DRILLING PROCEDURE

KLD-1

Name Position Date Signature

Prepared by: Taufan Arhammar Drilling Engineer

Completion
Prepared by: Janico Zaverson M
Engineer
Bertha Sondang/ BERTHA
Prepared by: Geologist SONDANG
Digitally signed by BERTHA SONDANG M
DN: cn=BERTHA SONDANG M, o, ou,
email=bertha.martinauly@pertamina.com, c=US

Bangsawan Arief
Date: 2020.08.23 09:46:24 +07'00'

Digitally signed by Atmaji

Linda Atmaji
Nugroho

Prepared by: Linda F/ Atmaji N Geophysicist


Digitally signed by Linda
Fransiska I D DN: cn=Atmaji Nugroho,
DN: cn=Linda Fransiska I D, o=Subsurface, ou=West

Fransiska o=PHE ONWJ, ou, Asset,


email=linda.fransiska1@pertam
ina.com, c=ID Nugroho email=atmaji.nugroho@pert
amina.com, c=ID

ID
Date: 2020.08.23 11:02:49
Date: 2020.08.23 11:07:45
+07'00'
+07'00'

Digitally signed by debby

debby
irawan
DN: cn=debby irawan,

Prepared by: Debby Irawan Petrophysicist o=Subsurface, ou=PHE


ONWJ,

irawan
email=mk.debby.irawan@p
ertamina.com, c=ID
Date: 2020.08.23 10:44:31
+07'00'

Adrianus
Reservoir /
Prepared by: Pradipta/Jemi
Production Eng.
Jaenudin
Digitally signed by Eko Prasetyo
DN: cn=Eko Prasetyo, o=PHE ONWJ,

Reviewed by: Eko Prasetyo Operation Geologist ou=Subsurface,


email=eko.prasetyo.s@pertamina.co
m, c=ID
Date: 2020.08.23 09:55:32 +07'00'

Gas Asset Asst.


Reviewed by: Icuk Wibowo
Manager
Mochamad Fajar Drilling Engineering
Reviewed by:
Sany Asst. Manager
Drilling Operation
Reviewed by: Aris Kurniawan
Asst. Manager

Reviewed by: M. Iqbal West RM Manager

Reviewed by: Achmad Dicky Y Drilling Manager

Sr. Manager
Approved by: David Tobing
Sub-Surface
Sr. Manager Drilling
Approved by: Widoyo Krisnanto
and Well Services
Distribution:
Benny Nuryadi Sr. Manager Production
David Tobing Sr. Manager Sub-Surface
Roylan S/Leksmono PHE ONWJ Wellsite Leaders
Geoffrey D’sa Cardoso Rig Manager (ENSCO 67)
Hendra Siswanto DD Coordinator (Uzma)
Hulyadi MWD/LWD Coordinator (Schlumberger)
Agung Heru Wijanarko Drilling Fluid Coordinator (MI Indonesia)
Warti Nur Raisyah Cementing Services Coordinator (Halliburton)
Benny Nuryadi Sr. Manager Production

Drilling Engineering Team Drilling Engineers

KLD-1 Operations File


Table of Contents

LIST OF ATTACHMENTS ......................................................................................... 3

1. GENERAL WELL INFORMATION ............................................................... 4


1.1. OBJECTIVES .................................................................................................. 4
1.2. KEY PERFORMANCE INDICATORS ............................................................. 4
1.3. WELL INFORMATION ..................................................................................... 4
1.4. FORMATION TOPS AND TARGETS (RKB-MSL =112’) ................................. 5
1.5. RESERVOIR DATA ......................................................................................... 5
1.6. OPERATION SUMMARY ................................................................................ 6

2. DRILLING ASSURANCES ......................................................................... 14


2.1. SIMOPS ........................................................................................................ 14
2.2. PLATFORM HANDOVER .............................................................................. 14
2.3. WATER DEPTH AND SEABED CONDITION ............................................... 14
2.4. SHALLOW HAZARD ASSESSMENT ............................................................ 14
2.5. MOVE-IN AND RIG-UP ................................................................................. 14
2.6. PRE-SPUD AND RIG ACCEPTANCE ........................................................... 14

3. TECHNICAL PROGRAMS .......................................................................... 16


3.1. CASING PROGRAM (RKB-MSL =112’) ........................................................ 16
3.2. BOP/CASING PRESSURE TEST ................................................................. 16
3.3. WELLHEAD AND TREE PROGRAM ............................................................ 16
3.4. BIT PROGRAM ............................................................................................. 16
3.5. DRILLING FLUID PROGRAM ....................................................................... 17
3.12. WELL DIAGRAM ........................................................................................... 18
3.13. TRAJECTORY (EXISTING)........................................................................... 20

KLD-1 Drilling Procedure Page 2 of 22 Revision Aug, 2020


List of Attachments
1. Well Initiation Document
2. MOM of Engineering Screening
3. Drill Well on Paper Slides
4. MOM of Peer Review 1 & Peer Review 2
5. Offset Wells
6. SIMOPS
7. Drilling Fluids Program
8. Wellhead and X-Tree

KLD-1 Drilling Procedure Page 3 of 22 Revision Aug, 2020


1. GENERAL WELL INFORMATION
1.1. OBJECTIVES

1.1.1. Re-entry well in full compliance with HSE and operation procedures.
1.1.2. Drill out cement and cement retainer in 9-5/8” and 7” casing.
1.1.3. Re-perforate KL-34A and KL-47A, new perforation KL-34B.
1.1.4. Complete the well with 2-7/8” x 3-1/2” Dual Completion

1.2. KEY PERFORMANCE INDICATORS


Days per 10K -
Reserve Access 10.8 BSCF and 0.2 MMBC
Estimate Initial Production 10 MMSCF and 200 BCPD

