KLD-1
Completion
Prepared by: Janico Zaverson M
Engineer
Bertha Sondang/ BERTHA
Prepared by: Geologist SONDANG
Digitally signed by BERTHA SONDANG M
DN: cn=BERTHA SONDANG M, o, ou,
email=bertha.martinauly@pertamina.com, c=US
Bangsawan Arief
Date: 2020.08.23 09:46:24 +07'00'
Linda Atmaji
Nugroho
ID
Date: 2020.08.23 11:02:49
Date: 2020.08.23 11:07:45
+07'00'
+07'00'
debby
irawan
DN: cn=debby irawan,
irawan
email=mk.debby.irawan@p
ertamina.com, c=ID
Date: 2020.08.23 10:44:31
+07'00'
Adrianus
Reservoir /
Prepared by: Pradipta/Jemi
Production Eng.
Jaenudin
Digitally signed by Eko Prasetyo
DN: cn=Eko Prasetyo, o=PHE ONWJ,
Sr. Manager
Approved by: David Tobing
Sub-Surface
Sr. Manager Drilling
Approved by: Widoyo Krisnanto
and Well Services
Distribution:
Benny Nuryadi Sr. Manager Production
David Tobing Sr. Manager Sub-Surface
Roylan S/Leksmono PHE ONWJ Wellsite Leaders
Geoffrey D’sa Cardoso Rig Manager (ENSCO 67)
Hendra Siswanto DD Coordinator (Uzma)
Hulyadi MWD/LWD Coordinator (Schlumberger)
Agung Heru Wijanarko Drilling Fluid Coordinator (MI Indonesia)
Warti Nur Raisyah Cementing Services Coordinator (Halliburton)
Benny Nuryadi Sr. Manager Production
1.1.1. Re-entry well in full compliance with HSE and operation procedures.
1.1.2. Drill out cement and cement retainer in 9-5/8” and 7” casing.
1.1.3. Re-perforate KL-34A and KL-47A, new perforation KL-34B.
1.1.4. Complete the well with 2-7/8” x 3-1/2” Dual Completion
Reservoir
Interval Fluid Top MD EMW Temp
Formation Pressure
[ft MD] Type [ft] [ppg] [degF]
[psig]
Gas,
KL-34A 3,886-3,940 3,886 1,567 8.53 176
Condensate
Gas,
KL-34B 3,964-3,983 3,964 1,567 8.41 176
Condensate
Gas,
KL-47 5,840-5,860 5,840 2,093 8.39 207
Condensate
Summary:
25 July 2020
Annulus A: 0 psi
Annulus B: 300 psi. Bleed off until zero and observe for a while – No
build up pressure.
12 August 2020:
Annulus A: 0 psi
Annulus B: 20 psi after two weeks left after first observation. Monitor for
12 hours and no build up pressure
Slot Coordinates:
KLD-1
Latitude: 06°02'14.339"S Easting: 339207.174mE
Longitude: 107°32'49.109"E Northing: 9332519.960mE
CEMENT PLUG
Balanced Cement plug
(300'-600'MD) 22 bbls Slurry
1,577 1,575 Shallow Gas
6,875 PBTD
7,002 5,584 7" Csg, 26.0 ppf, L-80, Mod BTC
KLU-1
Final
7,910 6,312 TD
EXPLORATION WELL
RIH and tag TOC estimation at 3594’ MD. Circulate and condition mud to 9.7
ppg. Pressure Test casing to 500 psi for 5 minutes and 1500 psi for 10
minutes. Drill out cement plug #2 and 9-5/8” cement retainer to 3814’ MD
(estimation end of cement below CR).
Continue and RIH until tag TOC at 4390’ MD. Circulate hole clean. Increase
MW to 9.9 ppg. POOH and L/D BHA.
BHA: 8-1/2” Rock Bit 217/227/237 – Bit Sub – 7” junk basket – 3 x 6-1/2” Drill
Collar – X/O – 9 X 5-1/2” HWDP – X/O – 6-1/2” Drilling Jar – X/O – 20 X5-
1/2” HWDP – 5-1/2” DP.
