Professional Documents
Culture Documents
7. In the case when Bank is involved in funding, will PLN 7. We will provide this information in the RFP stage.
EPI allow mutual discussion regarding Shareholder
Agreement with Bank?
8. Will PLN EPI guarantee certain amount of facility 8. PLN EPI will guarantee that all investments in SPC facilities
utilization? For example: in this project will be returned with service rates/tariffs
a. Guaranteed fixed daily payment rate; or that will be included in the LISA.
b. Guaranteed fixed daily volume utilization; or
c. Other form of value.
9. When is the defined target for the effective date of the 9. To be announce later (TBA)
LNG Infrastructure Service Agreement?
10.In what language the Agreement between PLN EPI and 10. English and Bahasa
Project Sponsor will legally be applied?
11.Regarding gas demand information in chapter 6. To 11. Yes. PLN EPI will provide certain information regarding
provide the best proposal in terms of technical and gas demand, power plant operation model and others
commercial, we also need information about peak technical information later on RFP Process.
demand, not only average gas demand. For example, if
it may be possible in certain periods of days every
month, the peak gas demand is as twice as average gas
demand, then we need to calculate the proper size for
each facility. In short, operation pattern.
No. Company Email Date Question Answer
12.Will PLN EPI allow revision of opex throughout the 20- 12. OPEX cost will be divided into fix cost and variable cost.
year term of the project? For example, as we know fuel Fuel cost is parts of variable cost component.
cost may escalate significantly in a short period due to
major world situation and condition.
13.Regarding chapter 7 Part F. Will the development 13. The development budget that spent by PLN EPI and
budget spent by the selected Project Sponsor (both for Selected Project Sponsor after JDA process, will be
initial and future expansion) also be included as shared by SPC and will be calculated as SPC’s investment
investment costs? cost.
14.Regarding Schedule 1; Obligation on the SPC during 14. Other change law akan menjadi risiko PLN EPI.
project term: Are any circumstances related to
government policy will be possibly regarded as a cause
of force majeure?
15.Regarding land lease; will PLN EPI purchase and free the 15. Most of the land is own by PLN Persero, so the lease
land before leasing it to SPC? agreement shall be sign by SPC & PLN Persero. In the
event, the land not own by PLN Persero, PLN EPI will
assist with the land acquisition process but the land
purchase or lease agreement will be signed by SPC.
16.Since most of the design, construction, operating and 16. According to minutes of aanwijzing meeting stated that
especially financing risks are applied to SPC; Will PLN the land provide by PLN EPI and PLN EPI will evaluate the
EPI purchase and free the land in accordance to the detail design in the JDA stage in accordance with the
technical recommendation of Project Sponsor? requirement of technical and applicable regulation (with
no obligation PLN EPI to accept the recommendation).
Clarification Request:
Diesel or marine fuel for tugboats are not mentioned.
No. Company Email Date Question Answer
• Who will be responsible for the tugboat bunker
procurement?
3. Project Description in General 6.2, Page 6 3. The LNG carrier will be owned and on behalf on SPC’s
Issued to be clarified: name.
“LNG Infrastructure means facilities to receive LNG
cargoes delivered by (or on behalf of) PLN EPI to a
receival point in a Cluster…. including but not limited
to FSRU, LNG carriers, jetties, ….”
Clarification Request:
Our understanding is that the SPC will provide the LNG
infrastructure mentioned.
• Are the SPC allowed to hire any facilities to a sub-
contractor (not a member of consortium)? For
example, the SPC charters LNG carrier from a shipping
company not a member of the consortium.
Clarification Request:
What is the meaning of initial the deletions?
5. Qualification Criteria, 9.1.b, page 17 5. The Applicant cannot use its subsidiary experience. PLN
Issued to be clarified: EPI will accept experience of parent company’s applicant
“The experience as mentioned above are as long as the parent compeny has majority share in
recognized when the applicant or its parent (or applicant’s company.
No. Company Email Date Question Answer
holding) company has majority share and work portion
respectively in the project”
Clarification Request:
Please confirm our understanding as per below.
In the case that applicant is a parent or holding
company, subsidiary experiences will be recognized by
PLN EPI as long as the parent or holding company is the
majority shareholder in the subsidiary
1. Apakah di perbolehkan untuk leader hanya memiliki 1. Dalam hal peserta masuk dalam tahap PQ sebagai
D&B 5A2 tapi tidak memiliki pengalaman LNG yang konsorsium, maka kriteria pengalaman hanya perlu
rencananya akan KSO dengan yang memiliki dipenuhi oleh salah satu anggota konsorsium.
pengalaman.
2. Mohon info range ukuran kapal untuk muat di 2. informasi detail teknis akan disampaikan PLN EPI pada
Tangguh & Bontang. saat tahapan RFP.
PT. Enviromate
wildan.saliha 3 April
7 Technology
@gmail.com 2023 3. Mohon diinfo juga apakah ada manufacture vendor 3. Tidak ada, Bidders bebas selama manufacturer sudah
International
list? ada standar internasional yang divalidasi.