1.3. WELL INFORMATION

AFE Time and Costs Time Cost


Move In & Out 6.8 days
Dry Hole 0 days
Completion 11.3 days
Total 18.1 Days US$ 4,761,076 (incl. 10% tax)

Well Depth 7,910 ft MD / 6174 ft TVDRT / 6062 TVDSS


Reference Elevations Water depth: 64’, RKB-MSL = 112 (Original RKB)
Profile 2D - J-Type
KOP 1467’ MD / TVD
Inclination Max. 52º
Azimuth 232º at TD well
Departure 4149.8 feet to the South West
Completion Type 2-7/8” x 3-1/2” Dual Completion

KLD-1 Drilling Procedure Page 4 of 22 Revision Aug, 2020


1.4. FORMATION TOPS and TARGETS (RKB-MSL =112’)
TVD UTM
TVD RT
Target Name Subsea MD (ft) Remark
(ft) Easting (m) Northing (m)
(ft)
Surface Location 339,209.25 9,332,524.13
KL-30A (future target) -2950 3062 3246 339,003.69 9,332,457.00
KL-31A (future target) -3101 3213 3435 338,954.03 9,332,448.00
KL-31B (future target) -3133 3245 3476 338,944,56 9,332,448.00
KL-34A -3432 3544 3886 338,866.53 9,332,436.00
KL-34B -3485 3597 3964 338,840.53 9,332,422.00
KL-47 -4698 4810 5840 338,464.53 9,332,244.00

1.5. RESERVOIR DATA

Reservoir
Interval Fluid Top MD EMW Temp
Formation Pressure
[ft MD] Type [ft] [ppg] [degF]
[psig]
Gas,
KL-34A 3,886-3,940 3,886 1,567 8.53 176
Condensate
Gas,
KL-34B 3,964-3,983 3,964 1,567 8.41 176
Condensate
Gas,
KL-47 5,840-5,860 5,840 2,093 8.39 207
Condensate

KLD-1 Drilling Procedure Page 5 of 22 Revision Aug, 2020


1.6. OPERATION SUMMARY
This drilling procedure is a guideline for the operations. Personnel are expected to
make adjustments as required by the situation, to maintain safety and performance
standards. Significant changes to the procedure however must be justified in a
management of change (MOC) document.
Step DIMS Coding Description
1 Phase: PRE Preliminary Operation
Task: MOB KLD-1 Well Preparation
KLU-1 Mapping Pressure (25 July 2020 and 12 August 2020)

Summary:
25 July 2020
 Annulus A: 0 psi
 Annulus B: 300 psi. Bleed off until zero and observe for a while – No
build up pressure.

12 August 2020:
 Annulus A: 0 psi
 Annulus B: 20 psi after two weeks left after first observation. Monitor for
12 hours and no build up pressure

2 Phase: PRE MIRU


Task : MOB Under tow to KLD location. Soft pin, run anchors, approach the rig to KLD
platform. Preload & Jack-up the rig. Skid & transverse rig over the KLD-1 slot.
Note: Test BOP on stump while moving (test all size of string 2-7/8”, 3-1/2”,
5.5” and 4”).
Estimate water depth: 64ft, RKB-MSL: 112ft (Original KLU-1)

Slot Coordinates:

KLD-1
Latitude: 06°02'14.339"S Easting: 339207.174mE
Longitude: 107°32'49.109"E Northing: 9332519.960mE

Proposed Rig Heading 045 deg.


KLD-1 (KLU-1 exploration) existing status
 KLU-1 is currently temporarily abandoned since Oct 2012

KLD-1 Drilling Procedure Page 6 of 22 Revision Aug, 2020


Step DIMS Coding Description
 9-5/8” bridge plug set at 3704’ MD. Tested with 9.0 ppg MW to 1000
psi/10 min
 7” bridge plug (K-1 Drillable) set at 4700’ MD. Tested with 9.0 ppg MW
to 4000 psi/10 min
 7” bridge plug set at 6170’ MD. Tested with 9.0 ppg MW to 4000 psi/10
min
 7” bridge plug set at 6598’ MD. Tested with 9.0 ppg MW to 4000 psi/10
min
 DST KL-34 at 3906’ – 3940’
 DST KL-47 at 5840' - 5860'
RIG TBD
NAVIGATION LIGHT FIELD KL
PLATFORM -
MINI PLATFORM SLOT -
RT ELEVATION 112 ft
WELLHEAD
WATER DEPTH 64 ft
DEPTH NOT TO SCALE
MDRT TVDRT
[ft] [ft]

112 112 Sea Level


176 176 Sea Bed LEAD SLURRY

296 296 30" Cond. TAIL SLURRY

CEMENT PLUG
Balanced Cement plug
(300'-600'MD) 22 bbls Slurry
1,577 1,575 Shallow Gas

1,792 1,785 Minor Fault

1,800 1,793 9-5/8' x 13-3/8" ECP

2,046 2,032 13-3/8" Csg, 61.0 ppf, K-55, BTC


\

8 bbls cement on top (TOC at 3594'MD)


9-5/8" Cement Retainer (WL) 3704'MD
8 bbls cmt (squeeze) predicted cmt 3704-3814'MD

3,906 KL-34 A (Gas) (3906'MD-3940'MD) DST#4

4,497 7" x 9-5/8" TOL 16 bbls cement on top (TOC At 4390'MD)


