EPM-6600003907 pipes. 200 of Para 5.3 Externally coated line strung along the
Corrective Action: Tool box meeting shall be delivered
right of way shall be supported on rock-free sand,
to construction team in order to avoid such issues re-
sandbags, rubber tires,or similar compressible material
occurrence
to prevent coating damage.

Page 23 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

During the site surveillance on 26th July, 2019 at


Root Cause Analysis: Pipe thread damage during the
Installation for HDC2CL-2 to HDC2CL-1 as sta.3+000 to
loading and unloading
3+450, it was observed that the RTR pipe thread for the
Correction Action: The pipe be moved in the
Pipe No: 121919170120072 is found damaged which
quarantine area. Manufacturer (FPI) site supervisor will
violates SAES-L-650, 8, h) which states that” Threads
Damaged Threads on evaluate the nature and extent of damage. The subject
CPP-NGCP-NCR-RTR- shall be cleaned and carefully inspected before joining
the Pin End 10” Inch damaged pipe shall only be used if it authorized by
132 001 EPM-INCR- RTR/Plumbing SAES-L-650 Para 8, h and shall be free from any visible damage. Thread 26-Aug-19 26-Sep-19 22-Sep-19 Closed
Pipe manufacturer.
6600003843 damage evaluation shall be in accordance with the
No:121919170120072 Corrective Action: Construction team shall take care of
manufacturer construction manual. Where criteria are
pipes and fittings during the loading and unloading. RTR
not established, any thread damage shall be cause for
QC will conduct Quality Tool Box to aware the
rejection until resolved in writing by the manufacturer.”
construction the handling, storage, preservation,
unloading and loading of pipe and fittings.

Root Cause Analysis: Negligence of installer to follow


the Saudi Aramco Engineering Standards and
During the site surveillance on 26th July, 2019 at
Manufacturer requirement during the jointing of pipes.
Installation HDC2CL-2 to HDC2CL-1 sta. 3+000 to
Correction Action: Manufacturer site supervisor shall
3+450, it was observed that the RTR pipe installer
inspect the joint integrity and pipe surface shall be
CPP-NGCP-NCR-RTR- jumping over the installed Pipe No: 121917170120099
Poor Workmanship at qualified for acceptance by manufacture site supervisor.
133 002 EPM-INCR- RTR/Plumbing SAES-L-650 Sec 9.1 near the Joint No: 08 which violates SAES-L-650, Sec 26-Aug-19 15-Sep-19 15-Sep-19 CLOSED
Site During Installation Furthermore, pipe whole length will be visually inspected
6600003844 9.1, f) which states that” Where poor workmanship is
to verify that there is no bulging caused due to sudden
identified, they shall be reported in inspection logbook
load by jumping over the joint. Preventive Action:
for corrective action. A connecting joint identification
RTR QC shall arrange QTBM to aware the installers
system shall be developed.
SAES and Manufacturer requirements during jointing the
pipes.

Root Cause Analysis: Negligence of construction team


During daily site visit on date 3-09-2019 at Yard 2 and ignoring the standard requirements.
Haradh, it was observed that the Construction team is Correction Action: Remove the schedule 40 spacers
using PVC Schedule 40 Pipe as a rebar Supporter and from the foundations and replace it with schedule 80
Used of Low-Grade
CPP-NGCP-NCR-CIV-048 Spacer in the PS-01 Foundations which is a violation as PVC pipes and Notched from the bottom to allow the
134 Civil PVC Spacers and SAES-Q-012 Sec-6.7 Hameedullah 03-Sep-19 17-Sep-19 09-Sep-19 CLOSED
EPM-INCR-6600003913 per SAES-Q-012-Sec-6.7 which states that” Reinforcing ingress of concrete. Corrective Action:
supporters for Rebar
steel, where required, shall be supported with plastic or Construction team will purchase only PVC schedule 80
galvanized chairs. However, the use of PVC Schedule pipes for spacers and supporters. QC Civil Inspector
80 pipe as spacer is allowed. shall arrange Quality Tool Box meeting to aware the
Standard requirements.

Root Cause Analysis:


Negligence of Construction team and Ignoring the
SAES-Q-001 Requirements.
During internal inspection on date 03-Sep-2019 at CPP- Correction Action:
Precast Yard-2 HRDH it was found that the FBE coated Construction team shall Remove the Coated Rebar from
Not Maintaining Rebar were Directly in Contact with Ground Surface Ground and shall place it on the wood ribs or provide
CPP-NGCP-NCR-CIV-049 09-SAMSS-
135 Civil Preservation for FBE Sec. 15.3 which is Violation As per 09-SAMSS-106-Sec.III.B Sufiyan Ali 03-Sep-19 10-Sep-19 05-Sep-19 Polyethylene sheet beneath Rebar. QC inspector will CLOSED
EPM-INCR-6600003853 106-Sec
Coated Rebar which states that “Coated steel reinforcing bars shall be verify at Yard after Correction.
stored off the ground on protective cribbing. (ASTM Corrective Action:
A775/A 775-07b, Sec. 15.3)” Construction Team shall have padded area for storage
of FBE Coated rebar or Plastic sheet with a minimum
thickness of 0.25mm.

Root Cause Analysis: Negligence of construction team


During daily site visit on date 9-09-2019 at Yard 2 and ignoring the standard requirements
Haradh, it was observed that FORMWORK Inside Correction Action: All the
Surface for Skid foundation type1 was containing dust contaminated surfaces of Formwork shall be cleaned of
NO PROPER
CPP-NGCP-NCR-CIV-050 contaminated with form oil which is a violation as per dust, contaminated oil and other foreign material and
136 Civil FORMWORK SAES-Q-001 Sec. 3.2 Hameedullah 09-Sep-19 27-Sep-19 14-Sep-19 Closed
EPM-INCR-6600004050 SAES-Q-001-Sec. 3.2 which states that” Formwork provide new formwork oil.
CLEANING
surfaces and embedded materials are cleaned of Corrective Action: Construction team shall cover
mortar, grout, and foreign materials before concrete all foundations prior to concrete pouring and form
placement. (ACI 301-2010, Sec. 2.3.1.14)”. release agent shall be clean of any foreign material.
Toolbox meeting will be delivered.
Root Cause Analysis: Manufacturer transported the
pipe which is not as per standard requirements.
During Material receiving inspection on date 12-SEPT-
Correction Action: Subject defective RTR 12” pipe #
2019 at TCF1 yard, it was observed that one RTR 12”
121930104120084 remove from storage area and shift
pipe # 121934104120084 as per delivery note #
to quarantine area.
Discoloration and 0112120159949 arrived at CPP yard having fiber
CPP-NGCP-NCR-RTR-03 Corrective Action: CPP
137 RTR/Plumbing Roughness of the pipe SAMSS-042 Para 12.6.10 blooming discoloration and roughness of the pipe 12-Sep-19 12-Oct-19 11-Nov-19 CLOSED
EPM-INCR-6600004100 will inform the manufacturer (FPI) to make sure that
surface surface which is clear violation as per the 01-SAMSS-
pipes transported to CPP shall meet the standard
042 Para 12.6.10 which states that “Pipes and
requirements. Furthermore, CPP RTR material receiving
fittings shall be inspected for evidence of damage or
inspector will strictly monitor and check each and every
distortion.
pipe prior to receiving.

During site Inspection on date 12-Sep-2019 at HRDH


1192, it was observed that during lowering at Sta-2+500 Root Cause Analysis: Negligence of construction team.
the side of the trench was slided down into the trench Correction Action: All the slided edges of the trench
Insufficient Trench which makes the Bottom width of the trench around was removed at site and verified together with QCI and
CPP-NGCP-NCR-CIV-051
138 Civil Bottom Width for 8” SAES-L-450 Sec. 14.9.3b 400mm which is a violation as per SAES-L-450, Sec. 12-Sep-19 30-Sep-19 25-Sep-19 PID. Corrective Action: Construction team Closed
EPM-INCR-6600004097
Pipe at HRDH-1192 14.9.3b which states that” the minimum width of the shall not move Heavy Equipment’s near to the trench
bottom of the trench in rocky areas shall be 600 mm edges and shall maintain Minimum 6m distance while
wider than the pipe. The pipe shall be centered in the lowering the pipe or moving the equipment’s.
trench.

Root Cause Analysis:


Negligence of Construction team and Ignoring the
SAES-H-003 Sec. 7.4.4 Requirements.
During internal inspection on date 17-Sep-2019 at CPP- Correction Action:
Not Maintaining the Precast Yard-2 HRDH it was found that the Surface Construction team shall Remove all Lose Material and
CPP-NGCP-NCR-CIV-052 Proper Surface Preparation is not proper all the Honeycombs are not Fill the Honeycombs with Approved Material. QC
139 Civil SAES-H-003 Sec. 7.4.4 17-Sep-19 25-Sep-19 21-Sep-19 Closed
EPM-INCR-6600004151 Preparation Before Repaired Even Edges are also Damaged which is inspector will verify at Yard after Correction.
Coating Violation as per SAES-H-003 Sec. 7.4.4 which states Corrective Action:
that “All voids shall be prepared, primed and filled. CPP quality inspector will deliver a quality tool box
meeting to construction foreman at yard to avoid
recurrence

On dated 24 September 2019 during preclearing


inspection of joints at HRDH-1306 near to the joint
FW#62 it was found that metal damaged on pipe it is a Root Cause Analysis:
CPP- NGCP-NCR-H-018
clear violation against SAES-W-012 of para 10.15 Improper workmanship that may be affected the metal
140 EPM# INCR- 6600004239 Coating Metal damaged on pipe para 10.15 SAES-W-012 24-Sep-19 10-Oct-19 10-Oct-19 Closed
coated and clad or overlaid surface shall be protected damaged on pipes.
from the welding arc,associated weld spatter,and
damage from ground clamps or other associated
equipement.