4. We believe that minimum net power requirement 4. Pertanyaan tidak terkait dengan proyek ini.
mentioned as 50 MW will be the evaluating criteria. In
case any bidder provides more than 50 MW net
electrical output, will there be any impact on the
evaluation criteria?
1. Dalam general experience criteria tertulis : 1. General experience boleh dimiliki sekurang-kurangnya 1
"The applicant or in the case of consortium – at least anggota. Namun jika dalam evaluasi terdapat anggota
one (1) member of the consortium of the Applicant konsorsium yang tidak memenuhi kriteria lainnya (seperti
ratna.tisnasari 3 April shall have any one or more of the following financial criteria), maka akan menggagalkan konsorsium
8 PT Temas Tbk
@temasline.com 2023 experiences …", akan tetapi berdasarkan MOM tersebut.
aanwajzing no. 29 dengan jawaban kegagalan 1
anggota konsorsium akan menggagalkan konsorsium
tersebut.
No. Company Email Date Question Answer
Mohon untuk dapat dikonfirmasi apakah masing-
masing anggota konsorsium wajib memenuhi general
experience criteria atau boleh satu saja?
2. Terkait form management key personel dan 2. Management key personel yang disampaikan bisa Direksi
competent key personal, siapa yang harus dan/atau manajemen dari Divisi/Unit Perusahaan terkait
didaftarkan? Apakah management key harus dari yang menangani proyek ini.
pihak direksi? Dan untuk dokumen lampiran
(certificate dll) apakah ada spesifikasi khusus untuk
sertifikatnya?
3. Di dalam usaha shipping, Bill of Lading merupakan 3. Berdasarkan pemahaman kami, untuk pengangkutan LNG
kontrak pengangkutan. Apakah Bill of Lading bisa pasti terdapat kontrak pengangkutan. Untuk itu,
digunakan sebagai kontrak experience atau evidence pengalaman dalam pengangkutan LNG harus
document dalam hal pengangkutan LNG? dibuktikan/didukung dengan kontrak pengangkutan.
1. The majority of the shareholder of the Applicant (PNI) 1. Experience and Financial rating support criteria as
is Prism Energy International Ltd (PEI) a Singapore shown in the diagram can be applied, provided that SK
Based Company and the minority shareholder of the E&S is controlling Prism Nusantara International as
Applicant is SK E&S a South Korean-based company. evidencing by certain documents showing the authority
PEI (Singapore Based Company) is also 100% owned by of SK E&S direct Prism Nusantara International and the
SK E&S (South Korean Based Company). This makes SK document showing the corporate structure
PT. PRISM E&S the ultimate controlling shareholder in the PNI.
Nusantara 4 April Will it be accepted by PLN EPI if the Applicant (PNI) uses
9 reza@sk.com
International/SK 2023 SK E&S experience and financial rating support?
E&S
No. Company Email Date Question Answer
2. If Applicant has EPC experience as a project owner for 2. Accepted as stipulated in tabel Section 9.1.a
LNG infrastructure (not EPC contractor), will it be
accepted by PLN if that experience is claimed by
Applicant?
3. Can Applicant propose LNG Hub Terminal other than 3. It is not accepted. Bidders shall follow PLN EPI
Huadi FSRU after the Applicant win the tender of the requirement based on RFP document in order to submit
cluster (assuming Applicant can provide evidence that proposal.
LNG Hub Terminal is more efficient than Huadi FSRU)?
4. If only 2 companies/consortium are qualified as 4. The minimum number of participants who pass the
Qualified Applicant, will PLN EPI re-conduct the PQ prequalification stage is 2 to enter the RFP stage.
process?
5. If other LNG demand (non-PLN demand) exists inside 5. Transactions made by SPC are only with PLN EPI and if
the cluster and there is a potential to utilize the SPC there is additional demand outside of PLN EPI, then SPC
LNG infrastructure, is it possible to adjust the LISA (LNG transactions will also remain with PLN EPI.
Infrastructure Service Agreement)? If there is additional demand that causes additional
investment and OPEX cost in SPC, then there will be an
adjustment for LISA.
6. If the shareholder of SPC has their own LNG which has 6. LNG SPA will be signed by PLN EPI with LNG Supplier.
more economic/benefit to PLN EPI, is it possible that
PLN EPI purchases that LNG?
No. Company Email Date Question Answer
1. Scope of Works apakah akan diuraikan secara BOQ 1. Idem No.1 Answer
atau hanya secara Lump Sum Works?
2. Apakah pada point 9.2a Financial Criteria (ii) dan (iii) 2. Idem No.1 Answer
menggunakan (AND atau OR pd clause Kemampuan
Financial Perusahaan yg harus memenuhi DB-Rating
5A2?
3. Proposal yang harus diserahkan pada tanggal 2 May 3. Idem No.1 Answer
2023, secara single company atau sudah dalam suatu
Consortium?