7" BP (wireline) 4700'MD
4,711 4,088 9-5/8" Csg, 47.0 ppf, L-80, Geoconn

5,840 4,811 KL-47 (Gas) (5840'MD-5860'MD) DST#3

7" BP (wireline) 6170'MD

6,370 5,164 KL-50 (Oil) (6370'MD-6400'MD) DST#2

7" BP (wireline ) 6,598'MD

6,696 5,382 KL-52 (Water) (6696'MD-6724'MD) DST#1

6,875 PBTD
7,002 5,584 7" Csg, 26.0 ppf, L-80, Mod BTC

KLU-1
Final

7,910 6,312 TD
EXPLORATION WELL

 FMC UNIHEAD ASSY, UH-CM1, TYPE II, 13 3/8 SLIP-LOCK BTM


PREP X 13 5/8-5K (BX-160) FLAMP TOP,

KLD-1 Drilling Procedure Page 7 of 22 Revision Aug, 2020


Step DIMS Coding Description

 FMC solid block X-Tree installed for Temporary Abandonment

4 Phase: ABAN N/U BOP


Task : BOPSUR Hold PJSM. N/D TA cap. N/U tubing head attachment. N/U 13-5/8" 10K BOP
stack and pressure test connection to 250 psi/1500 psi. N/U bell nipple and
flow line. Install wear bushing.
5 Phase: CLEAN Drill Out Cement and Cement Retainer in 9-5/8” Casing.
Task : CLEAN
M/U 8-1/2” Rock Bit IADC 217/227/237. RIH and Tag TOC at 300’ MD.
Displace hole with 9.7 ppg 5-7% KCL Polymer. Drill out cement plug #1 to
600’ MD.

RIH and tag TOC estimation at 3594’ MD. Circulate and condition mud to 9.7
ppg. Pressure Test casing to 500 psi for 5 minutes and 1500 psi for 10
minutes. Drill out cement plug #2 and 9-5/8” cement retainer to 3814’ MD
(estimation end of cement below CR).

Continue and RIH until tag TOC at 4390’ MD. Circulate hole clean. Increase
MW to 9.9 ppg. POOH and L/D BHA.

BHA: 8-1/2” Rock Bit 217/227/237 – Bit Sub – 7” junk basket – 3 x 6-1/2” Drill
Collar – X/O – 9 X 5-1/2” HWDP – X/O – 6-1/2” Drilling Jar – X/O – 20 X5-
1/2” HWDP – 5-1/2” DP.
Note :
 Available 2 ea Bit IADC 217/227/237 and Junk Mill.
 Drill Out cement plug #1 (300-600’ MD)
 Drilling out cement plug #2 and 1 ea Cement Retainer K-1 Type.
(cement above CR 110 ft, K-1 CR 3-4 ft, cement below CR 106 ft)

KLD-1 Drilling Procedure Page 8 of 22 Revision Aug, 2020


Step DIMS Coding Description

 If CR rotate and unable to make progress, contingency to spot


cement then continue drill out cement plug.
 Pump Hi-Vis Sweep every stands drilled or as per dictated.
 Test casing to 1500 psi with 9.7 ppg MW. Hydrostatic pressure at top
of cement plug #2 (3494’ TVD) is 3262 psi which has accommodated
the worst case scenario of full evacuation gas/oil. The formation
pressure can be seen at table below.

Hydrostatic Surface Pressure


Pressure Depth EMW Grad Oil/Gas at Full evacuation
Formation HC
(Psi) (TVD, ft) (ppg) (psi/ft) Column Scenario
(psi) (Psi)
KL-34 1567 3544 8.50 Gas 0.15 531.6 1035.4
KL-47 2100 4812 8.39 Gas 0.15 721.8 1378.2
KL-50 2200 5164 8.19 Oil 0.37 1910.7 289.32
Table of Full Evacuation Gas/Oil Pressure

 MW calculated based on the probability of oil and gas column below


each plug. Above cement plug #2 will be 9.7 ppg and above cement
plug #3 will be 9.9 ppg to accommodate trapped pressure.

top Bottom Length Pressure each


MW
Casing Zone column column column Column
(ppg)
(TVD, ft) (TVD, ft) (TVD, ft) (psi)
9-5/8" KL-34 3494 3877 383 1,522.96 9.7

7" KL-47 4081 5032 951 1,990.64 9.9

7" KL-50 5032 5317 285 2,094.55 9.9

 KL-34 length of column:


From top of cement at 7” bridge plug above KL-47 to bottom of
cement 9-5/8” bridge plug above KL-34.
 KL-47 length of column:
From top of 7” bridge plug above KL-50 to bottom of 7” bridge plug
above KL-47.
 KL-50 Length of column:
From top of 7” bridge plug above KL-52 to bottom of 7” bridge plug
above KL-50.

KLD-1 Drilling Procedure Page 9 of 22 Revision Aug, 2020


Step DIMS Coding Description

column of mud
top Bottom Length Pressure each
Hydrostatic Pressure Overbalance MW Overbalance
Casing above plug
Zone column column column Column
(psi) (psi) (ppg) (ppg)
(TVD)(TVD, ft) (TVD, ft) (TVD, ft) (psi)
9-5/8" KL-34 3494
3494 3877 1,762.4
383 1,522.96 9.7
239.42 1.32

7" KL-47 4081


4081 5032 2,100.9
951 1,990.64 9.9
110.26 0.52

7" KL-50 5032


5032 5317 2,590.5
285 2,094.55 9.9
495.92 1.90

The MW calculation already comply with PDW Rev.03 with minimal


overbalance of 0.3 ppg for gas and 0.2 ppg for oil. (Section 3.6, Page 33)
6 Phase: CLEAN Drill Out Cement and Cement Retainer in 7” Liner
Task : CLEAN
M/U 6-1/8” Rock Bit IADC 217/227/237. RIH and Tag TOC at 4039’ MD. Drill
out cement plug #3 and 7” K-1 Bridge Plug. Push bridge plug down until top
of 7” bridge plug at 6170’ MD. Circulate Hole Clean. POOH. L/D BHA.

