You are on page 1of 9

Contract

C 311554
Number
Project ID IN000IN0079

Project Name SAIH RAWL COMBINED CYCLE POWER STATION

Document Type INSPECTION PLAN

Document Title ROOF WATERPROOFING WORKS


Unit Originator Disc Doc Sheet Rev
Area Seq No
Code Code Code Type No No
Document Number
LNG 75 102961 QA 5733 00011 0000 01

REVISION CONTROL

01 31-01-2017 First Issue-For review TSR

Rev. Date Description Prepared By

ITP- ROOF WATERPROOFING WORKS


Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01
Reference Standards: PDO SP 1279 : Dec 2009
C-311554 IN000IN0079

Document Preparation

Activity Name Designation Initials

Page 1 of 9
Prepared by TS REDDY QA/ QC Manager TSR
Reviewed &
Kota Prasad Contract Manager KAP
Approved by

Revision History

Revision
Date of Rev Revision Description
Number

01 31-01-2017 Issue for review

Page 2 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC -SRWL Reference Standards: PDO SP 1279 : Dec 2009
Sl Test Verification Verification Sub- BE
Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C

Review of Scope of work  All data supplied meets the applicable Contract
Contract C311554, P.O.
and Drawings, Contract PDO specifications. Specifications /
Approved Drawings,
1. Requirements.  PDO approved sub-contractor 100% QA Engineer. Company H H R/A
SP-1279
Approval of Contractor / Specification.
Subcontractor.
 As per Approved Method of statement
Contract C311554, and ITP As per the requirements of PDO Approval
Approval of Method
Applicable Standards as Controlling Documents, SP-1279. of Method
Statement , Inspection
2. per  From Company approved source. 100% QA Engineer. statement. H H H
and Test plan ,Material &
SP-1279-F Approved ITP,
Source
Clause 2.3.3 Approved MAS.

 The concrete deck to receive screed shall


be well brushed to remove laitance.
Before laying screeds the surface of the
concrete shall be free from surface dust C311554-C-REC-
SP-1279-F and dampened with clean water. QCI (Civil) 023
3. Surface preparation 100% H H W/A
Clause 2.3.2  Spot levels & survey shall be given for the
Preparation of screed to the required
slope and cross slope.
 Traps shall be provided at the rain water
outlet pipe areas.
4. Materials for screed SP-1279-F  Sand, cement and water required for 100% H H W/A
Clause 2.3.2 screed and angle fillets including mixing,
shall comply with the requirements of
SP-1279-D.
 Materials for screed shall be mixed on
the Worksite in a batch mixer of QCI (Civil) C311554-C-REC-
approved size and design complying with 023
BS 1305 or similar approved, producing a
uniform distribution of materials with
mass of uniform colour and consistency.
Page 3 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009

Sl Test Verification Verification Sub- BE


Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C

 The screeds shall be formulated of one


part OPC (complying with BS EN 197-1-
2000), to two parts of sand (complying
with BS 13139) to four parts aggregate,
14 mm maximum size complying with BS
12620.
 The proportion of materials for angle
fillets shall be one part OPC (complying
with BS EN 197-1-2000), to three parts
sand (complying with BS 13139).

5. Screed for roof SP-1279-F  The Contractor shall not proceed with 100% H H H
waterproofing works Clause 2.3.2 laying screed or angle fillets until the
existing concrete deck surface has been
approved by the Company.
 The Contractor shall lay screeds to the
specified thickness and/or falls as shown
in the Contract Documents and in
alternate bays not exceeding 11 m2.
Stop-ends shall be vertical and
positioned to coincide with construction QCI (Civil) C311554-C-REC-
023
joints in the concrete deck.
 Screed and angle fillets shall not pass
over roof expansion joints in the
concrete deck.
 Expansion joints shall comprise
impregnated fibre joint filler board to the
specified width.
 Screed and angle fillets shall be finished
smooth and even with a wood float
finish.

Page 4 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009

Sl Test Verification Verification Sub- BE


Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C

 Where specified, a steel trowel shall be


applied lightly to present an even dense
surface without laitance occurring.
6.  The entire surface shall be protected
from premature drying and rapid
temperature change by covering with
sand or hessian or polythene sheeting,
Curing & Protection of SP-1279-F and kept continuously damp for a
screed Clause 2.3.2 minimum period of 4 days.
 Care shall be taken to ensure that any
sheeting is securely fixed during this
period to prevent wind blowing under 100% QCI (Civil) C311554-C-REC- H W S
the covering. 023

7. Waterproofing system & SP-1279-F  The Waterproofing System and C311554-C-REC- H W R


materials. Clause 2.3.3 associated Works shall be laid in strict 100% 023
accordance with the manufacturer's
Approved AFC Drawing written instructions.
 Waterproofing system shall include-
Approved MAS - Screed to falls ( min 50mm )
- Bituthene 1200x HC or Equivalent
with 150mm laps on primed screed
to falls.
- 40x40 mm Bituthene or Equivalent QCI (Civil)
Fillet HC.
- Bituthene 1200x HC or Equivalent
and Solar Shield HC turned into
25x25 chase and plugged with 25x25
wooden batten and sealed with
servimastic sealant.
- 300x300 mm wide Bituthene 1200x
HC or Equivalent reinforcing strip in