Page 24 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis:
Due to everyday loading and offloading of coated pipes
On September 24, 2019,During Inspection it was found
hook pad got damaged.
that loading crew were lifting the coated pipes by hook
Correction Action:
CPP-NGCP-NCR-M-022 T-CPP- without padded it is the standard violation against
Lifting coated pipes by Muhammad The damaged pad shall be replaced and the hook shall
141 EPM #INCR ARAMCO- Mechanical Para 5.1.5 SAES-H-200 SAES-H-200 Para 5.1.5 for lifting operations when a 24-Sep-19 10-Oct-19 10-Oct-19 Closed
hook without pad. Saleem be covered with new rubber or shall be padded.
6600004240 02714 hook is used for handing large diameter pipes the hook
Corrective Action:
shall be of sufficient width and depth to fit inside the
Contractor QC will keep monitoring the hook while
pipe and shall be padded or covered with rubber.
loading and offloading of coated pipes.

On Sep 17, 2019, CPP QC noticed during routine Corrective Action: Awareness toolbox will be
inspection at 8”-HWYH-1003 F/L it was observed that conducted to avoid repeating such performance.
Modification of pipeline accepted pipeline string has been cutout without Correction Action:
CPP-NGCP-NCR-W-039
string after weld SATIP-W-12- information to maintain the cable crossing 1.0 M as per Additional weld joint will be added at the cutout point, PT
142 EPM #INCR Welding SH 004 Sanjeeva 17-Sep-19 16-Dec-19 16-Nov-19 Closed
acceptance @ 8”- 01 DWG TA-445856 SH 004 Rev 00, it is clear volition of test will be done at cutting edge and RT after welding to
6600004160
HWYH-1003 F/L SATIP-W-12-01, Item no 3.17 “Modification or Re-Work check welding soundness.
After Weld Acceptance is a Hold point by contractor and Root Cause Analysis: Lack of standard
Saudi Aramco”. awareness by construction crew.

Corrective Action: Awareness toolbox training will be


conducted to prevent future
On Sep 19, 2019, CPP QC noticed that the welding
recurrence, Site QC to monitor closely to follow standard
shelter was open during welding at HWYH-1112 joint #
CPP-NGCP-NCR-W-040 Improper shielding requirement.
(00-FW-022) which is a standard violation as per SAES-
143 EPM #INCR Welding during welding at SAES-W-012 Para 10.2.3 Sanjeeva 19-Sep-19 08-Oct-19 08-Oct-19 Correction Action: wind shelter shall be closed during Closed
W-012 (Para 10.2.3) which states that “Contamination
6600004093 HWYH-1112 welding and joint 00-FW-022 will be covered by 100 %
from the environment, such as wind-blown sand, shall
RT. Root Cause Analysis: welder’s
be prevented by the use of adequate shielding”.
tendency to open the tent door to avoid heat during high
temperature weather condition.

On Sep 22, 2019, CPP QC noticed an arc strike during Corrective Action: : Proper fixing of grounding clamp
the welding activities of joint no. 03-FW-269 at 8”- shall be provided for further fit-up and welding activities.
CPP-NGCP-NCR-W-041 HWYH-1073. This violates SAES-W-012, 10.10, which Correction Action: Correction Action: Grinding the
Arc strike at @ HWYH-
144 EPM #INCR Welding SAES-W-012 , 10.10, states: Arc strikes, gouges, and other indications of 22-Sep-19 09-Oct-19 08-Oct-19 defected area to remove the arc strike and apply PT test, Closed
1073
6600004269 careless workmanship (such as surface porosity, ground clamp to be fixed.
uneven weld profiles, and undercut) shall be removed Root Cause Analysis:Improper
by grinding. condition and fixing of grounding clamp

On Sep 23, 2019, CPP QC noticed during routine


Corrective Action: : Awareness toolbox will be
surveillance that the welder left electrodes in the quiver
conducted to avoid power switching off if the ovens filled
during lunch time and power was switch off, the
by electrodes.
temperature was below 65°C and the exposure time
CPP-NGCP-NCR-W-042 Improper handling of Correction Action: The affected electrodes are
exceed 2hr at 10" HWYH-1036 F/L which is a standard
145 EPM #INCR Welding welding electrodes @ SAES-W-012 Appendix 1 Varun O.S 22-Sep-19 22-Oct-19 08-Oct-19 discarded. One joint 00-FW-066 welded at Sep 23 will Closed
violation as per SAES-W-012 (Appendix 1) which states
6600004297 10" HWYH 1036 F/L covered by RT to verify weld soundness.
that “The exposure times may be doubled (to 4 hours
Root Cause
and 1 hour, respectively) if the electrodes are
Analysis:Welding foreman switch off power of electrode
continuously stored in a portable electrode oven heated
oven switch off during lunch time.
to 65°C minimum”.

Corrective Action: : CPP will inform the vendor to patch


the cut and bends of rebar before delivering to CPP.
CPP quality inspector will conduct a quality toolbox
During internal inspection of Rebar on date 25-Sep-
meeting to enhance the awareness to site foreman and
2019 at CPP-Precast Yard-2 HRDH it was found that
laborers to touch up the cut ends (if found) before
the FBE coated Rebar Were Installed for PS-06
CPP-NGCP-NCR-C-053 Not Apply the Touch installation of rebar.
foundations but didn’t Apply the Touch Up Paint at cut
146 EPM #INCR Civil Paint on End Cuts of SAES-Q-001 Sec. 5.6 26-Sep-19 05-Oct-19 03-Oct-19 Correction Action: Cut ends will be patched with Closed
ends and bends of Rebar which is Violation as per
6600004228 Rebars approved material for installed rebar. QC inspector will
SAES-Q-001 Sec. 5.6 states that ‘’All field cut ends of
verify at Yard after Correction.
rebar are coated with approved Epoxy Coating Material.
(ASTM A775/ A775M-2007, Sec. 11.4)’’
Root Cause Analysis:Some Cut ends were found un-
patched from vendor and construction team failed to
patch the ends before installation.

On Oct 04, 2019, CPP QC noticed during routine


inspection at 8”-HWYH-1003 F/L it was observed that Root Cause Analysis: Poor Workmanship and lack of
GTAW Filler Wire kept on the ground during Welding of knowledge
CPP-NGCP-NCR-W-045 Improper Handling of joint 06-FW-512 which may contaminated by dust, it is .Correction Action: The affected filler wires are
147 EPM Welding GTAW Welding Rods SAES-W-12 Appendix 2 clear volition of SAES-W-12, Appendix 2 “All electrodes Asish 03-Oct-19 30-Oct-19 24-Oct-19 discarded and RT will be done on joint number 06-FW- Closed
#INCR6600004447 @ 8”-HWYH-1003 F/L and wires shall be stored in sealed containers in a dry 512 for ensuring the soundness the joint.
environment. Any wires that have visible rusting or Corrective Action: Awareness toolbox will be
contamination shall not be used and shall be conducted to avoid repeating such violation.
discarded”.

On Oct 02, 2019, CPP QC noticed the pipe bevel was Root Cause Analysis: Careless workmanship from
not properly cleaned (Less than 25mm) prior to welding welding crew & unawareness of SAES-W-012
the weld joint 10-FW-859 at 16'' HWYH HK RH TR/L. Requirements.
CPP-NGCP-NCR-W-047 Not sufficient surface This violates SAES-W-012, 10.3.1, which states: Oil, Correction Action: Joint 10-FW-859, shall be 100%
148 EPM #INCR Welding cleaning @ 16'' HWYH SAES-W-012 10.3.1 moisture, rust, scale, sand, paint metallic coatings (e.g., Abdul 02-Oct-19 30-Oct-19 27-Oct-19 radiograph to ensure integrity/ soundness of weld. Closed
6600004429 HK RH TR/ zinc), or other foreign matter shall be removed from the Corrective Action:
weld surface and at least 25 mm of adjacent base metal Awareness Toolbox training will be conducted to prevent
prior to welding, including any such coatings on future recurrence, Site QC to monitor closely to follow
temporary attachments or supports. standard requirement.
Root Cause Analysis: Helper Un aware of handling of
On Oct 02, 2019, CPP QC noticed during routine
electrodes.
surveillance that the helper forgot to close the portable
Correction Action: The
CPP-NGCP-NCR-W-046 Opened portable oven oven lid after giving the electrodes to welder. Joint no:
affected electrodes are discarded. RT Will be done for
149 EPM #INCR Welding during welding @ 16”- SAES-W-012 Appendix 1 10-FW-862 @ 16”-HWYH-HK-RH-TR/L which is a Abdul 02-Oct-19 30-Oct-19 24-Oct-19 Closed
joint 10-FW-862 to check weld soundness.
6600004442 HWYH-HK-RH-TR/L standard violation as per SAES-W-012 (Appendix 1)
Corrective Action: Awareness toolbox will be
“Storing, Conditioning and exposure of SMAW
conducted regarding control and handling of
Electrodes Low Hydrogen Electrodes”.
Root Cause Analysis:consumables.
Careless workmanship from the
welders.
During routine inspection at HWYH-921, joint # (06-FW-
Correction Action: 100% RT will be performed for the
553) Welder (CPP-W-016) it was observed that welding
joint # 06-FW-553 to ensure quality/soundness of
CPP-NGCP-NCR-W-044 Insufficient wind shelter was open from both sides during welding in
welding.
150 EPM #INCR Welding shielding during welding SAES-W-012 Para. 10.2.1 strong wind which is a standard violation as per SAES- M Rizwan 05-Oct-19 05-Nov-19 23-Oct-19 Closed
Corrective Action: CPP QC Welding Inspector will
6600004444 at HWYH-921 W-012, Para. 10.2.1 which states that wind shelter or
monitor closely and Awareness Toolbox training will be
tents shall be required when wind is strong enough to
conducted to prevent future Recurrence.
affect arc stability or shielding gas coverage.

