Area: FT – FOREL
System: 86 – Telecommunication
Submitted For:
FOREL PROJECTS
Review Certified Info
Review does not constitute acceptance of design Supplier Name: PT. JETEC INDONESIA
details, calculations, test methods or materials
developed or selected by supplier nor does it relieve
supplier from full compliance with contractual or other
obligations
Tag No. : -
Date :
Project Procedure / Plans ID-F-FT-P-TD001-A08-00001 Rev. 0B
Integration Procedure of Telecom System WHP and FPSO
Medco E&P Natuna Ltd. Page 2 of 23
Revision Sheet
0A 31 Oct 22 Page 1
0A 31 Oct 22 Page 3
tidy
0A 31 Oct 22 Page 14
0A 31 Oct 22 Appendix A
0A 31 Oct 22 Appendix B
0A 31 Oct 22 Appendix G
Contents
1 INTRODUCTION .................................................................................................................................... 5
1.1 Purpose ......................................................................................................................................... 6
1.2 Scope ............................................................................................................................................ 6
1.3 Reference Documents .................................................................................................................. 6
1.3.1 Company Specifications and Standards .......................................................................... 6
1.3.2 Project Documents .......................................................................................................... 6
2 DEFINITIONS, ABBREVIATIONS & UNITS ......................................................................................... 7
2.1 Definitions ..................................................................................................................................... 7
2.2 Abbreviations ................................................................................................................................ 7
2.3 Units .............................................................................................................................................. 8
3 GENERAL DESIGN REQUIREMENT.................................................................................................... 8
3.1 Control Overview .......................................................................................................................... 8
3.2 Hazardous Area Classification and Protection ............................................................................. 9
3.3 Environmental Condition ............................................................................................................... 9
4 INTEGRATION PROCEDURE SUMMARY ......................................................................................... 10
4.1 Forel WHP Telecom System ...................................................................................................... 10
4.2 Bronang WHP Telecom System ................................................................................................. 11
4.3 Belanak FPSO Telecom System ................................................................................................ 11
4.4 Integration Tools ......................................................................................................................... 11
4.5 Location ...................................................................................................................................... 12
4.6 Acceptance ................................................................................................................................. 12
5 INTEGRATION PLANNING AND MANPOWER ................................................................................. 12
5.1 Manpower ................................................................................................................................... 12
5.2 Interdisciplinary Coordination and Responsibility ....................................................................... 12
5.3 HSE Management....................................................................................................................... 13
6 INTEGRATION REQUIREMENT ......................................................................................................... 13
7 INTEGRATION PROCEDURE ............................................................................................................. 14
7.1 Bronang WHP – Belanak FPSO Integration Test Procedure ..................................................... 14
7.2 Bronang WHP – Forel WHP and Forel FPSO Integration Test Procedure ................................ 14
8 List of Appendix.................................................................................................................................. 15
Appendix A – Bronang WHP – Belanak FPSO Integration Test Procedure ........................................ 16
Appendix B – Bronang WHP – Forel WHP and Forel FPSO Integration Test Procedure .................. 17
Appendix C – Certificate of Completion Bronang WHP – Belanak FPSO ........................................... 18
Appendix D – Certificate of Completion Bronang WHP – Forel WHP - Forel FPSO ........................... 19
Appendix E – Job Safety Analysis (JSA) ................................................................................................ 20
Appendix F – Livening Up Notice (LUN) ................................................................................................. 21
Appendix G – Bronang WHP – Belanak FPSO Integration Architecture ............................................. 22
Appendix H – Bronang WHP – Forel WHP and Forel FPSO Integration Architecture ....................... 23
Project Procedure / Plans ID-F-FT-P-TD001-A08-00001 Rev. 0B
Integration Procedure of Telecom System WHP and FPSO
Medco E&P Natuna Ltd. Page 5 of 23
1 INTRODUCTION
Medco E & P Natuna Ltd, hereafter known as COMPANY, is undertaking the development of Forel-
Bronang fields as part of the ongoing program for the development of oil and gas fields in the South
Natuna Sea Block B Production Sharing Contract Area from the Republic of Indonesia in 300 feet of
water as illustrated in Figure 1. Production from this field is estimated to start at the end of 2023.