4. Pada RFP nanti, EPI apakah akan memberikan Typical 4. Idem No. 1 Answer
OPEX Cashflow daripada Manajemen Operasi nya FSRU
& ORU atau dalam Gas Consumption dari tiap-tiap
Pembangkit dlm satu Hub?
5. Apakah proyek ini termasuk proyek strategis nasional 5-6. PLN EPI sedang mengusahakan untuk mendapatkan
(PSN) atau tidak, penegasan itu penting untuk kami fasilitas master list melalui pengusulan PSN program
PT. Jaya Jumli Jayajumliperkasa 4 April
10 ketahui sejak awal dikarenakan kalau bukan tergolong gaasifikasi. Namun demikian, program gasifikasi ini
Perkasa @gmail.com 2023
proyek PSN nantinya berisiko dapat terhenti saat merupakan program strategis dan pelaksanaannya
periode awal kampanye Pilpres sampai transisi berdasarkan penugasan dari Pemerintah kepada PLN
pergantian pimpinan pemerintahan.
sebagai bagian dari penugasan penyediaan listrik.
6. Pada aanwijzing PQ yang lalu pihak Panitia hanya
menjelaskan bahwa PLN EPI serius karena telah adanya
penugasan dari pemerintah kepada PLN EPI tanpa
menyebutkan siapakah pihak yg dimaksudkan
Pemerintah tersebut? Apakah assignment Pemerintah
tersebut ditujukan ke PLN Pusat sebagai holding
company dan dikukuhkan oleh suatu PERMEN atau
KEPMEN?
7. Dalam hal terjadi sengketa dengan pihak PLN EPI di 7. Risk matrix proyek gasifikasi ini sudah disampaikan pada
kemudian hari, apakah kami/Bidder nanti dapat dokumen PQ. Penyelesaian perselisihan antara PLN EPI
meminta jaminan (sebagai Sponsor) kepada pihak PLN dengan Sponsor akan diatur pada Joint Development
EPI terhadap resiko yang akan terjadi dikemudian hari? Agreement (JDA). Performance Guarantee akan diatur
No. Company Email Date Question Answer
Disisi lain pihak Sponsor nantinya akan dibebani oleh pada LNG Infrastructure Service Agreement antara PLN
Performance Guarantee... benarkah hal itu? EPI dengan SPC (Sponsor & PLN EPI).
8. PLN EPI didalam menyusun Risk Matrix, apakah telah 8. Proses pengadaan akan mengikuti ketentuan yang
memperhitungkan pula tentang adanya Political Risk, berlaku di PLN dan hal ini tidak ada kaitannya dengan
apabila estimasi Contract signing (tahap 2) tidak bisa periode Pemilihan Presiden.
diadakan sebelum awal periode PilPres? Menurut
Panitia, kapan target date daripada Contract Signing
(tahap 2)?
1. Administration: 1. Evaluasi dokumen aplikasi kualifikasi yang disampaikan
Clause 16. Evaluation of Pre-Qualification Applications peserta merujuk pada Klausa 16 Dokumen PQ. PLN EPI
(page 28) akan menyampaikan hasil evaluasi (pass/fail) kepada
Bagaimana tata cara pelaksanaan PQ untuk setiap peserta. Dalam hal peserta gagal pada proses
menentukan Qualified Applicants, apakah dilakukan kualifikasi, PLN EPI akan menyampaikan kriteria apa
secara terbuka atau tertutup di internal PLN EPI? yang menyebabkan peserta tersebut gagal untuk masuk
dalam shortlist.
6. Financial 6. Boleh
Clause 9.2.d (page 19)
Applicant shall submit a support and reference letter
from the reputable bank.
Terkait persyaratan bank support & reference letter,
apakah diperbolehkan dari bank manapun?
1. Pada document RFP (Tahap 2) nanti, apakah akan di 1. Pemilihan shipbuilder untuk proposal penyediaan FSRU
specify adanya pembelian FSRU ataupun LNG Carrier dan LNG Carrier diserahkan ke masing-masing peserta
dimana kami akan berkontrak pula dengan pengadaan.
Shipbuilders?
PT. Jaya Jumli Jayajumliperkasa 4 April
12 2. Dalam aanwijzing, disebutkan bahwa akan ditempuh 2. Pelaksanaan proyek gasifikasi oleh PLN EPI. PT PLN
Perkasa @gmail.com 2023
skema pendanaan PROJECT FINANCING, dimana (Persero) tidak akan memberikan jaminan apapun kepada
lazimnya menuntut jaminan dari debitur, apakah di debitur proyek gasifikasi.
PLN HOLDING akan menjamin?
No. Company Email Date Question Answer
3. Kalau untuk EPC Construction di asumsikan 2 tahun, 3. Parameter finansial yang dibutuhan peserta pengadaan
lalu dilanjut dengan 20 tahun kontrak SPC dengan PLN untuk menyusun proposal akan disampaikan pada
EPI (termasuk LISA), karena membuat FSRU & Vessel tahapan RFP.
cukup lama, dalam model proforma financial analysis,
berapa IRR yang akan dijadikan dasar bagi penyiapan
BOQ pada SoW pengadaan infrastruktur nya?