Page 5 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009

Sl Test Verification Verification Sub- BE


Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C

corner.
- Expanded polystyrene insulation 35
kg/cu.m 75mm thick with 15mm
rebate on edges.
- Separation layer of 500g Polythene
sheet.
- 300x300x30mm thick concrete slab
with pointing & set in 20 thick
screed.
- Expanded metal mesh laid under
insulation, approx. 300mm and bent
up to retain gravel topping at
gargoyle location.
- One layer of Bitustick AL self-
adhesive aluminum membrane of
girth 300 mm is taken from fillet end
up to the preformed groove on the
vertical area of upstand and tucked
inside the groove.
8. Laying of water proofing SP-1279-F  Waterproofing systems and associated
membrane Clause 2.3.3 Works should be laid by a specialist 100%
nominated subcontractor, experienced in QCI (Civil)
Approved AFC Drawing laying the specified waterproofing
system. C311554-C-REC- H W S
 Where specified in the Contract 023
Documents, built-up bitumen felt shall be
laid in accordance with the
manufacturer's written instructions and
BS 8217.
 Where specified in the Contract
Documents, mastic asphalt shall be laid

Page 6 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009

Sl Test Verification Verification Sub- BE


Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C

in accordance with the manufacturer's


written instructions and BS 8218.
 High density, sealed surface preformed
expanded polystyrene insulation
complying with BS 3837 shall be to the
specified thickness and U-values.
 Expanded polystyrene insulation shall be
loose laid with staggered joints and
SP-1279-F
edges butted together with a minimum
Clause 2.3.3
lap of 10 mm.
Loose-Laid Insulation
9.  The expanded polystyrene insulation H W R
Approved AFC Drawing 100% QCI (Civil)
shall be protected from wind uplift and
C311554-C-REC-
ultraviolet degradation prior to laying of
023
the protective tiles or gravel.
 Care shall be taken that the expanded
polystyrene is not damaged by foot
traffic, tools, etc.
 Any damaged panels shall be removed
and replaced.
10. Protection SP-1279-F  Solar reflective sheets shall be laid in H W R
Clause 2.3.3 accordance with the manufacturer's 100%
written instructions. QCI (Civil)
Approved AFC Drawing  Precast concrete slabs to sizes specified
on the drawings complying with BS C311554-C-REC-
EN1339. Concrete slabs shall be of a 023
light colour.
 Stone ballast protection shall be 20 mm
diameter washed wadi gravel, free from
all sharp stones and any deleterious
matter to the specified thickness.
 Check all the miscellaneous footings

Page 7 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009

Sl Test Verification Verification Sub- BE


Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C

installed over the water proofing


membrane sealed properly
 All flat roofs shall be tested by damming
all water-outlets and flooding the entire
surface with water to a minimum depth
of 75 mm for a period of not less than 24
hours. Any leaks found shall be made C311554-C-REC-
Sampling & testing of SP-1275 good to the approval of the Company. 023
11. 100% QCI (Civil) H W M
roof waterproofing Sec 2.11  Testing shall be conducted prior to laying Guarantee
any protection system. Test sheets shall Certificate
be provided and signed by Company site
representative.
 Supplier has to give Guarantee for the
W/P system for a period of 10 years
Final inspection and  Review all check List and Forms C311554-C-REC-
12. Check list and Forms 100% QCI (Civil) H W R
Document  As Built Drawings 023

Inspection and test mark-up legend: M = Monitor, W = Witness, H = Hold Point, R = Document Review, A= Document Approval

The following definitions shall apply:

Hold Point (H): A critical step in fabrication and testing where it is mandatory that the responsible party inspect the component/equipment or witness an activity. Activities
designated as a Hold Point shall not proceed unless the responsible party is present or the Hold Point is formally waived. The Company shall be notified at a duration specified in
the contract in advance of the activity.

Witness Point (W): A critical step in fabrication and testing where it is desirable that the responsible party inspect the component/equipment or witness an activity. The
responsible party shall be notified at a duration specified in the contract in advance of the activity. Once proper notification is given, the activity may proceed according to the
schedule regardless of the Company’s attendance.

Monitor Point (M): A critical step in fabrication and testing where it is optional that the responsible party inspect the component/ equipment or witness an activity. The
responsible party shall be notified at a duration specified in the contract in advance of the first occurrence of the activity at each worksite. No further notification for like activities
at each worksite shall be required. The activity may proceed with or without the Company’s attendance.

Approval Point (A): A critical step in design, procurement, and or fabrication and testing where it is mandatory that the responsible party approve a document/qualification/
equipment/or activity. The responsible party shall be notified at a duration specified in the contract in advance of the first occurrence of the activity or provided the document in a

Page 8 of 9
Company : Petroleum Development Oman ITP – ROOF WATERPROOFING WORKS
Contractor : Bahwan Engineering Co LLC Doc No : LNG-75-102961-QA-5733-00011-0000 Rev.01 Contract Ref : C311554
Contract : EPC - SRWLl Reference Standards: PDO SP 1279 : Dec 2009

Sl Test Verification Verification Sub- BE


Activity Controlling Document Acceptance Criteria PDO
No Frequency Personnel Record Con C

period of time specified by the contract. The activity may not proceed without the responsible party’s approval.

Review Point (R): A critical step in design, procurement, and or fabrication and testing where it is desirable that the responsible party review the document/qualification/
equipment/or activity. A separate notification is not needed unless otherwise specifically requested; the responsible party may perform this along with any of the other intervention
types.

Page 9 of 9

You might also like