1.1 Purpose
The purpose of this document is as reference and guidance for methodology and documentation /
record of Integration Procedure Telecom System WHP and FPSO. This test shall be performed to
verify and validate that the functionality of the equipment, hardware and software, related to EPCI of
Wellhead Platforms and Pipeline for Forel Bronang Project are meet project requirement and
specification.
1.2 Scope
The scope of this Integration Procedure Telecom System WHP and FPSO covers for the Telecom
System at Forel WHP, Bronang WHP, and additional Telecom System at Belanak FPSO.
2.2 Abbreviations
CCR : Central Control Room
CCTV : Closed-Circuit Television
CPY : Company
CTR : Contractor
DMR : Digital Microwave Radio
FOBOT : Fiber Optic Break Out Tray
FPSO : Floating Production, Storage & Offloading
ICSS : Integrated Control and Safety System
LAN : Local Area Network
LPU : Lightning Protection Unit
LUN : Livening Up Notice
MEPN : Medco E&P Natuna
MFP : Minimum Facility Platform
Project Procedure / Plans ID-F-FT-P-TD001-A08-00001 Rev. 0B
Integration Procedure of Telecom System WHP and FPSO
Medco E&P Natuna Ltd. Page 8 of 23
2.3 Units
The project shall use the system of units as given in doc.no. ID-F-FT-PP0-BOD-GN-00-
0001_R9_Integrated Basis of Design, for all calculations, drawings and in all project documentation.
All structural, flowlines and layout documents shall use the metric system. All vendor documentation
and equipment shall also utilize equivalent systems.
All field telecommunication equipment mounted outdoor will be designed for installation in an area
classification Zone 2, Gas Group IIA, Temperature class T3 and shall be certified Ex d as minimum
in hazardous area. Zone 0 or Zone 1 certified equipment shall be provided when it is required by
the hazardous area classification.
Due to high temperature, humidity and salt content, tropic proofing shall be applied to ensure
equipment operate continuously without their normal physical and functional reliability being
affected by the tropical environment. Tropic proofing shall be accomplished by applying protective
coating to prevent the growth of fungus, corrosion and absorption of moisture.
If any specific instruments are unable to comply with above requirements, CTR / SI shall inform
CPY for approval.
The marine growth can be taken as 2.0” (5.0 cm) for all elevations with 1325 kg/m3 marine growth
density.
− 2 units FOBOT
− 2 units PIDU
• CCTV System, consists of :
o 1 IP PTZ Cameras
o 1 IP Fixed Cameras
o 2 units CCTV Junction Box
o 2 units CCTV Washers
4.5 Location
The Integration will be held in Offshore Forel WHP, Bronang WHP and Belanak FPSO.
4.6 Acceptance
Formal Integration Telecom System acceptance shall be indicated by a Certificate of Completion,
which shall be signed by all parties involved as a proved that Integration Telecom System has been
performed.
The Certificate of Completion are enclosed in Appendix C – Certificate of Completion Integration
Telecom System Bronang WHP – Belanak FPSO and Appendix D – Certificate of Completion
Integration Telecom System Bronang WHP – Forel WHP - Forel FPSO.
Table 5.2 Manpower and estimate duration for Integration Telecom System Bronang WHP to Forel
WHP and Forel FPSO
1. Commissioning CTR H
2. Telecom Engineer H
Project Procedure / Plans ID-F-FT-P-TD001-A08-00001 Rev. 0B
Integration Procedure of Telecom System WHP and FPSO
Medco E&P Natuna Ltd. Page 13 of 23
3. Construction MEPN M
4. Commissioning MEPN W
5. Operation MEPN W
6 INTEGRATION REQUIREMENT
Other Subsystem Required for Test . The following subsystems to be completed prior to perform
Integration Telecom System.
For Bronang :
1. Solar Panel System
2. Distribution Board 24 VDC
3. Telecommunication System local Bronang WHP and additional Telecommunication System at
Belanak FPSO
For Forel :
1. Distribution Board 24 VDC
2. Telecommunication System at local Forel WHP, Bronang WHP and Forel FPSO
3. UPS System
Project Procedure / Plans ID-F-FT-P-TD001-A08-00001 Rev. 0B
Integration Procedure of Telecom System WHP and FPSO
Medco E&P Natuna Ltd. Page 14 of 23
7 INTEGRATION PROCEDURE
7.1 Bronang WHP – Belanak FPSO Integration Test Procedure
The purpose of this test is to ensure that all telecom communication system with minimum
disturbance with existing facility between Bronang WHP and additional telecom system on Belanak
FPSO integrated and function properly as per reference documents and to verify all the data
transferred is sent received correctly.