BHA: 6-1/8” Rock Bit – Bit Sub – X/O – 5-3/8” junk basket – X/O – 4-3/4” Drill
Collar – X/O – 9x3-1/2” DP – 4-3/4” Jar – 90x 3-1/2” DP – X/O – 5-1/2” DP

Note:
 After lower slip is drilled out, push BP to top of next 7” bridge plug at
6170’ MD.

 Pump Hi-Vis Sweep every stands drilled or as per dictated

7 Phase: CLEAN Mix and pump 7” Cement Plug


Task : CEMENT
M/U and RIH 3-1/2” Open end tubing until tag top of bridge plug in 7” casing
at 6170’ MD estimated. Mix and pump 7” cement plug. POOH 1 stand and
circulate bottom up. POOH to surface and L/D string.
8 Phase: CLEAN M/U and RIH 7” and 9-5/8” Wellbore Clean out Assembly
Task : SCRAP
M/U and RIH 6-1/8” rock bit (open nozzles), full 9-5/8” x 7” WBCO package
and RIH, scrape existing perforation, production packer setting depth, KL-47,
KL-34A/B zone perforation interval. Displace hole with 9.1 ppg filtered
completion brine. Circulate and sweep hole until NTU < 30. POOH and L/D
BHA.

Note:
Completion fluid weight based on calculation below

KLD-1 Drilling Procedure Page 10 of 22 Revision Aug, 2020


Step DIMS Coding Description
Hydrostatic
Completion
Pressure Depth EMW Pressure of Overbalance Overbalance
Formation Fluid
(Psi) (TVD, ft) (ppg) comp fluid (psi) (ppg)
(ppg)
(psi)
KL-34 1567 3544 8.50 9.1 1,677.02 110.02 0.60
KL-47 2100 4812 8.39 9.1 2,277.04 177.04 0.71
KL-50 2200 5164 8.19 9.1 2,443.60 243.60 0.91

The MW calculation already comply with PDW Rev.03 with minimal


overbalance of 0.3 ppg for gas and 0.2 ppg for oil. (Section 3.6, Page 33)
9 Phase: PROD Run Logging #1 (GR-CCL-CBL) for 7” casing
Task : EVAL
R/U E-Line. M/U and RIH GR-CCL-CBL tool to top of 7” bridge plug. Log up
and L/D tool.
- Inside 7” Liner: from top of 7” bridge plug to top of liner hanger

Run Logging #2 (GR-CCL-CBL) for 9-5/8” casing


R/U E-Line. M/U and RIH GR-CCL-CBL tool to top of 9-5/8” liner hanger. Log
up and L/D tool.
- Inside 9-5/8” Casing: From 4200’ MD to surface

Notes:
CBL data at KLU-1 Exploration Well

Run Logging #3 (PLT)


R/U E-Line. M/U and RIH PLT tool to top of 7” bridge plug. Log up and L/D
tool.
- Inside 7” Liner: from top of 7” bridge plug to top of liner hanger
- Inside 9-5/8” Casing: From 4200’ MD to surface

Run Logging #4 (Caliper)


R/U E-Line. M/U and RIH PLT tool to top of 7” bridge plug. Log up and L/D
tool.
- Inside 7” Liner: from top of 7” bridge plug to top of liner hanger
- Inside 9-5/8” Casing: From 4200’ MD to surface

10 Phase: PROD Re-perforation KL-47 with E-Line


Task : PERFOB
Hold PJSM. M/U and RIH 4-1/2”, 12 SPF, Deep Perforation guns GR for
correlation. RIH and perforate KL-47 zone. POOH. L/D gun. R/D E-Line
Monitor losses at all times.
Notes:
 Detail perforation procedure will be in separated document
 Estimate perforation length: Approximately 20’ interval perf at KL-47
(5840’ - 5860’ MD)
 Safety Switch will be activated 200 ft below sea bed
 Using safe deto as precaution if any stray electric current happened
 Trip Tank Monitoring if any losses happened during RIH

KLD-1 Drilling Procedure Page 11 of 22 Revision Aug, 2020


Step DIMS Coding Description
11 Phase: PROD Re-perforation KL-34A and new perforation KL-34B with TCP
Task : PERFOB
Hold PJSM. M/U and RIH 4-1/2”, 12 SPF, Deep Perforation TCP guns GR
for correlation. RIH and perforate KL-34 A/B zone. POOH. L/D gun.
Notes:
 Detail perforation procedure will be in separated document
 Running Speed TCP gun 2-2.5 min per stand to avoid hammering
effect
 Estimate perforation length: Approximately 65’ interval perf from both
KL-34A (3886’-3932’ MD) and KL-34B (3964’-3983’ MD)
 Trip Tank Monitoring if any losses happened during RIH
 TCP Crew standby at rig floor to detect anomalies and report to DSV
 Fill up string with manual line instead of connected to top drive.