During site Surveillance on date 10-Oct-2019 at HRDH


1160, it was observed that before Dumping of Select Fill
Root Cause Analysis: Negligence of Surveyor.
Material for the fourth layer, the surveying sticks for the
Wrong Elevation of Corrective Action: Surveyor shall mark the Surveying
CPP-NGCP-NCR-W-054 layer elevation was more than 300mm which is a
151 Civil layer and Improper SAES-A-114 Sec. 6.3.7 10-Oct-19 20-Oct-19 17-Oct-19 sticks according to Required Material Elevation as per Closed
EPM #INCR violation as per SAES-A-114-Sec. 6.3.7 which states
Surveying Standard and as per IFC Drawing.
that” Compacted surfaces of fill and backfill shall be
finish graded to the cross sections, lines, grades, and
elevations as indicated on the drawings.”

Page 25 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

During the hydrotest activity, between HDC2CL2 to


HDC2CL1 10" RTR Condensate line (Test Length 490
Root Cause Analysis: FPI will investigate and provide
Mater; Station No B/B (3+000 to 3+490 Joint number 40
root cause.
CPP-NGCP-NCR-RTR-04 Leakage found during to 41) on 6th October 2019, Leakage found at the pin
152 RTR/Plumbing SAES-L-650 Para 11.6. 09-Oct-19 10-Jan-20 Corrective Action: Effected pipe Closed
EPM-INCR-6600004408 hydrotest of RTR end of the pipe No # 12191570120024, This is clear
shall be replace and Re hydrotest shall be perform.
violation of SAES-L-650 Para 11.6. "If during hydrotest
there is evidence of leakage, the leak source shall be
identified and repaired, and the hyrotest repeated"
Root Cause Analysis: Negligence of Manufacturer to
During Material receiving inspection on date 09-Oct- maintain the documentation of delivered material
2019 at TCF1 yard, it was observed that one RTR 12”
pipe # 121935103120101 as per delivery note # Corrective Action: CPP shall move the pipe in the
0112120167992 arrived at CPP yard having two quarantine are until Manufacture shall provide new
CPP-NGCP-NCR-RTR-05 Traceable to the
153 RTR/Plumbing SAES-L-650 Para 6.2,h traceable number which is clear violation as per the 09-Oct-19 13-Dec-19 12-Dec-19 delivery note which comply with pipe CLOSED
EPM-INCR-4533 material certificate
SAES-L-650 (Para 6.2,h) which states that “The #121935103120101. Preventive Action: CPP
product code for each pipe and fitting shall be verified to RTR QC shall firmly monitor the delivered material and
be traceable to the material certificate prior to manufacture shall make sure the documents comply with
installation. the delivered material.
Root Cause Analysis: Construction team didn’t follow
During daily site visit on date 12-OCT-2019 at HWYH- the SAES-L-450 requirements.
1036 it was observed that waste material on both sides Correction Action: The construction team shall remove
of the right of way at HWYH-1036 from km 2+300 to all the waste material from the right of way and carry it to
CPP-NGCP-NCR-CIV-055
Waste Material on both 3+900. But the construction team has started the Right the approved designated location.
154 INCR# EPM-INCR- Civil SAES-L-450 Sec.19.1 12-Oct-19 17-Nov-19 18-Nov-19 Closed
sides of Right of Way of way without remove waste material which is clear Corrective
6600004530
violation of SAES-L-450 Sec.19.1 Construction waste Action: Construction team shall remove all the waste
materials shall be removed from the right-of-way as the material from the right of way. Subsequently, CPP
construction progresses. quality department will firmly monitor the right of way
work.

Root Cause Analysis: Careless workmanship and lack


of awareness/knowledge.
During the CPP yard surveillance on dated 03-July- Correction Action: Cable drum shall be carefully placed
2019 it has been observed that the MV cable reels is on the flanges without damaging the cable.
Unapproved method of placed on the flat side of flanges which is non- Corrective Action:
CPP-NGCP-NCR-E-009
155 Electrical/CP MV cable drum NEC110.3 SAIC-P-3201 compliance the standard requirements as per 13-Oct-19 13-Nov-19 31-Oct-19 The CPP yard supervisor is strictly instructed not to Closed
EPM-INCR-6600004519
placement NEC110.3, SAIC-P-3201 which clearly stated that violate the standard requirements. A quality tool box
“Cable reels shall be shipped and handled on edges of meeting will be delivered in order to increase the quality
flanges only (not on flat side of flanges)”. awareness. Subsequently, quality department will
enhance the CPP yard surveillance to avoid recurrence.

Root Cause Analysis: Construction team Failed to


comply the requirements of SAES-A-111 Table 1
During daily site visit on Date 12-October-2019 it was Correction Action: Site
observed that the distance from the boundary of construction team shall propose another area for borrow
CPP-NGCP-NCR-CIV-056 Borrow pit near Well pad RH-CK Hawiyah existing oil pit
Setback Distance from
156 EPM-INCR# 6600004504 Civil SAES-A-111 Table -1 and Gas sites is 50 meter which is Violation as per 12-Oct-19 12-Nov-19 18-Nov-19 location to take sample. Closed
the Borrow pit
SAES-A-111 Table -1 which states that “ minimum Corrective Action: CPP site QC inspector will deliver a
setback distance from the boundary of Borrow pits shall quality toolbox to site construction team to enhance the
be 100meter from the existing oil and Gas sites borrow pit location construction requirements.
Subsequently, CPP QC department will closely monitor
to avoid re-occurrence.
Root Cause Analysis: Construction team ignored the
SATIP-L-450-01 requirements.
During site Surveillance on date 14-Oct-2019 at HRDH Correction Action: Construction team will remove the
CPP-NGCP-NCR-CIV-057 Sand bedding & 1171, it was observed that construction team backfill the backfill material from trench and offer to SAPID to
157 EPM-INCR# 6600004586 Civil lowering without STA 4+941 SATIP-L-450-01. Tie-in joint @STA 4+941 to 5+054 without sand bedding 14-Oct-19 14-Nov-19 14-Nov-19 inspect the sand bedding and lowering activities. CLOSED
inspection. and pipe lowering inspection it is clear violation as per Corrective Action:
SATIP-L-450-01. QC Civil Inspector will arrange Quality tool box to
describe the construction team SATIP-L-450-01
requirements.

Root Cause Analysis: Careless workmanship and lack


During the CPP yard surveillance on dated 15-Oct-2019 of awareness/knowledge.
it has been observed that the overhead poles had been Correction Action: Overhead
placed in three layers which violates the standard Poles shall be placed in two layers with necessary
requirements which clearly states that “Poles shall be separators without damaging the poles Corrective
CPP-NGCP-NCR-E-10
Overhead Poles placed delivered in bundles of 6 poles with the arrangement of Action:
158 EPM-INCR# 6600004596 Electrical/CP 16-Oct-19 16-Nov-19 31-Oct-19 Closed
in three layers 2 layers, with 3 poles per layer, and strapped at four (4) The CPP yard supervisor is strictly instructed not to
locations of equal distances with the use of steel straps violate the standard requirements. A quality tool box
size 31 mm x 0.8 mm (min.) and necessary wood meeting will be delivered in order to increase the quality
separators, padding or cushion material underneath the awareness. Subsequently, quality department will
steel straps.” enhance the CPP yard surveillance to avoid recurrence.
.

On Oct 14, 2019, CPP QC noticed during routine


Root Cause Analysis: welding done without coating
surveillance that the pipe coating was damaged during
protection from welder.
welding at 8’’-UTMN 2231 F/L Joint # (02-FW-173)
CPP-NGCP-NCR-W-49 Pipe coating damage Correction
which is a standard violation as per SAES-W-012 (Para Muhammad
159 EPM-INCR#6600004523 Welding during welding @ 8’’- SAES-W-012 Para 10.15 14-Oct-19 15-Dec-19 16-Nov-19 Action: Touch up will be done for damage area and will Closed
10.15) which states that “coated and clad or overlaid Shahbazudain
UTMN 2231 F/L be verified by holiday test.
surface shall be protected from the welding arc,
Corrective Action: Awareness toolbox
associated weld spatter, and damage from ground
will be conducted to construction crew.
clamps or other associated equipment”.

Root Cause Analysis:


Foundations were not kept in enough space to avoid
over spray from the coating application on nearby
foundations.
On dated 15 Oct 2019 in CPP concrete coating yard
Corrective Action:
HARADH2, during inspection of APCS-03 Coated
Defective area should be roughened with coarse emery
OPTF foundations PS-06, It was observed that on 2
paper to remove over spray from top layer and applied
CPP-NGCP-NCR-CIV-58 foundations finished coating has application defects,
one more coat to make the final layer uniform and free of
160 EPM-INCR#6600004610 Civil Civil/Coating SAES-H-001 Para 9.3.5 Such as pin holes and over spray. This is violating the 15-Oct-19 15-Nov-19 15-Nov-19 Closed
application related defects.
finished coating dry film requirements as per SAES-H-
Preventive Action:
001 Para 9.3.5. which states that “Finished coating film
CPP construction team will provide enough space
shall generally free of application related defects such
between foundations to avoid over spray. Furthermore,
as runs, sags, drips, dry spray or foreign matter.”
CPP quality inspector will deliver a quality toolbox to
enhance the awareness. Subsequently, CPP quality
department will firmly monitor to avoid recurrence.

Page 26 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

Root Cause Analysis:


Negligence by Construction crew towards Saudi Aramco
On dated 14 October 2019 during site surveillance at
Engineering Standards and Requirements.
HWYH-EJ RH flow line it is found that welded string
Correction Action:
(joint FW-156) has been laid on rocky soil and coating
Coating damaged pipes shall be lifted by proper padded
deteriorated on pipes. It is a clear violation of Material
support with a minimum gap of 150mm off the ground
CPP-NGCP-NCR-H-19 handling storage and preservation procedure (CPP-
PRO-0010 with rock free sand padding.
161 EPM-INCR#6600004524 Coating Mechanical/Coating para 7 NGCP-QC-PRO-0010 Rev-02) para 7d which states 14-Oct-19 29-Oct-19 27-Oct-19 Closed
Rev-02 Corrective Action:
that “During storage the coated pipes shall be placed at
Toolbox meeting shall have arranged for construction
least 150 mm off the ground or on either rock free sand
crew on importance of Saudi ARAMCO Engineering
berms covered with polyethylene sheeting or on padded
Standards and Requirements. Care shall be taken by
skids spaced and leveled so that the pipes are
construction crew during the padding activity to comply
supported without damaging the coating”.
with SAES-H-200, Storage and Handling requirements.