1 Obtain permit-to-work
Prepare drawings and related documents
2 for testing
Confirm that 24 VDC distribution board, in
3 correct state at Bronang WHP
Confirm that 120 VAC distribution in
4 correct state at Belanak FPSO
Ensure network cable connection are
5 already pre-commissioned and properly
configured and connected.
Confirm that Telecommunication system
6 already power up and working properly.
Ensure the communication check is
7 already be done and all the connection
are good.
Completion of all outstanding punch items
8 in to punch list with no “A” priorities
outstanding
Check that there are not any outstanding
9 site queries/instructions that can affect
the Integration test
All the test sheet for Integration Telecom System Procedure Bronang WHP to Belanak FPSO can
be seen at Appendix A - Bronang WHP – Belanak FPSO Integration Test Procedure.
7.2 Bronang WHP – Forel WHP and Forel FPSO Integration Test Procedure
The purpose of this test is to ensure that all telecom communication system between Bronang WHP,
Forel WHP and telecom system on Forel FPSO integrated and function properly as per reference
documents and to verify all the data transferred is sent received correctly.
1 Obtain permit-to-work
Confirm that 24 VDC distribution board, in
2 correct state at Bronang WHP
Confirm that UPS system already power
3 up and working properly at Forel WHP
Confirm that the telecommunication
4 system at Forel FPSO already power up
and working properly upon integration
test
Ensure network cable connection are
4 already pre-commissioned and properly
configured and connected
Project Procedure / Plans ID-F-FT-P-TD001-A08-00001 Rev. 0B
Integration Procedure of Telecom System WHP and FPSO
Medco E&P Natuna Ltd. Page 15 of 23
8 List of Appendix
1. Appendix A – Bronang WHP – Belanak FPSO Integration Test Procedure
2. Appendix B – Bronang WHP – Forel WHP and Forel FPSO Integration Test Procedure
3. Appendix C – Certificate of Completion Bronang WHP – Belanak FPSO
4. Appendix D – Certificate of Completion Bronang WHP – Forel WHP - Forel FPSO
5. Appendix E – Job Safety Analysis (JSA)
6. Appendix F – Livening Up Notice (LUN)
7. Appendix G – Bronang WHP – Belanak FPSO Integration Architecture
8. Appendix H – Bronang WHP – Forel WHP and Forel FPSO Integration Architecture
Project Procedure / Plans ID-F-FT-P-TD001-A08-00001 Rev. 0B
Integration Procedure of Telecom System WHP and FPSO
Medco E&P Natuna Ltd. Page 16 of 23
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
Activation of
17 CB-09 Switch on CB-09
86-TDC-008
The presence of 24
18 CB-10 Switch on CB-10 VDC on Input and
Output CB-10
REMARK :
1.2 BRONANG WHP UHF RADIO PANEL (86TAD-004) POWER SUPPLY CHECK
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
• Check the presence of
24 VDC in TB Feeder
24 VDC (TB-24-F1).
Incoming • MCB-01 in OFF MCB-01 main circuit Breaker
1
UHF Panel : Position. function
• Feeder 1 • Measure the load
current of incoming 24
VDC TB Feeder
2 MCB-01 Switch on MCB-01 Activation of CONV-1
Measure the load current of
CONV-1 Function and
3 CONV-1 incoming is 24 VDC, and
activation of 86-TUZ-4001
outgoing is 24 VDC
Measure the load current of
4 86-TUZ-4001 incoming is 24 VDC, and Activation of 86-TUC-4001
0B outgoing is 12 VDC
REMARK :
REMARK :
2 FUNCTIONAL TEST
This test is intended to verify local parameter of Telecom System equipments.
2.1 BRONANG WHP TELECOM SYSTEM LOCAL PARAMETER
Acceptance
Result
NO Item Activity Description Objective
PASS FAIL
Fixed Camera 2
8 IP Address Check 10.80.31.132 / 255.255.255.224
86-TQN-4002
Note : 1. Layer 3 Switch with a premium license for routing protocol will be used instead of the Router due to
delivery time constraints.