1. Clause 7.2 1. PLN EPI will provide detail information about technical
….PLN EPI would have right to acquire a greater and financial at RFP stage.
share………………
If PLN EPI at the indicated time will increase it’s
shareholding in the SPC, up to what max %
shareholding? This will be important for investors.
10. Para 9.1 10. Participants can convey related experiences for the last
General Experience Criteria 10 years period (2012-2022).
Please clarify if this refers to Scheduling during
Operation:
“The procurement and delivery of and vessel
scheduling All for, ships, barges or other vessels for
marine transport of LNG within the last ten (10) years”
No. Company Email Date Question Answer
11. Chapter 6 11. We will provide this information in the RFP stage.
General description of the cluster requirements
What are the vessel requirements per cluster or is this
up to the bidder?
14. 6.5 14. Jetty facilities at each power plant location in Papua Utara
Papua Utara Cluster Cluster will be part of the SPC work. PLN EPI will have an
What is the loading facility? Is this existing or need to LNG contract supply DES with LNG supplier.
be part of the Bidder’s work and how is the LNG supply
to the loading point ensured?
15. 6.6 15. Because there is a limitation with capacity of LNG Carrier
Papua Selatan Cluster in Tangguh (LNG source) and small demand gas in Papua
Why not basing this on milk run concept with 1 LNG Selatan.
carrier delivering from Tangguh?
16. 7.5
Payment to SPC 16. We will provide this information in the RFP stage.
How will the payments be structured? Fixed monthly
fee based on OPEX/CAPEX return or…?
No. Company Email Date Question Answer
17. Para 10.2 17. Only Qualified Applicant in PQ process who can
Consortium participate in RFP stage. Sub-contractor is not required to
Understand from the prebid meeting that only register in the PQ stage.
applicants who participate in PQ are accepted as
members of the consortium during RFP stage.
18. –
18. SPC will provide tugs
General
During operation, according to Indonesia regulation, it
required to provide assist tugs for every location. Who
will responsible to provide assist tugs?
19. –
19. PLN EPI
General
According to Indonesian law, the marine LNG terminal
is regarded as special port and it required special
permits from SeaCom. To whom it permits will be
given?
20. Form E
20. According to clause 9.3 on the PQ Document
(a) ………...on any historical record pursuant to Clause
8.3 of the Pre-Qualification Document
There is no Clause 8.3 on the Pre-Qualification
Documents.
No. Company Email Date Question Answer
21. – 21. Permitted
General
Is it permitted and subject NOT disqualified if 2
companies registered on this PQ stage have the same
shareholder or partial shareholder on each company?
The intention to register 2 companies is intended to
participate in different clusters as written on the PQ
document.
22. – 22. PLN EPI will provide technical detail information at RFP
General stage
Total of floating infrastructure
24. Para 6.6/6.7 24. For Papua Utara will be provided by BUMD Papua.
Papua Utara Cluster/Papua Selatan Cluster
During the pre-PQ meeting, the PLN EPI informed that
LNG transportation from BP Tangguh to the Power
Plant location will be provided by BUMD Papua. Please
confirm.
As background, our company group’s structure and role Financial and historical criteria as shown in the diagram can
are as below. be applied, provided that Tokyo Gas Co, Ltd is controlling PT
Tokyo Gas Indonesia as evidencing by certain documents
showing the authority of Tokyo Gas Co, Ltd to direct PT Tokyo
Gas Indonesia and the document showing the corporate
structure
a.fukushima 4 April
14 Tokyo Gas
@tokyogas-asia.com 2023
1. Apakah persyaratan QHSE diwajibkan untuk dimiliki 1. Pada tahap PQ bisa salah satu anggota konsorsium.
setiap anggota konsorsium? Atau boleh min. 1 anggota
memiliki QHSE?
2. Pada ketetuan financial criteria, diatur bahwa Laporan 2. Bagi perusahaan lokal bisa tetap dalam bentuk IDR.
Keuangan Audited harus :
a. Certified by notary public
b. Ekuivalen dalam USD
Apakah dua ketentuan tersebut wajib bagi perusahaan
ratna.tisnasari 4 April local dan foreign?
15 Temas Line
@temasline.com 2023 Dikarenakan laporan audited kami dalam bentuk IDR,
Apakah kami perlu mengubah menjadi USD? Apabila
perlu, apakah ada kriteria untuk dokumen yang
menunjukkan konversi IDR ke USD tersebut?
3. Apakah yang dimaksud dengan notarized copies of 3. Sama. Keterangan notaris yang menyatakan bahwa
original dengan certified by notary public sama? dokumen copy sesuai dengan aslinya.
apabila berbeda, mohon bantuan penjelasannya.
No. Company Email Date Question Answer
4. Apakah dokumen-dokumen dibawah ini perlu di 4. Sepanjang tidak disyaratkan secara tegas dalam PQ
certified copy/notarized copies of original/certified by Documents dan formulir lampirannya, maka dokumen
notary public: tersebut tidak diperlu di certified copy/notarized copies
a. Qualified rating agencies report (D&B, S&P, of original/certified by notary public.