Root Cause Analysis:


On dated 14 October 2019 during site surveillance at
Negligence by construction team towards Saudi Aramco
HRDH-DK RH TR/L it was observed that welded string
engineering standards and requirements.
(joint FW-551 and 552) external coating has damaged .
Correction Action:
CPP-NGCP-NCR-H-20 It is a clear violation of Material handling storage and
Coating damaged on PRO-0010 Holiday testing and repair shall be done on the damaged
162 EPM-INCR#6600004601 Coating para 7 preservation procedure (CPP-NGCP-QC-PRO-0010 14-Oct-19 29-Oct-19 28-Oct-19 Closed
pipe. Rev-02 area prior to lowering in the trench.
Rev-02) para 7a which states that “The coated pipe
Corrective Action:
shall be handled at all times in a manner that prevents
Tool box meeting shall be conducted to construction
damage to the pipe walls, beveled ends and to the
team in order to avoid any reoccurrence of such issues.
While opening vendor applied coatings.
packing box for visual inspection
of 20” ball valves class # 900 (SERIAL # 18-98265, Tag
# H91-HRDH-RHEK-MOV-0001) and (SERIAL # 98266,
Tag # H91-HRDH-RHEK-MOV-0002) at TCF-1 ware
house on 12TH Sep, 2019 is found that the hand
wheels were broken this is a Violation of: Correction Action: CPP reported SAPMT/SAPID
CPP-NGCP-NCR-M-021 T-CPP- BALL VALVE 20”
(i) SAEP-35 Para 5.1 which states “Appropriate care Representative- for further action.
163 EPM # INCR 6600004131 ARAMCO- Mechanical CLASS # 900 Found SAEP-35 Para 5.1 Irshad Alam 12-Dec-19 10-Dec-19 CLOSED
and consideration shall be taken to prevent any damage Root Cause Analysis: To be provided by Company/
02714 handle damage.
to the valve assembly during handling and Valve vendor.
transportation.
(ii) As per manufacturer packaging and preservation
procedure check for the physical damage compile the
list
Onof controls
dated and report
15 October thewhile
2019 damage
final to the equipment.
visual inspection Root Cause Analysis:
of ARO Coating at 20”-HRDH-K2-RH-TR/L in KM During activity of Horizontal directional drilling (HDD)
1+418.77 to 1+470.80 it is found that ARO wrapping pipe, pulling hook broken and ARO Wrapping were
CPP-NGCP-NCR-H-21 have damaged on several areas this is a clear violation damaged.
PRO-0026-
164 EPM-INCR#6600004626 Coating ARO Coating damage para1.6.6 against procedure (CPP-NGCP-CM-PRO-0026-Rev 0) 15-Oct-19 14-Nov-19 30-Oct-19 .Correction Action: Closed
Rev 0
of Nonmetallic composite wrapping para1.6.6 protect The damaged area will be sweep blasted again. Holiday
materials during handling and installation to prevent testing, Repair shall be done and DFT, Hardness to be
damage and contamination. verified prior to re pulling.

Root Cause Analysis: Careless workmanship from the


welders.
On Oct 02, 2019, CPP QC noticed during routine
Correction Action: 100% RT will be performed for the
surveillance that the helper forgot to close the portable
CPP-NGCP-NCR-W-043 joint # 06-FW-553 to ensure quality/soundness of
oven lid after giving the electrodes to welder. Joint no:
EPM #INCR Opened portable oven welding.
165 Welding SAES-W-012 Appendix 1 10-FW-862 16”-HWYH-HK-RH-TR/L which is a Abdul Raheem 02-Oct-19 30-Nov-19 24-Oct-19 Closed
6600004442 during welding @ 16 Corrective Action: CPP QC Welding Inspector will
standard violation as per SAES-W-012 (Appendix 1)
monitor closely and Awareness Toolbox training will be
“Storing Conditioning and exposure of SMAW
conducted to prevent future Recurrence.
Electrodes Low Hydrogen Electrodes”.

Root Cause Analysis: Careless workmanship and lack


of communication from welder and welding foreman.
During site Inspection on 05-OCT-2019 at HRDH-619, Correction Action: All the slag and spatter will be
(Joint # 04-FW-366) Welder (CPP-W-076) it was found removed and 100% RT will be performed to ensure
CPP-NGCP-NCR-W-048 Slag and Spatter was that slag and spatters was not clean properly from soundness of weld.
166 EPM # 6600004419 Welding not Clean properly from SAES-W-012 Para-10.6.2 completion of weld joint, Which is a standard violation M Sarfraz 05-Oct-19 05-Nov-19 30-Oct-19 Preventive Action: Quality awareness tool box talk will Closed
completed Weld. as per SAES-W-012 Para-10.6.2 which states that” All be conducted and CPP QC will monitor closely together
slag, flux, and spatter shall be removed from the with welding crew to avoid future recurrence.
completed weld and surrounding areas.

Root Cause Analysis: Careless workmanship and lack


of communication from welder and welding foreman.
On Oct 02, 2019, CPP QC noticed during routine Correction Action: All the slag and spatter will be
surveillance that the helper forgot to close the portable removed and 100% RT will be performed to ensure
CPP-NGCP-NCR-W-050
oven lid after giving the electrodes to welder. Joint no: soundness of weld.
EPM # 6600004511 Opened portable oven
167 Welding SAES-W-012 Appendix 1 10-FW-862 16”-HWYH-HK-RH-TR/L which is a Imran Manzoor 06-Oct-19 30-Oct-19 24-Oct-19 Preventive Action: Quality awareness tool box talk will Closed
during welding @ 16
standard violation as per SAES-W-012 (Appendix 1) be conducted and CPP QC will monitor closely together
“Storing Conditioning and exposure of SMAW with welding crew to avoid future recurrence.
Electrodes Low Hydrogen Electrodes”.

Root Cause Analysis: welder’s tendency to open the


tent door to avoid heat during high temperature weather
On Oct 20, 2019, CPP QC noticed that the welding
condition.
shelter was open during welding at HWYH-1118 joint #
CPP-NGCP-NCR-W-051 Correction Action: wind shelter shall be closed during
Wind shelter was open (01-FW-145E) which is a standard violation as per
EPM #6600004743 welding and joint 01-FW-145E will be covered by 100 %
168 Welding during welding at SAES-W-012 Para 10.2.3 SAES-W-012 (Para 10.2.3) which states that Umair Mukhtar 20-Oct-19 27-Nov-19 16-Nov-19 Closed
RT. Corrective Action: Awareness
HWYH-1118 “Contamination from the environment, such as wind-
toolbox training will be conducted to prevent future
blown sand, shall be prevented by the use of adequate
recurrence, Site QC to monitor closely to follow standard
shielding”.
requirement.

On Oct 24, 2019, CPP QC noticed during routine


Corrective Action: Awareness toolbox will be conducted
inspection at 16”-HWYH-GK RH TR/L it was observed
to avoid repeating such performance.
CPP-NGCP-NCR-W-052 Modification of pipeline that accepted pipeline string has been cutout (Pipe not
Correction Action:
EPM #6600004767 string after weld SATIP-W-12- joint) near joint 08-FW-736 without information to adjust
169 Welding Item no 3.17 Sageer Ahmed 21-Oct-19 20-Nov-19 16-Nov-19 Additional weld joint will be added at the cutout point, PT Closed
acceptance 16”- 01 slope for more excavation due to road crossing area, it
test will be done at cutting edge.
HWYH-GK RH TR/L is clear volition of SATIP-W-12-01, Item no 3.17
Root Cause Analysis: Lack of standard awareness by
“Modification or Re-Work After Weld Acceptance is a
construction crew.
Hold point by contractor and Saudi Aramco”.

Page 27 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
During site Surveillance on date 30-Oct-2019 at STA-
3+485 to 3+550 HRDH 1148, it was observed that width Root Cause Analysis: Negligence of Construction.
CPP-NGCP-NCR-CIV-059 of the flat top of the dike berm for 8” flowline was less Correction Action: The flat top of the dike berm will be
Improper berm
EPM #6600004734 than 40cm which is a violation as per SAES-L-450-Sec. extended at least 40cm (Twice of the Pipe Día) and QCI
170 Civil construction for 8”F/L at SAES-L-450 Sec. 14.10.3g 30-Oct-19 20-Nov-19 11-Nov-19 Closed
14.10.3g which states that” The width of the flat top of will verify at site prior to inspection.
HRDH-1148
the dike berm shall be at least twice the pipe diameter Corrective Action: Toolbox shall
along the overall minimum cover above the top of the be conducted.
pipe.”

During internal inspection on 03-Nov-2019 at CPP- Root Cause Analysis: Negligence of Construction team
Precast Yard-2 HRDH it was found that Formwork and Ignoring the SAES/IFC Drawing Requirements.
CPP-NGCP-NCR-CIV-060 Not Maintaining the Dimensions for foundations (SKID-F1 and F3) was not Correction Action: Construction
EPM #6600004897 Proper Formworks in Diagonal and not in proper shape which is a violation shall correct the formwork of foundations in proper shape
171 Civil SAES-Q-001 Sec. 3.2 03-Nov-19 15-Nov-19 11-Nov-19 CLOSED
Dimension as per IFC as per SAES-Q-001-Sec. 3.2 which states that” Forms and it shall be in Diagonal. Corrective Action:
Drawings shall result in a final structure that conforms to shapes, Tool Box shall be conducted and give Awareness
lines, and dimensions of the members as required by regarding IFC Drawings.
the IFC drawings. (ACI 318M-2011, Sec. 6.1.1).”