REMARK :
Acceptance
Result
NO Item Activity Description Objective
PASS FAIL
Note : 1. Layer 3 Switch with a premium license for routing protocol will be used instead of the Router due to
delivery time constraints.
REMARK :
Acceptance
NO Item Activity Description Result
PASS FAIL
Bronang WHP Telecom
1 Check that all communication data traffics are up and running.
equipments
Belanak Telecom
2 Check that all communication data traffics are up and running.
equipments
Make sure Active + Active of DMR communication between
DMR Link A and B at Bronang WHP and Belanak FPSO is correct.
3 Bronang WHP / Belanak Simulate link failure between Link A and Link B by
FPSO disconnecting Link A DMR and ensuring that Link B is takes
over the communication link and vice versa.
CCTV and ICSS Check that 2 (two) CCTVs Bronang WHP and ICSS data shall
4 monitoring at Belanak be monitored from Belanak FPSO during Link A / Link B DMR
FPSO communication active,.
CCTV equipments at Check that the CCTV function / control from CCTV
5 Bronang WHP and workstation / CCTV console at Belanak FPSO into CCTV
Belanak FPSO equipments Bronang WHP are working properly.
Monitor and records bandwidth utilization via PRTG
software. Monitor bandwidth utilization on the following
Bandwidth Monitoring devices:
during test integration. • 86-TDC-009 (IP 10.80.33.1/27)
6 Monitor & record vessel • 86-TDC-006 (IP 10.80.31.1/27)
draft for antenna • 86-TDC-007A (IP 10.80.30.31.2/27)
elevation • 86-TDC-007B (IP 10.80.31.3/27)
• 86-TDC-008 (IP 10.80.31.130/27)
BER/Ethernet Test with Monitor and Record the following value for :
estimation 1 (one) hour • Throughput
7 for Link A DMR and Link • Latency
B DMR on Bronang WHP • Frame Loss
and Belanak FPSO. Ensure the overall test result are “PASS”
0B
REMARK :
Acceptance
Result
NO Item Activity Description
PASS FAIL
Communication Between UHF Check that Radio Handheld can communicate using
1
Handheld Radio in Bronang WHP Repeater in Bronang WHP
REMARK :
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
The presence of 24
16 CB-07 Switch on CB-07 VDC on Input and
Output CB-07
The presence of 24
VDC on RLY-01 and
17 CB-08 Switch on CB-08
activation of
86-TPC-001
REMARK :
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
• Check the presence of 24 VDC
in TB Feeder TB-24-F3 no. 1 &
2 on Telecom Panel 1
24 VDC • 86TAD-001
MCB-01 main circuit
1 Incoming • Check the presence of 24 VDC
Breaker function
Feeder in TB Feeder (TB-24-F1)
• MCB-01 in OFF Position.
• Measure the load current of
incoming 24 VDC Feeder.
Activation of
4 CB-01 Switch on CB-01
86-TDC-002
Activation of
5 CB-02 Switch on CB-02
86-TDC-003A
Activation of
6 CB-03 Switch on CB-03
86-TDC-003B
Activation of
7 CB-04 Switch on CB-04
86-TDC-004A
Activation of
8 CB-05 Switch on CB-05
86-TDC-004B
Activation of
9 CB-06 Switch on CB-06
86-TDC-005
REMARK :
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
REMARK :
1.4 BRONANG WHP UHF RADIO PANEL (86TAD-004) POWER SUPPLY CHECK
Acceptance
Measurement Result
NO Item Activity Description Objective
Result
PASS FAIL
• Check the presence of
24 VDC in TB Feeder
24 VDC (TB-24-F1).
Incoming • MCB-01 in OFF MCB-01 main circuit Breaker
1
UHF Panel : Position. function
• Feeder 1 • Measure the load
current of incoming 24
VDC TB Feeder
2 MCB-01 Switch on MCB-01 Activation of CONV-1
Measure the load current of
CONV-1 Function and
3 CONV-1 incoming is 24 VDC, and
activation of 86-TUZ-4001
outgoing is 24 VDC
Measure the load current of
4 86-TUZ-4001 incoming is 24 VDC, and Activation of 86-TUC-4001
outgoing is 12 VDC
0B
REMARK :
2 FUNCTIONAL TEST
This test is intended to verify local parameter of Telecom System equipments.