Moody's, Fitch or Hasil Penilaian Tingkat
Kesehatan BUMN)
b. CV of management key and CV of competent key
personnel
c. evidence of tax payment
d. OHSAS
e. organization structure
1. Clause 2.3 1. The context that was conveyed during the explanation
There is statement in clause 2.3 that "PLN EPI is seeking meeting was that for the RFP process all participants were
an optimized design solution for the LNG distribution asked to submit offers based on references to the RFP
infrastructure services within a Cluster and (subject to document. This aims to provide equal treatment in the
the terms of any RFP or RFPs) may consider solutions evaluation of bid proposals to all participants.
across more than one Cluster.
2. Clause 2.4 2. LISA will be signed between PLN EPI and SPC.
Will be there any clause in the Contract/agreement
later that PLN will not do any new bidding/tender if
there is any future development in the cluster area?
No. Company Email Date Question Answer
3. Clause 9.1 3. Yes it is.
Can we as PQ registered company become a member
of the consortium and appoint another company (who
is not registered in this PQ) becomes a leader?
4. Clause 6.5 4. PLN EPI will become a shareholder in each SPC so that PLN
The integration of Nusa Tenggara Cluster is on HUB EPI will make sure design HUB Huadi and Nusa Tenggara
Huadi, while the scope of HUB Huadi is under Sulawesi cluster connected.
and Nusa Tenggara Cluster.
Question : How you make all of them interconnected?
6. It is said that the service rate from PLN EPI will be a fix 6. We will provide any information related at RFP stage.
rate with no adjustment for 20 years. How PLN EPI will
calculate the fix rate for SPC? Or whether the SPC can
negotiate the rate?
1. Subclause 9.2 Financial Criteria AND Table 16.1 – 1. For listed companies may not be notarized since their
Checklist of PQ Evaluation financial statement can be accessed by the public, so can
Content: be known it source.
Kawasaki Kisen Wijaya.Wira 4 April
17 Page 18, point b
Kaisha (K LINE) @id.kline.com 2023
The submitted audited financial statements shall be
certified by a notary public and ….
No. Company Email Date Question Answer
No 19. LATEST THREE (3) YEARS AUDITED FINANCIAL
REPORTS
Question:
Should the AFR notarize/be certified by a public notary
even though it is a listed company whose financial
statements are audited and appropriately disclosed
per the stock exchange rules?
2. Form B.1.1 2. Yes, it is applicable if Applicant is consortium.
Content:
(Applicant who are not applying as a consortium for the
execution and completion of the Projects, should mark
the following items 6, 7, 8 and 9 as “not applicable”,
delete the items and initial the deletions)
Question:
Items 5,6,7 and 8 instead?
Question:
Should these be Clause 9.1 instead?
Question:
Should this be Clause 9.3 instead?
Question:
On what ground is stamp duty requested? Does stamp
duty apply to any other form for this PQ? Does this
apply to Foreign Company Applicants too?
10.Clause 12
Content: 10. After the submission of the qualification application
Pre-qualification Schedule documents, PLN EPI will inform the announcement
schedule for further activities/events.
Question:
Noted the submission time limit is now 2 May 2023.
What is the timing of events going forward?
PT. PRISM 1. The majority of the shareholder of the Applicant (PNI) 1-2. Idem no.9
Nusantara 4 April is Prism Energy International Ltd (PEI) a Singapore
18 reza@sk.com
International/SK 2023 Based Company and the minority shareholder of the
E&S Applicant is SK E&S a South Korean-based company.
No. Company Email Date Question Answer
PEI (Singapore Based Company) is also 100% owned by
SK E&S (South Korean Based Company). This makes SK
E&S the ultimate controlling shareholder in the PNI.
Will it be accepted by PLN EPI if the Applicant (PNI) uses
SK E&S experience and financial rating support?
3. Clause 9.2, a, (i)~(iii) : What is the exact meaning of 3. PLN EPI has its own considerations in submitting
"based on its audited financial statement fiscal year financial criteria at the PQ stage.
minimum 2021" while it is required to demonstrate
the current credit rating?
4. Clause 9.2, b : In case the applicant fails to meet the 4. Credit support can be in the form of a letter from a
financial criteria, they may utilize the guarantee from reputable bank stating that the bank will support and
the parent company or credit support from a reputable provide a credit line with a certain value based on the
bank. In this regard, we would like to inquire about the bank's appetite and reference in providing support to
details of the “reputable bank's credit line support” the participant.
such as the type/contents of guarantee required and
the definition of the reputable bank
No. Company Email Date Question Answer
5. If Applicant has EPC experience as a project owner for 5. Yes
LNG infrastructure (not EPC contractor), will it be
accepted by PLN if that experience is claimed by
Applicant?
