Hand over note

Hand over to : Mr.P.Shankar - QA/QC Inspector.

Construction Package PID2242/CPPP10.

1) MPT Report No.007 to be Signed


Construction package. PID 2245/CPRA 01

1) Weld Visual report no. VI 003 T o be signed

Construction package. PID 2244/CPRP 01

1) All BSP comments are cleared

Construction package. PID 2249/CPAP 12

1) MPT Report no.22 &23 to be signed

Construction package. PID 2249/cpwj-21

1) MPT Report no.32 & 33 to be signed

Construction package. PID 2266/AMRJ 01

1) Material Traceability Reports No.FI-006,FI-001 &FI-007 To be


signed and all other reports to be reviewed.

Construction package. PID 2266/AMDP 06

1)All punch item to be transferred to revised punch list which is


available with Mr.Shim and also to be closed out by getting
signature from BSP,Since the all the punch item are already
completed.

Note:-The following construction package to be resubmitted to BSP


after Mr.Shankar clear the above item.

1)PID 2249 /CPAP 12 &CPWJ 21

2)PID 2245/CPRA 01

3)PID 2242/CPPP 10

4) PID 244 /CPRP 01