2.1 FOREL WHP TELECOM SYSTEM LOCAL PARAMETER
Acceptance
Result
NO Item Activity Description Objective
PASS FAIL
ICSS Switch B
6 VLAN 100 10.80.30.3 / 255.255.255.128
86-TDC-004B
LAN/WAN
IP Address Check Interface
7 SWITCH 10.80.30.130 / 255.255.255.192
Management
86-TDC-002
DMZ SWITCH A IP Address Check Interface
8 10.80.30.131 / 255.255.255.192
86-TDC-003A Management
PTZ Camera
10 IP Address Check 10.80.30.195 / 255.255.255.192
86-TQN-3001
Fixed Camera
11 IP Address Check 10.80.30.196 / 255.255.255.192
86-TQN-3002
Note : 1. Layer 3 Switch with a premium license for routing protocol will be used instead of the Router due to
delivery time constraints.
Integration Telecom System Procedure with FPSO Telecom System
Appendix B – Bronang WHP – Forel WHP and Forel FPSO Integration Test Procedure Page 8 of 13
REMARK :
ICSS Switch B
6 VLAN 100 10.80.31.3 / 255.255.255.224
86-TDC-007B
Fixed Camera 1
7 IP Address Check 10.80.31.131 / 255.255.255.224
86-TQN-4001
Fixed Camera 2
8 IP Address Check 10.80.31.132 / 255.255.255.224
86-TQN-4002
Note : 1. Layer 3 Switch with a premium license for routing protocol will be used instead of the Router due to
delivery time constraints.
REMARK :
2.3 BRONANG WHP – FOREL WHP AND FOREL FPSO END-TO-END COMMUNICATION TEST
This test is intended to verify Ping test for Integration Telecommunication System with expected result
“Replay” from destination. Make sure that all communication data traffics related to integration are up
and running.
Acceptance Result
NO Item Activity Description Objective
PASS FAIL
Test Ping to Destination IP
86-TDC-003A IP 10.80.30.131
DMZ Switch A Pass : Replay
1 86-TDC-003B IP 10.80.30.132
Forel FPSO Fail : RTO Request Time Out)
86-TVC-001 IP 10.80.30.129
86-TDC-003A IP 10.80.30.131
DMZ Switch B Pass : Replay
2 86-TDC-003B IP 10.80.30.132
Forel FPSO Fail : RTO Request Time Out)
86-TVC-001 IP 10.80.30.129
86-TDC-001 IP 10.80.30.1
86-TDC-004A IP 10.80.30.2
86-TDC-007A IP 10.80.31.2
86-TDC-007B IP 10.80.31.3
86-TDC-001 IP 10.80.30.1
86-TDC-004A IP 10.80.30.2
86-TDC-007A IP 10.80.31.2
86-TDC-007B IP 10.80.31.3
86-TDC-001 IP 10.80.30.193
86-TDC-005 IP 10.80.30.194
86-TQN-3001 IP 10.80.30.195
86-TDC-008 IP 10.80.31.130
86-TQN-4001 IP 10.80.30.131
86-TQN-4002 IP 10.80.30.132
Integration Telecom System Procedure with FPSO Telecom System
Appendix B – Bronang WHP – Forel WHP and Forel FPSO Integration Test Procedure Page 11 of 13
REMARK :
Acceptance
NO Item Activity Description Result
PASS FAIL
Bronang WHP Telecom Check that all communication data traffics are up and
1
equipments running
Forel WHP Telecom Check that all communication data traffics are up and
2
equipments running
0B Check that the Active + Active of DMR communication
between Bronang WHP and Forel WHP is correct.
DMR Link A and B at Bronang
3 Simulate link failure between Link A and Link B by
WHP / Forel WHP
disconnecting Link A DMR and ensuring that Link B is
takes over the communication link and vice versa.
Open web browser and access the specified IP provided
CCTV monitoring via
for each Bronang WHP CCTVs. Check that 2 (two)
4 temporary laptop at Forel
CCTVs Bronang WHP could be monitored from
WHP
temporary laptop at Forel WHP via DMR communication.