6. Can Applicant propose LNG Hub Terminal other than 6. Idem answer number 9.3
Huadi FSRU after the Applicant win the tender of the
cluster (assuming Applicant can provide evidence that
LNG Hub Terminal is more efficient than Huadi FSRU?
8. If other LNG demand (non-PLN demand) exists inside 8. Idem answer number 9.5
the cluster and there is a potential to utilize the SPC
LNG infrastructure, is it possible to adjust the LISA (LNG
Infrastructure Service Agreement)?
9. If the shareholder of SPC has their own LNG which has 9. Idem answer number 9.6
more economic/benefit to PLN EPI, is it possible that
PLN EPI purchases that LNG?
Reference to PLN EPI Pre-Qualification, appreciate Single Applicant may form the consortium at later stage (RFP
clarification regarding Form B.1.1. point 4. Paragraph stage) provided that the single Applicant shall form the
in the box quoted below consortium with another Qualified Applicant.
5. Administration 5. Applicant can submit the latest tax report in the form of:
Can PLN EPI specify which tax report should be Annual Tax Return or Corporate Income Tax or others
submitted by Applicant for the pre-qualification report tax related that participants comply with tax
process? provisions.
No. Company Email Date Question Answer
6. Administration 6. QHSE regulations and standards that apply to the
Can PLN EPI specify/breakdown QHSE Standard management of participating companies.
documents that Applicant shall submit for pre-
qualification process?
14.Technical
Is PLN EPI responsible to provide the Tangguh and Java 14. Yes, we will provide this information in RFP stage.
1 terminal data required for ship to shore / ship to ship
compatibility analysis in later stage?
17.Technical 17. No
Can applicant propose Floating Storage & Regasification
Barge for the offshore solution?
1. Reference: Prequalify Documents, Section 1.3 and 1. We will provide any related question about technical at
Section 1.5 RFP stage.
PT Prima Osean Septiani 6 April
21 Question:
Nusantara @soechi.id 2023
As mentioned in section 1.3 that the prequalify is for
giving CONTRACTOR have the opportunity to work
No. Company Email Date Question Answer
with PLN EPI in design, develop and operate LNG
Infrastructure within a Cluster or Clusters
2. Reference: Prequalify Documents, Section 6.2 2. We will provide any related question about technical at
Question: RFP stage.
CONTRACTOR’s scope under this CONTRACT is limited
to build LNG Receiving Terminal only and any cross
country pipeline will be out of CONTRACTOR’s scope.
For Example pipeline from LNG Receiving Terminal
Jungkat to MPP Siantan at Kalimantan cluster.
Please confirm that the selection of subcontractor (s) of Yes, it will follow SPC management. However, the responsible
PT Golar Jamsir 6 April EPCI, Shipyard, Vendors, Ship Management, and others to perform the obligation under LISA shall be hold by SPC.
22
Indonesia @psu.co.id 2023 follows the SPC’s management system or Winners'
management system whichever is suitable/available.
Eligibility of Applicants (Point 3.2)
PT BSGL 1. During the RFP stage, will it be possible to merge two 1. Not possible since according to Section 3.3 PQ
Glayn 6 April
23 (Consortiom Qualified Applicant consortiums? Meaning that there Documents: the maximum number of members of the
@jsk.co.id 2023
BSGL) will be more than 5 companies in a consortium consortium is five (5) companies.
No. Company Email Date Question Answer
General Experience Criteria (Point 9.1)
2. Will the Recommended Vendor List be introduced in 2. No
the PLN EPI RFP?
3. Will PLN EPI introduce any Tax Exemption Policy for 3. No
this project?
4. What is the NG Supply method in the Lombok Area? 4. We will provide any related question about technical at
1) There are two power plants in Kalimantan Cluster, RFP stage.
and PLN EPI guides in ITP clause 6.4 that “Gas fuel
for GFPP in Siantan will be supplied through gas
pipeline from Jungkat.”
2) Although there are two Power Plants in the
Lombok Cluster, there is only one LNG Receiving
Terminal. However, in ITP clause 6.5, there is no
guide to supply NG from PLTMGU Lombok Peaker
to MPP Lombok in any way. The distance between
the two power plants on Google Map is about 7.4
km in a straight line.
5. Regarding General Experience Criteria, It is stated that 5. No. Only related with LNG.
one of the reference requirements is "EPC Contractor
of LNG Regasification Facility (Land-based or floating
terminal) or LNG Plant", but we'd like to know
whether NG Plant Reference can be also acceptable?
6. Is there any general restriction on investment 6. There is no restrictions for investment companies.
companies like bank participating in consortiums? However, based on the banking law, banks are prohibited
Other than the audit financial statements and to conduct business activities other than financial
financial criteria. services.
11.Is it acceptable if only one member of consortium 11. Not accepted. Bank Reference letter & Bank Support
(include leader) submit Bank Reference letter & Bank Letter shall submit by each member.
Support Letter for concortium?
12.Is it acceptable if submit only Bank Reference Letter 12. Yes. In case the applicant fails to meet the financial
without Bank Support Letter? criteria, they may utilize credit support from a reputable
bank.