During surveillance on date 13-Nov-2019 at TCF1


Fabrication shop, it was found that 8”Class 900 WN RJ
11.13 mm WT ASTM A707 L3 CL3 flanges total number
CPP-NGCP-NCR-M-024
T-CPP- of 03 boxes (QTY=60) issued from TCF1 warehouse for
EPM #6600005100 Issuance of Material Qaiser
172 ARAMCO- Mechanical PRO-0010 para 6.1.1 fabrication without material receiving inspection done. 13-Nov-19 28-Nov-19 20-Dec-19 Root Cause Analysis: Negligence of storekeeper. CLOSED
without inspection done Shahzadhahzad
02714 This is a clear violation against the procedure of (CPP-
NGCP-QC-PRO-0010) para 6.1.1 After successful
inspection and issuance of IRC, the material will be
delivered to site.

Root Cause Analysis: Negligence of Construction


During site Surveillance on date 10-Nov-2019 at
Team at YARD-CPP.
HWYH-1088 it was observed that foundation delivered
at site has no Tag or Identification which is a clear
Correction Action: All the foundations which has been
CPP-NGCP-NCR-CIV-061 NO IDENTIFICATION violation as per SAES Q-012, para 3.2 which states
delivered at site will be marked with proper tag and put
EPM #6600004968 OR TAG PROVIDED that” Individual architectural precast elements are
173 Civil para 3.2 SAES Q-012 10-Nov-19 02-Dec-19 02-Dec-19 date of casting as well in order to place the foundations CLOSED
FOR FOUNDATIONS clearly marked with identification as shown on the shop
at exact location as marked in the IFC Drawings.
AT HWYH-1088 drawing including date of casting or serially numbered.
Corrective Action: Toolbox
(PCI MNL 117, Division 2, Section 2.6.2)
shall be conducted. Each foundation shall have proper
tag which shows the Date of casting, foundation type
and any reference (IF HAVE).

During the site surveillance on 13th October, 2019 at


Installation
area between HDC2CL-2 to HDC2CL-1 as sta.3+000 to Root Cause Analysis: Damaged pipe delivered from
3+450, it was observed that the RTR pipe thread for the FPI which were found by CPP QC Inpsector just before
Pipe No: 121916170120010, installation.
121918170120064, Pipe No:121918170120023 is found Corrective Action: thread
CPP-NGCP-NCR-RTR-06 RTR PIPE THREAD
174 RTR/Plumbing SAES-L-650 Para 8,h damaged which violates SAES-L-650, 8, h) which states 12-Oct-19 15-Dec-19 damage shall remove from site and store into the Closed
EPM-INCR-6600004502 DAMAGE
that” Thread damage evaluation quarantine area. Preventive
shall be in accordance with the manufacturer Action: CPP QC shall conduct tool box meeting
construction manual. Where criteria are not established, and update the quarantine log.
any thread damage shall be
cause for rejection until resolved in writing by the
manufacturer.”

On dated 17-November-2019 in CPP Concrete coating


Yard-2 HARADH, During surface prepration inspection
Root Cause Analysis:
Improper concrete prior the application of APCS-03 OF OPTF Founditions
Careless workmanship from construction Civil crew. Also
CPP-NGCP-NCR-CIV-062 surface prepration prior Type (SKID-F1 02pcs ) have cracks,pop outs ,
175 Civil SAEP-H-003 para 7.1.3 Ghulam Fareed 17-Nov-19 28-Nov-19 28-Nov-19 Foundations were not kept enough space between CLOSED
EPM-INCR-6600005222 to application of APCS- irregularities and not cured also giving loose materials
founditions
03 while scratching a screwdriver across the surface.This
is the violating the surface prepration as per SAEP-H-
003 para 7.1.3 and 7.2.1.1

Root Cause Analysis: CPP construction team ignored


the pipe protection requirements at road crossing.
During the site surveillance on 23rd November, 2019, Correction Action: CPP shall provide
between HDC2CL2 to HDC2CL1 10” RTR Condensate the pipe protection under road crossings as per
line crossing the dirt road at Station No: 17+370 to approved installation procedure i:e CPP-NGCP-CM-
RTR PIPE INSTALLED
17+390, the RTR line installed at 1.2M pipe cover but PRO-0028_2
CPP-NGCP-NCR-RTR-07 AT ROAD CROSSING Station No: SATIP-L-450-
176 RTR/Plumbing backfilled without providing any precautions to protect 23-Nov-19 15-Jan-20 15-Jan-20 Corrective Action: CPP construction shall CLOSED
EPM-INCR-6600005320 WITHOUT 17+370 04(RTR).
the RTR pipe as per the Approved Installation communicate with vendor and appropriate protection of
PROTECTION
procedure which says that “Precautions shall be taken pipe at road crossings shall be arranged prior to
to protect the pipes, which cross underneath roads construction of road crossing section of RTR pipe.
against the possible consequences of traffic loads.”

On November 10 2019 during material receiving


inspection of the company supplied cladded spools (CS
API5L GRX60 base metal cladded with 3mm UNS0625
Root Cause Analysis: To be provided by
incoloy) water mark with rust and corrosion has
company/Supplier
CPP-NGCP-NCR-M-023 observed in butt weld and CRA Weldoverlay surface in
T-CPP- Correction Action: CPP Reported to SAPMT/SAPID
EPM #6600004970 Visible Corrosion in most of the spool,randomly verified the spools are SP- Thirunavukkaras
177 ARAMCO- Mechanical SAEP-35 Para 5.1 10-Nov-19 10-Feb-20 02-Feb-20 representative for further action. Closed
cladded spools 141-57001-01A,SP-141-41002-01D,SP-141-39003- u
02714
07,SP-141-37004-09B,SP-141-90004-03, This violates
the standard requirements of 01-SAMSS-044 Para 13
which states that all open ends of the spool shall be
suitably covered to prevent contamination from dust or
moisture during storage and transportation.

During the site surveillance on 24th November, 2019,


between HDC2CL2 to HDC2CL1 10” RTR Condensate Root Cause Analysis: CPP construction team ignored
line at Station No: 18+280, it is found that the barricading which is required prior to backfilling
equipment were crossing over the installed line with Correction Action: CPP along with FPI site supervisor
HEAVY EQUIPMENT
CPP-NGCP-NCR-RTR-08 pipe cover 200mm., which is a clear violation as per shall excavate the area and check if the RTR pipe is
178 RTR/Plumbing CROSSING OVER 24-Nov-19 24-Jan-20 Closed
EPM-INCR-6600005324 Approved Installation Procedure which states that “To undamaged.
INSTALLED RTR LINE
Preclude damage to the pipe and disturbance to pipe Corrective Action: CPP construction shall barricade
embedment, a minimum depth of backfill above the pipe the area or backfill required area immediately after
should be maintained before allowing vehicles or heavy installation.
construction equipment to traverse the pipe trench.”

Page 28 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N

On Oct 21, 2019, CPP QC noticed during routine Root Cause Analysis: modification done as per
inspection at 8”-HWYH-1134 F/L it was observed that Technical query TR-02029-003-01933/19-CPP for
two accepted pipeline string has been cutout (Pipe not crossing of existing pipelines and CPP start cutting
Modification of pipeline joint) near joint 01-FW-122 and 01-FW-131without without notification due Lack of standard awareness by
CPP-NGCP-NCR-W-053 string after weld information to adjust slope due to thrust boring area, it construction crew.
179 Welding Binish 21-Oct-19 20-Nov-19 16-Nov-19 CLOSED
EPM-INCR-6600004756 acceptance @ 8”- is clear volition of SATIP-W-12-01, Item no 3.17 Correction Action: Additional two weld joint will be
HWYH-1134 “Modification or Re-Work After Weld Acceptance is a added at the cutout point, PT test will be done at cutting
Hold point by contractor and Saudi Aramco”. edge Corrective Action:
Awareness toolbox will be conducted to avoid repeating
such performance

General reply:Corrective action has been verified and


found satisfactory .However contractor shall take
adequate preventive action to prevent there currence of
the nonconformance.
During routine inspection at CPP-4 Fabrication Shop on
General reply:CORRECTIVE ACTION IMPLEMENTED.
03-Nov-2019.It was observed that Welder (CPP-W-198)
CPP-NGCP-NCR-W-054 CLOSE THIS NCR
Improper Welding was welding with open lid of portable oven. Which
180 EPM-INCR-6600004887 Welding M Saif 05-Nov-19 05-Dec-19 18-Nov-19 Preventive:Tool Closed
Consumable Handing violate the requirement of SAES- W-012 Appendix 1
box awareness session for handing welding consumable
NOTE-2 which states the proper use of the oven (e.g.,
shall be conducted to welder and welding crew
closed lid, continuously on while in use).
Corrective:The exposed electrodes shall be discarded.
Root cause:Carelessness and poor
workmanship from welder CPP-W-198

Root Cause Analysis:


During routine inspection on 26 Nov 2019 at TCF-1 Power supply generator at fabrication shop was break
fabrication shop-1 was observed that there were no down.
power supply to maintain the holding oven temperature Correction Action:
CPP-NGCP-NCR-W-055 Inappropriate storage
which violate the requirement of SAES-W-012 Appendix Electrode in the oven shall be discarded.
181 EPM-INCR-6600005419 Welding and handling of Welding B.P Kumar 26-Nov-19 26-Dec-19 11-Dec-19 Closed
1 for Low hydrogen electrodes SFA 5.5 smaw electrode Corrective Action:
Electrodes
which states that electrode must be maintained at 120 Tool box awareness session shall be conducted for
degree Celsius temperature continuously in holding welding crew for storage and handling of welding
oven. electrode at fabrication shop.