Monitor and records bandwidth utilization via PRTG
software. Monitor bandwidth utilization on the following
devices:
• 86-TDC-001 (IP 10.80.30.1/25)
• 86-TDC-004A (IP 10.80.30.2/25)
Bandwidth Monitoring during • 86-TDC-004B (IP 10.80.30.3/25)
5
test integration • 86-TDC-005 (IP 10.80.30.194/26)
• 86-TDC-006 (IP 10.80.31.1/27)
• 86-TDC-007A (IP 10.80.30.31.2/27)
• 86-TDC-007B (IP 10.80.31.3/27)
• 86-TDC-008 (IP 10.80.31.130/27)
BER/Ethernet Test with Monitor and Record the following value for :
estimation 1 (one) hour for • Throughput
6 Link A DMR and Link B DMR • Latency
on Forel WHP and Bronang • Frame Loss
WHP. Ensure the overall test result are “PASS”
REMARK :
2.5 BRONANG WHP – FOREL WHP AND FOREL FPSO UHF RADIO COMMUNICATION TEST
The test is intended to verify communication between UHF handheld radio Bronang WHP, Forel WHP
and Forel FPSO.
Acceptance
Result
NO Item Activity Description
PASS FAIL
Communication Between UHF Check that Radio Handheld can communicate using
1
Handheld Radio in Bronang WHP Repeater in Bronang WHP
REMARK :
THE UNDERSIGNED HAS INSPECTED AND WITNESSED THE TESTS WITHIN THIS PROCEDURE
(PROJECT DOCUMENT ID-F-FT-P-TD001-A08-00001) AND ITS APPENDICES.
THE UNDERSIGNED ACCEPTS THAT THE SYSTEMS HAVE BEEN TESTED TO THE AGREED
PROCEDURES (PROJECT DOCUMENT ID-F-FT-P-TD001-A08-00001 AND ITS APPENDICES) AND
MEETS THE REQUIREMENTS OF THE CLIENT ORDER.
PT. JETEC INDONESIA PT. MEINDO ELANG INDAH MEDCO E&P NATUNA
Representative Representative Representative
THE UNDERSIGNED HAS INSPECTED AND WITNESSED THE TESTS WITHIN THIS PROCEDURE
(PROJECT DOCUMENT ID-F-FT-P-TD001-A08-00001) AND ITS APPENDICES.
THE UNDERSIGNED ACCEPTS THAT THE SYSTEMS HAVE BEEN TESTED TO THE AGREED
PROCEDURES (PROJECT DOCUMENT ID-F-FT-P-TD001-A08-00001 AND ITS APPENDICES) AND MEETS
THE REQUIREMENTS OF THE CLIENT ORDER.
THE INTEGRATION TELECOM SYSTEM IS ATTENDED, WITNESSED, VERIFIED AND APPROVED BY THE
FOLLOWING REPRESENTATIVE(S):
PT. JETEC INDONESIA PT. MEINDO ELANG INDAH MEDCO E&P NATUNA
Representative Representative Representative
DATE ISSUED:
JOB SAFETY ANALYSIS LAST REVIEWED DATE:
Job Description:
REVIEWED BY:
Area/Unit: Forel WHP, Bronang WHP and Belanak FPSO
(Name & Signature)
SUPERVISOR.
Tag No/Equipment Description:
(Name & Signature)
RESPONSIBLE PERSON:
References:
(Name & Signature)
PPE Required to do this Job: Yes Page: 1 of 2
Potential Hazard Risk Level before Control Statement Risk Level after
Job Step Potential Event Mitigation (H,M,L)
(Physical, Chemical, Biological, Mitigation
(C x L) (Required to reduce severity & likelihood)
Psychosocial, Ergonomic)
Work preparation 1. Psychosocial: Miscommunication 1. Miscommunication M (2x3) 1. Conducting toolbox meeting/Pre-Job Safety Meeting before L (2x1)
2. Physical: Mechanical, Gravity, 2. First Aid because of Pinch, doing work and delegating work according to competencies.
- PTW already been approved
Noise Slip, Trip & Fall 2. Work leader to ensure all team member understand with the
- Coordination with PROJECT &
OPS 3. Ergonomic: Mismatch, Awkward risk and its mitigation.
- Pre-Job Safety Meeting 3. Work leader must ensure all team member understand the
scope of work and its boundaries.
1. Psychosocial: Miscommunication 1. Miscommunication M (2x3) 4. Use
1. Competent
proper person.
PPE. L (1x2)
Material Preparation
2. Physical: Mechanical, Electricity, 2. First Aid because of Pinch, 5. Installing
2. Make surebarricade.
your hands and fingers are free from pinched point.