13.Is it acceptable if applicant submit Reference letter & 13. We recommend you to use reputable bank in Indonesia
Support Letter that issued by reputable Financial (Banks that have been registered and recognized by OJK).
Institute as well as Bank such as Macquarie, KIND
“Korea Overseas INfrastructure & Urban 14. Amount of the value in support letter based on the bank’s
Development Corporation”(under Korean ministry of appetite and reference in providing to support applicant.
No. Company Email Date Question Answer
commerce industry and energy) or JCM “Japan joint
Credit Mechanism”, etc?
14.How much the amount of the value supposed to be
capped in support letter by bank? If there is required
certain amount of value from PLN EPI then, is it
acceptable to combine bank’s supporting letter for
each consortium members to reach a certain amount
of value that PLN EPI requires.
1. Tanggal penyampaian dokumen aplikasi tanggal 2 Mei
1. Other: 2023.
Tanggal pemasukan dokumen adalah tanggal 02 Mei
2023. Kami mengajukan agar pemasukan dokumen
diundur ke tanggal 10 Mei 2023.
2. Klausa 9.1.a: 2. Boleh
"The Applicant or in the case of consortium - at least
one (1) member of the consortium of the Applicant
shall have any one or more of the following
experiences". Is it allowed if the consortium had only
one or two criteria?
PT Padma (Apakah diperbolehkan apabila konsorsium hanya
rachmat.rajiv 6 April
24 Energi dapat memenuhi salah satu atau dua kriteria saja?)
@titissampurna.com 2023
Indonesia 3. Klausa 9.1.a: 3. Tidak bisa. Harus menggunakan pengalaman dengan
Is it allowed if the consortium experience is only in proyek sejenis yaitu LNG.
CNG, LPG, or Natural Gas facility or transportation?
(Apakah diperbolehkan apabila konsorsium hanya
memiliki pengalaman pada fasilitas atau transportasi
CNG, LPG, atau natural Gas saja? Dan bukan
pengalaman pada LNG)
4. Table 6.8 - Capacity of LNG Infrastructures in 4. Informasi terkait teknis akan disampaikan pada saat RFP.
Sulawesi - Maluku
Please advice based on Table 6.8 - Due to potential
ORU scope in LNG Receiving Terminal at Kolaka, who
No. Company Email Date Question Answer
will accommodate the ORU Scope? It will be build by
others company or exactly will be build by SPC?
(Berdasarkan Tabel 6.8 terdapat keterangan
Potential ORU Scope in LNG Receiving Terminal at
Kolaka, siapa yang nantinya akan menyiapkan Scope
ORU tersebut? Apakah ORU akan dibangun oleh
pihak lain atau pasti akan dibangun oleh SPC?)
5. Table 16.1 - Checklist of Pre-Qualification 5. Ya bisa.
Evaluation
On Point 12 - Summary sheet list of Applicant
Facilities, can bidder submit an active facility that
operated by bidder it self?
(Apakah bidder dapat mensubmit fasilitas yang
masih aktif dioperasikan oleh bidder sendiri?)
6. Table 16.1 - Checklist of Pre-Qualification 6. Dapat salah satu. Pada tahap PQ dapat hanya
Evaluation melampirkan Letter of Intent.
On Point 14 - Consortium Agreement, Certified by
public notary or letter of intent to form a consortium.
To form a consortium, is it must be a consortium
agreement or it can be a letter of intent only?
(Untuk membuat konsorsium, apakah harus berupa
consortium agreement atau dapat berupa letter of
intent saja?)
7. Special Purpose Company (SPC) 7. PLN EPI akan menyediakan ekuitas sesuai dengan proporsi
PLN EPI will hold 30% (thirty percent) shares in the nilai saham yang dimilikinya pada SPC.
SPC. Is the equity portion required for the project
financing will also be provided by PLN EPI?
8. Other
Who is responsible for the land acquisition and legal 8. PLN EPI.
permit? (Siapakah yang bertanggung jawab untuk
penyediaan lahan dan pengurusan legalitas serta
perizinan?)
No. Company Email Date Question Answer
9. Other
Terkait medis di site, apakah client (PLN EPI) memiliki 9. Tidak. Kesehatan dan Keselamatan Kerja Sub-Kontraktor
klinik yang dapat dipakai oleh Kontraktor? Dan proyek menjadi tanggung jawab SPC.
adakah Rumah sakit atau Klinik terdekat yang
menjadi rujukan?
10.Other 10. Limbah yang dihasilkan dari fasilitas SPC, akan menjadi
Siapakah yang bertanggung jawab terhadap limbah tanggung jawab SPC.
Domestik & B3?
11.MOM Aanwijzing No. 11. Ya. Jika salah satu member dalam suatu konsorsium tidak
002.MOM/EPI.01.02/PLNEPI/2023 (Halaman 5/14, dapat memenuhi kriteria, maka konsorsium dimaksud
Pertanyaan No. 29) akan gugur.
Merujuk ke MOM No.