Root Cause Analysis: Construction team didn’t follow


During daily site visit on date 25-Nov-2019 at Precast the Standard Requirements for Storage of the Steel
Yard 3 Hofuf, it was observed that the Rebar stored in Rebar.
the storage area is not lifted off the ground, instead it Correction Action: CPP shall provide the wooden
(ASTM touching the ground which is a violation as per 09- planks down side of the rebar.
CPP-NGCP-NCR-Civ-063 Stored FBE Rebar ends
182 Civil A775/A 775- Sec. 15.3 SAMSS-106 Nadeem Akram 27-Nov-19 05-Dec-19 04-Dec-19 Corrective Closed
EPM-INCR-6600005428 are touching Ground
07b Sec. III.B which states that “Coated steel reinforcing Action: CPP QC civil inspector shall conduct tool box to
bars shall be stored off the ground on protective explain the standard requirements to the construction
cribbing. (ASTM A775/A 775-07b, Sec. 15.3).”. crew.

It has been noticed that approved Subcontractor MAGE


QC manager Mohammed Ibrahim went for vacation
without any proper notification or replacement. This
Root Cause Analysis: Negligence in following Schedule
violates Schedule Q para. 5.14, which state that
Q Requirement.
CONTRACTOR shall make quality personnel changes
Correction Action:
required due to vacations, illness, temporary
Subcontractor MAGE Shall Provide Immediate
CPP-NGCP-NCR-E-11 assignments, emergency leave resignations or other
Absence of Sub- Replacement for QC Manager.
183 EPM-INCR# 6600005608 Electrical/CP reasons as necessary to maintain the quality coverage. 04-Dec-19 03-Jan-20 01-Jan-20 Closed
contractor QC Manager Preventive Action:
Hence,Subcontractor MAGE shall notify at least thirty
Sub-Contractor shall be notified regarding their timely
(30) calendar days in advance of scheduled absences
reporting for the QC official’s availability/annual vacation
or changes. All other changes such as illness and
and Emergency leave Schedule.
emergency leaves shall be notified within twenty-four
(24) hour. MAGE shall investigate the root cause and
provide an immediate replacement along with
preventive action to avoid recurrence.

During site Surveillance on date 14-DEC-2019 at RH-


Root Cause Analysis: Negligence of Construction
CJ (HWYH). it was observed that Precast foundations
Team. Correction Action: CPP shall provide All
IMPROPER STORAGE off load at site without wooden pallets or polythene
the foundations which has been delivered at site Shall
CPP-NGCP-NCR-CIV-064 & HANDLING OF sheet which is a clear violation as per SAES Q-012,
have plastic sheet beneath each foundation.
184 EPM-INCR# 14000 Civil PRECAST CONCRETE SAES Q-012 para 7.2 para 7.2 which states that” Precast members are kept 14-Dec-19 28-Dec-19 26-Dec-19 Closed
FOUNDATIONS AT free of mud and other damaging materials at all times,
Corrective Action: Toolbox shall be conducted. Each
RH-CJ (HAWIYAH) and are stored in the job site on non-staining wooden
foundation shall have proper platform and shall not be in
pallets or platforms in such a manner to ensure
touch with ground directly.
drainage and drying when exposed to the elements.

During site Inspection on date 18-DEC-2019 at RH-DK,


Root Cause Analysis: The material used for backfilling
it was observed that Moisture Content is 15% in Select
was pre-mixed and after raining the rain water added
Fill Material used for Backfilling of Remote Header DK
further`. Correction Action: The layer shall
HIGH MOISTURE HRDH and Optimum Moisture Content is 9.1% which is
scarify in order to dry the moisture content in Select fill
CPP-NGCP-NCR-CIV-065 DURING a violation as per SAES-A-114-Sec. 6.3.4 which states
material and start compaction after the moisture content
185 EPM-INCR# 14000 Civil COMPACTION TEST SAES-A-114 Sec. 6.3.4 that “Compaction shall begin only after the fill or backfill 18-Dec-19 30-Dec-19 30-Dec-19 Closed
I in the required limits. Corrective
OF SELECTFILL) at has been properly placed and the material to be
Action: Construction shall take care of the Moisture
HRDH-RH-DK compacted is at the proper moisture content. +/- 3% of
according to weather conditions and shall begin
the optimum moisture content per ASTM D1557 or
compaction only when the moisture is within the required
ASTM D698, whichever is applicable. (PIP-CVS02100,
limits.
Sec. 4.3.7.7.3)”

During site Surveillance on date 18-Dec-2019 at HRDH


Root Cause Analysis: Negligence of Construction and
1147, it was observed that Slope of well pad was not
Ignorance of Standard requirements.
compacted from the outer most edge which is a
CPP-NGCP-NCR-CIV-066 Correction Action: Horizontal fill layer shall be
Improper/Uncompacted violation as per SAES-A-114-Sec. 6.3.2.2 which states
186 EPM-INCR# 14000 Civil SAES-A-114 Sec. 6.3.2.2 18-Dec-19 18-Jan-20 16-Jan-20 compacted from the outer edge and after reaching the CLOSED
slope at HRDH-1147 that “Construction of new slopes shall be accomplished
required/final level of pad then trim it back to achieve the
by compacting horizontal fill layers at least 1 roller width
final slope . Corrective Action:
beyond the design edge of the slope then trimming back
Toolbox shall be conducted
to achieve the final slope dimensions.”

Root Cause Analysis: Construction crew removed the


side boom for stringing of other pipes and left the
spool/pipe without proper support.
Correction
On Dec 08, 2019, CPP QC noticed that the side boom
Action: Joint 14-FW-1171 cutout, PT done on the weld
Removal of side boom was removed before completion of hot pass of joint no.
CPP-NGCP-NCR-W-056 bevel and Re-welded. RT will be covered for the joint 14-
before completion of hot 14-FW-1171 at 16" HWYH HK-RH TR/L. This violates
187 EPM-INCR- Welding Abdul Raheem 08-Dec-19 10-Feb-20 16-Jan-20 FW-1171. Closed
pass @ 16" HWYH HK- SAES-W-012 (Para 10.7.3) which states that ‘The hot
Corrective Action:
RH TR/L pass shall be made while the pipe is still fully supported
Awareness toolbox training will be conducted to prevent
by the side boom tractor or supports’.
future
recurrence, Site QC to monitor closely to follow standard
requirement.

Page 29 of 42
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP Internal NCR LOG (Construction)

Total Open Closed Remarks Last Updated : 10-May-2020


Summary of INCRs Total
315 19 296
Discipline-wise
Discipline-wise Summary Total Open Closed Remarks Total Open Closed Remarks
Summary
Mechanical 54 8 46 Civil 103 2 101

Electrical &
Coating 42 4 38 Cathodic 20 3 17
Protectton
Telecommunicatio
Welding 84 3 81 2 0 2
n
Procurement RTR/Plumbing 11 0 11

Instrument 1 1 0
TARGET
STANDARDS VIOLATED REVISED
S. Raised Closed DATE OF
NCR NO. DISCIPLINE Title DESCRIPTION Originator DATE OF ISSUE TARGET COMPLETION DATE ACTION TAKEN Status
No. transmittal transmittal COMPLETIO
DOC. REF. PARA NO. DATE
N
Root Cause Analysis: Lack of awareness of Saudi
On Dec 09, 2019, CPP QC noticed that during welding
Aramco standards by the construction team.
Moving of Pipe During of fill pass of Joint No. 03-FW-253 at 16”-HWYH-GK-RH
CPP-NGCP-NCR-W-057 Correction Action: Joint
Welding Removal of @ TR/L the pipe was lifted by side boom to place the sand
188 EPM-INCR- Welding Mir Muzaffar Ali 09-Dec-19 10-Feb-20 16-Jan-20 03-FW-253 will be covered by 100% RT and MT to verify Closed
16”-HWYH-GK-RH bags below the pipe. It is a clear violation of the
weld soundness.
TR/L standard SAES-W-012 (Para 10.7.4) which states:” The
Correction Action: Joint 03-FW-253 will be covered by
pipe shall not be lifted or moved during welding.”
100% RT and MT to verify weld soundness.

Root Cause Analysis:


Lack of knowledge about Aramco standards.
On Dec.14, 2019, CPP QC noticed during routine
Correction Action:
inspection at 8”-HWYH-975 F/L it was observed that
CPP-NGCP-NCR-W-058 Lack of number of Tack Re-Fit up done, PT done at bevel and 4 tacks welded
lack number of tack weld (3. tacks weld only) during fit-
189 EPM-INCR- Welding Weld @ 8”-HWYH-975 SAES-W-12 Para 10.9.3 14-Dec-19 14-Feb-20 16-Jan-20 Corrective Action: Awareness toolbox training will be Closed
up inspection of joint 02-FW-218, it is clear volition of
F/L conducted to prevent future
SAES-W-12, Para 10.9.3 “Pipe diameter above
recurrence, Site QC to monitor closely to follow standard
101.6mm minimum of four equally spaced tacks”.
requirement.

On dated 14 December 2019 during site surveillance at


HRDH-K4 welded string from FW-012 to FW-33
Root Cause Analysis:
witnessd that some of the APCS 104B (FBE) coated
Rubber tires used to support welded string which were
pipe string laid on inappropriate supports and touching
not placed correctly between pad area and pipes also
the ground, which may cause to FBE coating damage
end caps were not used to protect the beveld end.
and it is a clear violation of pipe handling and storage
Corrective Action:
as per SAES-H-200, Para 5.2.1 which stated that:
Effected pipes shall be lifted by placing proper support
During storage the coated pipes shall be placed at least
with a minimum gap of 150mm off the ground. All area
150 mm off the ground on either rock-free sand berm
shall be holiday tested and repair according to approved
CPP-NGCP-NCR-H-004 covered with polyethylene sheeting or on padded skids
190 Coating Mechanical/Coating SAES-H-200 Para 5.2.1 23-Apr-19 23-May-19 25-Apr-19 repairing procedure prior to lowering, also need to cover Closed
EPM-INCR-6600002350 spaced and leveled so that the pipes are supported
the beveled end with end caps.
without damaging the coating. All possible efforts shall
Preventive Action:
be exerted to prevent direct contact of the coated pipes
Tool box meeting shall have arranged for construction
with the ground or ground moisture.
crew on importance of Saudi ARAMCO Engineering
During the site visit also found that pipes available at
Standards and Requirements. Care shall be taken by
sites are not covered with end caps or any suitable
construction crew during the padding activity to comply
cover which can protect the pipe from sand, water and
with SAES-H-200, Storage and Handling requirements.
other contimination and its clear violation of pipe
handling and storage as per SAES-H-200, para 5.1.1.