- Prepare Tools & Equipment at Site 6.
Weather. Slip, Trip & Fall. 3. Obtain
Proper weather forecast from Radio
body position/ergonomic Operator.
position
3. Ergonomic: Mismatch, Awkward 3. Pinch point. 4. Using full body harness at high location activities.
5. Make sure your hands and fingers are free from pinched point.
6. Housekeeping of the equipment must be maintained to prevent
the equipment from falling from a height and a tripping hazard.
Telecom System Operating 1. Psychosocial: Miscommunication 1. Miscommunication M (3x2) 1. Use proper PPE. L (2x1)
2. Physical: Electricity. 2. First Aid because of Pinch, 2. Installing barricade/sign at work activities.
- Check and identify the tag number
3. Ergonomic: Mismatch, Awkward Slip, Trip & Fall. 3. Activities done by in-charge and authorized personnel.
to be tested at Telecom Panels,
UHF Radio Panel, CCTV Junction 4. Pinch point. 3. Mechanical 4. Make sure your hands and fingers are free from pinched point.
Boxes and CCTV Washer 4. Trigger Alarm
- Installation of DMR Antennas, UHF
Antenna, ODU, LPU, Telecom
Panels, UHF Radio Panel, CCTV
Cameras, CCTV Junction Boxes
and CCTV Cameras.
- Operating of Data Network, DMR.
UHF Repeater and CCTVs.
Doc No:
DATE ISSUED:
JOB SAFETY ANALYSIS LAST REVIEWED DATE:
Job Description:
REVIEWED BY:
Area/Unit: Forel WHP, Bronang WHP and Belanak FPSO
(Name & Signature)
SUPERVISOR.
Tag No/Equipment Description:
(Name & Signature)
RESPONSIBLE PERSON:
References:
(Name & Signature)
PPE Required to do this Job: Yes Page: 2 of 2
Potential Hazard Risk Level before Control Statement Risk Level after
Job Step Potential Event Mitigation (H,M,L)
(Physical, Chemical, Biological, Mitigation
(C x L) (Required to reduce severity & likelihood)
Psychosocial, Ergonomic)
CCTV Workstation, NVR, joystick 1. Psychosocial: Miscommunication 1. Miscommunication M (3x2) 1. Use proper PPE. L (2x1)
and Monitor Operating 2. Physical: Electricity. 2. First Aid because of Pinch, 2. Installing barricade/sign at work activities.
3. Ergonomic: Mismatch, Awkward Slip, Trip & Fall. 3. Activities done by in-charge and authorized personnel.
- Check and identify the tag number
to be tested at CCTV Workstation, 4. Pinch point. 3. Mechanical 4. Make sure your hands and fingers are free from pinched point.
NVR, joystick and Monitor 4. Trigger Alarm
- Installation of CCTV Workstation,
NVR, joystick and Monitor.
- Operating of CCTV Workstation,
NVR joystick and Monitor.
Revalidation by the Responsible Person is required prior to commencing the activity or the Work Leader has changed or if the method of work has changed significantly.
Responsible Person Name & Signature Date Responsible Person Name & Signature Date
LUN No : xx
System No :
Sub-System No :
Reference Drawing No :
(to be attached)
This System and Sub-System, including the following components and all associated cabling and control devices will
be energised,
Date : Time :
The energisation will not occur until relevant Mechanical Completion Acceptance Certificate (MC-SAC) is approved
relating to each piece of equipment to be livened up.
No equipment will be livened up unless a Permit is obtained and warning sign and barriers is installed.
LUN No : xx
System No :
Sub-System No :
Reference Drawing No :
(to be attached)
This System and Sub-System, including the following components and all associated cabling and control devices will
be energised,
Date : Time :
The energisation will not occur until relevant Mechanical Completion Acceptance Certificate (MC-SAC) is approved
relating to each piece of equipment to be livened up.
No equipment will be livened up unless a Permit is obtained and warning sign and barriers is installed.
LUN No : xx
System No :
Sub-System No :
Reference Drawing No :
(to be attached)
This System and Sub-System, including the following components and all associated cabling and control devices will
be energised,
Date : Time :
The energisation will not occur until relevant Mechanical Completion Acceptance Certificate (MC-SAC) is approved
relating to each piece of equipment to be livened up.
No equipment will be livened up unless a Permit is obtained and warning sign and barriers is installed.