CONTIGENCY PLAN:
Re-perforation KL-34A and new perforation KL-34B with E-Line
Hold PJSM. M/U and RIH 4-1/2”, 12 SPF, Deep Perforation guns GR for
correlation. RIH and perforate KL-34 A/B zone. POOH. L/D gun. R/D E-Line
Monitor losses at all times.
Notes:
 Detail perforation procedure will be in separated document
 Estimate perforation length: Approximately 65’ interval perf from both
KL-34A (3886’-3932’ MD) and KL-34B (3964’-3983’ MD)
 Safety Switch will be activated 200 ft below sea bed
 Using safe deto as precaution if any stray electric current happened
 Trip Tank Monitoring if any losses happened during RIH
12 Phase: CLEAN M/U and RIH 7” and 9-5/8” Wellbore Clean out Assembly
Task : SCRAP
M/U and RIH 6-1/8” rock bit (open nozzles), full 9-5/8” x 7” WBCO package
and RIH, scrape perforation, production packer setting depth, KL-47, KL-
34A/B zone perforation interval. Circulate and sweep hole until NTU < 30.
POOH and L/D
12 Phase: RUNCMP Run 2-7/8” x 3-1/2” Dual Completion
Task : RUNCOM
Hold PJSM. M/U and RIH 2-7/8”, 6.5#, L-80, EUE8RD tubing long string and
3-1/2”, 9.3 ppf, L-80, EUE8rd short string. Continue to RIH tubing with
accessories completion. Hold 4000 psi on the control line to SCSSV while
RIH.
Notes:
 Please refer to the Completion Procedure for details.

13 Phase: TUBHGR Install Dual split tubing hanger


Task : RNTBHG
Space out the tubing hanger. Land the tubing hanger, energize hanger lock
ring, over pull test to 30 klbs/5minutes above string weight of completion
string. Drop the 1-3/4” phenolic ball. Pump down the tubing and pressure up
the string against the pump out sub to 500 psi, hold for 10 minutes then
increase pressure to 3000 psi. Once production packer is set, hold for 10-15
minutes. Bleed off tubing pressure to 2000 psi. Pressure test annulus to 1000
psi. Close SCSSV. Bleed off tubing pressure above SCSSV to 500 psi for
inflow test SCSSV. Equalize pressure above SCSSV to 2000 psi, open
SCSSV and bleed off annulus and tubing pressure to 0 psi. Pressure up
tubing slowly to shear out the ball seat to 4500psi. Confirmed ball seat
sheared by pumping down tubing. Secure well.
Note :
 Please refer to the completion procedure for details
 Ensure to land the tubing hanger properly before set the packer.

KLD-1 Drilling Procedure Page 12 of 22 Revision Aug, 2020


Step DIMS Coding Description
14 Phase: TUBHGR N/D BOP
Task: BOPSUR  Hold PJSM. Set BPV and test. N/D BOP.
15 Phase: WHDTRE N/U X-mas tree
Task: WHSUR  Hold PJSM. N/U Dual 13-3/8” 3K block X-mas tree, pull BPV, install test
plug and cavity test the X-mas tree to 3000 psi. Pull and recover test plug.
Close all X-mas tree valves. Proposed X-Mass Tree Orientation:

16 Phase: POST Skid to KLD-3


Task: DEMOB

KLD-1 Drilling Procedure Page 13 of 22 Revision Aug, 2020


2. DRILLING ASSURANCES

2.1. SIMOPS
Simultaneous operations (SIMOPS) represent one of the most significant hazards while drilling
this well. To reduce the risks of incidents, all operations performed on the KLD platform will be
governed by the West Java SIMOPS plan. The PHE ONWJ Well site Leader (WSL) has been
designated as the Person in Charge (PIC) and will have the ultimate authority to control
simultaneous operations.
The condition of all existing wells on the KLD platform has to be checked on a daily basis by
the Production Representative onboard the rig. The status of these checks shall be reported
on the PHE ONWJ Daily Drilling Report. The following information is required: tubing, casing
annuli pressures, status of the well (shut/flow).
The KLD platform has no producing wells and active pipeline. but only during GREEN SIMOPS
activities. Specific precautions to be taken during the KLD-1 drilling program are documented
in the SIMOPS Meeting Notes.

2.2. PLATFORM HANDOVER


PHE ONWJ Operations Policy, reference 2.6.
A 'well handover' system formalizing the transfer of responsibility for the control of
a well and documenting well conditions shall be in place.

An inspection of the KLD platform will be conducted by Drilling and Production Team.
Outstanding issues from this inspection are documented in the well handover checklist. The
KLD production Superintendent shall ensure that the outstanding items are complete before rig
arrives at the soft pin location. Upon rig arrival, both parties shall sign a platform handover form
indicating the condition of the wells/jacket as a formal handover from Production Team to
Drilling Team.

Before releasing the rig from the KLD platform, the Drilling WSL and the production
representative onboard the rig shall document the final condition of the wells in the platform
handover form. The KLD production superintendent/offshore installation manager shall inspect
the wells and jacket (if required) and upon his satisfaction both parties shall sign the handover
form as a formal handover from Drilling Team to Production Team.

2.3. WATER DEPTH AND SEABED CONDITION


PHE ONWJ Operations Policy, reference 2.6.
Attempts shall be made to clear the seabed or well site location of all debris prior to
leaving the location. Any debris left at site shall be documented.

2.4. SHALLOW HAZARD ASSESSMENT


Not Applicable

2.5. MOVE-IN AND RIG-UP


A pre-move meeting and through review of the Navigation and Rig Positioning Procedure shall
be conducted on-board the rig prior to the rig arriving at the soft pin location. Key points to
emphasize are:
2.5.1 The rig can only move to the soft pin location and run/recover anchors at night if all
survey equipment is 100% operational, and weather conditions are suitable.
2.5.2 Final move on from soft pin location can only be done at night if all involved parties
(PHE ONWJ & ENSCO) agree to proceed, the positioning equipment on the rig and
on all nominated vessels is 100% operational, weather conditions are less than those
stated in the Ensco Rig Move Procedures, Sufficient lightings are provided during