002.MOM/EPI.01.02/PLNEPI/2023, Bersama ini kami
mohon konfirmasinya apabila dalam konsorsium
salah satu membernya tidak dapat memenuhi
kriteria teknis namun member lainnya memenuhi
seluruh persyaratan prakualifikasi, apakah
konsorsium tersebut gugur?
12.FORM B.1.1 Halaman 2 12. Notarized copies of original
Merujuk kepada FORM PQ B.1.1 halaman 2, point 5.
Apakah dokumen yang ada pada point 5 tersebut
diharuskan noterized copies (legalisir notaris)? Atau
diperbolehkan hanya copy dokumen tanpa legalisir
notaris?
1. On the Form B.1.4.d, The meaning of COMPETENT 1. Any structural and/or functional employees who have
KEY PERSONNEL is ambiguous. Could you kindly expertise related to the project, as evidenced by the CV
specify exactly which person this means? or certicate of competency.
HYUNDAI LNG
6 April
25 SHIPPING CO., jylee@hls.co.kr
2023 2. We are going to put our 135K CBM Sized LNG carrier 2. Detail information about capacity FSRU will provide at
LTD.
into the project as a Hub FSRU. Hence, we believe RFP stage.
that only Sulawesi-Maluku Cluster could capable the
size of 135K vessel according to your PQ documents.
No. Company Email Date Question Answer
Is this correct? Or please let us know if there are
other clusters where 135K FSRU can be deployed.
1. With regard to the LNG Receiving Terminal at Huadi, it 1. See the explanation of the answer to question number
has been ascertained that a Floating Storage and 13.23 above. Any detail technical information will be
Regasification Unit (FSRU) will be utilized to provide provided at RFP stage.
liquefied natural gas (LNG) to a power plant with a
capacity of 1150 MW. However, it has come to our
attention that the indicative average gas demand is
provided as only 18.30 BBTUD which might be
sufficient to produce only 120 – 140 MW of power. We
request you to clarify whether our understanding of
indicative average gas demand is correct. If our
understanding is correct, we request you to clarify how
the powerplant is intended to receive the ~90%
shortfall of natural gas.
2. The average gas demand for the cluster over a 20-year 2. Correct
PT Armada 10
agung.sembodo@ar period has been indicated in BBTUD units. Bidder
26 Gema April
madagema.co.id wishes to understand if BBTUD is “Billion British
Nusantara 2023
Thermal Units per Day”.
3. The bidder is aware that PLN EPI mandates an initial 3. PLN EPI would be contributing the capital in proportion to
share of 30% in the Special Purpose Company (SPC). its shareholding. Assumption related minimum debt to
Therefore, the bidder would like to ascertain the PLN equity ratio will be provided at RFP stage.
would be contributing the capital in proportion to its
shareholding. If yes, given that the project will be
financed through a combination of debt and equity,
Bidder would like to understand the required
minimum debt to equity ratio.
4. Bidder wishes to understand the future expansion 4. See the explanation of the answer to question number
plans for each cluster. 2.17-23 above. Any detail technical information will be
provided at RFP stage.
No. Company Email Date Question Answer
Section 8 5-6. Any detail technical information will be provided at RFP
5. PLN EPI is kindly requested to provide high level project stage.
schedule (key milestones such as target contract
award, first gas, etc)
Table 6.8:
SCHEDULE 1:
7. PLN EPI to advise whether it is allowed to occupy 7.Provision of engineering, PMT resources for the FEED
overseas engineering and PMT resources (under preparation process will be carried out on the JDA
Parent Company of Applicant) for FEED, detailed between the Sponsor and PLN EPI
engineering, and project execution.
No. Company Email Date Question Answer
Klausa 3 1. PLN EPI memiliki pertimbangan dalam menentukan
1. Mengapa jumlah anggota konsorsium maksimum maksimal jumlah anggota konsorsium. Perlu dipahami
hanya 5 perusahaan? bahwa PLN EPI akan masuk ke dalam bagian SPC yang
dibentuk dengan perusahaan sponsor.
2. Apakah pada tahap RFP untuk Cluster Nusa tenggara 2. Tidak
yang memiliki 6 lokasi LNG Infrastructure dan Cluster
Sulawesi-Maluku yang memiliki 7 lokasi LNG Infra
Structure diperbolehkan membentuk konsorsium
dengan anggota maksimum 7 perusahaan ?
3. Apakah perusahaan yang tidak memiliki experience 3. Bisa. Sepanjang disepakati Bersama dengan anggota
yang relevan dengan project dapat menjadi konsorsium yang lain. Selain itu leader consortium juga
10 Consortium Leader ? harus memenuhi financial criteria yang dipersyaratkan.
PT Hanochem suwarto@hanochem.
27 April
Tiaka Samudera com
2023 Klausa 6
4. Pihak manakah yang menyediakan “Right of Way” 4-6. Detail teknis akan disampaikan pada saat RFP.
untuk pipa gas yang diminta dibangun dari MPP
Jungkat ke PLTG Santan di Pontianak?