Root Cause Analysis:


Negligence of the QC in requesting and registering the
joint details
On Dated-19-Dec-2019, NGCP pipeline project, BI-10- Correction Action:
02029-0003, During the review of daily welding reports The welded joint FW#79 T2 RW shall be rectified in
CPP-NGCP-NCR-W-059 for Joint No FW#79 T2 RW 8” (HWYH-1115), it is DWR (SATR-W-2007) as per the requirements NDE will
Wrong Weld Number SAES-W-012-
191 EPM-INCR- Welding Para 17.4 noticed that the Cut and Re-weld joint are marked with 18-Dec-19 17-Mar-20 12-Jan-20 be performed. Closed
Identification 01
as new Joint No by Welding Inspector, it is a clear Preventive Action:
violation as per SAES-W-012-01 Para 17.4 & SAES- Warning letter issued to the concerned QC and
1160 Para 6.2 awareness of weld identification shared with concern
welding qc.

Root Cause Analysis:


On 18-DEC-2019, CPP QC observed during welding at Lack of knowledge about WPS-15.
16” HWYH-GK-RH TR/L joint 08-FW-689 that flow rate Correction Action:
CPP-NGCP-NCR-W-060 Flow rate of shielding of shielding gas was not as per the Welding Procedure RT will be done at joint 08-FW-689.
192 EPM-INCR- Welding gas @ 16” HWYH-GK- 15-25 WPS-15 Specification WPS-15. As per WPS the flow rate is 15- 18-Dec-19 14-Feb-20 16-Jan-20 Corrective Action: Awareness toolbox training will be Closed
RH TR/ 25 liter/min but during welding it was 32 liter/min. conducted to prevent future
recurrence, Site QC to monitor closely to follow standard
requirement.

Root Cause Analysis: Construction team did not follow


the requirements of SAES-L-450 SEC 14.6.3
During daily site visit on date 23-DEC-2019 at HRDH-
Correction Action: The CPP
1177, it was observed that the CPP construction team
Inappropriate pipe construction team shall remove the crossing & prepare
CPP-NGCP-NCR-CIV-067 make unsatisfied temporary road crossing & improper
cover & temporary road pipe cover as per SAES-L-450.
193 EPM-INCR# 14000 Civil sec 14.6.3 SAES-L-450 pipe cover at HRDH-1177 sta 1+900 this is clear 23-Dec-19 08-Jan-20 08-Jan-20 CLOSED
crossing at HRDH-
violation as per SAES-L-450 sec 14.6.3 All pipeline
1177. Corrective Action: CPP civil QC will deliver a quality
shall have a minimum cover of 900mm. Additional cover
tool box meeting to guide the construction crew about
is required at road or rail crossing,
the requirements of Saudi Aramco engineering
standards SAES-L-450.

Root Cause Analysis:


Pipe has been lifted by side boom during tack welding.
Correction Action:
The tack weld containing crack should be removed by
On 02-JAN-2020, CPP QC observed that tack weld had grinding and new tack weld must made before welding
crack after fit up completion of joint number 03-FW-283 the joint.100%RT and PT bevel to be conducted for 03-
CPP-NGCP-NCR-W-061 Crack occurred in tack
at 16”-HWYH-CK-RH-TR/L. It is a clear FW-283
194 EPM-INCR# 14000 Welding weld@16”-HWYH-CK- SAES-W-012 10.9.4 02-Jan-20 02-Apr-20 21-Jan-20 Closed
violation against SAES-W-012 clause 10.9.4 which Corrective Action:
RH-TR/L
states “any cracked tacks shall be removed before Awareness tool box training will be conducted to prevent
welding the joint”. future
recurrence; Site QC to monitor closely to follow
standard requirement.

Page 30 of 42
PROJECT T

S
STANDARDS VIOLATED
S. No. SALBE NO. SALBE TYPE DISCIPLINE
DOC. REF. PARA NO.

SANCR- attachment IV Para


1 Saudi Aramco NCR Mechanical Schedule Q
500013964 1.2.3 and 1.3.
SANCR-
2 Saudi Aramco NCR Civil SAES-A-114 Para-6
500014443

Para-5
SAEP-1152
Para-7.5.2
SANCR- Shedule Q
3 Saudi Aramco NCR Mechanical Appendix-D
500015156 SAEP-381
Para-4.3
SAES-W-016
Para 6.2.4 &
SANCR-50001531 SAEP-
Saudi Aramco NCR Mechanical appendix #D,Annex
1 35SAMSS-048
A,para-7,para 1 31
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

SAUDI ARAMCO NCR LOG

TITLE DESCRIPTION DATE OF ISSUE

On 11 April, 2019 the Contractor completed Girth weld APCS


113C Tape wrap application activity for 8 Inch Flow line in Well
Head HARD-1171 and HARD-1309 two locations a total of 125
joints without presents of Contractor#s Coating Inspector and
proceeded work with unapproved Coating applicators. This
activities are HOLD POINT for the contractor QC Coating
inspector as per SA TIP-H-002-11 activity 3.1, 3.2, 3.3. It is a
Failure to perform violation against Schedule Q attachment IV Para 1.2.3 and 1.3.In
15 April 2019
inspection per ITP view of this Multiple violation categorized as moderate,EPM LBE
is 4500015348 therefore escalated to company NCR in
accordance with escalation process defined in SAEP-381
Paragraphs 6.2.1 and 6.2.2 further to Appendix D, Item No-18
and 07.
Contractor is required to investigate the root causes and its
analysis provide immediate corrective actions as per Schedule-
Q, Paragraph 7.5.4.
Repeat ed Violat ion Unapproved f ill mat er Descript ion of Def
iciency: - Repeat ed Violat ion- Unapproved f ill and Backf ill Mat
erials.
Repeat ed Violat ion- EPM LBE Number 4500031340 issued
Sept ember 19, 2019 relat ed t o oversized st ones and
unapproved f ill mat erials delivered at HRDH-331 MLV-1 area
at Haradh.
Despit e of a f irst violat ion LBE Number EPM 4500036046
issued on July 02,2019 and second Violat ion LBE Number EPM
4500024319 issued on August 19, 2019 also Cont ract or
issued several Minor INCRs and t here is no evident act ion t
aken t o avoid t he repeat ed occurrences by cont ract or.
The non-conf ormit y repeat ed is regarding t he f ailure of Cont
ract or t o cont rol oversized and unapproved f ill mat erials
delivered at various sit e in Haradh and Haw iyah w it h ref
Standard/Procedure/Co
erence t o SAES-A-114, Para-6 w hich st at es t hat Fill and
ntract Violation
Backf ill Mat erials sources of supply shall be
SAES-A-114,PARA-6
approved by Saudi Aramco and General Fill Mat erial shall
consist of gravel, sand and/or marl. The maximum size of t he f
ill mat erial shall be one-half t he lift t hickness or 75 mm (3
inches),
w hichever is less. Select Fill or #St ruct ural Fill# shall be
composed only of inorganic mat erial and shall have 100%
passing t he 5 cm (2 in) sieve and f rom 0 t o 20% passing t he
No. 200 sieve.
In view of t his repeat ed violat ion cat egorized as moderat e, t
heref ore Escalat ed t o company NCR in accordance w it h
escalat ion process def ined in SAEP-381 Paragraphs-6.2.4,
7.5.3 & 7.5.4.3
f urt her t o Appendix A-2.
Cont ract or is required t o invest igat e t he root causes and it s
analysis provide immediat e correct ive Act ions as per
Schedule-Q, Paragraph 7.5.4.

Valve repair without approved procedure


On dated March 11, 2020, Inspection Department noticed that
contractor CPP carried out valve repair work without approved
procedure and using the wrong tools without notifying to Saudi
Aramco.
At TCF-1 CPP Lay down yard Contractor workers performing
chipping and Filing the CRA Alloy 82 5 Internal cladded Valves
by using the Carbon steel Files and Carbon steel chisels and
without approved manufacture procedures or method
Standard/Procedure/Co statements. These valves are rejected and Quarantine due to
ntract Violation Accumulated spatters was observed in 33 nos.-8"x 6"x 900# 17 March 2019
reduced bore Manual Ball Valves during material receiving
inspection, in the lnconel 825 CRA weld overlay cladded area on
Inside surface of the body. Which shows that contractor third
party inspector failed to do the final visual inspection Therefore,
PID initiated EDR # 400023828 to Vendor for further
Investigation.
This condition violates the requirements of SAEP-1152 Para-5 &
Schedule-Q General, Para 7 .5.2 and 7.5.7. &SAES-W-16, Para-
4.3, 4.5. In addition, SAEP-381 Appendix D. S/N 10 and
Para-6.2.1.
Contractor failed to preserve valves after field hydro testing,
repeated Standard Violations I-BE no 4500086105, dated 22
April 2020 and I-BE no 4500085998, dated 21 April 2020 were
issued for the follow ing non-conformances: Water observed in
the valve cavity of field hydro tested valves for 8-lnch 900 Rating
Gate valves, 72 Numbers 8 X 6 Inch Reduced bore Ball valves,
Multiple Standard Field hydro tested valves are stored in un-approved location,
violation for Material behind Fabrication shop-and Valves are without any protection 22 April 2020
Preservations and exposed to rain, Valves not stored as per manufacturer
recommendation. The aforementioned observation violates the
requirement of SAEP-35, para-7 & appendix A, 04 SAMSS-048,
Annex A, section 1 01 Contractor QCP, CPP-NGCP-CM-PRO-
0021 para 1 31 manufacturer QCP procedure PCQOI 00501 ,
section 6.5. Therefore as per SAEP-381 Para 6.2.4 & appendix
#D section u 13 the observed violation was escalated to SANCR.
line Project

Last Updated : 10-May-2020


REVISED COMPLE
TARGET DATE OF
TARGET TION ACTION TAKEN STATUS REMARKS
COMPLETION
DATE DATE

Root Cause Analysis:


Careless workmanship
from the MT Technician.
Correction Action: All the
joints 24’’-HWGCP-1-T/L
SWEET (T/L-DJ-54) & 24’’-
HWYH-GGM-TR/L-2 (TRL-
2-DJ-19, TRL-2-DJ-60)
shall be cleaned as per
SAEP-1144, Para-9.
N/A N/A N/A
Corrective Action: Closed
Awareness Toolbox
training will be conducted
to prevent future
recurrence, Site QC to
monitor closely to follow
standard requirement.