KLD-1 Drilling Procedure Page 14 of 22 Revision Aug, 2020


move alongside the platform, approval from PHE ONWJ Tier 1 (Senior Manager or
alternate) is granted, Sufficient rest time for AHV Masters prior to move to final
alongside. After 8 hours of continuous work on the bridge, a minimum of uninterrupted
4 hours rest is required. Otherwise, a double-Master scheme shall be considered.
2.5.3 Move on shall be with anchors. A second tug will be available to provide additional
assistance if required.
2.5.4 Move on should not be undertaken if there are strong winds or currents that could push
the rig onto the platform if anchor(s) slip or fail.
Upon final positioning the following data shall be recorded in the daily drilling and IADC reports:
 TM and Geographical coordinates (stating geodetic datum)
 Rig Heading
 Water Depth
 RKB-MSL
 RKB-Mud line
 Rig leg penetrations
 Fore/Aft and Port/Stbd skid distances
 Rig acceptance date and time

2.6. PRE-SPUD and RIG ACCEPTANCE


The following minimum acceptance checks shall be completed to the satisfaction of PHE’s WSL
prior to accepting the drilling rig on operating rate:
 Review of documentation, inspection records, and certification of all critical rig components.
 Visual inspection and function test of all critical rig systems, particularly the circulating
system, firefighting equipment and BOP accumulator.
 Pre spud Rig Inspection Checklist properly filled out.
 An emergency evacuation and medical drill will be held prior to spudding the well. The
purpose of this drill is to check all emergency contact numbers and response time.
 A pre spud meeting will be conducted with all key supervisors.
 330 bbls of 11.0 ppg kill weight mud will be prepared, tested and ready for use.
 13-5/8” BOP stack (on test stump) and choke and kill manifold successfully tested to
250/3000 psi for 5/10 minutes with chart recording.
Note: The 13-5/8” BOP stack is nippled-up on the wellhead, test to 1500 psi
 All high pressure mud lines from mud pumps to the Top Drive tested to 250/3000 psi.
Note: mud lines will be tested from the rig floor to the last 4’’ valve on the mud pump
(6-1/2’’ liners only good for 3980 psi).
 Remote ESD controls shall be placed on the rig floor and the rig main deck. These controls
shall be function tested and crews shall be shown how to operate.

KLD-1 Drilling Procedure Page 15 of 22 Revision Aug, 2020


3. TECHNICAL PROGRAMS
3.1. CASING PROGRAM (RKB-MSL =112’)
Depth (ft) Opt
Casing Weight Drift Burst Collapse M/U
Hole Section Grade Conn.
Size [lb/ft] ID [in] [psi] [psi] Torque
MD TVD [ft.lbs]

Conductor Leopard
- 30” 296 296 310 X-52 28.00
(Existing) SD
Intermediate
17-1/2” 13-3/8” 2,046 2,032 61.0 K-55 BTC 12.367 3,450 1,950
1 (Existing)
Production 1
12-1/4” 9-5/8” 4,711 4,088 47.0 L-80 Geoconn 8.530 6,870 4,760
(Existing)
Production 2
8-1/2” 7” 7,002 5,584 26.0 L-80 MBTC 6.151 7,240 5,410
(Existing)

3.2. BOP/CASING PRESSURE TEST


BOP/Diverter Casing
BOP/Diverter
Hole Section Casing Size Connection Pressure
Size
Test Test

9-5/8”, 47 ppf, L-
Completion Production 13-5/8” BOP 1500psi 1500psi
80, Geoconn

3.3. WELLHEAD and TREE PROGRAM


Section Type Size Additional Features
TUBING HEAD ATTACHMENT ASSY, 13
5/8-5K (BX 160) FLAMP BTM X
Tubing Head 13-3/8” 5K Tubing
D 13 5/8-5K (BX-160) CLAMP (#13) HUB
Attachment Head Attachment
TOP W/ STDD HOLES F/ FLAMP
CONNECTION, 13.505 BOWL
P4000040523
DUAL BLOCK VALVE, ASSY, D2S, 3 1/8
13-5/8” – 3M Flange X 3 1/8-3K, W/ PNEUM ACTD UP
Solid Block X- MASTER(S), W/15 DEG BONN, 13 5/8-5K
E x 3-1/8” x 3-1/8” – 3M
mas tree FLAMP BTM X 3 1/8-5K STDD TOP,
assembly
CRES TOP, 5.046 CTR, W/TWO 3 1/8-3K
STDD OUTS, 3.375 SBMS POCKET, F/
4.460 EN, M120 PLUS

3.4. BIT PROGRAM


Drilling Parameters
Bit IADC /
Hole Section TFA WOB
Name Type rpm gpm
[klbs]
IADC
Drill Out inside
8-1/2” Rock Bit 217/227/ 2 – 15 60-100 550-700
9-5/8”
237
IADC
Drill Out inside
6-1/8” Rock Bit 217/227/ 2 – 15 60-100 300 -400
7”
237

KLD-1 Drilling Procedure Page 16 of 22 Revision Aug, 2020


3.5. DRILLING FLUID PROGRAM
Well KLD-1

Hole section / casing size 9-5/8” and 7” Casing


Purpose DOC and drill out bridge plug
Hole inclination Deg 52
Formation Main
Drilling fluid system 5 - 7% KCl Polymer
Mud density ppg 9.7-9.9
Plastic viscosity cP ALAP <25
Yield point lbs/100ft2 25-35
6-RPM - 10-12
Gel strength 10 sec GEL / 10 min lbs/100ft2 8-10 / 10-25
Fluid loss API / HTHP FL cc / 30 min NC / NC
pH - 9.5 – 10.5
KCl % wt 5-7
Drill solid % Vol <35
MBT ppb <10