Note :
Available 2 ea Bit IADC 217/227/237 and Junk Mill.
Drill Out cement plug #1 (300-600’ MD)
Drilling out cement plug #2 and 1 ea Cement Retainer K-1 Type.
(cement above CR 110 ft, K-1 CR 3-4 ft, cement below CR 106 ft)
column of mud
top Bottom Length Pressure each
Hydrostatic Pressure Overbalance MW Overbalance
Casing above plug
Zone column column column Column
(psi) (psi) (ppg) (ppg)
(TVD)(TVD, ft) (TVD, ft) (TVD, ft) (psi)
9-5/8" KL-34 3494
3494 3877 1,762.4
383 1,522.96 9.7
239.42 1.32
BHA: 6-1/8” Rock Bit – Bit Sub – X/O – 5-3/8” junk basket – X/O – 4-3/4” Drill
Collar – X/O – 9x3-1/2” DP – 4-3/4” Jar – 90x 3-1/2” DP – X/O – 5-1/2” DP
Note:
After lower slip is drilled out, push BP to top of next 7” bridge plug at
6170’ MD.
Note:
Completion fluid weight based on calculation below
Notes:
CBL data at KLU-1 Exploration Well
CONTIGENCY PLAN:
Re-perforation KL-34A and new perforation KL-34B with E-Line
Hold PJSM. M/U and RIH 4-1/2”, 12 SPF, Deep Perforation guns GR for
correlation. RIH and perforate KL-34 A/B zone. POOH. L/D gun. R/D E-Line
Monitor losses at all times.
Notes:
Detail perforation procedure will be in separated document
Estimate perforation length: Approximately 65’ interval perf from both
KL-34A (3886’-3932’ MD) and KL-34B (3964’-3983’ MD)
Safety Switch will be activated 200 ft below sea bed
Using safe deto as precaution if any stray electric current happened
Trip Tank Monitoring if any losses happened during RIH
12 Phase: CLEAN M/U and RIH 7” and 9-5/8” Wellbore Clean out Assembly
Task : SCRAP
M/U and RIH 6-1/8” rock bit (open nozzles), full 9-5/8” x 7” WBCO package
and RIH, scrape perforation, production packer setting depth, KL-47, KL-
34A/B zone perforation interval. Circulate and sweep hole until NTU < 30.
POOH and L/D
12 Phase: RUNCMP Run 2-7/8” x 3-1/2” Dual Completion
Task : RUNCOM
Hold PJSM. M/U and RIH 2-7/8”, 6.5#, L-80, EUE8RD tubing long string and
3-1/2”, 9.3 ppf, L-80, EUE8rd short string. Continue to RIH tubing with
accessories completion. Hold 4000 psi on the control line to SCSSV while
RIH.
Notes:
Please refer to the Completion Procedure for details.
2.1. SIMOPS
Simultaneous operations (SIMOPS) represent one of the most significant hazards while drilling
this well. To reduce the risks of incidents, all operations performed on the KLD platform will be
governed by the West Java SIMOPS plan. The PHE ONWJ Well site Leader (WSL) has been
designated as the Person in Charge (PIC) and will have the ultimate authority to control
simultaneous operations.
The condition of all existing wells on the KLD platform has to be checked on a daily basis by
the Production Representative onboard the rig. The status of these checks shall be reported
on the PHE ONWJ Daily Drilling Report. The following information is required: tubing, casing
annuli pressures, status of the well (shut/flow).
The KLD platform has no producing wells and active pipeline. but only during GREEN SIMOPS
activities. Specific precautions to be taken during the KLD-1 drilling program are documented
in the SIMOPS Meeting Notes.
An inspection of the KLD platform will be conducted by Drilling and Production Team.
