Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC -SRWL Reference Standards: PDO SP 1279 : Dec 2009
Sl Test Verification Verification Sub- BE
Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C
Review of Scope of work All data supplied meets the applicable Contract
Contract C311554, P.O.
and Drawings, Contract PDO specifications. Specifications /
Approved Drawings,
1. Requirements. PDO approved sub-contractor 100% QA Engineer. Company H H R/A
SP-1279
Approval of Contractor / Specification.
Subcontractor.
As per Approved Method of statement
Contract C311554, and ITP As per the requirements of PDO Approval
Approval of Method
Applicable Standards as Controlling Documents, SP-1279. of Method
Statement , Inspection
2. per From Company approved source. 100% QA Engineer. statement. H H H
and Test plan ,Material &
SP-1279-F Approved ITP,
Source
Clause 2.3.3 Approved MAS.
5. Screed for roof SP-1279-F The Contractor shall not proceed with 100% H H H
waterproofing works Clause 2.3.2 laying screed or angle fillets until the
existing concrete deck surface has been
approved by the Company.
The Contractor shall lay screeds to the
specified thickness and/or falls as shown
in the Contract Documents and in
alternate bays not exceeding 11 m2.
Stop-ends shall be vertical and
positioned to coincide with construction QCI (Civil) C311554-C-REC-
023
joints in the concrete deck.
Screed and angle fillets shall not pass
over roof expansion joints in the
concrete deck.
Expansion joints shall comprise
impregnated fibre joint filler board to the
specified width.
Screed and angle fillets shall be finished
smooth and even with a wood float
finish.
Page 4 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009
Page 5 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009
corner.
- Expanded polystyrene insulation 35
kg/cu.m 75mm thick with 15mm
rebate on edges.
- Separation layer of 500g Polythene
sheet.
- 300x300x30mm thick concrete slab
with pointing & set in 20 thick
screed.
- Expanded metal mesh laid under
insulation, approx. 300mm and bent
up to retain gravel topping at
gargoyle location.
- One layer of Bitustick AL self-
adhesive aluminum membrane of
girth 300 mm is taken from fillet end
up to the preformed groove on the
vertical area of upstand and tucked
inside the groove.
8. Laying of water proofing SP-1279-F Waterproofing systems and associated
membrane Clause 2.3.3 Works should be laid by a specialist 100%
nominated subcontractor, experienced in QCI (Civil)
Approved AFC Drawing laying the specified waterproofing
system. C311554-C-REC- H W S
Where specified in the Contract 023
Documents, built-up bitumen felt shall be
laid in accordance with the
manufacturer's written instructions and
BS 8217.
Where specified in the Contract
Documents, mastic asphalt shall be laid
Page 6 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009
Page 7 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009
Inspection and test mark-up legend: M = Monitor, W = Witness, H = Hold Point, R = Document Review, A= Document Approval
Hold Point (H): A critical step in fabrication and testing where it is mandatory that the responsible party inspect the component/equipment or witness an activity. Activities
designated as a Hold Point shall not proceed unless the responsible party is present or the Hold Point is formally waived. The Company shall be notified at a duration specified in
the contract in advance of the activity.
Witness Point (W): A critical step in fabrication and testing where it is desirable that the responsible party inspect the component/equipment or witness an activity. The
responsible party shall be notified at a duration specified in the contract in advance of the activity. Once proper notification is given, the activity may proceed according to the
schedule regardless of the Company’s attendance.
Monitor Point (M): A critical step in fabrication and testing where it is optional that the responsible party inspect the component/ equipment or witness an activity. The
responsible party shall be notified at a duration specified in the contract in advance of the first occurrence of the activity at each worksite. No further notification for like activities
at each worksite shall be required. The activity may proceed with or without the Company’s attendance.
Approval Point (A): A critical step in design, procurement, and or fabrication and testing where it is mandatory that the responsible party approve a document/qualification/
equipment/or activity. The responsible party shall be notified at a duration specified in the contract in advance of the first occurrence of the activity or provided the document in a
Page 8 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009
period of time specified by the contract. The activity may not proceed without the responsible party’s approval.
Review Point (R): A critical step in design, procurement, and or fabrication and testing where it is desirable that the responsible party review the document/qualification/
equipment/or activity. A separate notification is not needed unless otherwise specifically requested; the responsible party may perform this along with any of the other intervention
types.