Corrective
Action:Corrective Action
And implemented this
INCR Closed
N/A N/A N/A Closed

N/A N/A N/A Closed


N/A N/A N/A Open
PROJECT TITLE:- North Gas Compression Pipeline Project
CONTRACT No. / BI-10- 02029-003

CPP SALBE LOG


Last Updated : 10-May-2020
STANDARDS VIOLATED
TARGET DATE OF
S. No. SALBE NO. SALBE TYPE DISCIPLINE TITLE DESCRIPTION DATE OF ISSUE REVISED TARGET DATE COMPLETION DATE ACTION TAKEN STATUS REMARKS
DOC. REF. PARA NO. COMPLETION

Contractor shall implement an ongoing training program to introduce and familiarize all contractor and
SALBE-PN-EPM4500007536 Acknowledged. Contractor will
13 Violation Mechanical Schedule Q Para. No.-5.15. Training Program subcontractor personnel with the project quality requirements for their area of responsibility as per Schedule 03 January 2019 04 March 2019 N/A N/A CLOSED
comply schedule'Q' requirements.
Q-Para. No.-5.15.

Root casue: Careless


workmanship of site crew.
Corrective Action:FBE coated
pipes being re-instated with
on Jan 09, 2019,during inspection at HWYH-1134 it is been noted that FBE Coated Pipes laid with proper supports and padding to
inadequate supports, some pipes are direct contact to the ground it may lead FBE coating damage.it is protect external FBE coating.
Improper storage violation against the SAES-H-200, Para 5.2.1 requirement.which states that, During storage the coated Preventive Action:CPP quality
23 SALBE-SV-EPM4500007729 Violation Mechanical SAES-H-200 5.2.1 10 January 2019 10 April 2019 N/A 1/13/2019 department will enhance the site CLOSED
the coated pipes pipes shall be placed at least 150 mm off the ground on either rock-free sand berms covered with
surveillance and awareness
polyethylene sheeting or on padded skids spaced and leveled so that the pipes are supported without
to site crew in order to avoid
damaging the coating.Reply required within 48 hours in accordance with Schedule Q ,para 7.5.6.
recurrence. As an action CPP
quality department will conduct
again a quality awareness toolbox
meeting to re-educate site crew.

Focus assessment was conducted at HRDH-1170 area last Jan. 21, 2019 at
around 2pm in order to assess on-going and planned civil acti
vities. The following opportunities for improvement and proactive
notifications were observed. 1. Contractor has to install temporar
y or permanent kilometer markers to be spaced at every 1km during and
after trenching activities as per scope of work para. 8.4. 2.
Pipeline Trenching Intersecting points between existing pipeline shall be properly Acknowledged with thanks. CPP
57 SALBE-PN-EPM4500008647 Violation Mechanical scope of work para. 8.4. 2 23 January 2019 21 February 2019 N/A N/A CLOSED
Activities identified with caution markers in order to preserve and work safely will comply he requirements.
within existing pipelines, Buried pipeline crossing each other shall
have a minimum clearance of 0.6m. 3. Survey stakes and referen Root Cause:
ces shall be installed accordingly and survey report must be verified Mr. shankar left for his personal
by contractor QC to match with design coordinates. Any major emergency for 3-4 days during
changes shall be documented accordingly as per approved field the weekends and anticipated to
engineering change control procedure. be back at work at start of week
and he failed to do so.
Correction Action:
On 16 March 2019, BI-10-02029-0003, Contractor CPP, during site visit at
Late notification is being
material yard bending area TCF-1 it has been observed Contr
transmitted by CPP to Saudi
actor approved QC inspector Mr. Shankar has left on an emergency
Aramco to notify the leave of Mr.
SALBE-SV- vacation since last Thursday, March 14, 2019. Without any informati
Q.C Personal shankar officially.
187 EPM#4500013150 Violation Mechanical Schedule Q on and notification. This is the violation of Schedule Q para 5.14 which 20 March 2019 26 March 2019 11 April 2019 CLOSED
absent notification Corrective Action:
states, All other changes such as illness and emergency lea
CPP quality department will follow
ves shall be notified within 24 hours. Contractor has to provide the
the schedule 'Q' requirements in
Root cause, corrective and preventive action for it. Initiated
order to notify any emergency
by PID Rajendran Thambusamy Root Cause: CPPpersonnel.
construction
para 5.14 leave of quality
failed toGeneral
provide Reply:
the corrective
action which exceeded
Official notification have the time
been
on 15 April 2019 Project inspection has issued a Nonconformance report
frame of 7through
sent days astransmittal
per schedule
500013964 against Prime contractor CPP for related to Coatin
T-CPP-ARAMCO-01380 "Q". for leave
g activities. Until now 5 May 2019 contractor not yet submitted any root
of Mr.Corrective
Shankar. Action:
Hence, this
SALBE-SV-EPM cause and corrective action plan for this issue. It is a vi
355 Violation Mechanical Schedule Q Late Reply for NCR 06 May 2019 8/4/2019 5/12/2019 CPPviolation
submittedcanthe
beRoot Cause CLOSED
closed.
4500017600 olation of Schedule Q Para 7.5.4 which states that Contractor shall
and corrective actions through
investigate the root cause of non-conformities and initiate Corr
official transmittal for SAPMT and
ective Actions to prevent recurrence of nonconformities maximum seven
SAPID confirmation.
[7] days of the issue date
Preventive Action:
Para 7.5.4 CPP will comply the Schedule "Q"
requirements in any future case.
n May 02, 2020, Contractor CPP, BI No. 10-02029-0003, PID representative found that, 04Nos
scraper trappers 1. 510-L-0012-4869 4M, 2. 510-L-0013- 4869 4N, 3. 510-L-0005- 4869 4H, 4.
510-L-0007- 4869 4J were installed without material receiving inspection and pre-installation
inspection of scraper trappers. This is violation to the requirements of SATIP-L-420-01, activity
item no. 3.3, Which is hold point for contractor QC Inspector and it violates Schedule Q, attachment
SALBE-SV-EPM Instalation Done
2413 Violation Mechanical Schedule Q, para 3.3 IV, para 3.3 which states that CONTRACTOR shall visually inspect all incoming equipment for 04 May 2020 07 June 2020 OPEN
004500089038 Prior reciver QC
damage and for conformance to all applicable requirements, including the CONTRACTORs
inspection release, when applicable, with verified Material Test Reports. Contractor is advised to
analyze the root cause with corrective and preventive action within the ACD date. Contractor shall
comply the standard requirement without fail in order to avoid violation escalation as per SAEP-
381.

On 01 may 2020 During Material receiving and pre installation , Flow line connection OPTF Skids
It was noted that OPTF SKIDS Inlet and Outlet connection, Orientation marking mismatching with
the P&ID and plan drawing .Due to the wrong Orientation marking provided OPTF SKID Valves and
spectacled blinds are installed wrong orientation instant of open, close vice versa for the Eight
Orientation
SALBE-SV-EPM OPTF skids S.no:- HWYH-942,HWYH-1002, HWYH-1076, HWYH-1134, HWYH-1071, HWYH-969,
2414
004500088906
Violation Mechanical Schedule Q, para 3.3 mismatching with
HWYH-1055, and HWYH-1087.whic is violating the standard drawing requirements Ex:, TA-130185
03 May 2020 01 August 2020 Closed
the P&ID
Sht001 rev-0F1, BA-760448 Sht001 Rev 0F2 and TA-130571 Sht001 Rev0F1,TA-130220 Sht01
rev 0F2.Prior to initiate RFI to SAPID contractor shall verify the remaining skids. Hence skid is
received with FAT test and V.P.C.I preservation, contractor is requested to provide the corrective
action and root cause by vendor Alderlay, KSA.

On 09 May 2020, During Material Receiving inspection of 16inch X 22inch Dia Cl900 Scraper Traps
number H92- L- 0025 at HWYH EJ RH and H92- L- 0028 at HWYH CK RH respectively, ID noticed
rust formation inside the Scraper Launchers since they are not preserved with VpCI 309 inhibitor as
per Manufacturer recommendation in Handling, Shipping and Storage procedure with Clients P.O
number- 03-KSA04-PR-01-016, para. 03. This is a violation against Schedule Q Attachment IV,
VpCI 309
para. 06, which states that CONTRACTOR shall include procedures for handling, storage, and
inhibitor as per
SALBE-SV-EPM preservation of material as specified in all applicable specifications, manufacturer
2416 Violation Mechanical #NAME? para. 03 Manufacturer 09 May 2020 09 July 2020 OPEN
004500090444 recommendations and COMPANYs standards. The procedure shall list all inspection schedules for
recommendation
maintaining the quality of the material or equipment as well as provide for documentation that the
in Handling
required activities have been performed. Individuals responsible for special handling, storage and
preservation shall be fully qualified to do so, and supplied with predetermined WORK and
inspection instructions. Contractor is advised to analyze the root cause with corrective and
preventive action within the ACD date. Contractor shall comply the standard requirement without
fail in order to avoid violation escalation as per SAEP- 381.
RTR 10
Welding 69
Coating 7
Civil 81,92
###