KLD-1 Drilling Procedure Page 17 of 22 Revision Aug, 2020


3.12. WELL DIAGRAM
RIG TBD
NAVIGATION LIGHT FIELD KL
PLATFORM -
MINI PLATFORM SLOT -
RT ELEVATION 112 ft
WELLHEAD
WATER DEPTH 64 ft
DEPTH NOT TO SCALE
MDRT TVDRT
[ft] [ft]

112 112 Sea Level


176 176 Sea Bed LEAD SLURRY

296 296 30" Cond. TAIL SLURRY

CEMENT PLUG
Balanced Cement plug
(300'-600'MD) 22 bbls Slurry
1,577 1,575 Shallow Gas

1,792 1,785 Minor Fault

1,800 1,793 9-5/8' x 13-3/8" ECP

2,046 2,032 13-3/8" Csg, 61.0 ppf, K-55, BTC


\

8 bbls cement on top (TOC at 3594'MD)


9-5/8" Cement Retainer (WL) 3704'MD
8 bbls cmt (squeeze) predicted cmt 3704-3814'MD

3,906 KL-34 A (Gas) (3906'MD-3940'MD) DST#4

4,497 7" x 9-5/8" TOL 16 bbls cement on top (TOC At 4390'MD)


7" BP (wireline) 4700'MD
4,711 4,088 9-5/8" Csg, 47.0 ppf, L-80, Geoconn

5,840 4,811 KL-47 (Gas) (5840'MD-5860'MD) DST#3

7" BP (wireline) 6170'MD

6,370 5,164 KL-50 (Oil) (6370'MD-6400'MD) DST#2

7" BP (wireline ) 6,598'MD

6,696 5,382 KL-52 (Water) (6696'MD-6724'MD) DST#1

6,875 PBTD
7,002 5,584 7" Csg, 26.0 ppf, L-80, Mod BTC

KLU-1
Final

7,910 6,312 TD
EXPLORATION WELL
Existing Well Diagram

KLD-1 Drilling Procedure Page 18 of 22 Revision Aug, 2020


PROPOSED WELL DIAGRAM
RIG TBD
FIELD KL
PLATFORM KLD
SLOT 1
RT ELEVATION 112 ft
WATER DEPTH 64 ft
DEPTH
MDRT TVDRT
[ft] [ft]

112 112 Sea Level


176 176 Sea Bed LEAD SLURRY

296 296 30" Cond. TAIL SLURRY

CEMENT PLUG

1,800 1,793 9-5/8' x 13-3/8" ECP

2,046 2,032 13-3/8" Csg, 61.0 ppf


\ , K-55, BTC

3-1/2, 9.3 ppf, L80 EUE

2-7/8, 6.5 ppf, L80, EUE

3,906 KL-34A (3886'-3932' MD)


3,972 KL-34B (3964'-3983' MD)

4,497 7" x 9-5/8" TOL

4,711 9-5/8" Csg, 47.0 ppf,


L-80, MBTC

5,838 4,810 KL-47 (Oil) (5840'MD-5860'MD)

6,170 7" BP (wireline) 6170'MD

6,598 7" BP (wireline ) 6,598'MD

6,875 PBTD
7,002 7" Csg, 26.0 ppf, L-80, Mod BTC

KLD-1

7,910 6,312 TD
RECOMPLETION WELL

Proposed Well Diagram


KLD-1 Drilling Procedure Page 19 of 22 Revision Aug, 2020
3.13. TRAJECTORY (Existing)

Max dogleg : 3.5 deg/100 ft


Max Inc : 52 deg
Azm : 232 deg

Detail Trajectory (Original RKB-MSL = 112’)

MD (ft) Inc (°) Azi (°) TVD (ft) N/S (ft) E/W (ft) V.Sec. (ft) DLeg (°/100ft)
0.0 0.00 0.00 0.0 0.0 0.0 0.0 0.00
415.8 0.27 334.38 415.8 0.9 -0.4 0.0 0.06
507.3 0.39 338.29 507.3 1.4 -0.6 -0.1 0.13
599.0 0.41 332.82 599.0 1.9 -0.9 -0.1 0.05
691.7 0.48 342.73 691.7 2.6 -1.2 -0.1 0.11
784.7 0.53 325.15 784.7 3.3 -1.5 -0.2 0.17
876.0 0.49 317.21 876.0 4.0 -2.0 0.0 0.09
967.0 0.71 314.16 967.0 4.7 -2.7 0.3 0.24
1062.2 1.18 259.00 1062.2 4.9 -4.1 1.4 1.02
1156.2 2.45 255.94 1156.1 4.2 -7.0 4.3 1.35
1249.7 3.66 249.84 1249.5 2.7 -11.7 9.2 1.34
1344.4 5.32 242.35 1343.9 -0.4 -18.5 16.6 1.86
1438.4 6.41 243.15 1437.4 -4.8 -27.0 26.2 1.16
1531.8 7.08 243.36 1530.2 -9.7 -36.8 37.2 0.72
1625.4 8.47 243.53 1622.9 -15.4 -48.1 49.9 1.49
1719.8 10.68 244.32 1716.0 -22.3 -62.2 65.6 2.35
1813.5 12.91 242.00 1807.7 -30.9 -79.3 84.7 2.43
1908.3 14.54 242.62 1899.8 -41.4 -99.2 107.2 1.73
2111.9 21.00 245.40 2093.5 -68.4 -155.1 169.3 3.20
2210.7 24.17 244.34 2184.7 -84.5 -189.5 207.2 3.23
2306.0 26.79 245.23 2270.8 -102.0 -226.6 248.2 2.78
2401.2 29.74 249.00 2354.7 -119.4 -268.1 293.1 3.62
2496.4 30.76 251.17 2436.9 -135.7 -313.2 340.7 1.57