Outstanding issues from this inspection are documented in the well handover checklist. The
KLD production Superintendent shall ensure that the outstanding items are complete before rig
arrives at the soft pin location. Upon rig arrival, both parties shall sign a platform handover form
indicating the condition of the wells/jacket as a formal handover from Production Team to
Drilling Team.
Before releasing the rig from the KLD platform, the Drilling WSL and the production
representative onboard the rig shall document the final condition of the wells in the platform
handover form. The KLD production superintendent/offshore installation manager shall inspect
the wells and jacket (if required) and upon his satisfaction both parties shall sign the handover
form as a formal handover from Drilling Team to Production Team.
Conductor Leopard
- 30” 296 296 310 X-52 28.00
(Existing) SD
Intermediate
17-1/2” 13-3/8” 2,046 2,032 61.0 K-55 BTC 12.367 3,450 1,950
1 (Existing)
Production 1
12-1/4” 9-5/8” 4,711 4,088 47.0 L-80 Geoconn 8.530 6,870 4,760
(Existing)
Production 2
8-1/2” 7” 7,002 5,584 26.0 L-80 MBTC 6.151 7,240 5,410
(Existing)
9-5/8”, 47 ppf, L-
Completion Production 13-5/8” BOP 1500psi 1500psi
80, Geoconn
CEMENT PLUG
Balanced Cement plug
(300'-600'MD) 22 bbls Slurry
1,577 1,575 Shallow Gas
6,875 PBTD
7,002 5,584 7" Csg, 26.0 ppf, L-80, Mod BTC
KLU-1
Final
7,910 6,312 TD
EXPLORATION WELL
Existing Well Diagram
CEMENT PLUG
6,875 PBTD
7,002 7" Csg, 26.0 ppf, L-80, Mod BTC
KLD-1
7,910 6,312 TD
RECOMPLETION WELL
MD (ft) Inc (°) Azi (°) TVD (ft) N/S (ft) E/W (ft) V.Sec. (ft) DLeg (°/100ft)
0.0 0.00 0.00 0.0 0.0 0.0 0.0 0.00
415.8 0.27 334.38 415.8 0.9 -0.4 0.0 0.06
507.3 0.39 338.29 507.3 1.4 -0.6 -0.1 0.13
599.0 0.41 332.82 599.0 1.9 -0.9 -0.1 0.05
691.7 0.48 342.73 691.7 2.6 -1.2 -0.1 0.11
784.7 0.53 325.15 784.7 3.3 -1.5 -0.2 0.17
876.0 0.49 317.21 876.0 4.0 -2.0 0.0 0.09
967.0 0.71 314.16 967.0 4.7 -2.7 0.3 0.24
1062.2 1.18 259.00 1062.2 4.9 -4.1 1.4 1.02
1156.2 2.45 255.94 1156.1 4.2 -7.0 4.3 1.35
1249.7 3.66 249.84 1249.5 2.7 -11.7 9.2 1.34
1344.4 5.32 242.35 1343.9 -0.4 -18.5 16.6 1.86
1438.4 6.41 243.15 1437.4 -4.8 -27.0 26.2 1.16
1531.8 7.08 243.36 1530.2 -9.7 -36.8 37.2 0.72
1625.4 8.47 243.53 1622.9 -15.4 -48.1 49.9 1.49
1719.8 10.68 244.32 1716.0 -22.3 -62.2 65.6 2.35
1813.5 12.91 242.00 1807.7 -30.9 -79.3 84.7 2.43
1908.3 14.54 242.62 1899.8 -41.4 -99.2 107.2 1.73
2111.9 21.00 245.40 2093.5 -68.4 -155.1 169.3 3.20
2210.7 24.17 244.34 2184.7 -84.5 -189.5 207.2 3.23
2306.0 26.79 245.23 2270.8 -102.0 -226.6 248.2 2.78
2401.2 29.74 249.00 2354.7 -119.4 -268.1 293.1 3.62
2496.4 30.76 251.17 2436.9 -135.7 -313.2 340.7 1.57