KLD-1 Drilling Procedure Page 20 of 22 Revision Aug, 2020


2589.4 31.61 252.80 2516.4 -150.6 -359.0 388.2 1.29
2685.1 33.23 256.43 2597.2 -164.2 -408.4 438.5 2.65
2780.1 33.23 256.12 2676.7 -176.5 -459.0 489.2 0.18
2872.7 32.93 255.79 2754.3 -188.8 -508.0 538.4 0.38
2966.8 33.15 256.50 2833.2 -201.1 -557.9 588.4 0.47
3061.0 34.50 257.03 2911.5 -213.1 -608.9 639.4 1.47
3156.1 35.10 257.09 2989.5 -225.2 -661.8 692.0 0.63
3250.3 35.87 256.74 3066.2 -237.6 -715.1 745.1 0.85
3344.1 37.14 257.53 3141.7 -250.0 -769.5 799.3 1.44
3438.8 39.11 258.17 3216.1 -262.3 -826.6 855.8 2.12
3533.4 40.76 257.62 3288.6 -275.1 -886.0 914.4 1.78
3626.9 41.93 256.99 3358.9 -288.6 -946.3 974.3 1.33
3722.8 43.52 257.30 3429.3 -303.1 -1009.6 1037.4 1.67
3817.0 45.52 258.31 3496.5 -317.1 -1074.3 1101.3 2.25
3909.7 47.42 258.59 3560.3 -330.5 -1140.1 1166.1 2.06
4003.5 48.22 257.73 3623.3 -344.8 -1208.1 1233.2 1.09
4099.2 48.54 256.00 3686.8 -361.0 -1277.8 1302.7 1.39
4191.6 48.69 254.46 3748.0 -378.7 -1344.8 1370.5 1.26
4286.5 49.63 253.31 3810.0 -398.6 -1413.8 1441.0 1.35
4380.9 50.05 250.90 3870.9 -420.8 -1482.4 1512.2 2.00
4474.8 49.70 249.95 3931.4 -444.9 -1550.1 1583.4 0.86
4569.0 48.29 249.12 3993.2 -469.7 -1616.7 1654.0 1.64
4662.0 47.91 245.21 4055.3 -496.6 -1680.4 1723.0 3.16
4711.0 47.72 242.84 4088.2 -512.5 -1713.1 1759.3 3.60
4880.0 49.36 247.20 4200.1 -565.9 -1827.9 1885.9 2.16
4928.3 49.86 248.41 4231.4 -579.8 -1861.9 1922.5 2.17
5022.7 51.10 245.82 4291.5 -608.1 -1929.0 1995.2 2.49
5115.9 51.38 244.23 4349.9 -638.8 -1994.9 2067.8 1.36
5210.0 51.37 241.65 4408.6 -672.2 -2060.3 2141.3 2.14
5304.6 51.06 238.85 4467.9 -708.8 -2124.3 2214.9 2.33
5398.8 51.29 236.71 4526.9 -747.9 -2186.4 2288.0 1.79
5492.5 50.60 235.22 4586.0 -788.6 -2246.7 2360.2 1.44
5586.8 49.98 233.48 4646.2 -830.9 -2305.7 2431.9 1.56
5681.6 49.81 232.19 4707.3 -874.7 -2363.4 2503.2 1.06
5776.1 48.60 231.89 4769.0 -918.7 -2419.8 2573.5 1.30
5869.5 48.03 232.34 4831.2 -961.6 -2474.9 2642.0 0.71
5964.8 48.13 232.44 4894.8 -1004.8 -2531.1 2711.6 0.13
6059.0 48.15 232.66 4957.7 -1047.5 -2586.8 2780.6 0.18
6153.0 48.23 232.47 5020.3 -1090.1 -2642.4 2849.5 0.17
6247.7 48.28 232.36 5083.4 -1133.2 -2698.4 2919.0 0.10
6342.8 48.58 231.91 5146.5 -1176.8 -2754.5 2988.8 0.47
6436.3 48.01 233.23 5208.7 -1219.3 -2810.0 3057.4 1.22
6531.3 48.21 233.26 5272.2 -1261.6 -2866.7 3127.2 0.21
6625.5 48.05 234.35 5335.0 -1303.0 -2923.3 3196.4 0.88
6720.0 47.88 234.36 5398.3 -1343.9 -2980.3 3265.7 0.18
6811.9 48.66 234.89 5459.5 -1383.6 -3036.2 3333.6 0.95
6906.7 49.01 234.52 5521.8 -1424.8 -3094.4 3404.2 0.47

KLD-1 Drilling Procedure Page 21 of 22 Revision Aug, 2020


7001.7 49.11 234.17 5584.1 -1466.7 -3152.7 3475.1 0.30
7095.2 49.43 234.27 5645.1 -1508.1 -3210.3 3545.1 0.35
7189.0 49.23 233.52 5706.3 -1550.0 -3267.7 3615.4 0.64
7283.1 49.00 233.62 5767.9 -1592.3 -3325.0 3685.6 0.26
7377.6 49.26 233.23 5829.7 -1634.8 -3382.4 3756.0 0.42
7472.3 49.70 232.84 5891.2 -1678.2 -3439.9 3826.9 0.56
7566.9 49.06 232.65 5952.8 -1721.6 -3497.0 3897.5 0.69
7661.4 48.43 232.12 6015.1 -1765.0 -3553.3 3967.4 0.79
7755.3 48.56 231.79 6077.3 -1808.3 -3608.7 4036.3 0.30
7910.0 48.25 231.50 6180.0 -1880.1 -3699.4 4149.8 0.24

KLD-1 Drilling Procedure Page 22 of 22 Revision Aug, 2020